DE3314813C1 - Method of producing galleries and tunnels from precast concrete tubes - Google Patents

Method of producing galleries and tunnels from precast concrete tubes

Info

Publication number
DE3314813C1
DE3314813C1 DE19833314813 DE3314813A DE3314813C1 DE 3314813 C1 DE3314813 C1 DE 3314813C1 DE 19833314813 DE19833314813 DE 19833314813 DE 3314813 A DE3314813 A DE 3314813A DE 3314813 C1 DE3314813 C1 DE 3314813C1
Authority
DE
Germany
Prior art keywords
trench
concrete pipes
width
cutting head
pipes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DE19833314813
Other languages
German (de)
Inventor
Benedikt Dipl.-Ing. 4200 Oberhausen Weiss
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE19833314813 priority Critical patent/DE3314813C1/en
Application granted granted Critical
Publication of DE3314813C1 publication Critical patent/DE3314813C1/en
Expired legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

To produce galleries or tunnels from precast concrete tubes (1), a method is described in which the concrete tubes (1) are driven successively from a pressing pit (9) as a continuous line of tubes in an open trench (3) by means of a hydraulic driving device (10). The walls of the trench (3) are secured by perpendicular sheeting panels (4), the overall depth T of which is determined by the natural angle of slope of the ground. At an angle alpha of slope of less than 45 DEG , the sheeting panels (4) reach with their bottom edge down to the lateral lines (8) of the concrete tubes (1), the width B of the trench (3) corresponding to the outside diameter D of the concrete tubes (1). If the angle alpha of slope is above 45 DEG , the bottom edge of the sheeting panels (4) points to just above the outer shell of the concrete tubes (1), the width B of the trench (3) being smaller than the outside diameter D of the concrete tubes (1). <IMAGE>

Description

Bei der in F i g. 1 und 2 dargestellten Ausführung werden mehrere Betonrohre 1 von einer Preßgrube 9 aus mittels einer hydraulischen Vortriebseinrichtung 10 an der Sohle eines Grabens 3 vorgedrückt, wobei der am In the case of the in FIG. 1 and 2 illustrated embodiment are several Concrete pipes 1 from a press pit 9 by means of a hydraulic propulsion device 10 pushed forward at the bottom of a trench 3, with the on

vorderen Ende befindliche steuerbare Schneidkopf 2 den nicht freigelegten Teil des Grabens 3 anschneidet.front end located controllable cutting head 2 the unexposed Part of the trench 3 cuts.

Die Preßgrube 9 kann in üblicher Weise mit einer Vorpreßschiene 11 und einem Widerlager 12 für die hydraulische Vortriebseinrichtung 10 ausgerüstet sein.The press pit 9 can be provided in the usual way with a pre-press bar 11 and an abutment 12 for the hydraulic propulsion device 10 be.

Am Kopfende des Rohrstranges, vor dem Schneidkopf 2, erfolgt der Aushub des Grabens 3 mittels eines Grabenbaggers 0. dgl. Nach Aushub eines geeigneten Profils werden die Grabenwände durch Verbautafeln 4 gesichert. Vorzugsweise werden Verbaueinheiten verwendet, die aus zwei parallel angeordneten und durch Spreizorgane 5 in dem vorgesehenen Abstand gehaltenen Verbautafeln 4 bestehen. Ist ein Stück des Grabens mit einer entsprechenden Breite ausgehoben worden, wird die Verbaueinheit mit dem Bagger eingesetzt und, gegebenenfalls nach weiterem Aushub, bis zu der vorgesehenen Einbautiefe Tnach unten gedrückt. At the head end of the pipe string, in front of the cutting head 2, the Excavation of the trench 3 by means of a trench excavator 0. The like. After excavation of a suitable one Profile the trench walls are secured by sheeting panels 4. Preferably be Shoring units used, which consist of two parallel arranged and spreading organs 5 shoring panels 4 held at the intended distance exist. Is a piece of the trench has been dug with a corresponding width, becomes the shoring unit used with the excavator and, if necessary after further excavation, up to the intended Installation depth T pressed down.

