EP0197021A1 - Verfahren zum Bauen eines Tunnels - Google Patents
Verfahren zum Bauen eines Tunnels Download PDFInfo
- Publication number
- EP0197021A1 EP0197021A1 EP86870032A EP86870032A EP0197021A1 EP 0197021 A1 EP0197021 A1 EP 0197021A1 EP 86870032 A EP86870032 A EP 86870032A EP 86870032 A EP86870032 A EP 86870032A EP 0197021 A1 EP0197021 A1 EP 0197021A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- tunnel
- successive
- reinforced concrete
- shells
- vertical
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
Definitions
- the present invention relates to a method for making a tunnel by means of prefabricated concrete elements, joined together on site by concreting.
- the tunnels are produced either by pouring successive tunnel sections in place, or by aligning prefabricated tunnel sections.
- the tunneling process which consists of aligning prefabricated tunnel sections allows the length of the site to be reduced.
- the prefabricated sections are placed, the backfilling and finishing work can be carried out.
- the process according to the present invention in fact calls upon a certain number of standardized prefabricated elements, of relatively reduced weight (approximately 10 tonnes), the handling of which requires only more mobile lifting devices, of the type commonly used on most Construction sites.
- These lifting devices can be automobile cranes, which do not need to be mounted on rails.
- the use of standardized prefabricated elements makes it possible for the process of the invention to make tunnels of small section and tunnels of larger section, for example for large gauge metro, underground railway, etc., by juxtaposing a greater or lesser number of these standardized elements.
- the method according to the invention makes it possible to vary the section of the tunnels, which can thus pass from a minimum section (for a single tunnel section of line) to a maximum section (sections of tunnel comprising stations, with landing platforms, waiting rooms, etc.) passing through intermediate sections.
- the subject of the present invention is a method for producing a tunnel by means of prefabricated concrete elements, which are joined together by concreting, after placement.
- the successive phases of realization of the tunnel are executed in order along the site, from the advancement front where the earthworks and the front excavation of the excavation are done to the area where the backfilling and the covering of the completed tunnel are done.
- the vertical elements partially constituting the side walls of the tunnel are oblong shells of reinforced concrete having a cylindrical arch whose generator is parallel to the major axis of the shells; these shells are closed at each of their ends by a base in half line, perpendicular to their major axis.
- These shells are arranged in such a way that their concavity is directed towards the interior of the tunnel, and that their vault is directed towards the walls of the trench.
- the shells have two flat and parallel longitudinal sides extending the arch on each side thereof.
- An advantageous embodiment of these elements has, on the outside of the vault, a substantially planar rear face which is connected perpendicular to the lateral faces of the element, which are also substantially planar.
- the shells have on the outer faces of the longitudinal sides two grooves parallel to the major axis of the shells, capable of receiving the lateral edges of the two formwork plates.
- the grooves located near the free edge of the plane longitudinal sides of the hulls, and therefore located on the inside of the tunnel are widened at their upper part, so as to constitute close to the level which the edge will occupy. upper side of the plate in place, shoulders on which the end of a lintel sits.
- the reinforced concrete footings as well as the connecting footings ensuring continuity between them are provided, on their upper bearing face, with a rebate parallel to the axis of the tunnel and directed towards the interior of the tunnel.
- the assembly of a beam, of the two reinforced concrete columns which support each of the ends of this beam and the footings supporting each of these reinforced concrete columns, forms a gantry capable of taking up the vertical pressures exerted by the earth and the roads. higher, as well as the horizontal earth pressure.
- the method according to the invention has a number of advantages.
- the arch shape of the hulls preferably used offers the advantage of taking up the horizontal loads of pushing the earth after backfilling behind the side walls of the tunnel with relatively thin partitions and not requiring additional reinforcements.
- the hulls can be prefabricated in molds specially made for this purpose but, for small series, it is more economical to use molds of standardized shape, generally of rectangular section.
- the face turned towards the outside of the tunnel is practically planar and is connected perpendicular to the lateral faces, which are also practically planar.
