EP0279165B1 - Apparatus for the replacement of runners of shaft furnaces - Google Patents

Apparatus for the replacement of runners of shaft furnaces Download PDF

Info

Publication number
EP0279165B1
EP0279165B1 EP88100101A EP88100101A EP0279165B1 EP 0279165 B1 EP0279165 B1 EP 0279165B1 EP 88100101 A EP88100101 A EP 88100101A EP 88100101 A EP88100101 A EP 88100101A EP 0279165 B1 EP0279165 B1 EP 0279165B1
Authority
EP
European Patent Office
Prior art keywords
tapping
drawing elements
spout
platform
runners
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP88100101A
Other languages
German (de)
French (fr)
Other versions
EP0279165A1 (en
Inventor
Bruno Kämmerling
Werner Dipl.-Ing. Rosker
Eckhard-Karl Scholz
Dipl.-Ing. Kowalski Wolfgang
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MAN Gutehoffnungshutte GmbH
Original Assignee
MAN Gutehoffnungshutte GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MAN Gutehoffnungshutte GmbH filed Critical MAN Gutehoffnungshutte GmbH
Priority to AT88100101T priority Critical patent/ATE55154T1/en
Publication of EP0279165A1 publication Critical patent/EP0279165A1/en
Application granted granted Critical
Publication of EP0279165B1 publication Critical patent/EP0279165B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces
    • C21B7/14Discharging devices, e.g. for slag

Definitions

  • the invention relates to a device for replacing tapping troughs in shaft furnaces.
  • Pig iron and slag are tapped from a blast furnace at regular intervals. Depending on the amount of pig iron produced, there are eight to twelve taps within 24 hours. During the tapping process, pig iron and slag are separated from one another in a so-called main tapping channel. Such main tapping channels on large blast furnaces have recently been carried out with large cross sections. The main tapping trough is usually followed by other tapping troughs and tipping troughs for pig iron (until they are handed over to pans or torpedo cars) and slag. While the slag is being removed from the main tapping channel, the pig iron remains in this channel between tapping.
  • blast furnaces that have only one tap hole.
  • Such blast furnaces must be throttled for the time of repair or relining of the fireproof tapping lining, or the blast furnace must be shut down for long periods of work.
  • Also known is a device for changing the main tapping channel of a blast furnace (DE patent application P 36 24 266.7), in which at least four lifting elements are arranged in a stationary or non-stationary manner in front of the tapping hole of the blast furnace on the hut floor, which act on trusses on which the main tapping channel rests, the channel to be replaced can be lowered onto a means of transport located on the hut floor, in particular rail-bound, and the newly delivered channel can be raised from the means of transport to the level of the casting platform, and that the main tapping channel with the crossbeams is pneumatically actuated by means of the steel structure of the casting platform Holding arms is held.
  • the object of the invention is to provide a replacement device for tapping troughs in shaft furnaces, the installation of which does not require expensive earthwork and foundation work and which can also be erected subsequently in existing metallurgical plants.
  • a replacement device should be designed so that it is also portable, so that only one device for replacing tapping troughs has to be purchased in a metallurgical plant with several furnaces, especially since the times of use of the changing device can be easily coordinated.
  • Tapping troughs on shaft furnaces have a high weight, for example more than 100 t including the refractory lining.
  • the required lifting height from the hut floor to the racking platform is over 4 m. Raising and lowering the tapping trough for repair purposes places considerable demands on the traction mechanism.
  • the tapping channel (4) is located on the transport means (1) which can be moved on rails in the hut hallway (2). Traverses (10), which are arranged under the tapping channel (4), can be seen between the tapping channel and the transport platform. Stranded ropes or climbing bars (6) of the tension elements (5) are attached to the crossbeams (10).
  • the tension elements (5) are arranged on support beams (7) welded to the tapping platform (3) of the shaft furnace.
  • the tension elements are supplied by a hydraulic pump unit (not shown here).
  • FIG. 2 shows, in contrast to FIG. 1, tension elements (5) which are arranged on the crossbeams (10) of the tapping channel (4).
  • the device works in reverse, i.e. the traction elements (5) are pulled up or down with the tapping channel (4) to the tapping platform (3).
  • a known strand or rod conveying system in which loads are moved with the aid of electrohydraulically driven lifters, is suitable for the replacement device according to the invention.
  • FIG. 3 and 4 show an embodiment in which the tension elements (5) and the hydraulic pump unit (8) are arranged on a transportable platform (9).
  • the hydraulic hoses for connecting the pump unit and tension elements have not been shown.
  • This platform can be made in one or more parts and stands with its feet on the gutter support beams (7) of the racking platform (3).
  • the tapping channel (4) is detachably attached to the rods or strands (6) of the tension elements (5) by means of a shackle connection (12), which is only indicated.
  • the tapping channel (4) is raised to the level of the tapping platform (3), the tapping channel (4) is supported with the aid of retractable and retractable supports (11) arranged laterally under the tapping platform.
  • the supports (11) are pushed through corresponding openings in the channel support supports (7).
  • the platform (9) with the pulling elements (5) can be removed by a crane.
  • hydraulic pump unit (8) can also be set up (not shown), for example on the side of the tapping platform (3), in which case hose connections to the traction elements (5) must exist.
  • Fig. 5 shows a tapping channel (4) hanging on rods or stranded ropes (6).
  • the tension elements (5) are mounted here on the platform of a slewing ring (13) which runs on rails which are located on the platform (9).
  • the slewing ring (13) can be moved through 360 ° in the horizontal.
  • Fig. 6 is to show that it is possible with the help of the slewing ring (13), the tapping channel (4) hanging on the tension elements (5), deviating from the position assumed on the tapping platform (3), during the lowering to a different angular position bring.
  • the rails for the means of transport are e.g. arranged at right angles to the position of the gutter from the tapping platform.

