DE2804419A1 - cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position - Google Patents

cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position

Info

Publication number
DE2804419A1
DE2804419A1 DE19782804419 DE2804419A DE2804419A1 DE 2804419 A1 DE2804419 A1 DE 2804419A1 DE 19782804419 DE19782804419 DE 19782804419 DE 2804419 A DE2804419 A DE 2804419A DE 2804419 A1 DE2804419 A1 DE 2804419A1
Authority
DE
Germany
Prior art keywords
locking
channel
bridge
bridges
installation duct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19782804419
Other languages
German (de)
Inventor
Hans-Helmut Nolten
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NOWA PLAST NOLTEN KG
Original Assignee
NOWA PLAST NOLTEN KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NOWA PLAST NOLTEN KG filed Critical NOWA PLAST NOLTEN KG
Priority to DE19782804419 priority Critical patent/DE2804419A1/en
Publication of DE2804419A1 publication Critical patent/DE2804419A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0431Wall trunking

Abstract

The cable runway has a U-shaped cross-section with grooves (5) along the insides of its top edges. L-shaped and U-shaped bridges (4) may locate in these grooves and support various electrical components, e.g. switches, sockets, junctions. The bridge has hooked tongues to retain it in the grooves. The vertical side (or sides) of the bridge locates at its lower end in a groove (14) along the bottom of the runway.

Description

Installationskanal Installation channel

Die Erfindung betrifft einen Installationskanal zur Leitungsverlegung und zum Geräteeinbau mit einem Boden und zwei Seitenwänden, die am Oberrand in längsrichtung des Kanals verlaufende Lagerstellen zur Aufnahme der Geräte-und Leitungsbrücken aufweisen.The invention relates to an installation duct for laying cables and for device installation with a base and two side walls, which are longitudinally at the upper edge Bearing points running along the channel to accommodate the device and cable bridges exhibit.

Installationskanäle der vorgenannten Art werden in zunehmendem Umfang für die Verlegung von Leitungen und gleichzeitig zur Montage von Installationsgeräten, insbesondere Steckdosen, Schalter, Sicherungen usw. benutzt. Die Kanäle haben im allgemeinen rechteckigen Querschnitt mit Abmessungen, die vom jeweiligen Verwendungszweck abhängen, und werden in größeren Längen aus Kunststoff im Spritzverfahren hergestellt. Zur Aufnahme der Installationsgeräte und zum Halten der Leitungen dienen Geräte- und Leitungsbrücken oder -klammern, die die offene Oberseite des Kanals überbrücken und an Lagerstellen festgelegt sind. Nach Fertigstellung der Installation kann ein Deckel aufgebracht werden, der das Innere des Kanals schützt.Installation channels of the aforementioned type are increasing in scope for laying cables and at the same time for installing accessories, in particular sockets, switches, fuses, etc. are used. The channels have im general rectangular cross-section with dimensions depending on the intended use depend, and are manufactured in larger lengths from plastic by injection molding. To accommodate the installation devices and to hold the cables, device and cable bridges or brackets that cover the open top of the Bridge canal and are set at storage locations. After completing the Installation, a cover can be applied to protect the interior of the duct.

Zur Befestigung der Brücken und Klammern ist es bereits bekannt, am Oberrand der Kanalseitenwände eine kurze, zum Kanalinnern weisende Wand entlang laufen zu lassen, die als Lagerstelle für die Installationsbrücken, Leitungsklammern u.ä. Installationshilfen dienen. Die Festlegung erfolgt dabei mit Hilfe von in regelmäßigem Abstand angeordneten Löchern in den als Lagerstellen dienenden Wänden. Die Brücken und Klammern besitzen am Ende Befestigungshaken, die durch die Öffnungen gedrückt werden können und so für eine Festlegung sorgen.To attach the bridges and brackets, it is already known on Along the upper edge of the canal side walls a short wall facing the inside of the canal to run as a storage point for the installation bridges, cable clamps etc. Installation aids serve. The determination takes place with the help of in regular Spaced holes in the walls serving as bearings. The bridges and clips have fastening hooks at the end that are pushed through the openings can be and thus ensure a definition.