Die Einbautiefe Tder Verbautafeln 4 wird durch den natürlichen Böschungswinkel a des Erdreichs bestimmt. The installation depth T of the shoring panels 4 is determined by the natural slope angle a of the soil determined.

Steht ein Boden mit einem Böschungswinkel n kleiner als 45" an, hierzu gehören auch alle rolligen Böden, Sandböden u.dgl., so reichen die Verbautafeln 4 mit ihrer Unterkante bis zur Höhe der Seitenlinien 8 der Betonrohre 1, wobei die Breite B des Grabens 3 dem Außendurchmesser D der Beton rohre entspricht. Bei dieser Ausführung kann das Erdreich vor dem Schneidkopf auch bei einem extrem niedrigen Böschungswinkel 0' nur bis zur Höhe der Unterkante der Verbautafeln 4 nachrutschen, und der Schneidkopf 2 fährt in diesem Fall etwa den halben Rohrquerschnitt auf. Handelt es sich hingegen um einen bindigen, stehenden Boden mit einem natürlichen Böschungswinkel größer als 45°, z. B.If there is a ground with an angle of repose n less than 45 ", do this If all coarse soils, sandy soils, etc., also belong, the shoring panels are sufficient 4 with its lower edge up to the level of the side lines 8 of the concrete pipes 1, the Width B of the trench 3 corresponds to the outer diameter D of the concrete pipes. At this Execution can be the soil in front of the cutting head even at an extremely low level Slope angle 0 'only slide up to the level of the lower edge of the shoring panels 4, and in this case the cutting head 2 opens about half the pipe cross-section. If, on the other hand, it is a cohesive, standing soil with a natural one Slope angle greater than 45 °, e.g. B.

einen lehmhaltigen Boden, kann die Breite B des Grabens 3 kleiner als der Außendurchmesser D gewählt werden (vgl. F i g. 3). Die Bautiefe T ist in diesem Fall geringer und die Verbauplatten 4 liegen mit ihrer Untcrkante knapp über dem Außenmantel der Betonrohre 1.a loamy soil, the width B of the trench 3 can be smaller can be selected as the outer diameter D (see FIG. 3). The overall depth T is in In this case less and the shoring panels 4 are just above with their lower edge the outer jacket of the concrete pipes 1.

Die F i g. 2 und 3 lassen die Seitenböschungen 6 mit zwei verschiedenen Böschungswinkeln a erkennen. Beide Seitenböschungen 6 schneiden sich bei diesen Ausführungen etwa unterhalb der Mittelachse der Bctonrohre 1. Die beim Aushub vor dem Schneidkopf 2 entstehende Endböschung 7 wird ebenfalls vom Schneidkopf 2 angeschnitten. The F i g. 2 and 3 leave the side slopes 6 with two different ones Detect slope angles a. Both side slopes 6 intersect at these Executions approximately below the central axis of the concrete pipes 1. The during excavation before The end slope 7 created by the cutting head 2 is also cut by the cutting head 2.

- Leerseite -- blank page -

Claims (1)

