DE2130927A1 - Method for building underground cavities - Google Patents

Method for building underground cavities

Info

Publication number
DE2130927A1
DE2130927A1 DE19712130927 DE2130927A DE2130927A1 DE 2130927 A1 DE2130927 A1 DE 2130927A1 DE 19712130927 DE19712130927 DE 19712130927 DE 2130927 A DE2130927 A DE 2130927A DE 2130927 A1 DE2130927 A1 DE 2130927A1
Authority
DE
Germany
Prior art keywords
shell
hole
earth
cavity
driven
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DE19712130927
Other languages
German (de)
Inventor
Rudolf Amberg
Werner Dr Heierli
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of DE2130927A1 publication Critical patent/DE2130927A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/04Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate against air-raid or other war-like actions
    • E04H9/10Independent shelters; Arrangement of independent splinter-proof walls
    • E04H9/12Independent shelters; Arrangement of independent splinter-proof walls entirely underneath the level of the ground, e.g. air-raid galleries
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Description

Dr. Werner Heierli, Ing. Rudolf Amberg, Verfahren zum Bau von unter der Erde liegenden Hohlräumen Die vorliegende Erfindung betrifft ein Verfahren zur Herstellung bzw. zum Bau von unter der Erde liegenden Hohlräumen.Dr. Werner Heierli, Ing.Rudolf Amberg, method for building under The present invention relates to a method for Manufacture or construction of underground cavities.

Ein besonderes Anwendungsgebiet der Erfindung liegt im Bau von unterirdischen Atomschutzräumen für militärische Zwecke, wo u.U. innert sehr kurzer Zeit eine grössere Anzahl solcher Schutzräume für je ein oder zwei Leute zu erstellen ist. A particular field of application of the invention is in the construction of underground structures Nuclear shelters for military purposes, where possibly a larger one within a very short time Number of such shelters is to be created for one or two people each.

Bei den heutigen Bauverfahren wird entweder einfach ein Loch ausgegraben, was sehr zeitraubend und unter Umständen eine nur bedingt wirksame Lösung ist, oder es wird ein Loch ausgegraben, oder eventuell ausgesprengt und in dieses dann eine vorfabrizierte Betonkammer eingegraben. Diese Lösung vermag zwar einen wirkungsvollen Schutz gewährleisten, ist aber sehr zeitraubend und natürlich sehr kostspielig. Sie kommt praktisch nur für vorausgeplante stationäre Anlagen in Frage. Bei diesen bekannten Verfahren wird zudem das den eigentlichen Schutzraum direkt umgebende Erdreich gelockert bzw. dieses auf der Erdoberfläche angehäuft, was wiederum einen grossen Aufwand für Tarnung bedingt.With today's construction methods, either a hole is simply dug, which is very time-consuming and possibly only a partially effective solution, or a hole is dug, or possibly blasted out, and then a hole is made into it prefabricated concrete chamber dug in. This solution can be an effective one Ensuring protection is very time consuming and of course very costly. In practice, it can only be used for stationary systems that have been planned in advance. With these The known method is also the one that directly surrounds the actual protective space Soil loosened or this piled on the earth's surface, which in turn a great effort required for camouflage.

Ein weiteres Anwendungsgebiet könnte in der raschen und wirtschaftlichen Herstellung von Sockeln fffr die Verankerung von Masten und dgl. liegen. Another area of application could be in the rapid and economic Manufacture of bases for anchoring masts and the like.

Das erfindungsgemässe Verfahren zeichnet sich dadurch aus, dass zuerst ein Loch bis zur gewünschten Tiefe in die Erde vorgetrieben, dann eine aufweitbare Hülle in das Loch gesteckt, und schliesslich die Hülle von innen her zum Aufweiten gebracht wird, und dabei die Hülle, sich an die umliegende Erde anlegend, letztere verdrängt. The inventive method is characterized in that first a hole is driven into the earth to the desired depth, then an expandable one Cover put into the hole, and finally the cover from the inside to expand is brought, and thereby the shell, resting on the surrounding earth, the latter repressed.