Die Anbringung der Befestigungsöffnungen bedingt einen zusätzlichen Arbeitsgang und verteuert daher die Installationskanäle. Außerdem ist die Befestigung der Brücken und Klammern nicht sicher genug und umständlich durchzuführen.The attachment of the fastening openings requires an additional one Operation and therefore makes the installation ducts more expensive. Also is the attachment the bridges and brackets are not secure enough and cumbersome to carry out.

Schließlich sollten Brücken und Klammern an jeder gewünschten Stelle eines Kanals angebracht werden können, ohne an die Position von Befestigungslöchern gebunden zu sein.Finally, bridges and brackets should be in any desired location a channel can be attached without changing the position of mounting holes to be bound.

Die Erfindung hat sich demgemäß die Aufgabe gestellt, Installationskanäle und daran angepaßte Geräte- und Leitungsbrükken zu schaffen, die eine einfache und sichere Montage bei kleinem Aufwand ermöglichen. Zur Lösung der Aufgabe geht die Erfindung aus von einem Installationskanal der eingangs genannten Art und ist dadurch gekennzeichnet, daß die Lagerstellen als Rastnuten für die Brücken ausgebildet sind. Die Geräte- und Leitungsbrücken können dann an beliebiger Stelle ohne Verwendung von Werkzeugen durch Eindrücken in die Rastnuten dauerhaft befestigt werden. Ein unbeabsichtigtes Lösen ist nicht ohne weiteres und ohne Werkzeug möglich und außerdem ergibt sich eine stabilisierende Verbindung der sich gegenüberliegenden Kanalseitenwände.The invention has accordingly set itself the task of installing ducts and adapted device and cable bridges to create that enable simple and safe assembly with little effort. To solve the The object of the invention is based on an installation duct of the type mentioned at the beginning Kind and is characterized in that the bearings act as locking grooves for the bridges are trained. The device and cable bridges can then be placed anywhere Permanently attached by pressing into the locking grooves without the use of tools will. Unintentional loosening is not possible without further ado and without tools and there is also a stabilizing connection of the opposing Channel sidewalls.

Sine Weiterbildung der Erfindung sieht vor, daß die Rastnuten eine von der Oberseite in die Nut hineinragende, im Querschnitt rastnasenförmige Rastkante besitzen, die zum Innern des Kanals hin eine Schrägfläche aufweist, und daß die Brücken mit an die Rastnuten angepaßten Rastleisten ausgestattet sind, die auf der Außenseite ebenfalls eine mit der Schrägfläche der Rastkante zusammenwirkende Schrägfläche aufweisen. Die beiden Schrägflächen erleichtern das Eindrücken einer Brücke in die verrastete Lage, in der die Rastkante der Rastnut und die Rastleiste der Brücke ineinander eingreifen. Ein Lösen dieses Eingriffs ist dann nur noch mit einem Werkzeug möglich.Sine development of the invention provides that the locking grooves a Latch-shaped locking edge protruding from the top into the groove in cross-section have, which has an inclined surface towards the interior of the channel, and that the Bridges are equipped with locking strips adapted to the locking grooves on the Outside also an inclined surface cooperating with the inclined surface of the locking edge exhibit. The two inclined surfaces make it easier to push a bridge into the locked position in which the locking edge of the locking groove and the locking strip of the bridge interlock. This intervention can then only be released with a tool possible.

Die Brücken oder Klammern müssen nicht symmetrisch ausgebildet sein. So sieht die Erfindung in ihrer weiteren Ausbildung vor, daß die Brücke auf einer Seite eine zum Boden des Kanals hinunterführende Stütze aufweist, deren Unterkante in eine Bodenlängsnut des Kanals eingreift. Die Brükke oder auch Klammer kann dann zunächst auf der Seite der Stütze eingerastet werden, wobei durch den Eingriff der Stütze in die Bodenlängsnut ein sicherer Halt auch dann gegeben ist, wenn die andere Seite der Brücke hochgebogen wird, um Kabel durch den entstehenden Spalt in den Kanal ohne Durchziehen einlegen zu können. Das ist besonders wichtig bei der Deckenmontage von Kanälen, bei der sonst häufig ein mühsames Durchziehen der Leitungen von Brücke zu Brücke erforderlich wird.The bridges or brackets do not have to be symmetrical be. So the invention provides in its further training that the bridge on a Side has a down to the bottom of the channel support, the lower edge of which engages in a bottom longitudinal groove of the channel. The bridge or bracket can then are first snapped into place on the side of the support, whereby by engaging the Support in the bottom longitudinal groove a secure hold is given even when the other Side of the bridge is bent up to allow cables through the resulting gap into the Channel can be inserted without pulling through. This is particularly important for ceiling mounting of canals, which otherwise often involve laborious pulling through of the lines from the bridge to bridge becomes necessary.

