DE2754874A1 - Multiple purpose mine gallery working platform - has telescopic column on front half, with tilting cross member carrying holders - Google Patents

Multiple purpose mine gallery working platform - has telescopic column on front half, with tilting cross member carrying holders

Info

Publication number
DE2754874A1
DE2754874A1 DE19772754874 DE2754874A DE2754874A1 DE 2754874 A1 DE2754874 A1 DE 2754874A1 DE 19772754874 DE19772754874 DE 19772754874 DE 2754874 A DE2754874 A DE 2754874A DE 2754874 A1 DE2754874 A1 DE 2754874A1
Authority
DE
Germany
Prior art keywords
lifting device
route
platform
working platform
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19772754874
Other languages
German (de)
Inventor
Helmut Heisterkamp
Harry Janowski
Walter Knaebe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
RAG AG
Original Assignee
Ruhrkohle AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ruhrkohle AG filed Critical Ruhrkohle AG
Priority to DE19772754874 priority Critical patent/DE2754874A1/en
Publication of DE2754874A1 publication Critical patent/DE2754874A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms

Abstract

The multiple purpose working platform for mines has a front part (4) and rear part (5) supported by vertical members (22, 23) suspended from trolleys (6, 20) travelling along rails in turn supported from overhead chains (10, 11, 12). The rear part (4) carries a crane for lifting roof cladding members etc., and the front part (4) carries a telescopic support (36) with a forked member (63) at the top carrying a horizontal square section beam (65) across it. The forked member can tilt about a horizontal hinge pin (61), and the beam (65) has a set of e.g. three V shaped carries (66, 67, 68) along it. Between the beam and the top telescopic members is a hydraulic cylinder forming part of a tilting mechanism.

Description

"Mehrzweckbühne für den Streckenvortrieb im Untertage-"Multi-purpose platform for tunneling in underground

berg- und Tunnelbau Die Erfindung betrifft eine MehrzweckbUhne für den Streckenvortrieb im Untertageberg- und Tunnelbau mit einer auf einem Rahmen ausgebildeten Arbeitsplattform, die über Hebezeuge anhebbar und absenkbar und mit mehreren Laufkatzen längs einer oder mehrerer nebeneinander angeordneter Laufschienen in Streckenlängsrichtung fahrbar ist und ein mit einem Hinterteil fluchtendes und mit diesem eine Baueinheit bildendes Vorderteil des Rahmens und der Plattform sowie eine Ausbauhilfe aufweist, welche eine Hubvorrichtung und einen Hubbalken mit mehreren längs des Hubbalkens im Abstand angeordneten gabelförmigen Konsolen zur Aufnahme des Ausbauprofiles der Firstsegmente des Streckenausbaus aufweist. mining and tunneling The invention relates to a multi-purpose platform for tunneling in underground mining and tunneling with one on one frame trained work platform that can be raised and lowered via hoists and with several trolleys along one or more side-by-side rails is movable in the longitudinal direction and is aligned with a rear part and with this a structural unit-forming front part of the frame and the platform as well has an expansion aid, which has a lifting device and a lifting beam with several Fork-shaped consoles arranged at a distance along the lifting beam for receiving of the expansion profile of the ridge segments of the route expansion.

Solche Vorrichtungen dienen zur Durchführung möglichst aller Arbeiten, die von einem oberhalb der Streckensohle gelegenen erhöhten Standplatz aus durchgeführt werden. Dazu gehört z.B. das Montieren der Verbindungen zwischen den ein- oder mehrteiligen Firstsegmenten und den dazugehörigen Stempeln, aber auch das Abbbohren bestimmter Schüsse in der Firste und einen gegebenenfalls anzuwendenden Einbruch. Vielfach dienen Mehrzweckbühnen darüberhinaus zur Verlagerung weiterer Vorrichtungen, die beim Streckenvortrieb benötigt werden. In Betracht kommen insoweit beispielsweise Schutzgitter zur Abdeckung der Ortsbrust und gegebenenfalls Bohrlafetten.Such devices are used to carry out as much work as possible, which are carried out from an elevated stand above the bottom of the route will. This includes, for example, assembling the connections between the one-part or multi-part Ridge segments and the associated stamps, but also the drilling off of certain Shots in the roof and a possible break-in. Multiple Multipurpose platforms also serve to relocate other devices, the are required when driving. In this respect, for example, come into consideration Protective grille to cover the face and, if necessary, drill mounts.

Zu solchen Vorrichtungen gehört auch die eingangs erwähnte Ausbauhilfe, welche das Einbauen der Streckenrahmen erleichtern soll.Such devices also include the removal aid mentioned at the beginning, which should facilitate the installation of the track frame.