- Such an embodiment coincides with the form of standard molds.
- the number of prefabricated elements used being reduced (indeed, it mainly comprises only the footings, vertical elements forming the vertical walls, lintels, upper beams and slabs), the installation of these is a series of repeated operations, which promotes speed of execution.
- the construction of a heavy-type metro tunnel can progress at the rate of approximately 3 running meters per day.
- the disturbance caused to residents is therefore minimal, thanks to the speed of execution and therefore thanks to the mobility of the site.
- the site is all the more mobile as the site facilities are reduced, thanks in particular to the manufacture of a maximum of elements off the site (prefabrication in the factory).
- the process according to the invention also lends itself to the construction of tunnels in an aquiferous environment, thanks to the arrangement of the hulls, which will thus serve as a passage for sheets as will be described below. It is indeed important in the case of aquifers, not to oppose the movements of groundwater.
- the process allows to marry the various unevennesses of the ground as well as the changes of direction imposed by the layout, while using the majority of the prefabricated elements above.
- the method also lends itself to the production of tunnels of various widths, for example, narrow in a straight line, wide at the station, passing through intermediate sections connecting the narrow sections and the wide sections. As will be described below, these different widths are produced with the available prefabricated elements already described.
- the process according to the invention makes it possible to combine the structural work and the finishing touches; in particular inside the stations one can take advantage of the shape of the hulls.
- the dimensions of these shells can vary between relatively wide limits, but according to a particular and advantageous embodiment of the invention, the width of these shells is between 2 and 3 meters.
- the walls of the stations present species of niches, which can be fitted out, as required, for example, by installing telephone booths, automatic distributors, benches, etc.
- the benches can advantageously be continuous or interrupted ribs cast in the mass during the manufacture in the factory of the shells.
- the shells forming the walls of the tunnel between the stations can be arranged to receive electrical devices such as junction boxes, lighting, signaling devices, etc.
- the particular configuration of the walls can also be used advantageously acoustically. Indeed, sounds are picked up by the surface of the walls, which considerably lowers the acoustic level and thus improves the comfort of tunnel users, especially passengers waiting at stations.
- prefabricated reinforced concrete footings 1 of generally rectangular shape, the upper face 2 of which has a rebate 3, are deposited on the bottom of the trench, leaving a space between the successive soles 1.
- Each sole is arranged so as to be perpendicular to the vertical walls of the tunnel to be constructed, so that the rebate 3 is directed towards the interior of the tunnel.
- each connecting flange 4 also has on its upper face 6 a rebate 7 connecting the rebates 3 of two successive flanges 1.
- Oblong reinforced concrete shells 8 having a cylindrical vault 9 whose generatrix is parallel to their major axis, two plane longitudinal sides 10 extending this vault 9 on each side, and closed by a base, 11 in half-moon at each of their ends, are arranged on each continuous base 5, so as to provide an interval between successive shells 8, and so that their vault 9 is directed towards the wall of the trench and, consequently, that their concavity is directed towards the interior of the tunnel.
- the shells 8 are placed in such a way that each shell 8 is supported both on two successive flanges 1 and therefore that.
- the interval between two successive shells is located in line with a sole 1.
- the shells 8 are placed by means of a positioning mannequin carrying a pair of shells 8, so as to simultaneously place two shells 8 on each side of the tunnel, one in line with the other.
- the interval between two successive shells 8 is closed, on the side of the wall of the trench, by an exterior formwork plate 12 and, on the interior side of the tunnel, by an interior formwork plate 13.
- the two formwork plates 12, 13 are spaced apart and are arranged parallel to the axis of the tunnel.
- the formwork plates 12, 13 are, for example, made of asbestos-cement and delimit, with the external faces 14 of the sides 10 facing two successive shells 8, a vertical space between two successive shells 8. In this vertical space is inserted a concrete reinforcement 15.
- the external formwork plates 12 have substantially the same height as the vertical elements 8.