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Furnace Charging Or Discharging (AREA)
  • Manufacture And Refinement Of Metals (AREA)
  • Blast Furnaces (AREA)
  • Furnace Housings, Linings, Walls, And Ceilings (AREA)
  • Investigating Or Analysing Biological Materials (AREA)
  • Measuring Or Testing Involving Enzymes Or Micro-Organisms (AREA)
  • Chutes (AREA)
  • Arc Welding In General (AREA)
  • Vending Machines For Individual Products (AREA)

Abstract

A device for changing tap runners in shaft furnaces includes tap runners which have linings subject to wear and therefore such runners must be repaired regularly. Transport of the runner requires a considerable crane capacity with correspondingly heavy building construction. The device according to the invention permits transport of the tap runner without a casting room crane. Instead, the tap runner is raised or lowered between the mill floor, or another level, and a tapping platform by means of hydraulically driven traction elements taking support on runner supports arranged at tapping platform level.

Description

Die Erfindung betrifft eine Vorrichtung zum Auswechseln von Abstichrinnen an Schachtöfen.The invention relates to a device for replacing tapping troughs in shaft furnaces.

Der Abstich von Roheisen und Schlacke aus einem Hochofen erfolgt in periodischen Abständen. Je nach Menge des produzierten Roheisens ergeben sich acht bis zwölf Abstiche innerhalb von 24 Stunden. Beim Abstichvorgang werden Roheisen und Schlacke in einer sogenannten Hauptabstichrinne voneinander getrennt. Derartige Hauptabstichrinnen an Großhochöfen werden in neuerer Zeit mit großen Querschnitten ausgeführt. An die Hauptabstichrinne schließen sich in der Regel weitere Abstichrinnen und Kipprinnen für Roheisen (bis zur Übergabe in Pfannen oder Torpedowagen) und Schlacke an. Während die Schlacke aus der Hauptabstichrinne abgeführt wird, verbleibt das Roheisen zwischen den Abstichen in dieser Rinne.Pig iron and slag are tapped from a blast furnace at regular intervals. Depending on the amount of pig iron produced, there are eight to twelve taps within 24 hours. During the tapping process, pig iron and slag are separated from one another in a so-called main tapping channel. Such main tapping channels on large blast furnaces have recently been carried out with large cross sections. The main tapping trough is usually followed by other tapping troughs and tipping troughs for pig iron (until they are handed over to pans or torpedo cars) and slag. While the slag is being removed from the main tapping channel, the pig iron remains in this channel between tapping.