Eine Mehrfachbühne mit den eingangs bezeichneten Merkmalen ist bekannt (DT-PS 24 57 247). Bei der bekannten Vorrichtung verläuft der Hubbalken quer zur Streckenlängsrichtung und hat zwei Konsolen zur Unterstützung eines Firstsegmentes. Die Hebevorrichtung dient dazu, das zunächst in die Konsolen eingelegte Firstsegment anzuheben und an die Streckenfirste zu pressen, bis durch Setzen der Stempel der betreffende Ausbaurahmen vollendet ist. Diese Arbeitsweise setzt beim Ausbauen eines Abschlages das mehrfache Absenken und Anheben der Bühne voraus und hat den Nachteil eines verhältnismäßig geringen Rationalisierungsgrades. Ihre Arbeitsweise stößt neuerdings auch auf Schwierigkeiten, welche durch die im Hinblick auf die Verletzungsgefahr durch fallende Gegenstände im Streckenvortrieb ergangenen bergbehördlichen Vorschriften bedingt sind. Diese Vorschriften schreiben eine Vorpfändung in den Abschlagbereich zwingend vor, welche in dem zunächst nicht ausgebauten Raum zwischen der Ortsbrust und dem letzten der vollständig gesetzten Streckenbaue eine weitgehende Abdeckung der Firste vorsieht, unter deren Schutz die Arbeiten in diesem Streckenabschnitt durchgeführt werden sollen.A multiple stage with the features mentioned at the beginning is known (DT-PS 24 57 247). In the known device, the walking beam runs transversely to Longitudinal direction and has two consoles to support a ridge segment. The lifting device serves to lift the ridge segment that is initially inserted into the consoles to be lifted and pressed against the ridge of the route until the stamp is set relevant expansion frame is completed. This way of working is used when expanding a The downsizing is the multiple lowering and raising of the stage and has the disadvantage a relatively low degree of rationalization. Your way of working comes across recently also to difficulties caused by the risk of injury Mining authority regulations issued by falling objects while driving are conditional. These regulations write a pre-attachment in the discount area compulsory, which in the initially not developed space between the face and the last of the completely set track structures provide extensive coverage the roof provides under whose protection the work in this section of the route should be carried out.

Bekannt ist das Vorpfänden mit mehreren Vorpfändschienen, die jeweils mit mehreren Konsolen auf einigen der bereits stehenden Streckenrahmen aufgehängt werden und in den nicht ausgebauten Streckenabschnitt vorgezogen werden können. Auf diese Vorpfändschienen werden die Firstsegmente aufgelegt, die dann verzogen und schließlich mit den Stempeln zu den Bauen vervollständigt werden.The pre-pledging is known with several pre-pledging rails, each with multiple consoles on some of the already standing route frame can be hung up and moved to the undeveloped section of the route can. The ridge segments are placed on these Vorpfändschienen, which then warped and finally completed with the stamps on the buildings.

Auch diese Arbeitsweise stößt neuerdings auf Schwierigkeiten, weil die Bergbehörden eine zusätzliche Bohlenabdeckung und mehr als zwei Vorpfändschienen je Streckenort vorschreiben, um die Gefährdung durch fallende Gegenstände auszuschließen. Dann aber wi-d dieses bislang vielfach bekannte und angewandte Vortriebsverfahren unwirtschaftlich.This way of working has recently encountered difficulties because the mining authorities an additional plank cover and more than two pre-pledging rails Prescribe for each route location in order to exclude the risk of falling objects. But then this tunneling method, which has been widely known and used so far, will be used uneconomical.

Bekannt ist ferner eine Mehrzweckbühne (Zeitschrift Glückauf 110, 74 Nr. 21, 22 896, 897 und 943, 948).A multi-purpose stage is also known (Glückauf 110 magazine, 74 No. 21, 22 896, 897 and 943, 948).

Die Arbeitsplattform ist nur unmittelbar unterhalb der Ausbauhilfe angeordnet und wird mit der Hubvorrichtung der Ausbauhilfe angehoben und abgesenkt. Die Ausbauhilfe hat einen in Streckenlängsrichtung angeordneten Hubbalken mit mehreren im Abstand voneinander angeordneten gabelförmigen Konsolen, so daß alle Firstsegmente eines Abschlages gleichzeitig angehoben werden können. Die Firstsegmente eines Abschlages werden mit einer solchen Mehrzweckbühne durch Einbringen der mit Drähten auf den Segmenten befestigten Verzugmatten und der Abstandsbolzen zu einem tragfähigen Schutzdach verbunden, das im Abstand vor Ort montiert und dann nach vorn in den Abschlagbereich gefahren wird, wo die Hubvorrichtung das Dach zunächst bis zum Anschluß an den bereits stehenden Streckenausbau und dann bis zur Anlage an die Streckenfirste anhebt. Danach können alle weiteren Arbeiten unter dem Schutz des Daches durchgeführt werden (DT-PS 64 61 454).The work platform is only directly below the expansion aid arranged and is raised and lowered with the lifting device of the removal aid. The expansion aid has a lifting beam with several in the longitudinal direction of the route at a distance from each other fork-shaped consoles, so that all ridge segments of a discount can be raised at the same time. The ridge segments of a tee can be achieved with such a multi-purpose platform by inserting the wires onto the Segments attached warping mats and the spacer bolts to a stable protective roof connected, mounted at a distance on site and then forward into the tee area is driven, where the lifting device is the roof first up to the connection to the already the existing track extension and then lifts up to the system on the roof of the track. Thereafter all further work can be carried out under the protection of the roof (DT-PS 64 61 454).