- the internal formwork plates 13 are significantly lower.
- a lintel 16 which is supported by its ends, on the sides 10 facing two successive shells 8, as will be described later.
- Transverse upper beams 17 are then placed perpendicular to the axis of the tunnel, so as to rest at each of their ends on lintels 16 facing each other.
- the transverse upper beams 17 in turn support upper reinforced concrete slabs 18, arranged so that each slab 18 is supported by its front edge on a transverse upper beam 17, and by its rear edge on the upper beam transverse 17 next, relative to the direction of advancement of the site, and also so that the lower surface of the slabs 18 is at the same level as the lower surface of the bases 11 in upper half-moon of the shells 8, so as to present these a continuous surface which can be left bare and constitute the ceiling of the tunnel, between the upper transverse beams 17.
- the bases 11 in a half-moon have a thickness - (about 14 cm) greater than that of the slabs 18 - ( about 5 cm) and therefore protrude above the upper surface of the slabs 18.
- the edge of the bases 11 in the upper half-moon advantageously constitutes with the upper edge of the formwork plates e exteriors 12 a side formwork for pouring the upper slab 19.
- a slab 21 is then poured between the two continuous bases 5 formed by the flanges 1 and the connecting flanges 4, cast therebetween, so as to cover the rebates 3 and 7.
- This slab 21 will support gutters 22 intended for passage cables, pipes, etc., as well as the track infrastructure, for example the ballast 23 of a railway 24.
- the tunnel Before the final backfilling, the tunnel is plugged in order to seal it.
- Fig. 2 is a view, on a large scale, of three successive shells 8, showing the external 12 and internal 13 formwork plates and the lintels 16 on which the upper transverse beams 17 are supported before joining with the reinforced concrete columns 20 poured into the intervals between the successive shells 8.
- the shells 8 have, on the outer faces 14 of the plane and parallel longitudinal sides 10 of the shells 8, two grooves 25, 26 parallel to the major axis thereof; the grooves 25 located on the side of the wall of the trench of two external faces 14 facing two successive shells 8 receive and guide the lateral edges of an external formwork plate 12.
- This external formwork plate 12 constitutes the connection between two successive shells 8, on the outside of the tunnel, and thus ensures the continuity of the outside side wall of the tunnel.
- the plates 12 have substantially the same length as the shells 8 and their small upper edge arrives at substantially the same height as the upper surface of the base 11 in the half-moon shape of the shells 8.
- the grooves 26 located near the free edges of the longitudinal sections, therefore on the inside of the tunnel with two exterior faces 14 facing two successive shells 8 receive and guide the lateral edges of an interior formwork plate 13.
- This inner plate 13 constitutes the inner connection between two successive shells 8, and therefore the continuity of the inner wall of the tunnel.
- the interior plates 13 and the interior of the concavity of the shells 8 can advantageously be left bare, thus participating by their shapes and by a judicious choice of their colors, in the interior decoration of the tunnel. , in particular the law of underground stations and other places accessible to the public.
- the interior plates 13 have a length less than that of the shells 8.
- the space situated above the small upper edge of each interior plate 13 is occupied by a lintel 16 and by the end of the transverse beam 17 which it supports.
- this beam 17 is offset downwards by a distance equal to the added thicknesses of the slabs 18 and of the upper slab 19, so that the upper surface of the upper slab 19 is at the same level as the upper surface of the bases. 11 in the upper half-moon of the shells 8, the edge of these bases 11 thus acting as lateral formwork for the upper slab 19, with the upper edge of the external formwork plates 12.
- the grooves 26 located near the free edges of the longitudinal sections are widened at their upper part, so as to constitute, near the level of the upper edge of the internal formwork plate, shoulders 27 on which the end of a lintel sits. 16.
- Fig. 3 is a partial view, on a larger scale, of the junction zone between two shells constituting the side walls of the tunnel, showing another method of fixing the lintels.
