DE628610C - Process for the foundation of dams or similar structures on peatland - Google Patents

Process for the foundation of dams or similar structures on peatland

Info

Publication number
DE628610C
DE628610C DER89793D DER0089793D DE628610C DE 628610 C DE628610 C DE 628610C DE R89793 D DER89793 D DE R89793D DE R0089793 D DER0089793 D DE R0089793D DE 628610 C DE628610 C DE 628610C
Authority
DE
Germany
Prior art keywords
foundation
bog
dams
soil
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DER89793D
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JOACHIM RATHJENS DR ING
Original Assignee
JOACHIM RATHJENS DR ING
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JOACHIM RATHJENS DR ING filed Critical JOACHIM RATHJENS DR ING
Priority to DER89793D priority Critical patent/DE628610C/en
Application granted granted Critical
Publication of DE628610C publication Critical patent/DE628610C/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Description

Verfahren zur Gründung von Dämmen oder ähnlichen Bauwerken auf Moorboden Die Erfindung betrifft ein Verfahren zur Gründung von Dämmen oder ähnlichen Bauwerken auf Moorboden. Die Herstellung von Straßen, Dämmen u. dgl. über Moorstrecken bietet stets besondere Schwierigkeiten. Auf das Moor aufgebrachte Schüttungen ergeben meist erhebliche Verdrückungen und Rutschungen des Moores, so daß einerseits für die Schüttungen bedeutend mehr Massen benötigt werden, wie es sonst notwendig ist, anderseits aber auch die Dammkrone bzw. die Straße oft noch lange Zeit nach der Herstellung durch Sackungen in der Moorstrecke stark beschädigt wird, wodurch teure Ausbesserungsarbeiten notwendig werden.Procedure for the foundation of dams or similar structures on peatland The invention relates to a method for the foundation of dams or similar structures on bog soil. The production of roads, dams and the like over bog routes offers always special difficulties. Embankments applied to the moor usually result considerable displacement and landslides of the bog, so that on the one hand for the debris significantly more masses are required, as is otherwise necessary, but on the other hand even the top of the dam or the road often continues long after it has been built Sagging in the peat bog is badly damaged, resulting in expensive repair work become necessary.

Zur Vermeidung dieser Nachteile ist es bereits bekannt, das Moor unter dem Dammfuß vor Ausführung der Dammschüttung zu entfernen und die Schüttung von dem tragfesten Untergrund aus hochzuführen. Durch die Entfernung des Moores und diebedeutend größere Massenschüttung wurde aber der ganze Bau so verteuert, daß oft deswegen von seiner Ausführung abgesehen wurde.To avoid these disadvantages, it is already known to use the bog under to remove the foot of the dam before the embankment is carried out and to remove the embankment from to be carried up from the stable subsurface. By removing the bog and the significantly larger mass discharge, however, made the whole building so expensive that it has often been refrained from executing it because of this.

Man hat ferner auch Gründungen mit sog. Sandpfählen ausgeführt, wobei einzelne Gruben durch das Moor bis auf den tragfähigen Untergrund hergestellt und diese mit Sand verfüllt werden. Auf diese Sandpfähle wird dann der Dammkörper aufgeschüttet. Ein Nachteil dieser Gründung liegt jedoch darin, daß das zwischen den Sandpfählen auf dem Untergrund liegende Moor durch die aufgeschütteten Erdmassen Verdrückungen und Verschiebungen erfährt, so daß die an sich tragfähigen Sandpfähle seitlich verschoben werden können.Furthermore, foundations with so-called sand piles have been carried out, whereby individual pits through the bog down to the stable subsoil and these are filled with sand. The dam body is then piled onto these sand piles. A disadvantage of this foundation, however, is that it is between the sand piles The bog lying on the subsurface was displaced by the earth masses that had been piled up and experiences shifts, so that the load-bearing sand piles shifted laterally can be.

Während die vorerwähnten Verfahren eine auf dem tragbaren Untergrund fußende Grün-' dung unter Beseitigung des Moores an den betreffenden Stellen vorsehen, soll bei einem weiteren bekannten Verfahren, der sog. Dammversenkung, das Moor durch Belastung mit anderem Boden zusammengedrückt und tragfähig gemacht werden. Bei diesem Zusammenpressen des Moores auf seinem tragfähigen Untergrund tritt jedoch der Nachteil auf, daß die Moormassen seitlich unter dem Dammkörper herausgedrückt werden und hochquellen. Auch die Anordnung von neben dem Damm verlaufenden Gräben kann diesen Nachteil nicht beseitigen, so daß ein so gegründeter Damm noch sehr lange durch Niedergehen der Dammschüttung und Auftreiben der Randmassen Veränderungen erfährt und nicht als fester Baugrund, wie ihn z. B. eine Kunststraße erfordert, angesprochen werden kann.During the aforementioned procedures one on the portable surface provide for a foundation with the removal of the bog at the relevant locations, in another known process, the so-called embankment sinking, the moor is supposed to be cut through Load can be compressed with other soil and made load-bearing. With this one Compression of the bog on its stable subsoil, however, has the disadvantage on that the moor masses are pushed out laterally under the dam body and high springs. The arrangement of trenches running next to the dam can also do this The disadvantage does not eliminate, so that a dam established in this way can last for a very long time The embankment embankment falls and the marginal masses are swelled up undergo changes and not as a solid building site, as it is for. B. requires an art street, addressed can be.

Die Nachteile der bekannten Verfahren sollen nun gemäß der Erfindung dadurch beseitigt werden, daß zur Gründung von Dämmen, Straßen o. dgl. auf Moorboden in dem Moor durch Umschichtung von Moorboden und dem darunterliegenden tragfähigen Boden bis in den tragfähigen Untergrund reichende Gründungskörper hergestellt werden. Bei dieser Gründung wird der Moorboden zwar auch mit anderem Boden belastet und in zusammengepreßtem Zustand zum Tragen des Bauwerkes- mitbenutzt, jedoch im Gegensatz zu dem bekannten Verfahren in einer Weise, die jede seitliche Bewegung und damit ein Abrutschen des belasteten Moores verhindert. Nach dem Verfahren gemäß der Erfindung gelangt das im Profil des betreffenden Gründungskörpers umgeschichtete Moor in eine im tragfähigen Untergrund liegende Grube, wo es, von der üblichen Moorschicht @ gänzli ,h getrennt, durch die Belastung mit dem bei der Umschichtung daraufgebrachten festen Boden zusammengedrückt wird. Auf diese Weise erhält der umgeschichtete Moorboden in kurzer Zeit und mit Sicherheit 'die notwendige Tragfähigkeit, so daß eine gute Standfestigkeit des ganzen Gründungskörpers gewährleistet ist.The disadvantages of the known methods are now to be found in accordance with the invention be eliminated by establishing dams, roads or the like on peatland in the bog by shifting the bog soil and the load-bearing beneath it Foundation bodies that reach into the load-bearing subsoil can be produced. With this foundation, the bog soil is also loaded with other soil and in compressed Condition for supporting the structure - shared, however, in contrast to the known method in a way that any lateral Movement and thus slipping of the polluted bog is prevented. After the procedure according to the invention, the redeployed in the profile of the foundation body in question arrives Moor into a pit lying in the load-bearing subsoil, where there is, from the usual moor layer @ completely, h separated, by the load with the one applied during the redeployment solid ground is compressed. In this way the rearranged bog soil is preserved in a short time and with certainty 'the necessary load-bearing capacity, so that a good Stability of the whole foundation body is guaranteed.

` Bei Verwendung geeigneter Maschinen, die die Umschichtung ohne besondere Förderung der einzelnen Schichten bewerkstelligen, ist das Verfahren nach der Erfindung gegenüber anderen Verfahren zur Erzielung einer gleich guten Gründung auch besonders wirtschaftlich durchzuführen. Es ändert an dem Verfahren aber grundsätzlich nichts, wenn, wie es durch örtliche Verhältnisse oder Bodenverhältnisse bedingt sein kann, die Arbeitsgänge eine gewisse örtliche Trennung erfahren; auch ist das Verfahren nach der Erfindung nicht an eine bestimmte Form der herzustellenden Gründungskörper gebunden. In der Zeichnung ist ein Ausführungsbeispiel für eine gemäß der Erfindung herzustellende Dammgründung dargestellt, bei welchem die Gründung durch mehrere unter dem aufgeschütteten Damm in der beschriebenen Weise hergestellte langgestreckte schmale Gründungskörper gebildet wird. Die Zeichnung zeigt im Querschnitt die Dammschüttung a und die in dem Moor hergestellten Gründungskörper b, in welchen Moor und tragfähiger Boden umgeschichtet sind. Bei dieser Ausführungsart wird das Moor zwischen den rippenförmigen Gründungskörpern b gleichmäßig und einheitlich zusammengehalten, so daß auch Rutschungen des nicht umgeschichteten Moores vermieden werden und eine gleichmäßige Lage der Dammkrone gesichert ist. Bemerkenswert ist noch, daß die im Moor befindlichen Rippen b aus tragfähigem Boden eine gute Entwässerung der nicht umgeschichteten Moormengen unter dem Dammfuß- bewirken.`When using suitable machines that allow redeployment without special To accomplish the promotion of the individual layers, is the method according to the invention also special compared to other methods to achieve an equally good foundation to be carried out economically. It does not fundamentally change the procedure, if, as may be due to local or soil conditions, the work processes experience a certain spatial separation; also is the procedure according to the invention not to a certain shape of the foundation body to be produced bound. In the drawing is an embodiment of one according to the invention The dam foundation to be produced is shown, in which the foundation is carried out by several elongated ones made under the embankment in the manner described narrow foundation body is formed. The drawing shows the embankment in cross section a and the foundation bodies produced in the bog b, in which bog and more load-bearing Soil are rearranged. In this embodiment, the bog is between the rib-shaped Foundation bodies b held together evenly and uniformly, so that also landslides of the not redeployed bog can be avoided and an even position of the Dam crest is secured. It is also noteworthy that the ribs in the bog b a good drainage of the non-relocated bog from stable soil effect under the perineal foot.

Claims (1)

PATENTANSPItUCH:e Verfahren zur Gründung von Dämmen oder ähnlichen Bauwerken auf Moorboden, dadurch gekennzeichnet, daß in dem Moor durch Umschichtung von Moorboden und dem darunter befindlichen tragfähigen Boden bis in den tragfähigen Untergrund reichende Gründungskörper hergestellt «:erden.PATENT APPLICATION: e method for the foundation of dams or similar Structures on bog soil, characterized in that in the bog by redeployment from bog soil and the load-bearing soil underneath to the load-bearing one Foundation bodies reaching underground produced «: earth.
DER89793D 1934-02-01 1934-02-01 Process for the foundation of dams or similar structures on peatland Expired DE628610C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DER89793D DE628610C (en) 1934-02-01 1934-02-01 Process for the foundation of dams or similar structures on peatland

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DER89793D DE628610C (en) 1934-02-01 1934-02-01 Process for the foundation of dams or similar structures on peatland

Publications (1)

Publication Number Publication Date
DE628610C true DE628610C (en) 1936-04-07

Family

ID=7418223

Family Applications (1)

Application Number Title Priority Date Filing Date
DER89793D Expired DE628610C (en) 1934-02-01 1934-02-01 Process for the foundation of dams or similar structures on peatland

Country Status (1)

Country Link
DE (1) DE628610C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1213804B (en) * 1960-03-22 1966-03-31 Hendrik Clement Van Zi Gerhard Process for improving the condition of the subsoil

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE1213804B (en) * 1960-03-22 1966-03-31 Hendrik Clement Van Zi Gerhard Process for improving the condition of the subsoil

Similar Documents

Publication Publication Date Title
DE2132820A1 (en) Process for the production of the substructure for roads, rails, houses, etc. Like., As well as drainage equipment
DE10333613A1 (en) Process to enhance railway line soil load bearing characteristics by insertion of concrete columns
DE628610C (en) Process for the foundation of dams or similar structures on peatland
AT352639B (en) SHORE SHORING
DE938119C (en) Method and device for the production of a waterproofing apron in the subsurface
DE2219567A1 (en) PROCEDURE FOR NIGHTLY INSTALLATION OF AN UNDERGROUND STRUCTURE
DE2260473A1 (en) METHOD AND DEVICE FOR THE PRODUCTION OF DRAENS, PLUG COMPACTIONS OD. DGL
DE952787C (en) Process for the production of a dike from lowerable concrete floating boxes
DE1934170A1 (en) Removal of mineral oil impregnant from - vicinity of bore holes
DE2640214B2 (en) Method of making a path on the inclined embankment of a dam
AT110374B (en) Method and device for producing channels.
DE810032C (en) Method for filling under railway sleepers
DE701891C (en) Device for the production of foundation stakes
DE568333C (en) Process for the production of press concrete piles
DE2137417A1 (en) LAYING OF PIPES FOR DRAINING GROUNDWATER AND Leachate
DE974948C (en) Process to improve the load-bearing capacity of natural soil layers and artificial heaps by introducing load-bearing material under rocking
DE599787C (en) Process for the production of bored piles with a widened pile base
DE627752C (en) Method and tool for compacting the subsoil of road surfaces
DE398627C (en) Method for the production of site stakes from concrete by means of a driving pipe
DE657544C (en) Process for the manufacture and equipping of compressed air caisson in the field
DE516047C (en) Method for producing a ground anchor
DE368880C (en) Process for establishing dams
DE2611091C1 (en) Arrangement for preventing the embankment from slipping sideways on the embankment of a dam on which vehicles are traveling
DE421073C (en) Procedure for flushing piles
DE616707C (en) Caisson and method of bringing it down