Die bergbehördlichen Vorschriften schreiben für derartige Ausbauhilfen jedoch neuerdings verhältnismäßig hohe Andruckkräfte vor, die u.a. von der Sohlenbreite und der Anzahl der Baue abhängen, deren Firstsegmente in dem Kappenschirm vereinigt sind. Das ergibt sich daraus, daß der Kappenschirm bereits bei seiner Anlage an die Streckenfirste als Ausbau wirken soll und deswegen der Ausbauwi-derstand von der Hubvorrichtung aufgebracht werden muß. Beispielsweise liegen die Andrücke in Größenordnungen von 16 - 20 t. Die hierzu erforderlichen Kräfte sind so groß, daß sie nur nach erheblicher Verstärkung der Hubvorrichtung und der Teileaufgebracht werden können, welche die Reaktionskräfte auf die Streckenfirste übertragen. Außerdem ist es nachteilig, daß die Arbeitsplattform nicht so weit verlängert werden kann, daß sie auch in den bereits ausgebauten Teil der Strecke reicht. Das scheitert daran, daß die Tragkonstruktion zur Übertragung der Stützkräfte auf den bereits stehenden Ausbau zuviel Höhe einnimmt, so daß z.B. für das Bohren nicht mehr genug Arbeitsraum zur Verfügung gestellt werden kann. Die zur Abhilfe vorgesehenen Bohrlafetten haben den Nachteil, daß mit ihnen wichtige Schüsse bei Keileinbrüchen nicht gebohrt werden können.The mining authority regulations write for such expansion aids however, recently there have been relatively high pressure forces, which, among other things, depend on the width of the sole and the number of burrows, the ridge segments of which are united in the canopy are. This results from the fact that the parachute is already on when it is installed the ridge of the line should act as an expansion and therefore the expansion resistance of the lifting device must be applied. For example, the pressures are in Orders of magnitude from 16 - 20 t. The forces required for this are so great that it is only applied after the lifting device and parts have been considerably strengthened which transfer the reaction forces to the road ridges. aside from that it is disadvantageous that the work platform cannot be extended so far, that it extends into the already developed part of the route. That fails because that the supporting structure to transfer the supporting forces to the already standing Expansion takes up too much height, so that, for example, there is no longer enough working space for drilling can be made available. Have the drill mounts provided for remedial action the disadvantage that important shots are not drilled with them in the event of wedge break-ins can.

Der Erfindung liegt deshalb die Aufgabe zugrunde, die eingangs bezeichnete Mehrzweckbühne weiter zu entwickeln und zwar so, daß sie in dem zunächst ausgebauten Streckenabschnitt einen durch einen Kappenschirm der bekannten Art ausgebauten Arbeitsraum ermöglicht.The invention is therefore based on the object specified at the outset Multi-purpose stage to be further developed in such a way that it can be used in the initially expanded Route section a working area expanded by a canopy of the known type enables.

Gemäßder Erfindung wird diese Aufgabe dadurch gelöst, daß der Hubbalken in Streckenlängsrichtung verlaufend angeordnet ist, die Hubvorrichtung die in den Konsolen liegenden Firstsegmente bis zur Auflage auf für sich bekannte Vorpfändschienen untersetzt und das Vorderteil der Arbeitsplattform in etwa bis unter die vordere Hubbalkenkonsole reicht.According to the invention, this object is achieved in that the walking beam running in the longitudinal direction is arranged, the lifting device the ridge segments lying in the consoles up to the point where they are known for themselves Vorpfändschienen stocky and the front part of the working platform in about up reaches under the front walking beam console.

Die Arbeitsweise mit dieser Bühne ist ebenfalls neuartig. Zwar wird entsprechend der eingangs bezeichenten bekannten Arbeitsweise aus mehreren oder allen Firstsegmenten eines Abschlages der Kappenschirm auf dem Hubbalken montiert und mit der Arbeitsbühne in das Ort gefahren. Dort wird der Kappenschirm aber lediglich so weit angehoben, daß er sofort mit den in bekannter Anzahl und Anordnung vorgesehenen Vorpfändschienen unterfangen werden kann. Da anders als bei dem herkömmlichen Verfahren die Firstsegmente nicht mehr vor Ort verzogen und mit Abstandhaltern versehen werden müssen, sondern eine bereits tragfähige Konstruktion darstellen, entfallen die bergbehördlich vorgeschriebe Bohlensicherung und der erhöhte Andurck.The way of working with this stage is also new. True will in accordance with the known method of operation referred to at the outset consisting of several or all ridge segments of a tee, the canopy is mounted on the lifting beam and drove into the place with the work platform. There the canopy is only there raised so far that it can immediately be compared with those provided in the known number and arrangement Vorpfändschienen can be underpinned. As different from the conventional method the ridge segments are no longer warped on site and provided with spacers must, but represent an already stable construction, the mining authorities do not apply prescribed screed protection and the increased pressure.

Deswegen braucht die Hubvorrichtung nur noch die zum Anheben des Kappenschirmes notwendigen Tragkräfte aufzuweisen, benötigt aber keine Vorspannkräfte.Therefore, the lifting device only needs to lift the canopy have the necessary load-bearing capacities, but do not require any pre-tensioning forces.

Hieraus ergeben sich mehrere Vorteile. Die Rahmenkonstruktion der Arbeitsplattform kann ohne Schwierigkeiten so vergrößert werden, daß das Vorderteil die gesamte Länge des Kappenschirmes aufweist und mit dem Hinterteil eine Baueinheit bildet. Auf einer derart großen Arbeitsplattform können alle Arbeiten durchgeführt werden. Insbesondere lassen sich Sprengschüsse einwandfrei abbohren, die einen Standort oberhalb der Sohle und eine starke Neigung erfordert, wie beispielsweise bestimmte Sprengschüsse eines Keileinbruches.This has several advantages. The frame construction of the Working platform can be enlarged so that the front part has the entire length of the canopy and a structural unit with the rear part forms. All work can be carried out on such a large working platform will. In particular, explosive shots can be properly drilled from a location above the Sole and a steep slope requires, such as certain explosive shots of a wedge break-in.