- the shells 28 have, on the free edges of each of their plane and parallel longitudinal sections 29 in the vicinity of their base 30 in an upper half-moon, recesses 31 corresponding to the cross section of the lintels 32, and capable of receiving the ends of these lintels 32.
- Each lintel is thus received by its ends in the recesses 31 of two contiguous sides 29 of two successive shells 28 and is supported by shoulders 33. It is held in place by studs 34.
- Fig. 4 is a section, on a larger scale, of the junction zone between two shells 8, and shows in particular the position of the armature 15 inserted in the vertical space delimited by the shells 8 and by the outer plates 12 and interior 13, which are guided and held respectively by grooves 25 and 26, in which U-shaped steel sections 35 are embedded.
- the method according to the invention has the advantage of allowing the tunnel to follow the various unevennesses of the terrain as well as the height changes imposed by the layout.
- FIG. 5 to 7 An example of such a tunnel is illustrated in Figs. 5 to 7, in which the elements common to all the embodiments described have the same reference numbers.
- Figs. 5 and 6 illustrate a straight-aligned tunnel whose incline is sloping.
- the different production phases are the same as those described above for the construction of a straight and horizontal tunnel.
- the difference in level between two successive shells 8 is determined by the positioning and adjustment of the reinforced concrete footings 1.
- the difference in level between two successive flanges 1 requires the use of lintels 37 of a particular type.
- a lintel of this type as illustrated in FIG. 7, has at its upper surface two half-bearing surfaces 38 and 39 offset, separated by a rung 40 whose height is equal to the difference in level between two successive shells 8.
- the ends of two half-beams 41 and 42 (Fig. 5) will come to bear respectively on the half-surfaces 38 and 39. These beams 41 and 42 are, therefore, offset in height one relative to the other.
- connection with the vertical columns of the half-beams 41, 42 is done in the same way as in the case of a tunnel with a horizontal attitude, as described above (Insertion of a frame 15 in the vertical space between two successive shells 8, pouring a vertical column 20, securing each of the half-beams 41 and 42 therewith).
- the highest half-beam 42 of a pair of half-beams 41, 42 is at the same height as the lowest half-beam 41 of the next pair of half-beams 41, 42, a pre-slab 18 pressing at its ends on a half-beam 42 of a pair of half-beams 41, 42 and on the half-beam 41 of the next pair, will therefore be substantially horizontal.
- the tunnel completion works (concreting the upper slab, waterproofing, covering) are then carried out as described above.
- Fig. 8 illustrates an example of a curved tunnel, in which the elements common to all the embodiments have the same reference numbers.
- the construction phases of a curved tunnel are the same as before.
- the interval between the soles 1 of the row situated outside the curve is greater than the interval between the soles 1 of the row situated inside the curve.
- the connecting soles 43 cast in the intervals of the outer row will therefore be wider than the connecting soles 44 cast between the soles 1 of the inner row.
- the interval between two shells 8 situated outside the curve of the tunnel is also greater than the interval between two interior shells 8.
- the outer closure plates 45 between the shells 8 of the row located outside the curve will be wider than the outer closure plates 46 between the shells 8 of the row located inside the curve.
- the interior closure plates 47 of the exterior row of shells 8 will be wider than the interior closure plates 48 of the interior row of shells 8.
- Fig. 9 illustrates an example of a tunnel constructed in an aquifer.
- the section illustrated is in a straight line, but it goes without saying that the method applies as well to a tunnel in curved alignment as to a tunnel whose attitude is sloping.
- the tunnel section then comprises shells 53, the roof 54 of which is provided with openings 55 which put the interior of the latter in communication with the surrounding medium, and consequently allowing the passage of water.
- the cavity of these shells 53 is closed over the entire height by a vertical partition 56, provided with an access hole 57 - (Fig. 10). The interior of these shells thus fills with water to a level equal to the level of the sheet.
- a transverse pipe 58 located below the raft 21 and held by connecting flanges 59 between prefabricated flanges 1, connects two shells 53 on each side of the tunnel and facing each other.