Bei Abstichmengen an Roheisen von mehreren tausend Tonnen täglich unterliegt die feuerfeste Auskleidung der Hauptabstichrinne erheblichen mechanischen und thermischen Belastungen und demzufolge einem hohen Verschleiß. Aus diesem Grunde ist es erforderlich, die Auskleidung der Rinne in regelmäßigen Abständen zu reparieren bzw. komplett zu erneuern. Die Haltbarkeit von Abstichrinnen bis zur Zwischenreparatur liegt beispielsweise bei ca. 50000 t Roheisen, die komplette Erneuerung erfolgt nach einer Produktion von ca. 120000 - 130000 t Roheisen.With tapping quantities of pig iron of several thousand tons per day, the refractory lining of the main tapping channel is subject to considerable mechanical and thermal loads and consequently to a high level of wear. For this reason, it is necessary to repair or completely replace the gutter lining at regular intervals. The shelf life from tapping troughs to intermediate repairs is, for example, around 50,000 t of pig iron, and the complete replacement takes place after production of around 120,000 - 130,000 t of pig iron.

Bei Hochöfen mit mehr als einem Abstichloch werden die Arbeiten an der Abstichrinne vor Ort in der Gießhalle durchgeführt. Während dieser Reparaturzeit wird das Roheisen aus einem anderen Abstichloch - meist auch in einer zweiten Gießhalle - abgestochen, so daß sich dabei in der Regel keine oder nur geringfügige Einschränkungen des Betriebes ergeben.In the case of blast furnaces with more than one tap hole, work on the tapping channel is carried out on site in the casting hall. During this repair period, the pig iron is tapped from another tap hole - usually also in a second casting hall - so that there are usually no or only minor restrictions on operation.

Ganz anders sieht es aber bei Hochöfen aus, die mit nur einem Abstichloch versehen sind. Derartige Hochöfen müssen für die Zeit der Reparatur bzw. Neuzustellung der feuerfesten Abstichrinnenauskleidung gedrosselt gefahren werden, bzw. bei längerer Zeit andauernden Arbeiten muß der Hochofen stillgesetzt werden.The situation is completely different for blast furnaces that have only one tap hole. Such blast furnaces must be throttled for the time of repair or relining of the fireproof tapping lining, or the blast furnace must be shut down for long periods of work.

Dieser Umstand führte zu Überlegungen, die Hauptabstichrinne mit Hilfe des Gießhallenkrans auszuwechseln. Dabei ging man auch so vor, daß man bei aus mehreren Abschnitten zusammengesetzten Hauptabstichrinnen einzelne erneuerungsbedürftige Abschnitte auf die beschriebene Weise auswechselte.This fact led to considerations to replace the main tapping channel with the help of the casting hall crane. The procedure was also such that, in the case of main tapping channels composed of several sections, individual sections in need of renovation were replaced in the manner described.

Wegen der zuvor bereits erwähnten großen Abmessungen der Hauptabstichrinne sind zum Auswechseln erhebliche Krankapazität erforderlich und selbstverständlich eine entsprechend schwere Ausführung der Gießhallen-Stahlkonstruktion. Ferner sind große freie Flächen in der Gießhalle notwendig, auf denen die ausgebauten Rinnenabschnitte für die Reparatur- und Neuzustellungsarbeiten gelagert werden können.Because of the large dimensions of the main tapping channel mentioned above, considerable crane capacity is required for replacement and, of course, a correspondingly heavy design of the steel casting structure. In addition, large free areas are required in the casting hall, on which the removed gutter sections can be stored for repair and relining work.

Bekannt ist auch eine Vorrichtung zum Auswechseln der Hauptabstichrinne eines Hochofens (DE-Patentanmeldung P 36 24 266.7), bei der vor dem Abstichloch des Hochofens auf dem Hüttenflur mindestens vier Hubelemente stationär oder nicht stationär angeordnet sind, die an Traversen angreifen, auf denen die Hauptabstichrinne aufliegt, wobei die auszuwechselnde Rinne auf ein auf dem Hüttenflur befindliches, insbesondere schienengebundenes, Transportmittel absenkbar ist und die neu zugestellte Rinne vom Transportmittel auf die Höhe der Gießbühne anhebbar ist, und daß die Hauptabstichrinne mit den Traversen mittels an der Stahlkonstruktion der Gießbühne angeordneter pneumatisch betätigter Haltearme gehalten wird.Also known is a device for changing the main tapping channel of a blast furnace (DE patent application P 36 24 266.7), in which at least four lifting elements are arranged in a stationary or non-stationary manner in front of the tapping hole of the blast furnace on the hut floor, which act on trusses on which the main tapping channel rests, the channel to be replaced can be lowered onto a means of transport located on the hut floor, in particular rail-bound, and the newly delivered channel can be raised from the means of transport to the level of the casting platform, and that the main tapping channel with the crossbeams is pneumatically actuated by means of the steel structure of the casting platform Holding arms is held.