Vorzugsweise und gemäß einem weiteren Merkmal der Erfindung ist der Hubbalken mit einem Horizontalgelenk an einen ausfahrenden Teil der Hubvorrichtung angeschlossen und wird wiStmit einem Schwenkantrieb zusammen. Hierdurch ist es möglich, in einfallenden oder ansteigenden Streckenvortrieben den Kappenschirm so auszurichten, daß er dem Verlauf der Firste und der Vorpfändschienen folgen kann. Außerdem lassen sich mit dieser Vorrichtung Abweichungen der Vorpfändschienen von dem vorgegebenen Firstverlauf ausgleichen.Preferably and according to a further feature of the invention is the Lifting beam with a horizontal joint on an extending part of the lifting device connected and is combined with a rotary actuator. This makes it possible align the canopy in inclined or ascending drifts in such a way, that he can follow the course of the roof and the pre-pledging rails. Besides, let With this device deviations of the pre-pledging rails from the specified Compensate for the ridge.

Bei einer anderen Ausführungsform der Erfindung ist außerdem vorgesehen, die Hubvorrichtung auf einem Wagen zu befestigen, für den auf der Arbeitsplattform eine in Streckenlängsrichtung verlaufende Gleisführung vorgesehen ist. Dadurch ist man bezüglich des Bühnenstandortes in gewissen Grenzen frei und kann die Stellung der Laufkatzen wählen. Andererseits kann man durch Verfahren der Hubvorrichtung den vorgeschriebenen Bauabstand zwischen dem letzten der bereits stehenden Streckenrahmen und dem ortsabgewandten Firstsegment des Kappenschirmes herstellen.In another embodiment of the invention it is also provided to mount the lifting device on a trolley for the one on the work platform a track running in the longitudinal direction is provided. This is you are free within certain limits with regard to the location of the stage and you can change the position choose of trolleys. On the other hand, you can move the lifting device the stipulated construction distance between the last of the already standing track frames and produce the remote ridge segment of the canopy.

Die Hubvorrichtung besteht zweckmäßig aus einem Mehrfachteleskop und einem zwischen dem äußersten und dem innersten Teleskopglied wirkenden Schubkolbengetriebe.The lifting device expediently consists of a multiple telescope and a thrust piston mechanism acting between the outermost and the innermost telescopic member.

Die Einzelheiten, weiteren Merkmale und andere Vorteil der Erfindung ergeben sich aus der nachfolgenden Beschreibung einer Ausführungsform anhand der Figuren in der Zeichnung; es zeigen Fig. 1 in Seitenansicht eine Übersichtsdarstellung der neuen Mehrzweckbühne, Fig. 2 eine Stirnansicht des Gegenstandes der Fig. 1, Fig. 3 eine Ansicht, Draufsicht und Seitenansicht der Ausbauhilfe und Fig. 4 eine Einzelheit aus der Darstellung der Fig. 2.The details, other features, and other advantages of the invention emerge from the following description of an embodiment based on FIG Figures in the drawing; 1 shows a side view Overview of the new multi-purpose platform, Fig. 2 is a front view of the object 1, 3 show a view, top view and side view of the removal aid and FIG. 4 shows a detail from the illustration in FIG. 2.

Die Mehrzweckbühne nach den Figuren 1 und 2 besitzt einen Rahmen 1 ausgehreren in Streckenlängsrichtung verlaufenden I-Trägern 2 und mehreren quer dazu verlaufenden Trägern aus I-Profil von denen einer mit 3 bezeichnet ist. Der Rahmen dient zur Unterstützung einer Arbeitsplattform, die allgemein mit 4 bezeichnet ist und von einem Bohlenbelag 5 gebildet wird. Die Bühne besitzt ein Hinterteil, das bis zu einer ersten Gruppe von Laufkatzen reicht, die in Fig. 2 mit 6 und 7 bezeichnet sind. Die Laufkatzen fahren auf je einer Hängeschiene 8 bzw. 9, die in der Firste des ausgebauten Streckenteiles, wie bei 10, 11 und 12 angedeutet, abgehängt sind. Dieses Hinterteil der Arbeitsplattform ist mit 15 bezeichnet.The multi-purpose stage according to FIGS. 1 and 2 has a frame 1 several I-beams 2 and several transversely running in the longitudinal direction of the route supporting beams made from an I-profile, one of which is denoted by 3. Of the The frame is used to support a work platform, which is generally designated by 4 is and is formed by a plank covering 5. The stage has a rear part which extends to a first group of trolleys, which in Fig. 2 with 6 and 7 are designated. The trolleys each run on a hanging rail 8 or 9, which in the roof of the expanded section of the route, as indicated at 10, 11 and 12, is suspended are. This rear part of the work platform is denoted by 15.

Die erwähnten Laufkatzen 6 und 7 sind über Kuppelstangen 16 mit einer Antriebskatze 18 verbunden.The mentioned trolleys 6 and 7 are via coupling rods 16 with a Drive trolley 18 connected.

Weitere Kuppelstangen 19 dienen zum Anschluß von hinteren Laufkatzen 20, die wie die Laufkatzen 6 und 7 auf Hängeschienen angebracht sind.Further coupling rods 19 are used to connect rear trolleys 20, which, like the trolleys 6 and 7, are mounted on hanging rails.