- This pipe 58 is connected to the lower part of each shell 53 by an orifice 60 and allows the passage of the groundwater and the establishment of the equilibrium of the levels thereof on each side of the tunnel.
- the method according to the invention is not limited to the production of simple tunnels, such as those described above, and an example of which is illustrated in section in FIG. 11, allowing circulation along two parallel lanes, but also lends itself to the production of tunnels of greater width, for example, a tunnel of double width, as illustrated in section in FIG. 12.
- This tunnel comprises intermediate soles 6 1 arranged along the median axis of the tunnel, between the soles 1 of a pair of soles.
- These intermediate flanges 61 support intermediate columns 62.
- Each of these columns 62 supports the inner ends of two upper beams 63 perpendicular to the axis of the tunnel, the outer ends of which are supported by lintels and concreted with vertical columns (not shown) as described above
- the beams 63 are joined together and with the column 62 which supports them, the assembly thus obtained forming a double gantry, supported by the flanges 1 and the intermediate flange 61.
- Fig. 13 shows a particular embodiment of a double tunnel, using upper beams 6 4 of greater length, which allows the development of a central landing platform 65, between the traffic lanes.
- the width of the tunnel can be increased as desired, as required, thanks to the multiplication of intermediate elements (footings, columns 62, upper beams, etc.).
- the method according to the invention also lends itself to the production of intermediate tunnel sections, for joining, for example, a single tunnel section (line) to a double tunnel section - (station), passing through widths intermediaries.
- Fig. 14 shows a section along a horizontal plane, halfway up, of an advantageous embodiment of a shell 8 constituting a part of the vertical wall of a tunnel produced according to the invention.
- the face turned towards the outside of the tunnel 65 on the side opposite to the vault 9 is planar and is connected perpendicular to the lateral faces 14, which are practically planar of the shell 8.
- These external faces are also advantageously provided with their own grooves 66 to improve the joining of these elements and of the reinforced concrete columns between which they are placed.
- Recesses 67 are provided between the arch 9 and the flat rear face 65 so as to keep the shells thus produced their lightness. These recesses 67 are produced according to a known method, such as the insertion into the molds of polystyrene cores.
- This embodiment makes it possible to reinforce the rigidity of the structure of an element.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FR8503619 | 1985-03-12 | ||
FR8503619A FR2578904B1 (fr) | 1985-03-12 | 1985-03-12 | Procede pour la realisation d'un tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0197021A1 true EP0197021A1 (de) | 1986-10-08 |
EP0197021B1 EP0197021B1 (de) | 1988-10-19 |
Family
ID=9317112
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP19860870032 Expired EP0197021B1 (de) | 1985-03-12 | 1986-03-12 | Verfahren zum Bauen eines Tunnels |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP0197021B1 (de) |
DE (2) | DE3660969D1 (de) |
FR (1) | FR2578904B1 (de) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4880334A (en) * | 1988-04-11 | 1989-11-14 | Finic, B.V. | Tunnel construction apparatus and method |
ES2052433A2 (es) * | 1992-02-13 | 1994-07-01 | Codelfa Prefabbricati S P A | Sistema para la construccion de galerias artificiales con elementos prefabricados de hormigon. |