In weiterer Ausbildung der Erfindung besteht auch die Möglichkeit, daß die Brücke in zwei Abschnitte unterteilt ist, die sich gegenüberliegend in den Kanal einrastbar sind und ae eine zum Boden des Kanals hinunterfuhrende Stütze aufweisen, deren Unterkante in eine Bodenlängsnut des Kanals eingreift, und daß die freien Enden der Brückenabschnitte sich überlappen und an der Uberlappungsatelle mit einer einklinkenden Verzahnung versehen sind. Die beiden Abschnitte können dann getrennt eingeschnappt werden, wobei die Teilung nach dem Lösen der Verzahnung ein nachträgliches Einlegen von Kabeln ermöglicht.In a further embodiment of the invention there is also the possibility of that the bridge is divided into two sections facing each other in the Channel can be latched and ae have a support leading down to the bottom of the channel, whose lower edge engages in a bottom longitudinal groove of the channel, and that the free Ends of the bridge sections overlap and at the overlap atelle with a latching teeth are provided. The two sections can then be separated be snapped into place, the division after loosening the toothing a subsequent Insertion of cables allows.

Wenn ein leichtes Lösen der Rastverbindung zwischen der Rastleiste der Brücke oder Klammer und der Rastkante in der Nut erwünscht ist, beispielsweise um Geräteteile auswechseln zu können, oder Erweiterungen vorzunehmen, so kann nach einer Weiterbildung der Erfindung die Rastleiste an einem federnden Endabschnitt der Brücke angeordnet sein.If a slight loosening of the locking connection between the locking bar the bridge or bracket and the locking edge in the groove is desired, for example in order to be able to replace parts of the device, or to make extensions, so can according to a development of the invention, the locking strip on a resilient end portion be arranged on the bridge.

Durch Druckausübung läßt sich dann die Rastleiste außer Eingriff mit der Rastkante bringen, wobei die Verbindung gelöst wird. Zur Verwirklichung der Federung kann vorgesehen sein, daß die Rastleiste an einem durch zwei Schlitze gebildeten mittleren Endabschnitt der Brücke angeordnet ist, so daß die Rastverbindung durch Fingerdruck lösbar ist, und daß die seitlichen Endabschnitte so ausgebildet sind, daß sie ohne Einrasten tragend in der Rastnut des Kanals liegen.By applying pressure, the locking bar can then be disengaged from bring the locking edge, whereby the connection is released. To achieve the Suspension can be provided that the locking strip is formed on one by two slots middle end portion of the bridge is arranged so that the locking connection through Finger pressure is releasable, and that the side end portions are designed so that they are supporting without locking in the locking groove of the channel.

Zur Erleichterung des Eindrückens oder Einziehens der Brücken in die Nuten kann die Brücke mit einem oder mehreren Grifflöchern versehen sein.To make it easier for the bridges to be pushed in or pulled into the Grooves, the bridge can be provided with one or more finger holes.

Eine seitliche Verschiebung der Brücken und Klammern läßt sich verhindern, wenn nach einer Empfehlung der Erfindung die Rastnut und/oder die Bodenlängsnut mit Nocken ausgestattet sind.Lateral displacement of the bridges and brackets can be prevented, if, according to a recommendation of the invention, the locking groove and / or the bottom longitudinal groove are equipped with cams.

Die Kanäle und auch die Brücken oder Klammern werden aus Kunststoff im Spritzverfahren oder auch aus Metall, beispielsweise Aluminium, hergestellt.The channels and also the bridges or brackets are made from plastic by spraying or made of metal, for example aluminum.

Nachfolgend wird die Erfindung anhand von Ausführungsbeispielen in Verbindung mit den Zeichnungen näher beschrieben.In the following, the invention is illustrated in FIG Connection with the drawings described in more detail.

Es zeigen: Fig. 1 einen perspektivischen Querschnitt durch einen Installationskanal mit eingesetzter Brücke; Fig. 2 eine Teilansicht der Brücke gemäß Fig. 1; Fig. 3 einen Querschnitt durch einen weiteren Installationskanal mit eingesetzter Brücke, die eine Gerätedose trägt; Fig. 4 eine Aufsicht der Brücke gemäß Fig. 3; Fig. 5 einen Querschnitt durch einen Installationskanal mit eingesetzter, zweiteiliger Brücke.1 shows a perspective cross-section through an installation duct with inserted bridge; FIG. 2 shows a partial view of the bridge according to FIG. 1; Fig. 3 a cross-section through another installation duct with an inserted bridge, that carries a device box; FIG. 4 shows a plan view of the bridge according to FIG. 3; Fig. 5 a cross section through an installation duct with inserted, two-part Bridge.

In Fig0 1 ist perspektivisch ein kurzer Abschnitt eines Installationskanals 1 mit einem Boden 2 und Seitenwänden 3 dargestellt. Eine Brücke 4 ist in Nuten 5 am Oberrand der Seitenwände 3 eingerastet. Dazu weisen die Nuten 5 Rastnasen 6 auf, die zum Inneren der Nut hin eine Rastkante 7 und zum Kanal hin eine Schrägfläche 8 besitzen. Die Rastnase 7 läuft kontinuierlich über die Länge des Kanals durch.In Fig0 1 is a short section of an installation channel in perspective 1 shown with a base 2 and side walls 3. A bridge 4 is in grooves 5 snapped into place on the upper edge of the side walls 3. For this purpose, the grooves 5 have locking lugs 6, towards the interior of the groove a locking edge 7 and towards the channel an inclined surface 8 own. The locking lug 7 runs continuously over the length of the channel.

Die Brücke 4 besitzt auf der in der Zeichnung linken Seite eine Rastleiste 9, die ebenfalls mit einer Rastkante 10 und einer Schrägfläche 11 versehen ist. Auf der gleichen Seite ist die Brücke 4 mit einem an der zugeordneten Seitenwand 3 des Kanals 1 anliegenden Stützfuß 12 ausgestattet, dessen Unterkante 13 in eine zwischen einer Leiste 14 und der Seitenwand 3 gebildete Bodenlängsnut 15 eingreift. Auf der in der Zeichnung rechten Seite ist das Brückenende mit zwei Schlitzen 16 versehen, durch die ein mittlerer Abschnitt 17 und zwei Endabschnitte 18 gebildet werden. Nur der mittlere Abschnitt 18 besitzt eine Rastkante 19, die beim Einbringen in die Nut 5 hinter die Rastkante 7 schnappt und damit eine zugfeste Verbindung zwischen der Brücke 4 und der Kanalseitenwand 3 herstellt. Die beiden Endabschnitte 18 dienen mit unteren Auflageflächen lediglich einer Lastübertragung auf die Bodenfläche der Nut 5.The bridge 4 is on the left in the drawing one Locking strip 9, which is also provided with a locking edge 10 and an inclined surface 11 is. On the same side is the bridge 4 with one on the associated side wall 3 of the channel 1 abutting support foot 12 equipped, the lower edge 13 in a between a bar 14 and the side wall 3 formed bottom longitudinal groove 15 engages. The bridge end with two slots 16 is on the right-hand side in the drawing provided, through which a middle section 17 and two end sections 18 are formed will. Only the middle section 18 has a locking edge 19, which when it is introduced snaps into the groove 5 behind the locking edge 7 and thus a tensile connection between the bridge 4 and the channel side wall 3 produces. The two end sections 18 with lower bearing surfaces only serve to transfer loads to the floor surface the groove 5.

Bei der Verlegung von Leitungen, insbesondere bei der Deckenmontage solcher Kanäle kann die Brücke 4 zunächst einseitig auf der Seite ihres Stützfusses 12 in den Kanal eingerastet werden. Grifflöcher 20, die zur Schonung der Finger mit Abrundungen und einem inneren Verstärkungsring versehen sind, erleichtern das Einziehen der Rastleiste 9 in die Nut 5. Das andere Ende der Brücke 4 mit den drei Abschnitten 18,19 kann zunächst frei bleiben und auf der Oberseite der zugeordneten Kanalseitenwand 3 aufliegen. Durch Hochbiegen der Brücke 4 unter Verformung der am Stützfuß 12 anliegenden Kanalseitenwand 3 entsteht ein Spalt zum Einlegen von Leitungen,der sich federnd jeweils wieder schließt, so daß die Leitungen nicht herausfallen können. Abschließend werden dann die Enden der drei Abschnitte 17,18 in die Rastnut 5 eingeführt, wobei die Rastleiste 19 am mittleren Abschnitt 17 einschnappt. Wenn die Brücke auf der einen Seite wieder gelöst werden soll, beispielsweise um ein weiteres Kabel einzulegen, so genügt ein kräftiger Fingerdruck auf den mittleren Abschnitt 17, um die Rastverbindung außer Eingriff zu bringen.When laying cables, especially when installing on the ceiling The bridge 4 can initially use such channels on one side on the side of its support leg 12 must be snapped into the duct. Finger holes 20 to protect the fingers are rounded and have an inner reinforcing ring to make this easier Pulling the locking bar 9 into the groove 5. The other end of the bridge 4 with the three Sections 18,19 can initially remain free and on top of the associated Channel side wall 3 rest. By bending the bridge 4 while deforming the on the support foot 12 adjacent channel side wall 3 creates a gap for inserting lines, which resiliently closes again, so that the Lines cannot fall out. Then finish off the ends of the three Sections 17,18 introduced into the locking groove 5, the locking strip 19 on the middle Section 17 snaps into place. When the bridge on one side can be loosened again If you want to insert another cable, for example, a strong finger pressure is sufficient on the middle section 17 in order to disengage the locking connection.

In Fig. 3 ist ein Querschnitt durch einen weiteren Installationskanal 1 dargestellt, der ebenfalls einen Boden 2 sowie Seitenwände 3 besitzt und im wesentlichen nur durch seine Abmessungen von dem Kanal 1 in Fig. 1 abweicht. Als Beispiel ist anstelle einer unsymmetrischen Brücke 4 gemäß Fig. 1 in Fig. 3 eine Brücke 24 dargestellt, die eine Installationsdose 25 trägt. Eine Aufsicht der Brücke 24 zeigt Fig. 4. Die Brücke 24 besitzt wie die Brücke 4 auf beiden Seiten Rastleisten 29 mit jeweils einer Rastkante 30 und einer Schrägfläche 31. tEt den Rastleisten 29 wird die Brücke in die Nuten 5 eingeschnappt, die auf die gleiche Weise wie beim Ausführungsbeispiel nach Fig. 1 ausgebildet sind. Die Brücke 24 ist im mittleren Teil als Ring ausgebildet, der ein Innengewinde zur Aufnahme einer Installationsdose 25 mit entsprechendem Außengewinde besitzt. Durch eine Verdrehung der Dose 25 ist eine Höheneinstellung in bekannter Weise möglich. Auch der Kanal 1 gemäß Fig. 3 besitzt Bodenleisten 14 zur Bildung von Nuten 15, in die beim Einsatz einer Brücke, die einen Stützfuß entsprechend dem Stützfuß 12 in Fig. 1 besitzt, dessen Unterkante eingreifen kann.In Fig. 3 is a cross section through a further installation channel 1 shown, which also has a bottom 2 and side walls 3 and essentially differs from channel 1 in FIG. 1 only in terms of its dimensions. As an example is instead of an asymmetrical bridge 4 according to FIG. 1, a bridge 24 is shown in FIG. 3, which carries an installation box 25. A top view of the bridge 24 is shown in FIG Bridge 24, like bridge 4, has locking strips 29 on both sides, each with a locking edge 30 and an inclined surface 31. tEt the locking strips 29 is the bridge snapped into the grooves 5 in the same way as in the embodiment according to Fig. 1 are formed. The bridge 24 is designed as a ring in the middle part, an internal thread for receiving an installation box 25 with a corresponding Has external thread. By a twist of the can 25 is one Height adjustment possible in a known manner. The channel 1 according to FIG. 3 also has Bottom strips 14 to form grooves 15 in which when using a bridge that has a support foot corresponding to the support foot 12 in Fig. 1, the lower edge of which can intervene.

Der Installationskanal 1 bei dem Ausführungsbeispiel 5, ist, abgesehen von abweichenden Querabmessungen identisch mit dem Kanal 1 in Fig. 3. Im dargestellten Fall ist in den Kanal eine aus zwei Abschnitten 26,27 bestehende geteilte Haltebrücke eingesetzt. Jeder Abschnitt ist mit Rastleisten 29 gleich denen der Brücke 24 (Fig. 3,4) in Nuten 5 befestigt. Zusätzlich besitzt jeder Abschnitt einen Stützfuß 32, dessen Unterkante 33 in die Bodenlängsnut 15 eingreift, die wiederum durch eine Leiste 14 und die zugehörige Wand 3 des Kanals gebildet wird.The installation duct 1 in the embodiment 5 is apart of deviating transverse dimensions identical to channel 1 in FIG. 3. In the illustrated The case is a split retaining bridge consisting of two sections 26, 27 in the channel used. With locking strips 29, each section is the same as those of the bridge 24 (Fig. 3, 4) fastened in grooves 5. In addition, each section has a support leg 32, whose lower edge 33 engages in the bottom longitudinal groove 15, which in turn by a Bar 14 and the associated wall 3 of the channel is formed.

Nach dem Einsetzen der beiden Abschnitte 26,27 können diese zum Einlegen von Kabeln auseinandergebogen werden. Danach greifen die überlappend aufeinanderliegenden Endabschnitte mit einer Verzahnung 34 ineinander, die durch eine unsymmetrische Ausbildung der Zahnflanken nach Art von Sperrklinken dafür sorgt, daß eine Sperrung gegen eine Aufweitung der Kanalseitenwände 3 bewirkt wird.After the two sections 26, 27 have been inserted, they can be inserted be bent apart by cables. Then the overlapping ones grip each other End sections with a toothing 34 into one another, which by an asymmetrical Formation of the tooth flanks in the manner of pawls ensures that a lock against an expansion of the channel side walls 3 is effected.

Bei allen Ausführungsbeispielen ist der Installationskanal 1 am oberen Rand und auf der Außenseite der Wände 3 mit einer in Längsrichtung verlaufenden Kerbe 35 versehen, die zur einschnappenden Befestigung eines Deckels (nicht dargestellt) dient.In all exemplary embodiments, the installation channel 1 is at the top Edge and on the outside of the walls 3 with a longitudinal direction Notch 35 is provided, which is used for snap-fastening a cover (not shown) serves.

LeerseiteBlank page

Claims (8)