Die Laufkatzen 20 sowie 6 und 7 sind jeweils mit einem Hebezeug versehen, das einerseits von Schubkolbengetrieben 22, 23 und andererseits von Sicherungsketten 24, 25 (Fig. 2) gebildet wird. Im rückwärtigen Beach des Hinterteiles befindet sich ein Luft- und Wasserverteiler 26 sowie eine ebenfalls aus einem Schubkolbengetriebe bestehende Abstützung 27. Ein Kran 28 dient zum Anheben von Gegenständen, die auf der Arbeitsplattform benötigt werden.The trolleys 20 as well as 6 and 7 are each provided with a hoist, on the one hand by push piston gears 22, 23 and on the other hand by safety chains 24, 25 (Fig. 2) is formed. In the back beach of the rear part is located an air and water distributor 26 as well as one also from a push piston gear existing support 27. A crane 28 is used to lift objects that are on the work platform are required.

Ein Vorderteil 30 der Arbeitsplattform bildet mit dem Hinterteil eine Baueinheit. Auf der dementsprechend nach vorn verlängerten Rahmenkonstruktion ist ein Fahrgleis 31 ausgebildet, auf dem ein mit vier Rädern ver-33 sehener Wagen 32 mit Hilfe eines EIydraulFkzylinders /verfahr bar ist. Der Wagen fährt unterhalb des mit 34 im Vorderteil der Bühne bezeichneten Bohlenbelages und trägt eine Ausbauhilfe, deren Einzelheiten aus der Darstellung der Fig. 3 ersichtlich sind. Die Ausbauhilfe hat als wesentlichen Teil eine Hubvorrichtung, die allgemein mit 36 bezeichnet ist. Sie ist als Teleskop ausgebildet.A front part 30 of the work platform forms one with the rear part Unit. On the frame structure that has been extended to the front accordingly a track 31 is formed on which a carriage 32 provided with four wheels is movable with the help of an hydraulic cylinder. The car drives underneath of the plank covering marked 34 in the front part of the stage and carries an expansion aid, the details of which can be seen from the illustration in FIG. The expansion aid has a lifting device, which is generally designated by 36, as an essential part. It is designed as a telescope.

Das Teleskop hat einen rechteckigen Querschnitt. Das äußerste Teleskopglied 37 trägt auf Konsolen 38 Achsstummel 39 für Rollen 40, die auf den Unterflanschen 41 bzw. 42 von Längsträgern 43 bzw. 44 des Bühnenrahmens verfahrbar sind. In dem äußersten Teleskopglied 37 befindet sich ferner eine Konsole 45 zum gelenkigen Anschluß des Kolbens 46 eines Schubkolbengetriebes 47, dessen Kolbenstange 48 in das innerste Teleskopglied 49 der Hubvorrichtung 36 reicht und an dessen Stirnplatte 50 befestigt ist. Das innerste Teleskopglied ist mit Führungen 51 bzw. 52 versehen und leitet in einem mittleren Teleskopglied 53, das seinerseits Führungen 54 bzw. 55 für das innerste Teleskopglied 49 aufweist. Eine entsprechende Führung ist bei 58 und 59 im äußersten Teleskopglied 37 vorgesehen.The telescope has a rectangular cross-section. The outermost telescopic link 37 carries on brackets 38 stub axles 39 for rollers 40 on the lower flanges 41 and 42 of longitudinal members 43 and 44 of the stage frame can be moved. By doing outermost telescopic member 37 is also a bracket 45 for articulated connection of the piston 46 of a thrust piston mechanism 47, the piston rod 48 of which in the innermost Telescopic member 49 of lifting device 36 is sufficient and attached to its end plate 50 is. The innermost telescopic member is provided with guides 51 and 52 and guides in a central telescopic member 53, which in turn guides 54 or 55 for the innermost telescopic member 49. Appropriate guidance is provided at 58 and 59 in the outermost telescopic link 37.

Auf der erwähnten Stirnplatte 56 befindet sich die Buchse 60 eines allgemein mit 61 bezeichneten Horizontalgelenkes, dessen Gelenkbolzen bei 62 wiedergegeben ist. Der Gelenkbolzen sitzt in einer Gabel 63, die ihrerseits an der Unterseite eines als Kastenträger ausgebildeten Hubbalken 65 befestigt ist. Auf dem Hubbalken sind mehrere und insbesondere aus der Darstellung der Fig.1ersichtliche gabelförmige Konsolen 66, 67, 68 angebracht, wobei gemäß dem in Fig.1 wiedergegebenen Ausführungabeispiel drei Baue zum Ausbau eines Abschlages vorgesehen sind.On the face plate 56 mentioned there is a bushing 60 Horizontal joint generally designated 61, the pivot pin of which is shown at 62 is. The hinge pin sits in a fork 63, which in turn is on the underside a lifting beam 65 designed as a box girder is attached. On the walking beam are several fork-shaped ones, particularly evident from the illustration in FIG Consoles 66, 67, 68 attached, according to the embodiment shown in Fig.1 three buildings are planned to expand a tee.

Der Hubbalken 65 wirkt itt einem allgemein mit 69 bezeichneten Schwenkantrieb zusammen. Auch hierbei handelt es sich um ein Schubkolbengetriebe, dessen Zylinder 70 über ein Horizontalgelenk 71 an eine Konsole 72 angelenkt ist, die ihrerseits am innersten Teleskopglied 49 befestigt ist. Das Ende der Kolbenstange 73 ist gabelföraig und mit einem Horizontalgelenk 74 an eine Konsole 75 angelenkt, die an der Unterseite 76 des erwähnten Hubbalken 65 befestigt ist.The lifting beam 65 acts itt a pivot drive, generally designated 69 together. Here, too, it is a question of a push-piston gear, the cylinder of which 70 is articulated via a horizontal joint 71 to a bracket 72, which in turn is attached to the innermost telescopic member 49. The end of the piston rod 73 is fork-shaped and hinged to a bracket 75 with a horizontal joint 74, which is on the underside 76 of the aforementioned lifting beam 65 is attached.

Wie die Darstellung der Fig2 erkennen läßt, hat die Bühne eine Breite, die es eritSglicht, die Bühne durch den bereits ausgebauten Streckenabschnitt zu fahren, der allgemein mit 80 bezeichnet ist. Um andererseits eine vollständige Abdeckung des Firstbereiches im Ort zu ermöglichen, kann die Bühne durch seitliche Verlängerungen 81 und 82 verbreitert werden. In der aus Fig. 4 ersichtlichen Konstruktion sind zu diesem Zweck weitere Querträger 85 an Laufkatzen 86 und 87 angebracht, welche einen Querträger 88 der Rahmenkonstruktion als Laufschiene verwenden. Die Laufkatezn weisen zu diesem Zweck Tragrollen 89 auf, die auf dem Unterflansch 90 des Querträgers 88 laufen. Außerdem sind Druckrollen 91 vorgesehen, welche die Laufkatzen führen.As the representation in Fig. 2 shows, the stage has a width which makes it possible to access the stage through the already developed section of the route drive, which is indicated generally at 80. To the other hand, full coverage of the ridge area in place to allow the stage through lateral extensions 81 and 82 are widened. In the one shown in FIG For this purpose, further cross members 85 on trolleys 86 and 87 are constructed attached, which use a cross member 88 of the frame structure as a running rail. For this purpose, the Laufkatezn have support rollers 89 on the lower flange 90 of the cross member 88 run. In addition, pressure rollers 91 are provided which the Run trolleys.

In den Längsträgern, von denen einer bei 93 in Fig. 4 wiedergegeben ist, befinden sich Ausnehmungen 94, durch die die freien Enden der Querträger 85 hindurchtreten können. Der Bohlenbelag der zur Bühnenverbreiterung dienenden Enden 98 ist bei 99 wiedergegeben.In the side members, one of which is shown at 93 in FIG is, there are recesses 94 through which the free ends of the cross members 85 can pass through. The plank covering of the ends used to widen the stage 98 is shown at 99.

Die Arbeitsweise mit der beschriebenen Bühne ist folgende: Zunächst wird die Bühne in den bereits ausgebauten Streckenabschnitt zurückgezogen. Durc4Absenken der Hebezeuge 22, 23 wird die Bühne in einen bequemen Arbeitsbereich oberhalb der Streckensohle verbracht, so daß die Firstsegmente in die gabelförmigen onsolen 66 - 68 eingelegt und dort in der eingangs beschriebenen Weise zu einem Kappenschirm vervollständigt werden können. Dann werden die Hebezeuge 22 und 23 so betätigt, daß die Bühne über die im zu durchfahrenden Streckenabschnitt stehenden Einrichtungen und Maschir,en hinweg bis vor Ort fahren kann. Dabei sreicht das vordere Laufkatzenpaar 6, 7 das Ende der Hängeschienen, überfährt es jedoch nicht. Durch Verfahren des Wagens 32 wird der richtige Abstand zwischen dem letzten der stehenden Streckenbaue und dem ortsabgewandten Firstsegment in der Gabel 68 hergestellt.The working method with the described stage is as follows: First the stage is withdrawn into the already developed section of the route. By lowering the hoists 22, 23 will be in a comfortable work area above the stage Track sole spent so that the ridge segments in the fork-shaped onsoles 66 - 68 inserted and there in the manner described at the outset to form a visor can be completed. Then the hoists 22 and 23 are operated in such a way that that the stage is above the facilities in the section to be traveled through and Maschir, en can drive away to the spot. The front pair of trolleys reaches out 6, 7 the end of the hanging rails, but does not run over it. By procedure of Car 32 becomes the correct distance between the last of the standing track structures and the remote ridge segment in the fork 68.

Dann wird der Kappenschirm so weit angehoben, daß er mit den nicht dargestellten Vorpfändschienen unterfangen werden kann. Die weiteren Arbeiten laufen dann in herkömmlicher Weise ab.Then the canopy is raised so far that it does not come into contact with the shown can be underpinned. Further work is ongoing then in a conventional manner.

Claims (5)

Patentansprüch e 1. Mehrzweckbühne für den Streckenvortrieb im Untertageberg- und Tunnelbau mit einer auf einem Rahmen ausgebildeten Arbeitsplattform, die über Hebezeuge anhebbar und absenkbar und mit mehreren Laufkatzen längs einer oder mehrerer nebeneinander angeordneter Laufschienen in Streckenlängsrichtung fahrbar ist und ein mit einem Hinterteil fluchtendes und mit diesem eine Baueinheit bildendes Vorderteil des Rahmens und der Plattform sowie eine Ausbauhilfe aufweist, welche eine Hubvorrichtung und einen Hubbalken mit mehreren längs des Hubbalkens im Abstand angeordneten gabelförmigen Konsolen zur Aufnahme des Ausbauprofiles der Firstsegmente des Streckenausbaus aufweist, dadurch gekennzeichnet, daß der Hubbalken (65) in Streckenlängsrichtung verlaufend angeordnet ist, die Hubvorrichtung (36) die in den Konsolen liegenden Firstsegmente bis zur Auflage auf für sich bekannte Vorpfändschienen unterstützt und das Vorderteil (30) der Arbeitsplattform (15) in etwa bis unter die vordere Hubbalkenkonsole (66) reicht. Patent claims e 1. Multi-purpose platform for tunneling in underground mining and tunneling with a working platform formed on a frame that extends over Hoists can be raised and lowered and with several trolleys along one or more side-by-side running rails can be moved in the longitudinal direction of the route and a front part which is aligned with a rear part and forms a structural unit therewith of the frame and the platform as well as an expansion aid which has a lifting device and a walking beam having a plurality of fork-shaped spaced apart along the walking beam Has consoles to accommodate the extension profile of the ridge segments of the route extension, characterized in that the lifting beam (65) extends in the longitudinal direction of the route is arranged, the lifting device (36) the ridge segments lying in the consoles Supported up to the support on known Vorpfändschienen and the front part (30) the work platform (15) roughly to below the front walking beam console (66) is enough. 2. Mehrzweckbühne nach Anspruch 1, dadurch gekennzeichnet, daß der Hubbalken (65) mit einem Horizontalgelenk (61) an einen ausfahrenden Teil (49) der Hubvorrichtung (36) angeschlossen ist und mit einem Schwenkantrieb (69) zusammenwirkt.2. Multi-purpose stage according to claim 1, characterized in that the Lifting beam (65) with a horizontal joint (61) on an extending part (49) of the Lifting device (36) is connected and interacts with a pivot drive (69). 3. Mehrzweckbühne nach einem der Ansprüche 1 oder 2, dadurch gekennzeichnet, daß die Hubvorrichtung (36) auf einem Wagen (32) befestigt ist, für den auf der Arbeitsplattform (30) eine in Streckenlängsrichtung verlaufendes Gleis (41, 42) vorgesehen ist.3. Multi-purpose stage according to one of claims 1 or 2, characterized in that that the lifting device (36) is mounted on a carriage (32) for the Work platform (30) a track (41, 42) running in the longitudinal direction of the route is provided. 4. Mehrzweckbühne nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, daß die Hubvorrichtung (36) aus einem Mehrfachteleskop und einem zwischen dem äußersten und dem innersten Teleskopglied (37,49) wirkenden Schubkolbengetriebe (47) besteht.4. Multi-purpose stage according to one of claims 1 to 3, characterized in that that the lifting device (36) consists of a multiple telescope and one between the outermost and the innermost telescopic member (37,49) acting push piston gear (47). 5. Mehrzweckbühne nach einem der Ansprüche 1 bis 4, gekennzeichnet durch seitliche Verbreiterungen (81, 82) der Arbeitsplattform (15) durch fahrbare Querträger (85), die Längsträger (93) des Rahmens durchdringen.5. Multi-purpose stage according to one of claims 1 to 4, characterized by lateral extensions (81, 82) of the working platform (15) by mobile Cross members (85) penetrate the side members (93) of the frame.
DE19772754874 1977-12-09 1977-12-09 Multiple purpose mine gallery working platform - has telescopic column on front half, with tilting cross member carrying holders Withdrawn DE2754874A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19772754874 DE2754874A1 (en) 1977-12-09 1977-12-09 Multiple purpose mine gallery working platform - has telescopic column on front half, with tilting cross member carrying holders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19772754874 DE2754874A1 (en) 1977-12-09 1977-12-09 Multiple purpose mine gallery working platform - has telescopic column on front half, with tilting cross member carrying holders

Publications (1)

Publication Number Publication Date
DE2754874A1 true DE2754874A1 (en) 1979-06-21

Family

ID=6025699

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19772754874 Withdrawn DE2754874A1 (en) 1977-12-09 1977-12-09 Multiple purpose mine gallery working platform - has telescopic column on front half, with tilting cross member carrying holders

Country Status (1)

Country Link
DE (1) DE2754874A1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2950076A1 (en) * 1979-12-13 1981-06-19 Neuhäuser KG, 4670 Lünen Mine or tunnel gallery forwarding - has support cylinder for beam on elevating arms swinging up on elevator
DE3145272A1 (en) * 1981-11-14 1983-06-01 GTA GmbH Fertigungsbetrieb und Ingenieurbüro für Grubenbedarf, Transport- und Ausbautechnik, 4236 Hamminkeln Device serving as support and drilling aid for roadway driving in mining and tunnelling
DE3145270A1 (en) * 1981-11-14 1983-06-16 GTA GmbH Fertigungsbetrieb und Ingenieurbüro für Grubenbedarf, Transport- und Ausbautechnik, 4236 Hamminkeln Device serving as a support aid for roadway driving in mining and tunnelling
DE3153022A1 (en) * 1981-11-14 1983-11-24 GTA GmbH Fertigungsbetrieb und Ingenieurbüro für Grubenbedarf, Transport- und Ausbautechnik, 4236 Hamminkeln Arrangement serving as support and drilling aid for roadway driving in mining and tunnelling
CN102305086A (en) * 2011-05-27 2012-01-04 武汉大学 Multifunctional mobile operating platform for coal mine tunnel
CN106401633A (en) * 2016-09-28 2017-02-15 山东科技大学 Intelligent installation equipment for large-mining-height hydraulic support and application of intelligent installation equipment
CN106801614A (en) * 2017-04-11 2017-06-06 兖州煤业股份有限公司 A kind of servicing unit that hydraulic support is assembled for underground

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2360726B1 (en) * 1973-12-06 1975-01-09 Ruhrkohle Ag, 4300 Essen Multipurpose platform for drifting
GB1409022A (en) * 1973-02-01 1975-10-08 Coal Industry Patents Ltd Mine roof support equipment
DE2457247B2 (en) * 1974-12-04 1976-10-21 Ruhrkohle Ag, 4300 Essen MULTI-PURPOSE SCREEN FOR UNDERGROUND MINING AND TUNNELING
DE2704222C3 (en) * 1977-02-02 1981-11-19 Ruhrkohle Ag, 4300 Essen Procedure and multi-purpose platform for the expansion of sections of mining and tunneling that were excavated by blasting

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1409022A (en) * 1973-02-01 1975-10-08 Coal Industry Patents Ltd Mine roof support equipment
DE2360726B1 (en) * 1973-12-06 1975-01-09 Ruhrkohle Ag, 4300 Essen Multipurpose platform for drifting
DE2457247B2 (en) * 1974-12-04 1976-10-21 Ruhrkohle Ag, 4300 Essen MULTI-PURPOSE SCREEN FOR UNDERGROUND MINING AND TUNNELING
DE2704222C3 (en) * 1977-02-02 1981-11-19 Ruhrkohle Ag, 4300 Essen Procedure and multi-purpose platform for the expansion of sections of mining and tunneling that were excavated by blasting

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
Bergbau 12, 1977, S. 493-499 *
Glückauf 1974, Nr.21, S.896-897 *
Glückauf 1976, Nr.9, S. 471-475 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2950076A1 (en) * 1979-12-13 1981-06-19 Neuhäuser KG, 4670 Lünen Mine or tunnel gallery forwarding - has support cylinder for beam on elevating arms swinging up on elevator
DE3145272A1 (en) * 1981-11-14 1983-06-01 GTA GmbH Fertigungsbetrieb und Ingenieurbüro für Grubenbedarf, Transport- und Ausbautechnik, 4236 Hamminkeln Device serving as support and drilling aid for roadway driving in mining and tunnelling
DE3145270A1 (en) * 1981-11-14 1983-06-16 GTA GmbH Fertigungsbetrieb und Ingenieurbüro für Grubenbedarf, Transport- und Ausbautechnik, 4236 Hamminkeln Device serving as a support aid for roadway driving in mining and tunnelling
DE3153022A1 (en) * 1981-11-14 1983-11-24 GTA GmbH Fertigungsbetrieb und Ingenieurbüro für Grubenbedarf, Transport- und Ausbautechnik, 4236 Hamminkeln Arrangement serving as support and drilling aid for roadway driving in mining and tunnelling
CN102305086A (en) * 2011-05-27 2012-01-04 武汉大学 Multifunctional mobile operating platform for coal mine tunnel
CN102305086B (en) * 2011-05-27 2013-10-23 武汉大学 Multifunctional mobile operating platform for coal mine tunnel
CN106401633A (en) * 2016-09-28 2017-02-15 山东科技大学 Intelligent installation equipment for large-mining-height hydraulic support and application of intelligent installation equipment
CN106801614A (en) * 2017-04-11 2017-06-06 兖州煤业股份有限公司 A kind of servicing unit that hydraulic support is assembled for underground

Similar Documents

Publication Publication Date Title
EP1298283B1 (en) Tunnel boring machine
DE2554107C2 (en) Extension unit serving as a protective support for a tunneling machine
DE2815898A1 (en) DEVICE FOR POSITIONING CEILING SUPPORT IN A TUNNEL
DE2754874A1 (en) Multiple purpose mine gallery working platform - has telescopic column on front half, with tilting cross member carrying holders
DE3641544C1 (en) Method and apparatus for withdrawing the shields from a face in coal mines
DE3106337C2 (en) Device for fixing the hoisting ropes of a multi-rope shaft conveyor system
DE3813905C2 (en) Track jacking chamber for the preliminary expansion of a track location in underground mining operations
DE3009558C2 (en) Extension and auxiliary drilling device for the drifting with work platform and device for pneumatic backfilling of the extension
DE3153022C2 (en) Device used as an expansion aid for tunneling in mining and tunneling
DE2908452A1 (en) Mine gallery prefabricated support setting machine - is ring mounted on travelling bench on gantry on section cutting machine
DE2346853C3 (en) Machine for bringing in a track extension consisting of door frames
DE3020770C2 (en) Vehicle for the expansion of pits and tunnels
DE2323811A1 (en) SUPPORTING FRAME FOR WALKING FRAMES FOR DRIVE WORK
DE2811580C3 (en)
DE2461251C3 (en) Device for pre-assembly, transport and installation of a route or tunnel extension
DE3626948C2 (en)
DE4142632C1 (en) Walking support for mine tunnel roof - has jacks to support roof cam and breaker shield
DE1817054A1 (en) Face device for struts in underground mining
DE3045047A1 (en) DEVICE FOR MAKING HANGING AND / OR SHOCK BORE IN UNDERGROUND SPACES, ESPECIALLY IN CUTTING AND EXTRACTION OPERATIONS
DE2704222A1 (en) Mine gallery lining framework installation - includes transporting and swinging into position upper and lower channels with wire grids attached
DE2849474A1 (en) EXTRACTION MACHINE FOR UNDERGROUND MINING
DE3145270C2 (en) Device used as an expansion aid for tunneling in mining and tunneling
CH377758A (en) Auxiliary support for drifting, especially in underground mining
DE2950076A1 (en) Mine or tunnel gallery forwarding - has support cylinder for beam on elevating arms swinging up on elevator
DE2145150C3 (en) Method and device for producing a gear box for tunnels or galleries

Legal Events

Date Code Title Description
8110 Request for examination paragraph 44
8125 Change of the main classification

Ipc: E21D 11/40