US6234716B1 (en) * | 1995-11-17 | 2001-05-22 | Carlo Chiaves | Underground structural work including prefabricated elements associated with piles and a process for its production |
FR2843977A1 (fr) * | 2002-08-28 | 2004-03-05 | Conseil Service Investissement | Procede de realisation d'une plate-forme enjambant une tranchee au moyen de longerons prefabriques |
WO2012177143A2 (en) | 2011-06-21 | 2012-12-27 | Stabinor As | A method for constructing a tunnel course, and structural element for use by the method |
CN112576260A (zh) * | 2020-12-14 | 2021-03-30 | 中铁二院工程集团有限责任公司 | 拱盖法进洞施工方法以及拱盖法进洞支护结构 |
CN112576259A (zh) * | 2020-12-14 | 2021-03-30 | 中铁二院工程集团有限责任公司 | 拱盖法车站从主体进附属施工方法及结构 |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112049032B (zh) * | 2020-07-27 | 2022-05-17 | 成龙建设集团有限公司 | 一种市政公路门洞的加固方法 |
CN114017079B (zh) * | 2021-10-29 | 2023-10-13 | 国能神东煤炭集团有限责任公司 | 用于煤矿井下沿空掘巷的巷道支护装置 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1746566A (en) * | 1927-08-31 | 1930-02-11 | Robert B Tufts | Sewer construction |
FR685548A (fr) * | 1928-11-29 | 1930-07-11 | éléments en béton-armé pour la construction des conduits, des puits, des galeries de mines, etc. | |
FR2082092A5 (de) * | 1970-03-03 | 1971-12-10 | Gtmtp | |
FR2126202A1 (de) * | 1971-02-22 | 1972-10-06 | Sbaraglia Goffredo | |
FR2223513A1 (en) * | 1973-03-30 | 1974-10-25 | Socea | Tunnel made from prefabricated sections - has roof slab supported on shoulders extending from upper face of walls |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE519036C (de) * | 1928-11-30 | 1931-02-23 | Ernst Arnold | Eisenbetonplatte zum Aufbau von Waenden in Schaechten, Stollen u. dgl. |
-
1985
- 1985-03-12 FR FR8503619A patent/FR2578904B1/fr not_active Expired
-
1986
- 1986-03-12 EP EP19860870032 patent/EP0197021B1/de not_active Expired
- 1986-03-12 DE DE8686870032T patent/DE3660969D1/de not_active Expired
- 1986-03-12 DE DE1986870032 patent/DE197021T1/de active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1746566A (en) * | 1927-08-31 | 1930-02-11 | Robert B Tufts | Sewer construction |
FR685548A (fr) * | 1928-11-29 | 1930-07-11 | éléments en béton-armé pour la construction des conduits, des puits, des galeries de mines, etc. | |
GB335816A (en) * | 1928-11-29 | 1930-10-02 | Ernst Arnold | Reinforced concrete unit for the construction of shafts, tunnels and the like |
FR2082092A5 (de) * | 1970-03-03 | 1971-12-10 | Gtmtp | |
FR2126202A1 (de) * | 1971-02-22 | 1972-10-06 | Sbaraglia Goffredo | |
FR2223513A1 (en) * | 1973-03-30 | 1974-10-25 | Socea | Tunnel made from prefabricated sections - has roof slab supported on shoulders extending from upper face of walls |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4880334A (en) * | 1988-04-11 | 1989-11-14 | Finic, B.V. | Tunnel construction apparatus and method |
ES2052433A2 (es) * | 1992-02-13 | 1994-07-01 | Codelfa Prefabbricati S P A | Sistema para la construccion de galerias artificiales con elementos prefabricados de hormigon. |
US6234716B1 (en) * | 1995-11-17 | 2001-05-22 | Carlo Chiaves | Underground structural work including prefabricated elements associated with piles and a process for its production |
FR2843977A1 (fr) * | 2002-08-28 | 2004-03-05 | Conseil Service Investissement | Procede de realisation d'une plate-forme enjambant une tranchee au moyen de longerons prefabriques |
WO2012177143A2 (en) | 2011-06-21 | 2012-12-27 | Stabinor As | A method for constructing a tunnel course, and structural element for use by the method |
CN112576260A (zh) * | 2020-12-14 | 2021-03-30 | 中铁二院工程集团有限责任公司 | 拱盖法进洞施工方法以及拱盖法进洞支护结构 |
CN112576259A (zh) * | 2020-12-14 | 2021-03-30 | 中铁二院工程集团有限责任公司 | 拱盖法车站从主体进附属施工方法及结构 |
CN112576259B (zh) * | 2020-12-14 | 2022-04-15 | 中铁二院工程集团有限责任公司 | 拱盖法车站从主体进附属施工方法及结构 |
Also Published As