Patentanspruch: Verfahren zum Herstellen von Stollen oder Tunneln aus vorgefertigten Beton rohren, bei dem die Betonrohre von einer Preßgrube aus mittels einer Vortriebseinrichtung aufeinanderfolgend in einem Graben als zusammenhängender Rohrstrang vorgetrieben werden und ein nicht freigelegter Teil des Grabens durch einen Schneidkopf angeschnitten wird, dadurch gekennzeichnet, daß die Breite (B)des mit lotrechten Verbautafeln (4) ausgerüsteten Grabens (3) gleich oder kleiner als der Außendurchmesser (D) der Betonrohre (1) ist und daß die Verbautafeln (4) auf jeder Grabenseite bei einer dem Außendurchmesser (D) entsprechenden Breite.Claim: Method for producing galleries or tunnels from prefabricated concrete pipes, in which the concrete pipes from a press pit by means of a driving device successively in a trench as a contiguous one Pipe string are driven and a non-exposed part of the trench through a cutting head is cut, characterized in that the width (B) of the with vertical shoring panels (4) equipped trench (3) equal to or smaller than the outer diameter (D) of the concrete pipes (1) and that the shoring panels (4) on each side of the trench with a width corresponding to the outer diameter (D). (B) des Grabens (3) eine bis zu den Seitenlinien (8) der Betonrohre (1) reichende, oder bei einer geringeren Breite (B) des Grabens (3) eine bis knapp über die Betonrohre (1) reichende Bautiefe (T)erhalten. (B) of the trench (3) one up to the side lines (8) of the concrete pipes (1) Reaching, or with a smaller width (B) of the trench (3) one to just under Obtain depth (T) reaching over the concrete pipes (1). Die Erfindung betrifft ein Verfahren zum Herstellen von Stollen oder Tunneln aus vorgefertigten Betonrohren, bei dem die Betonrohre von einer Preßgrube aus mittels einer Vortriebseinrichtung aufeinanderfolgend in einem Graben als zusammenhängender Rohrstrang vorgetrieben werden und ein nicht freigelegter Teil des Grabens durch einen Schneidkopf angeschnitten wird. The invention relates to a method for producing studs or Tunnels from prefabricated concrete pipes, in which the concrete pipes from a press pit from by means of a driving device successively in a trench as a contiguous one Pipe string are driven and a non-exposed part of the trench through a cutting head is cut. Beim Herstellen von Stollen oder Tunneln aus vorgefertigten Betonrohren wird in Abhängigkeit von der Mächtigkeit des Erdreichs über den Betonrohren entweder in geschlossener oder in offener Bauweise gearbeitet. Bei einer Mächtigkeit bis zum zwei- bis dreifachen Rohrdurchmesser wird häufig die offene Grabenbauweise angewendet. When creating galleries or tunnels from prefabricated concrete pipes is depending on the thickness of the soil above the concrete pipes either worked in closed or open construction. With a thickness up to Open trench construction is often used for two to three times the pipe diameter. Bei der bekannten offenen Grabenbauweise wird ein relativ breiter Graben ausgehoben, wobei entweder der natürliche Böschungswinkel zu berücksichtigen ist oder die Grabenwandung durch zusätzliche Ausbauten, beispielsweise lotrechte Verbauplatten, gesichert werden muß. Weiterhin muß bei dieser Grabenbauweise das Grabenbett genau bereitet werden, damit die Betonrohre genau Stoß an Stoß zu liegen kommen. Die Rohre werden mittels eines Kranes, der auf einer neben dem Graben erforderlichen Bahn verfährt, von oben in die Graben gelegt. Nach dem Einlegen der Rohre wird der Graben ausgefüllt und das Gelände eingeebnet. Die bekannte offene Grabenbauweise hat bisher den Nachteil, daß für das Verlegen verhältnismäßig viel Arbeitsplatz benötigt wird. Um die Platzerfordernisse zu verringern und die Verlegeleistung zu steigern, ist aus der DE-AS 16 58 772 bekanntgeworden, Betonrohre von einer Preßgrube aus mittels einer hydraulischen Vortriebseinrichtung aufeinanderfolgend in einem im Querschnitt etwa V-förmigen Graben als zusammenhängenden Rohrstrang vorzutreiben, wobei ein nicht freigelegter Teil des Grabens durch den Schneidkopf angeschnitten wird. Diese hydraulische Vortriebsweise in einem offenen Graben mit natürlichem Böschungswinkel hat sich dort bewährt, wo ein genügend breiter Raum für den im Querschnitt V-förmigen Graben zur Verfügung steht. In the case of the known open trench construction, one becomes relatively wider Trench dug, taking into account either the natural slope angle or the trench wall by additional extensions, for example perpendicular Shoring panels, must be secured. Furthermore, with this trench construction, the The trench bed must be prepared precisely so that the concrete pipes lie exactly butt to abut come. The pipes are required by means of a crane, which is on a next to the trench Railway moves, laid in the trench from above. After inserting the pipes, the Filled in the trench and leveled the terrain. The well-known open trench construction has so far had the disadvantage that there is a relatively large amount of work space for laying is needed. To reduce the space requirements and to increase the laying capacity increase, has become known from DE-AS 16 58 772, concrete pipes from a press pit from successively in one by means of a hydraulic propulsion device to drive a roughly V-shaped trench in cross-section as a continuous pipe string, a non-exposed part of the trench being cut by the cutting head will. This hydraulic method of propulsion in an open trench with natural Slope angle has proven itself where there is a sufficiently wide space for the cross-section V-shaped trench is available. Für eine schmale Bauflächenbreite ist diese hydraulische Vortriebsweise ebensowenig geeignet, wie die bekannte offene Bauweise, bei der die Grabenwände mit Verbauplatten gesichert sind und die Rohre mit Hilfe eines Krans in den relativ breiten Graben verlegt werden.This hydraulic propulsion method is ideal for a narrow construction area just as unsuitable as the well-known open construction, in which the trench walls are secured with shoring panels and the pipes with the help of a crane in the relative wide trench to be laid. Der Erfindung liegt die Aufgabe zugrunde, ein Verfahren der gattungsgemäßen Art derart weiterzuentwickeln, daß ein Vortrieb auch bei schmalen Bauflächenbreiten möglich ist. The invention is based on the object of a method of the generic type Art to be further developed in such a way that tunneling even with narrow building area widths is possible. Diese Aufgabe wird dadurch gelöst, daß die Breite des mit lotrechten Verbautafeln ausgerüsteten Grabens gleich oder kleiner als der Außendurchmesser der Betonrohre ist und daß die Verbautafeln auf jeder Grabenseite bei einer dem Außendurchmesser entsprechenden Breite des Grabens eine bis zu den Seitenlinien der Betonrohre reichende, oder bei einer geringeren Breite des Grabens eine bis knapp über die Betonrohre reichende Bautiefe erhalten. This object is achieved in that the width of the perpendicular Shoring panels of equipped trench equal to or smaller than the outer diameter the concrete pipes is and that the shoring panels on each side of the trench at one of the Outside diameter corresponding width of the trench one to the side lines the concrete pipes reaching, or with a smaller width of the trench one to Preserved construction depth reaching just above the concrete pipes. Für die neue Bauweise wird nur eine äußerst schmale Bauflächenbreite benötigt. Die seitliche Absicherung der Grabenwand mit Verbautafeln oder Spunddielen geschieht nur bis zu einer solchen Tiefe, daß sich die an der Grabensohle bildenden Seitenböschungen etwa unterhalb der Mittelachse des Betonrohres schneiden und kein Erdmaterial mehr von den Seiten her nachrutscht. Only an extremely narrow building surface width is required for the new construction method needed. The lateral protection of the trench wall with sheeting panels or sheet piling happens only to such a depth that those formed at the bottom of the trench are formed Cut side slopes approximately below the central axis of the concrete pipe and no Earth material slides more from the sides. Bei rolligem Boden, wo der natürliche Böschungswinkel kleiner als 45" ist, reicht die Einbautiefe bis zu den Seitenlinien des Betonrohres. Das nur im Bereich des unteren Rohrquerschnitts vor dem Schneidkopf befindliche Material der Seitenböschungen wird beim Vortrieb angeschnitten bzw. aufgefahren. Bei dieser Einbautiefe kann auch bei extrem niedrigen Böschungswinkeln das Material nur bis zur Höhe der Unterkante der Verbautafeln nachrutschen. Ist der natürliche Böschungswinkel des Erdreichs größer als 45°, z. B. bei bindigen oder stehenden Böden, kann die Grabenbreite entsprechend noch kleiner gewählt werden, wobei dann die Unterkante der Verbautafeln knapp über dem Außenmantel der Betonrohre liegt. Für die lotrechten Verbautafeln wird kein Elementenschutz beansprucht.On rough ground where the natural angle of departure is less than 45 ", the installation depth extends to the side lines of the concrete pipe. That's only Material located in the area of the lower pipe cross-section in front of the cutting head the side embankments are cut or driven during the drive. At this The material can only be installed up to an installation depth even with extremely low slope angles slide up to the level of the lower edge of the shoring panels. Is the natural angle of repose of the earth greater than 45 °, e.g. B. in cohesive or standing soils, the The trench width can be selected to be even smaller, in which case the lower edge of the shoring panels is just above the outer jacket of the concrete pipes. For the perpendicular No element protection is claimed for shoring panels. Der Einbau der Verbautafeln und der Rohrvortrieb läßt sich günstig aufeinander abstimmen. Zunächst wird vor dem Schneidkopf entsprechend der beabsichtigten Grabenbreite ein Stück ausgebaggert und eine aus zwei Verbautafeln, die durch Spreizorgane in dem vorgesehenen Abstand gehalten werden, bestehende Verbaueinheit mittels des Baggers eingesetzt und, gegebenenfalls nach weiterem Aushub, bis zur vorgesehenen Einbautiefe nach unten gedrückt. Durch den Aushub bildet sich vor dem Schneidkopf eine Endböschung, deren Böschungswinkel etwa an der unteren Stelle des Schneidkopfes ansetzt. Beim Vortrieb schneidet der Schneidkopf auch die Endböschung an. Das vom Schneidkopf angeschnittene Material wird nach vorn auf die Endböschung geschaufelt oder geschoben und vom Bagger ausgehoben. Die Arbeitsvorgänge, nämlich das Ausbaggern des Erdreichs, das Einbauen der Verbautafeln und der Vortrieb des Rohrstrangs, können zeitlich aufeinanderfolgend oder gleichzeitig erfolgen. The installation of the shoring panels and the pipe jacking can be inexpensive match up. First, in front of the cutting head according to the intended Trench width dredged a piece and one from two shoring panels, which by spreading organs be kept at the intended distance, existing shoring unit by means of the Excavator used and, if necessary after further excavation, up to the intended Installation depth pressed down. The excavation forms in front of the cutting head an end slope whose angle of slope is approximately at the lower point of the cutting head starts. During the advance, the cutting head also cuts the end slope. That from Material cut into the cutting head is shoveled forward onto the end slope or pushed and lifted by the excavator. The operations, namely the dredging of the ground, the installation of the sheeting and the driving of the pipe string take place consecutively or simultaneously. Die Erfindung wird anhand der in der Zeichnung dargestellten Beispiele näher erläutert Es zeigt F i g. t einen lotrechten Längsschnitt durch eine Rohrvortriebsstrecke, F i g. 2 den Gegenstand der F i g. 1 in einem Querschnitt nach der Linie 1-1 und F i g. 3 ein anderes Ausführungsbeispiel einer Rohrvortriebsstrecke in einem Querschnitt. The invention is illustrated by the examples shown in the drawing explained in more detail It shows F i g. t a vertical longitudinal section through a pipe jacking section, F i g. 2 the subject of FIG. 1 in a cross section along the line 1-1 and F i g. 3 shows another embodiment of a pipe jacking section in a cross section.
DE19833314813 1983-04-23 1983-04-23 Method of producing galleries and tunnels from precast concrete tubes Expired DE3314813C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19833314813 DE3314813C1 (en) 1983-04-23 1983-04-23 Method of producing galleries and tunnels from precast concrete tubes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19833314813 DE3314813C1 (en) 1983-04-23 1983-04-23 Method of producing galleries and tunnels from precast concrete tubes

Publications (1)

Publication Number Publication Date
DE3314813C1 true DE3314813C1 (en) 1984-11-29

Family

ID=6197223

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19833314813 Expired DE3314813C1 (en) 1983-04-23 1983-04-23 Method of producing galleries and tunnels from precast concrete tubes

Country Status (1)

Country Link
DE (1) DE3314813C1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0206371A1 (en) * 1985-06-11 1986-12-30 Weiss Benedikt Cutter head for advancing prefabricated concrete pipes for the construction of galleries or tunnels
EP1067272A1 (en) 1999-07-09 2001-01-10 Benedikt Weiss Apparatus for forcing pipes in the underground

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"Tiefbau-BG" 1/1980, S.38-40 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0206371A1 (en) * 1985-06-11 1986-12-30 Weiss Benedikt Cutter head for advancing prefabricated concrete pipes for the construction of galleries or tunnels
EP1067272A1 (en) 1999-07-09 2001-01-10 Benedikt Weiss Apparatus for forcing pipes in the underground

Similar Documents

Publication Publication Date Title
DE69635549T2 (en) METHOD AND DEVICE FOR ESTABLISHING ENDLESS UNDERGROUND WALLS
DE4226067A1 (en) Device and method for stabilising highways in sloping locations - involves vertical injection posts fitted in lowermost stage with externally extending sections provided with inclined posts and steel reinforcement of concrete support wall
DE2250369C3 (en) Tunnel lining
DE2751972A1 (en) METHOD OF MANUFACTURING REINFORCED UNDERGROUND BUILDING PANEL
DE2622671A1 (en) EQUIPMENT FOR DRIVING A TRENCH IN THE OPEN SHEET FOR PIPE LAYING
EP0206371B1 (en) Cutter head for advancing prefabricated concrete pipes for the construction of galleries or tunnels
DE3314813C1 (en) Method of producing galleries and tunnels from precast concrete tubes
DE2450281A1 (en) Machine for excavation and shoring of trenches - has hydraulically actuated excavation plates with space for prefabricated shoring plates
DE2250635A1 (en) PROCEDURE FOR BUILDING A TUNNEL
DE3914736C2 (en)
DE2543997C2 (en) Method for pressing a particularly tubular structure into an earth dam or the like.
DE2159486C3 (en) Process and devices for the production of underground structures in hydraulic jacking
DE2622202C2 (en) Method and device for driving a deep trench using the knife shield method, in particular for the construction of tunnels
DE2322468C2 (en) Device for creating galleries, channels or tunnels
DE1915091A1 (en) Method and device for the production of channels using the diaphragm wall method
DE19542031A1 (en) Ground compacting by cutter arm with tools on endless cutter chain
DE4126408C2 (en) Method and device for producing a sealing wall and sealing wall suitable therefor
DE2161392C2 (en) Method and device for creating tunnels in an open excavation
DE2012861A1 (en) Device for the production of diaphragm walls
DE2135782C3 (en) Driving device for creating pipe trenches
DE4317553C2 (en) Soil exchange device next to a traffic route
DE8516946U1 (en) Cutting head for driving prefabricated concrete pipes for the production of galleries or tunnels
DE2531007C3 (en) Method and device for creating working shafts within trenches driven by shield driving
DE29913274U1 (en) Device for lifting and conveying material cut by the cutting head when driving prefabricated pipes
DE19607629C2 (en) Procedure for gradually driving a tunnel

Legal Events

Date Code Title Description
8100 Publication of the examined application without publication of unexamined application
D1 Grant (no unexamined application published) patent law 81
8364 No opposition during term of opposition
8339 Ceased/non-payment of the annual fee