Obgleich mit dieser bekannten Vorrichtung ein rascher Wechsel der Abstichrinne ermöglicht wird, bedarf es für die Installation doch einiger Vorbereitungsarbeiten, wie z.B. Erdarbeiten für die versenkbaren Hubelemente.Although this known device enables a rapid change of the tapping trough, some preparation work is required for the installation, e.g. Earthworks for the retractable lifting elements.

Aufgabe der Erfindung ist es, eine Auswechselvorrichtung für Abstichrinnen an Schachtöfen zu schaffen, bei deren Installation auf aufwendige Erd- und Fundamentarbeiten verzichtet werden kann und die sich auch nachträglich in vorhandene Hüttenwerksanlagen errichten läßt. Außerdem sollte eine solche Vorrichtung so konzipiert sein, daß sie auch transportabel ist, damit in einem Hüttenwerk mit mehreren Öfen nur eine Vorrichtung für das Auswechseln von Abstichrinnen angeschafft werden muß, zumal sich die Nutzungszeiten der Auswechselvorrichtung ohne weiteres abstimmen lassen.The object of the invention is to provide a replacement device for tapping troughs in shaft furnaces, the installation of which does not require expensive earthwork and foundation work and which can also be erected subsequently in existing metallurgical plants. In addition, such a device should be designed so that it is also portable, so that only one device for replacing tapping troughs has to be purchased in a metallurgical plant with several furnaces, especially since the times of use of the changing device can be easily coordinated.

Die Lösung dieser Aufgabe ist in Anspruch 1 angegeben. Vorteilhafte Einzelheiten sind in den Unteransprüchen aufgeführt.The solution to this problem is specified in claim 1. Advantageous details are given in the subclaims.

Abstichrinnen an Schachtöfen weisen ein hohes Eigengewicht auf, beispielsweise mehr als 100 t einschließlich der feuerfesten Ausmauerung. Die erforderliche Hubhöhe vom Hüttenflur zur Abstichbühne liegt bei über 4 m. Das Anheben und Absenken der Abstichrinne für Reparaturzwecke stellt an das Zugmittel erhebliche Anforderungen.Tapping troughs on shaft furnaces have a high weight, for example more than 100 t including the refractory lining. The required lifting height from the hut floor to the racking platform is over 4 m. Raising and lowering the tapping trough for repair purposes places considerable demands on the traction mechanism.

Die erfindungsgemäße Auswechselvorrichtung weist eine Reihe von Vorteilen auf gegenüber dem Stand der Technik:

  • - im Vergleich zum Einsatz von Druckelementen des Standes der Technik für das Heben und Absenken, bei denen eine Knickgefahr möglich ist, gewährleisten die erfindungsgemäßen Zugelemente während des gesamten Bewegungsablaufs eine absolut sichere Lage der Abstichrinne,
  • - die Zugelemente sind bei gleicher Nutzlast leichter und preisgünstiger als Druckelemente,
  • - es entfallen zustäzliche Führungsschienen, die bei Druckelementen erforderlich sind,
  • - keine Kosten für aufwendige Erdarbeiten, Fundamente und Entwässerungen,
  • - das Gewicht der Zugelemente ist im Verhältnis zum Gewicht der Abstichrinne so gering, daß keine nennenswerten Verstärkungen der Stützträger an der Abstichbühne notwendig sind,
  • - wegen ihres niedrigen Gewichtes kann die Auswechselvorrichtung als transportable Einrichtung an mehreren Schachtöfen eingesetzt werden,
  • - die instandgesetzte Abstichrinne braucht vor dem Anschlagen an die Zugelemente nicht genau unterhalb der Einbaulage zu stehen, wodurch ein Montagezeitgewinn ermöglicht wird,
  • - bei evtl. Störungen an den Zugelementen während eines Hubvorganges sind diese, da sie oberhalb der Last liegen, gefahrlos zugänglich.
The replacement device according to the invention has a number of advantages over the prior art:
  • in comparison to the use of pressure elements of the prior art for lifting and lowering, in which there is a risk of kinking, the tension elements according to the invention ensure an absolutely secure position of the tapping trough during the entire movement sequence,
  • - the tension elements are lighter and cheaper than pressure elements with the same payload,
  • - there are no additional guide rails that are required for pressure elements,
  • - no costs for complex earthworks, foundations and drainage,
  • the weight of the tension elements is so low in relation to the weight of the tapping channel that no significant reinforcements of the support beams on the tapping platform are necessary,
  • - Because of its low weight, the replacement device can be used as a transportable device on several shaft furnaces,
  • - The repaired tapping channel does not need to be under exactly before striking the tension elements to stand half of the installation position, which enables an assembly time saving,
  • - In the event of any malfunctions in the traction elements during a lifting process, they are safely accessible because they are above the load.