Publication number | Publication date |
---|---|
FR2578904A1 (fr) | 1986-09-19 |
DE3660969D1 (en) | 1988-11-24 |
DE197021T1 (de) | 1987-01-15 |
EP0197021B1 (de) | 1988-10-19 |
FR2578904B1 (fr) | 1987-07-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0180667B1 (de) | Vorgefertigte Baueinheiten und Gebrauch im Hochbau | |
EP1101871B1 (de) | Brückenoberbau aus Stahl und Verfahren zur Herstellung einer diesen Oberbau enthaltenden Brücke | |
EP0463925B1 (de) | Verfahren zur Herstellung eines halbunterirdischen Bauwerks an einem Bergabhang und auf diese Weise hergestelltes Bauwerk | |
EP0489054B1 (de) | Zellulare strukturen zum stützen von wänden | |
EP0060230A1 (de) | Tragkonstruktion aus einem Konglomerat oder armiertem Beton, insbesondere gegen Erdbeben, für ebene sowie gewölbte oder bogenförmige Konstruktionen, hergestellt aus Modul-Elementen | |
EP0102340A2 (de) | Verfahren zur Herstellung von Stahlbetonbauten wie unterirdischen Strecken, Strassentunnels usw; vorgefertigte Betonelemente für die Herstellung solcher Bauten | |
EP0197021B1 (de) | Verfahren zum Bauen eines Tunnels | |
FR2612988A1 (fr) | Structure de tunnel pour recouvrir une voie routiere ou ferroviaire encaissee | |
EP0560660B1 (de) | Mehrstöckige Untergrundgaragen und Bauverfahren dafür | |
EP0242497B1 (de) | Tunnelbauverfahren | |
BE1001360A3 (fr) | Pont semi-prefabrique. | |
FR2672937A1 (fr) | Structure tubulaire enterree et son procede de realisation. | |
CH434335A (fr) | Procédé de construction d'un passage sous voie et installation pour la mise en oeuvre de ce procédé | |
EP0424223A1 (de) | Verfahren zum schnellen Herstellen von zwei übereinander liegenden Strassen mit einem auf der bestehenden Strasse verlegten Bauwerk, ohne den Verkehr zu behindern | |
FR2824851A1 (fr) | Appui de pont prefabrique | |
FR2558868A1 (fr) | Procede de construction de parois de batiments ou autres murs, et element de coffrage pour sa mise en oeuvre | |
EP1211355A1 (de) | Unterbaumauer für eine Konstruktion und Verwirklichungsverfahren | |
FR2774106A1 (fr) | Dispositif de protection routiere et procede de realisation d'un tel dispositif | |
EP0321321B1 (de) | Gebäude mit vorgefertigten Elementen | |
EP1119663B1 (de) | Rohrförmige anlage | |
EP0004998A2 (de) | Baustruktur | |
FR2610339A1 (fr) | Procede de realisation de soubassements d'immeubles et moyens pour mettre en oeuvre ledit procede | |
FR2839990A1 (fr) | Ouvrage d'art prefabrique et procede de mise en place de l'ouvrage d'art | |
WO2007104838A1 (fr) | Ouvrage de passage couvert | |
FR2637306A1 (fr) | Element de construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): BE DE FR |
|
17P | Request for examination filed |
Effective date: 19860919 |
|
R17P | Request for examination filed (corrected) |
Effective date: 19860919 |
|
DET | De: translation of patent claims | ||
17Q | First examination report despatched |
Effective date: 19871201 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): BE DE FR |
|
REF | Corresponds to: |
Ref document number: 3660969 Country of ref document: DE Date of ref document: 19881124 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 19900313 Year of fee payment: 5 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 19910228 Year of fee payment: 6 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Effective date: 19910331 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 19910515 Year of fee payment: 6 |
|
BERE | Be: lapsed |
Owner name: S.A. ENTREPRISES KOECKELBERG Effective date: 19910331 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Effective date: 19921130 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Effective date: 19921201 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST |