US1746566A - Sewer construction - Google Patents

Sewer construction Download PDF

Info

Publication number
US1746566A
US1746566A US216626A US21662627A US1746566A US 1746566 A US1746566 A US 1746566A US 216626 A US216626 A US 216626A US 21662627 A US21662627 A US 21662627A US 1746566 A US1746566 A US 1746566A
Authority
US
United States
Prior art keywords
slabs
sewer
sides
floor
monolithic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US216626A
Inventor
Robert B Tufts
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US216626A priority Critical patent/US1746566A/en
Application granted granted Critical
Publication of US1746566A publication Critical patent/US1746566A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench

Definitions

  • Figure l is a perspectiv view of a portion of a sewer constructed according to the present invention.
  • Figure 2 is an enlarged transverse section of the same
  • Figure 3 is an enlarged detail perspective view of one of the joints in the side walls seen in Fig. l;
  • FIGS. 4 and 5 are plan views showing other-forms of joints
  • FIG. 6 is a detail elevation
  • Figure 7 is a section showing a variation in the joint between the side andthe bottom of the sewer.
  • I provide a plurality of precast slabs l of reenforcedconcrete which are employed to form the sides of j the sewer, and are preferably provided in their side edges with grooves 2 adapted to register when the slabs are set up edge to edge.
  • a recess or channel is thus formed into which grout, indicated at 3, is poured so as to key the adjacent slabs together and seal the joints against leakage of the matter flowing through the sewer.
  • Each slab y is provided on one face with a projecting ledge l at an intermediate point in its height for a purpose which will presently appear, it being noted that the under surface of the ledge is at a right angle ⁇ to the face of the slab while the upper surface of the ledge is inclined and merges into the face ofthe slab. While I have shown the grooves 2 as terminating short of the lower ends of the slabs, ⁇ it will be understood that they may Open through the slab end.
  • the slabs 1 are molded and permitted to set 85 before being ⁇ placed in position and may be castjat a central plant and shipped to the point of use, and, being thus produced under factory conditions can be more Cheap-ly and uniformly made than could be done in the field While contending with mud and water in The reenforcements can also be may be used.
  • The'joints between the slabs are made sand and water tight and the sides are so firmly anchored and braced that even a soft wet earth is held against sliding into the ditch.
  • the slabs may have sockets l1 formed therein, asin Fig. 6, so that when the floor is poured it will be automatically keyed to the sides, as indicated at 12 in Fig. 7.
  • a sewer consisting'of sides each composedr of'a plurality of preformed slabs set edge to edge with their lower ends embedded in the ground and the meeting edges sealed, a monolithic floor formed between the sides, and a monolithic roof formed over and carried by the sides.
  • a sewer consisting of sides each composed of preformed slabs of concrete set on end and edge to edge with their lower ends embedded in the ground and their meeting edges sealed, a monolithic cementitious floor formed between the sides and' interlocked therewith, and a. monolithic cementitious roof formed over and carried bv and interlocked with the sides.
  • a sewer composed of sides each consisting of preformed concrete slabs set edge to edge with their lower ends embedded in the ground and 'their meeting edges sealed and provided above their lower ends with lateral projections, a monolithic floor vformed between the sides and abutting the under surfaces of said projections, and a monolithic roof cast on and carried by the sides.
  • sewer construction which consists in forcing preformed concrete slabs into the ground in two rows along the line of the sewer to form the sewer side walls, sealing the joints between the slabs, pouring a monolithic cementitious floor between the rows of slabs at a level above the lower ends thereof, the floor uniting with the sides and pouring ay monolithic cementitious roof at and across the upper ends of the slabs.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)
  • Building Environments (AREA)

Description

Feb. 11, 1930. R B, TUFTS I 1,746,566
SEWER CONSTRUCTION Filed Aug. 3l, 1927 MMW www ,Patented Feb. 11, 1930 UNITED STATES PATENT OFFICE i` SEWER CONSTRUCTION Application filed August 31, 1927. Serial No. 216,626.
Apointed out in the appended Claims.
In the drawing, Figure l is a perspectiv view of a portion of a sewer constructed according to the present invention;
Figure 2 is an enlarged transverse section of the same;
Figure 3 is an enlarged detail perspective view of one of the joints in the side walls seen in Fig. l;
j Figures 4 and 5 are plan views showing other-forms of joints;
Figure 6 is a detail elevation, and
Figure 7 is a section showing a variation in the joint between the side andthe bottom of the sewer.
In carrying out the invention, I provide a plurality of precast slabs l of reenforcedconcrete which are employed to form the sides of j the sewer, and are preferably provided in their side edges with grooves 2 adapted to register when the slabs are set up edge to edge. A recess or channel is thus formed into which grout, indicated at 3, is poured so as to key the adjacent slabs together and seal the joints against leakage of the matter flowing through the sewer. Each slab yis provided on one face with a projecting ledge l at an intermediate point in its height for a purpose which will presently appear, it being noted that the under surface of the ledge is at a right angle `to the face of the slab while the upper surface of the ledge is inclined and merges into the face ofthe slab. While I have shown the grooves 2 as terminating short of the lower ends of the slabs,` it will be understood that they may Open through the slab end.
In building a sewer according to the present invention, I first excavate along the line the sewer is to follow and approximately to the ditch. more Vaccurately placed so that thinner slabs the desired depth. I then force into the soil, at the two sides of the ditch, rows of the slabs l to such depth that their lower ends will be below the subgrade 5 of the sewer. The grout 3 may be poured as the successive slabs are 55 placed so that it may set while subsequent Operations are being performed. When two i rows of slabs have been properly positioned to form the sides of the proposed sewer, they are braced apart by jacks or other devices now commonly employed for simi- `lar purposes and excavating then continued to the subgrade 5, whereupon plastic concrete is poured to cover the bottom ofthe excavation and form a monolithic iioor for the sewer, as shown at 6. It will be understood that metallic reenforcing elements may be laid in the floor as the concrete is poured and-it will be noted the floor is formed of such thickness that it abuts the under surfaces ofthe projections. 4f which, consequently, resist upward movment of the floor from pressure below while the floor resists downward movement of the sides. Afterthe floor has set, suitable falseworkis arranged at the top of the sides and concrete is then poured to form the monolithic top or roof 7, it being noted that ribs or shoul- Y ders 8 are formed on the under side of the roof to abut the side slabs and brace the side walls against Collapse from pressureof the surrounding earth. As the roof sets, the falsework is withdrawn and the spaces at the sides of and over the sewer are filled in the usual manner. 3
` The slabs 1 are molded and permitted to set 85 before being `placed in position and may be castjat a central plant and shipped to the point of use, and, being thus produced under factory conditions can be more Cheap-ly and uniformly made than could be done in the field While contending with mud and water in The reenforcements can also be may be used. The'joints between the slabs are made sand and water tight and the sides are so firmly anchored and braced that even a soft wet earth is held against sliding into the ditch.
I'Vhile I have particularly described the slabs as constructed with mating grooves 2, wo
other constructions may be used such as the tongue and groove arrangement shown at 9 in Fig. 4. The edges of the slabs may abut squarely as shown at l0 in Fig. 5 but greater care will then be required to properly seal the joints. Instead of the projections 4, the slabs may have sockets l1 formed therein, asin Fig. 6, so that when the floor is poured it will be automatically keyed to the sides, as indicated at 12 in Fig. 7.
Having fully described my invention what I claim as new and desire to secure by Letters- Patent, is
1. A sewer consisting'of sides each composedr of'a plurality of preformed slabs set edge to edge with their lower ends embedded in the ground and the meeting edges sealed, a monolithic floor formed between the sides, and a monolithic roof formed over and carried by the sides.
2. A sewer consisting of sides each composed of preformed slabs of concrete set on end and edge to edge with their lower ends embedded in the ground and their meeting edges sealed, a monolithic cementitious floor formed between the sides and' interlocked therewith, and a. monolithic cementitious roof formed over and carried bv and interlocked with the sides.
3. A sewer composed of sides each consisting of preformed concrete slabs set edge to edge with their lower ends embedded in the ground and 'their meeting edges sealed and provided above their lower ends with lateral projections, a monolithic floor vformed between the sides and abutting the under surfaces of said projections, and a monolithic roof cast on and carried by the sides.
4. The improvement in sewer construction which consists in forcing preformed concrete slabs into the ground in two rows along the line of the sewer to form the sewer side walls, sealing the joints between the slabs, pouring a monolithic cementitious floor between the rows of slabs at a level above the lower ends thereof, the floor uniting with the sides and pouring ay monolithic cementitious roof at and across the upper ends of the slabs.
In testimony whereof, I have signed this specification.
ROBERT B. TUFTS.
US216626A 1927-08-31 1927-08-31 Sewer construction Expired - Lifetime US1746566A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US216626A US1746566A (en) 1927-08-31 1927-08-31 Sewer construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US216626A US1746566A (en) 1927-08-31 1927-08-31 Sewer construction

Publications (1)

Publication Number Publication Date
US1746566A true US1746566A (en) 1930-02-11

Family

ID=22807821

Family Applications (1)

Application Number Title Priority Date Filing Date
US216626A Expired - Lifetime US1746566A (en) 1927-08-31 1927-08-31 Sewer construction

Country Status (1)

Country Link
US (1) US1746566A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3195312A (en) * 1963-10-11 1965-07-20 Mirrison Knudsen Company Inc Method for erecting precast retaining wall
US3555979A (en) * 1967-09-13 1971-01-19 Christian Veder Road support structure
US3967451A (en) * 1974-09-11 1976-07-06 Dames & Moore Storage facility with integral foundation
US4459063A (en) * 1980-08-07 1984-07-10 Shaw Christopher B Building construction
FR2578904A1 (en) * 1985-03-12 1986-09-19 Koeckelberg Sa PROCESS FOR THE PRODUCTION OF A TUNNEL
US4685829A (en) * 1984-11-05 1987-08-11 Marcel Matiere Modular construction system for a covered structure
US4880334A (en) * 1988-04-11 1989-11-14 Finic, B.V. Tunnel construction apparatus and method
US5029804A (en) * 1986-10-16 1991-07-09 Mcgregor Stephen Peter In situ brick or block making formwork
US5207038A (en) * 1990-06-04 1993-05-04 Yermiyahu Negri Reinforced earth structures and method of construction thereof
FR2684401A1 (en) * 1991-11-29 1993-06-04 Sogea Method for producing a tubular construction and construction relating thereto
US5944453A (en) * 1997-04-16 1999-08-31 998492 Ontario Inc. Undercut excavation with protection against seismic events or excessive ground movement
US6224359B1 (en) 1996-07-26 2001-05-01 Michael Mirko Domazet Apparatus for forming adobe blocks
US6234716B1 (en) * 1995-11-17 2001-05-22 Carlo Chiaves Underground structural work including prefabricated elements associated with piles and a process for its production
US20050248157A1 (en) * 2004-04-21 2005-11-10 Shonan Gosei-Jushi Seisakusho K.K. Rehabilitating pipe and a laying method thereof
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3195312A (en) * 1963-10-11 1965-07-20 Mirrison Knudsen Company Inc Method for erecting precast retaining wall
US3555979A (en) * 1967-09-13 1971-01-19 Christian Veder Road support structure
US3967451A (en) * 1974-09-11 1976-07-06 Dames & Moore Storage facility with integral foundation
US4459063A (en) * 1980-08-07 1984-07-10 Shaw Christopher B Building construction
US4685829A (en) * 1984-11-05 1987-08-11 Marcel Matiere Modular construction system for a covered structure
FR2578904A1 (en) * 1985-03-12 1986-09-19 Koeckelberg Sa PROCESS FOR THE PRODUCTION OF A TUNNEL
EP0197021A1 (en) * 1985-03-12 1986-10-08 S.A. Entreprises Koeckelberg Method for driving a tunnel
US5029804A (en) * 1986-10-16 1991-07-09 Mcgregor Stephen Peter In situ brick or block making formwork
US4880334A (en) * 1988-04-11 1989-11-14 Finic, B.V. Tunnel construction apparatus and method
US5207038A (en) * 1990-06-04 1993-05-04 Yermiyahu Negri Reinforced earth structures and method of construction thereof
FR2684401A1 (en) * 1991-11-29 1993-06-04 Sogea Method for producing a tubular construction and construction relating thereto
US6234716B1 (en) * 1995-11-17 2001-05-22 Carlo Chiaves Underground structural work including prefabricated elements associated with piles and a process for its production
US6224359B1 (en) 1996-07-26 2001-05-01 Michael Mirko Domazet Apparatus for forming adobe blocks
US5944453A (en) * 1997-04-16 1999-08-31 998492 Ontario Inc. Undercut excavation with protection against seismic events or excessive ground movement
US20050248157A1 (en) * 2004-04-21 2005-11-10 Shonan Gosei-Jushi Seisakusho K.K. Rehabilitating pipe and a laying method thereof
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station
US9822506B2 (en) * 2014-01-29 2017-11-21 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station

Similar Documents

Publication Publication Date Title
US1746566A (en) Sewer construction
KR102153902B1 (en) Slurry wall, construction method for the same and wire mesh assembly
CN110820757B (en) Foundation pit structure and foundation pit construction method
US2078069A (en) Building veneer construction
US5205675A (en) Precast cribbing wall system
CN105672205B (en) A kind of rock leakage preventing structure
CN205669211U (en) A kind of prefabricated Gravity Retaining Wall
JPS5820809A (en) Construction of dam
US2352338A (en) Building structure for insulation against insects
CN107288153A (en) A kind of prefabricated Gravity Retaining Wall
US1636114A (en) Pavement
KR200263961Y1 (en) Sectional block for retaining wall building
US2320690A (en) Building wall construction
KR200376814Y1 (en) Revetment Block Unit for Plants in Ground
US1515709A (en) Irrigation ditch
US1167159A (en) Construction of concrete sewers, aqueducts, &c.
GB520399A (en) Improvements in or relating to trenches or the like
JPS6261737B2 (en)
US1646997A (en) Concrete pavement for reservoirs, dams, levees, and the like
KR102371284B1 (en) Slurry wall, construction method for the same and wire mesh assembly
US2179429A (en) Cofferdam construction
JP4555972B2 (en) Waterway construction method and waterway structure
SU1527369A1 (en) Prefabricated dam
JPH0342095Y2 (en)
US1198459A (en) Concrete sheet-piling and process of constructing the same.