Ausführungsbeispiele der Auswechselvorrichtung werden nachstehend anhand der schematischen Zeichnungen näher erläutert.Exemplary embodiments of the exchange device are explained in more detail below with reference to the schematic drawings.

Es zeigen:

  • Fig. 1 einen Schnitt durch Abstichbühne und Hüttenflur mit der erfindungsgemäßen Auswechselvorrichtung,
  • Fig. 2 eine Alternative zu Fig. 1 im Schnitt,
  • Fig. 3 einen Längsschnitt mit angehobener Abstichrinne,
  • Fig. 4 einen Querschnitt zu Fig. 3,
  • Fig. 5 eine Alternative zu Fig. 3 im Längsschnitt,
  • Fig. 6 eine Draufsicht zu Fig. 5.
Show it:
  • 1 shows a section through tapping platform and hut floor with the replacement device according to the invention,
  • 2 shows an alternative to FIG. 1 in section,
  • 3 shows a longitudinal section with the tapping channel raised,
  • 4 shows a cross section to FIG. 3,
  • 5 shows an alternative to FIG. 3 in longitudinal section,
  • 6 is a top view of FIG. 5.

In den Figuren 1 und 2 befindet sich die Abstichrinne (4) auf dem auf Schienen auf dem Hüttenflur (2) fahrbaren Transportmittel (1). Zwischen Abstichrinne und Transportmittel-Plattform erkennt man Traversen (10), die unter der Abstichrinne (4) angeordnet sind. An die Traversen (10) sind Litzenseile oder Kletterstangen (6) der Zugelemente (5) angeschlagen.In Figures 1 and 2, the tapping channel (4) is located on the transport means (1) which can be moved on rails in the hut hallway (2). Traverses (10), which are arranged under the tapping channel (4), can be seen between the tapping channel and the transport platform. Stranded ropes or climbing bars (6) of the tension elements (5) are attached to the crossbeams (10).

Die Zugelemente (5) sind auf an der Abstichbühne (3) des Schachtofens angeschweißten Stützträgern (7) angeordnet. Die Zugelemente werden von einem (hier nicht dargestellten) Hydraulik-Pumpenaggregat versorgt.The tension elements (5) are arranged on support beams (7) welded to the tapping platform (3) of the shaft furnace. The tension elements are supplied by a hydraulic pump unit (not shown here).

Fig. 2 zeigt im Unterschied zu Fig. 1 Zugelemente (5), die an den Traversen (10) der Abstichrinne (4) angeordnet sind. Hier arbeitet die Vorrichtung in umgekehrter Weise, d.h. die Zugelemente (5) ziehen sich mit der Abstichrinne (4) zur Abstichbühne (3) hoch bzw. senken sich ab.2 shows, in contrast to FIG. 1, tension elements (5) which are arranged on the crossbeams (10) of the tapping channel (4). Here the device works in reverse, i.e. the traction elements (5) are pulled up or down with the tapping channel (4) to the tapping platform (3).

Ein bekanntes Litzen- bzw. Stangen-Beförderungssystem, bei dem Lasten mit Hilfe elektrohydraulisch angetriebener Heber bewegt werden, bietet sich für die erfindungsgemäße Auswechselvorrichtung an.A known strand or rod conveying system, in which loads are moved with the aid of electrohydraulically driven lifters, is suitable for the replacement device according to the invention.

Anstelle eines derartigen Beförderungssystems können auch (nicht dargestellte) mechanisch betätigbare Spindel-Zugelemente Verwendung finden.Instead of such a transport system, mechanically actuated spindle tension elements can also be used (not shown).

Die Fig. 3 und 4 zeigen ein Ausführungsbeispiel, bei dem die Zugelemente (5) und das Hydraulik-Pumpenaggregat (8) auf einer transportablen Plattform (9) angeordnet sind. Auf die Darstellung der Hydraulikschläuche zur Verbindung von Pumpenaggregat und Zugelementen wurde verzichtet. Diese Plattform kann ein- oder mehrteilig ausgeführt sein und steht mit ihrem Füßen auf den Rinnenstützträgern (7) der Abstichbühne (3). Durch eine nur angedeutete Schäkelverbindung (12) ist die Abstichrinne (4) an den Stangen bzw. Litzen (6) der Zugelemente (5) lösbar befestigt.3 and 4 show an embodiment in which the tension elements (5) and the hydraulic pump unit (8) are arranged on a transportable platform (9). The hydraulic hoses for connecting the pump unit and tension elements have not been shown. This platform can be made in one or more parts and stands with its feet on the gutter support beams (7) of the racking platform (3). The tapping channel (4) is detachably attached to the rods or strands (6) of the tension elements (5) by means of a shackle connection (12), which is only indicated.

Sobald die Abstichrinne (4) auf das Niveau der Abstichbühne (3) angehoben ist, wird die Abstichrinne (4) mit Hilfe von seitlich unter der Abstichbühne angeordneten vor- und zurückziehbaren Trägern (11) unterstützt. Die Träger (11) werden dabei durch entsprechende Öffnungen in den Rinnen-stützträgern (7) geschoben. Sobald die Abstichrinne (4) fest auf den Trägern (11) aufliegt und die Schäkelverbindung (12) gelöst ist, kann die Plattform (9) mit den Zugelementen (5) von einem Kran entfernt werden.As soon as the tapping channel (4) is raised to the level of the tapping platform (3), the tapping channel (4) is supported with the aid of retractable and retractable supports (11) arranged laterally under the tapping platform. The supports (11) are pushed through corresponding openings in the channel support supports (7). As soon as the tapping channel (4) lies firmly on the supports (11) and the shackle connection (12) is released, the platform (9) with the pulling elements (5) can be removed by a crane.

Selbstverständlich kann das Hydraulik-Pumpenaggregat (8) auch (nicht dargestellt) beispielsweise seitlich auf der Abstichbühne (3) aufgestellt sein, wobei dann Schlauchverbindungen zu den Zugelementen (5) bestehen müssen.Of course, the hydraulic pump unit (8) can also be set up (not shown), for example on the side of the tapping platform (3), in which case hose connections to the traction elements (5) must exist.

Fig. 5 zeigt eine an Stangen bzw. Litzenseilen (6) hängende Abstichrinne (4). Die Zugelemente (5) sind hier auf der Plattform eines Drehkranzes (13) gelagert, der auf Schienen, die sich auf der Plattform (9) befinden, läuft. Der Drehkranz (13) läßt sich um 360° in der Horizontalen bewegen.Fig. 5 shows a tapping channel (4) hanging on rods or stranded ropes (6). The tension elements (5) are mounted here on the platform of a slewing ring (13) which runs on rails which are located on the platform (9). The slewing ring (13) can be moved through 360 ° in the horizontal.

Fig. 6 soll zeigen, daß es mit Hilfe des Drehkranzes (13) möglich ist, die an den Zugelementen (5) hängende Abstichrinne (4), abweichend zur auf der Abstichbühne (3) eingenommenen Position, während des Absenkens in eine andere Winkellage zu bringen. Gemäß Fig. 5 sind die Schienen für das Transportmittel auf dem Hüttenflur z.B. im rechten Winkel zur Lage der Rinne von der Abstichbühne angeordnet.Fig. 6 is to show that it is possible with the help of the slewing ring (13), the tapping channel (4) hanging on the tension elements (5), deviating from the position assumed on the tapping platform (3), during the lowering to a different angular position bring. According to Fig. 5, the rails for the means of transport are e.g. arranged at right angles to the position of the gutter from the tapping platform.

Claims (8)

1. Apparatus for exchanging tapping spouts of a shaft furnace, characterized by drawing elements (5), which support spout-supporting carriers (7), arranged on tapping platform level, and with which the tapping spout (4) is raised or lowered between shop floor (2) or another level and the tapping platform (3).
2. Apparatus according to Claim 1, characterized in that the drawing elements (5) stand on crossbars (10), which are for their part arranged on the underside of the tapping spout (4).
3. Apparatus according to Claims 1 and 2, characterized in that the drawing elements (5) are arranged with their drives (8) on a transportable one- part or multi-part platform (9), which can be set down on the spout-supporting carriers (7).
4. Apparatus according to Claims 1 to 3, characterized in that the drawing elements (5) are hydraulically driven, operate on the principle of climbing cylinders, and in that stranded wire ropes, rods (6) or the like are provided as connecting means between drawing elements (5) and tapping spout (4).
5. Apparatus according to Claims 1 to 3, characterized in that the drawing elements (5) are mechanical spindle drawing elements.
6. Apparatus according to Claims 1 to 5, characterized in that the drawing elements (5) are set up on a turntable (13).
7. Apparatus according to Claim 6, characterized in that, with arrangement of the drawing elements (5) on a turntable (13), the suspended tapping spout (4) can be rotated during lowering or raising.
8. Apparatus according to Claims 1 to 7, characterized in that the rods (6) or stranded wire ropes of the drawing elements (5) are fastened to the spout-supporting carriers (7) and the drawing elements (5) are to be drawn up and let down with the tapping spout (4).
EP88100101A 1987-02-18 1988-01-07 Apparatus for the replacement of runners of shaft furnaces Expired - Lifetime EP0279165B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AT88100101T ATE55154T1 (en) 1987-02-18 1988-01-07 DEVICE FOR REPLACING TOOLING CHANNEL ON SHAFT FURNACES.

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE3705099 1987-02-18
DE19873705099 DE3705099A1 (en) 1987-02-18 1987-02-18 DEVICE FOR REPLACING TAPPING CHANNELS ON A TUBE OVEN

Publications (2)

Publication Number Publication Date
EP0279165A1 EP0279165A1 (en) 1988-08-24
EP0279165B1 true EP0279165B1 (en) 1990-08-01

Family

ID=6321229

Family Applications (1)

Application Number Title Priority Date Filing Date
EP88100101A Expired - Lifetime EP0279165B1 (en) 1987-02-18 1988-01-07 Apparatus for the replacement of runners of shaft furnaces

Country Status (7)

Country Link
US (1) US4828228A (en)
EP (1) EP0279165B1 (en)
CN (1) CN1017157B (en)
AT (1) ATE55154T1 (en)
CA (1) CA1332507C (en)
DE (2) DE3705099A1 (en)
FI (1) FI85505C (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19532040A1 (en) * 1995-08-31 1997-03-06 Gutehoffnungshuette Man Device for transporting liquid metal in the casting hall of a shaft furnace and method for operating this device
KR101147875B1 (en) 2004-06-04 2012-06-01 파울 부르쓰 소시에떼 아노님 Servicing equipment for a blast furnace and method for using the same

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
LU91135B1 (en) * 2005-01-31 2006-08-01 Wurth Paul Sa A runner replacement device
LU91134B1 (en) * 2005-01-31 2006-08-01 Wurth Paul Sa Device for moving a runner
CN105420434B (en) * 2015-11-17 2018-04-10 南京联合荣大工程材料有限责任公司 A kind of replaceable blast furnace iron outlet groove
CN116102580A (en) 2017-03-31 2023-05-12 巴斯夫欧洲公司 Pyrimidinium compounds and mixtures thereof for combating animal pests
EP3766879A1 (en) 2019-07-19 2021-01-20 Basf Se Pesticidal pyrazole derivatives
EP4198023A1 (en) 2021-12-16 2023-06-21 Basf Se Pesticidally active thiosemicarbazone compounds
WO2023203066A1 (en) 2022-04-21 2023-10-26 Basf Se Synergistic action as nitrification inhibitors of dcd oligomers with alkoxypyrazole and its oligomers

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1018217A (en) * 1911-10-30 1912-02-20 Paul Szathmary Conveyer for molten metal.
US1535731A (en) * 1924-02-26 1925-04-28 Frank B Mckune Slag skimmer
JPS5839354Y2 (en) * 1978-01-26 1983-09-05 日本坩堝株式会社 block gutter brick
DE3302154C1 (en) * 1983-01-22 1984-05-10 Mannesmann AG, 4000 Düsseldorf Rocking runner device for pig iron or slag, particularly for location in the blast furnace field
DE3624266A1 (en) * 1986-07-18 1988-01-21 Gutehoffnungshuette Man Apparatus for exchanging main tapping launders on blast furnaces

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19532040A1 (en) * 1995-08-31 1997-03-06 Gutehoffnungshuette Man Device for transporting liquid metal in the casting hall of a shaft furnace and method for operating this device
DE19532040C2 (en) * 1995-08-31 1999-05-27 Schloemann Siemag Ag Device for transporting liquid metal in the casting hall of a shaft furnace and method for operating this device
KR101147875B1 (en) 2004-06-04 2012-06-01 파울 부르쓰 소시에떼 아노님 Servicing equipment for a blast furnace and method for using the same

Also Published As

Publication number Publication date
DE3705099A1 (en) 1988-09-01
ATE55154T1 (en) 1990-08-15
CA1332507C (en) 1994-10-18
CN1017157B (en) 1992-06-24
EP0279165A1 (en) 1988-08-24
CN88100874A (en) 1988-08-31
FI880495A (en) 1988-08-19
FI85505B (en) 1992-01-15
US4828228A (en) 1989-05-09
FI880495A0 (en) 1988-02-03
FI85505C (en) 1992-04-27
DE3860370D1 (en) 1990-09-06

Similar Documents

Publication Publication Date Title
DE69914721T2 (en) Method and device for briefly relining or designing a blast furnace
DE4431503B4 (en) Machine for preparing welding work on a track
DE102006015307A1 (en) Mobile large crane
EP0279165B1 (en) Apparatus for the replacement of runners of shaft furnaces
DE2644260A1 (en) METHOD OF BUILDING A BOTTOM FURNACE
DE1533903B2 (en) Steel mill converter brick lining device
DE1658641C3 (en) Device for the production and assembly of a vertical nozzle bridging support or the like
EP0043078A2 (en) Method and apparatus for lifting or sinking buildings or parts thereof by using hydraulic-jack units which can be individually steered or grouped
EP2386515A1 (en) Transformer exchange
DE10149367B4 (en) Method and changing device for removing or installing assemblies of an electric arc furnace
DE3624266A1 (en) Apparatus for exchanging main tapping launders on blast furnaces
DE1508298B2 (en) Steel mill
DE102014224649B3 (en) Lifting system for a metallurgical plant, metallurgical plant and method for vertically displacing a component of a vessel unit
DE7833497U1 (en) MELT TREATMENT DEVICE WITH A LONG, TILTABLE TUBE
WO2015139984A1 (en) Apparatus for vertically raising and/or lowering a metallurgical vessel, facility having such an apparatus and method
EP0111283B1 (en) Suspended apparatus for changing tuyère stock assemblies
EP1661843B1 (en) Method for transferring a heavy load and lifting accessories for a lifting apparatus
DE1945262A1 (en) Swap body equipment for metallurgical purposes
AT217490B (en) Infeed device for metallurgical vessels such as crucibles or converters
DE1658602B1 (en) Device for assembling the prefabricated components of a prestressed concrete bridge, each comprising a complete bridge section, in cantilevered cantilevered sections
DE3122892C2 (en)
DE102009003917A1 (en) Two-position stand for pouring ladles in continuous casting plants, comprises two pan stools for setting through crane of the pouring ladles, where one of the pan stools is directly situated over splitter in the plant
DE2426232A1 (en) Ceramic firing tunnel kiln - comprises steel support structure for prefabricated brickwork
DE4333250A1 (en) Apparatus and method for mounting and dismounting bridges, in particular temporary bridges, in existing railway tracks
EP4001046A1 (en) Maintenance device for railway vehicles, running gear of a railway vehicle and maintenance method

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE DE FR GB IT

17P Request for examination filed

Effective date: 19880906

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: MAN GUTEHOFFNUNGSHUETTE AKTIENGESELLSCHAFT

17Q First examination report despatched

Effective date: 19900124

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE DE FR GB IT

REF Corresponds to:

Ref document number: 55154

Country of ref document: AT

Date of ref document: 19900815

Kind code of ref document: T

REF Corresponds to:

Ref document number: 3860370

Country of ref document: DE

Date of ref document: 19900906

ITF It: translation for a ep patent filed

Owner name: BARZANO' E ZANARDO MILANO S.P.A.

ET Fr: translation filed
GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)
PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
ITTA It: last paid annual fee
PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 19971223

Year of fee payment: 11

REG Reference to a national code

Ref country code: FR

Ref legal event code: TP

REG Reference to a national code

Ref country code: GB

Ref legal event code: 732E

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 19990107

REG Reference to a national code

Ref country code: FR

Ref legal event code: TP

REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20030110

Year of fee payment: 16

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20030122

Year of fee payment: 16

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20040108

Year of fee payment: 17

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040131

BERE Be: lapsed

Owner name: *THYSSEN KRUPP STAHL A.G.

Effective date: 20040131

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20040930

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.

Effective date: 20050107

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050802

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20051219

Year of fee payment: 19

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20070107

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20070107