Patentansprüche 1. Installationskanal zur Leitungsverlegung und zum Geräteeinbau mit einem Boden und zwei Seitenwänden, die am Oberrand in Längsrichtung des Kanals verlaufende Lagerstellen zur Aufnahme der Geräte- und Leitungsbrücken aufweisen, d a d u r c h g e k e n n z e i c h n e t, daß die Lagerstellen als Rastnuten (5) für die Brücken (4; 24; 26,27) ausgebildet sind. Claims 1. Installation duct for laying cables and for Device installation with a base and two side walls, which are longitudinally at the upper edge Bearing points running along the channel to accommodate the device and cable bridges show that the bearing points as locking grooves (5) for the bridges (4; 24; 26,27) are formed. 2. Installationskanal nach Anspruch 1, dadurch gekennzeichnet, daß die Rastnuten (5) eine an der Oberseite in die Nut hineinragende, im Querschnitt rastnasenförmige Rastkante (6) besitzen, die zum Inneren des Kanals hin eine Schrägfläche (8) aufweist, und daß die Brücken (4; 24; 26,27) mit an die Rastnuten (5) angepaßten Rastleisten (9,29) ausgestattet sind, die auf der Außenseite ebenfalls eine mit der Schrägfläche (8) der Rastkante (6) zusammenwirkende Schrägfläche (11) aufweist.2. Installation duct according to claim 1, characterized in that the locking grooves (5) projecting into the groove at the top, in cross section Latch-shaped locking edge (6) have an inclined surface towards the interior of the channel (8), and that the Bridges (4; 24; 26,27) with the locking grooves (5) adapted locking strips (9.29) are equipped, which are also on the outside an inclined surface (11) cooperating with the inclined surface (8) of the locking edge (6) having. 3. Installationskanal nach Anspruch 1 oder 2, dadurch gekennzeichnet, daß die Brücke (4; 26,27) auf einer Seite eine zum Boden (2) des Kanals (1) hinunterführende Stütze (12,32) aufweist, deren Unterkante (13,33) in eine Bodenlängsnut (15) des Kanals eingreift.3. Installation duct according to claim 1 or 2, characterized in that that the bridge (4; 26,27) on one side leads down to the bottom (2) of the channel (1) Support (12,32), the lower edge (13,33) in a bottom longitudinal groove (15) of the Channel intervenes. 4. Installationskanal nach Anspruch 3, dadurch gekennzeichnet, daß die Brücke in zwei Abschnitte (26,27) unterteilt ist, die sich gegenüberliegend in den Kanal (1) einrastbar sind und je eine zum Boden (2) des Kanals (1) hinunterführende Stütze (32) aufweisen, deren Unterkante (33) in eine Bodenlängsnut (15) des Kanals eingreift, und daß die freien Enden der Brückenabschnitte (26, 27) sich überlappen und an der Überlappungsstelle mit einer einklinkenden Verzahnung (34) versehen sind.4. Installation duct according to claim 3, characterized in that the bridge is divided into two sections (26,27) facing each other can be snapped into the channel (1) and one each leading down to the bottom (2) of the channel (1) Have support (32), the lower edge (33) of which in a bottom longitudinal groove (15) of the channel engages, and that the free ends of the bridge sections (26, 27) overlap and are provided with engaging teeth (34) at the point of overlap. 5. Installationskanal nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Rastleiste (19) an einem federnden Endabschnitt (17) der Brücke (4) angeordnet ist, derart, daß die Verbindung mit der Rastkante (6) des Kanals (1) leicht lösbar ist.5. Installation duct according to one of the preceding claims, characterized characterized in that the locking strip (19) at a resilient end portion (17) of the Bridge (4) is arranged in such a way that the connection with the locking edge (6) of the Channel (1) is easily detachable. 6. Installationskanal nach Anspruch 5, dadurch gekennzeichnet, daß die Rastleiste (19) an einem durch zwei Schlitze (16) gebildeten mittleren Endabschnitt der Brücke (4) angeordnet ist, so daß die Rastverbindung durch Fingerdruck lösbar ist, und daß die seitlichen Endab-Schnitte (18) so ausgebildet sind, daß sie ohne Einrasten tragend in der Rastnut (5) des Kanals liegen.6. Installation duct according to claim 5, characterized in that the locking strip (19) at a central end section formed by two slots (16) the bridge (4) is arranged so that the locking connection can be released by finger pressure is, and that the lateral Endab-cuts (18) are designed so that they are without Latch in place in the locking groove (5) of the channel. 7. Installationskanal nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Brücke (4) mit einem Griffloch (20) versehen ist.7. Installation duct according to one of the preceding claims, characterized characterized in that the bridge (4) is provided with a grip hole (20). 8. Installationskanal nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß die Rastnut und/oder die Bodenlängsnut mit Nocken zur Verschiebungssicherung ausgestattet ist.8. Installation duct according to one of the preceding claims, characterized characterized in that the locking groove and / or the bottom longitudinal groove with cams to prevent displacement Is provided.
DE19782804419 1978-02-02 1978-02-02 cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position Withdrawn DE2804419A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19782804419 DE2804419A1 (en) 1978-02-02 1978-02-02 cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19782804419 DE2804419A1 (en) 1978-02-02 1978-02-02 cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position

Publications (1)

Publication Number Publication Date
DE2804419A1 true DE2804419A1 (en) 1979-08-09

Family

ID=6030976

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19782804419 Withdrawn DE2804419A1 (en) 1978-02-02 1978-02-02 cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position

Country Status (1)

Country Link
DE (1) DE2804419A1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0054456A1 (en) * 1980-11-21 1982-06-23 Aparellaje Electrico, S.A. Detachable apparatus for reinforcing cable-ways or trunking intended to contain electrical conductors
US5792992A (en) * 1993-12-08 1998-08-11 Zorba Industries, Inc. Expandable surface raceway for wiring
DE19814567A1 (en) * 1998-04-01 1999-10-21 Kleinhuis Hermann Gmbh Flush mounting box for use with cable ducts, in particular dado ducting
EP0971466A1 (en) * 1998-07-08 2000-01-12 Hermann Kleinhuis GmbH. & Co. KG Built-in box for use in cable-ducts such as wall trunking
DE202011005478U1 (en) 2011-04-20 2011-06-30 GGK GmbH & Co. KG, 35753 Adapter for installing device mounting boxes in cable trunking systems
DE202022102609U1 (en) 2022-05-12 2022-05-25 Ggk Gmbh & Co Kg Multiple adapter for installing multiple device installation sockets on a cable routing duct

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0054456A1 (en) * 1980-11-21 1982-06-23 Aparellaje Electrico, S.A. Detachable apparatus for reinforcing cable-ways or trunking intended to contain electrical conductors
US5792992A (en) * 1993-12-08 1998-08-11 Zorba Industries, Inc. Expandable surface raceway for wiring
DE19814567A1 (en) * 1998-04-01 1999-10-21 Kleinhuis Hermann Gmbh Flush mounting box for use with cable ducts, in particular dado ducting
DE19814567C2 (en) * 1998-04-01 2000-03-30 Kleinhuis Hermann Gmbh Installation box for use in cable ducts, such as parapet ducts
EP0971466A1 (en) * 1998-07-08 2000-01-12 Hermann Kleinhuis GmbH. & Co. KG Built-in box for use in cable-ducts such as wall trunking
DE202011005478U1 (en) 2011-04-20 2011-06-30 GGK GmbH & Co. KG, 35753 Adapter for installing device mounting boxes in cable trunking systems
DE202022102609U1 (en) 2022-05-12 2022-05-25 Ggk Gmbh & Co Kg Multiple adapter for installing multiple device installation sockets on a cable routing duct

Similar Documents

Publication Publication Date Title
DE19841643B4 (en) Cable tray made of sheet metal
EP1587195B1 (en) Cable channel system
DE3113679A1 (en) Installation apparatus box for installation in installation channels (ducts)
DE3708357A1 (en) Cable installation duct
DE19649134A1 (en) Cable duct for electrical installation or apparatus
EP0248160B1 (en) Support for bus bars
DE2804419A1 (en) cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position
DE4323370A1 (en) Profiled strip made of insulating material for holding a large number of electrical cables (leads, lines)
DE3642895A1 (en) ELECTRODOSE FOR CABLE CONNECTIONS, ESPECIALLY FOR CABLE CHANNELS
EP3647513A1 (en) Pipe attachment
EP0018597A1 (en) Mounting, especially for placing and fixing floor-heating pipes on floors
DE202004003393U1 (en) Quick build prefabricated wall modules
DE202007006989U1 (en) Cutting lamination for cable ducts
DE3717363A1 (en) SOCKET FOR MOUNTING IN A CABLE RAIL
DE2803972C2 (en) Meter and distributor cabinet made from plastic extruder profiles
DE7803034U1 (en) Installation channel
DE102016124609A1 (en) Distribution box for installation in a wall opening
DE1962889C3 (en) Wall or ceiling cladding with slats
DE202007010127U1 (en) Bridging clamp for securing cables and wires in cable ducts
DE19828082A1 (en) Plastic wiring ducts with side panels for electrical installations
DE3441377A1 (en) Cable duct for holding installation lines
CH445595A (en) Installation duct for laying electrical cables
EP0524504A1 (en) Rectangular concrete building element with channel shaped cavity for the production of a sealed guttering system
EP2270403A1 (en) Bearing rail
DE102023111613A1 (en) Device for attaching electrotechnical units to cable ducts

Legal Events

Date Code Title Description
8139 Disposal/non-payment of the annual fee