Dieses Verfahren hat den Vorteil, wenig Zeit zu beanspruchen, indem nur ein Loch in die Erde vorgetrieben werden muss, z.B. durch Bohren oder Rammen, dann eim vorfabrizierte aufweitbare Hülle in das Loch gesteckt und die Hülle auf hydraulischem Wege oder durch Sprengung aufgeweitet wird, wobei die aufgeweitete Hülle eine Abstützung bildet. Damit ist ein einsturzsicherer Hohlraum gebildet. This method has the advantage of taking up little time by only one hole has to be driven in the earth, e.g. by drilling or ramming, then put a prefabricated expandable sleeve into the hole and open the sleeve is expanded hydraulically or by blasting, the expanded Shell forms a support. A collapse-proof cavity is thus formed.

Die Erfindung wird nachstehend anhand der Zeichnung noch etwas näher erläutert. In der Zeichnung zeigt: Fig. la-ld die verschiedenen Etappen, rein schematisch, beim Bau eines unterirdischen Schutzraumes-nach dem erfindungsgemässen Verfahren. The invention is explained in more detail below with reference to the drawing explained. The drawing shows: Fig. La-ld the different stages, purely schematically, in the construction of an underground shelter using the method according to the invention.

Wie aus der Zeichnung (Fig. la) hervorgeht, wird zuerst ein Loch oder Schacht 1 bis zur gewünschten Tiefe in die Erde vorgetrieben. Dies kann beispielsweise mit einem fahrbaren Bohr- oder Rammgerät erfolgen. Wenn ein unterirdischer Schutzraum für militärische Zwecke hergestellt wird, kann natürlich die beim Bohren anfallende Erde wegtransportiert werden. As can be seen from the drawing (Fig. La), a hole is made first or shaft 1 driven into the earth to the desired depth. This can be, for example be done with a mobile drilling or pile-driving device. If an underground shelter Manufactured for military purposes can of course be used for drilling Earth to be transported away.

Dann wird in das Loch 1 eine aufweitbare Hülle 2 mit Boden 3 in das Loch gesteckt. Am oberen Lochrand wird zweckmässig ein nicht oder nur beschränkt aufweitbarer Verstärkungsring 4 in das Loch 1 bzw. um die Hülle 2 gelegt, damit die obere Hohlraumöffnung (z.B. Einstiegsloch) beim späteren Aufweitungsvorgang nicht über ein gewünschtes Mass hinaus aufgeweitet wird (Fig.lb).Then an expandable shell 2 with a base 3 is inserted into the hole 1 Poked hole. At the upper edge of the hole, it is expedient to not or only to a limited extent Expandable reinforcing ring 4 placed in the hole 1 or around the sheath 2 so that the upper cavity opening (e.g. manhole) during the later expansion process is not expanded beyond a desired extent (Fig.lb).

Als Hülle wird z.B. ein auf geeignete Weise zusammengefalteter Mantel aus Metall, z.B. aus Stahl verwendet. Es ist auch möglich, eine Hülle aus Streckmetall zu verwenden. Es sind auch plastisch tetformbare Hüllen denkbar.A suitably folded jacket, for example, is used as a cover made of metal, e.g. steel. It is also possible to use an expanded metal shell to use. There are also plastically deformable shells conceivable.

Fig. lc zeigt, wie zum Aufweiten der Hülle eine Sprengladung 5 (es könnten auch mehrere an verschiedenen Stellen der Lochtiefe angeordnete Sprengladungen sein) innerhalb der Hülle 2 angeordnet werden. Zweckmässig wird die Hülle 2 auch noch mit einem inkompressiblen Medium, z.B. Wasser gefüllt, um die durch die Sprengung erzeugte Kraft zu verdammen,bzw. diese Kraft mehr oder weniger gleichmässig auf die gesamte Innenseite der Hülle 2 wirken zu lassen. Nach dem Aufweiten wird das Wasser selbstverständlich wieder abgepumpt. Fig. Lc shows how to expand the envelope a Explosive charge 5 (there could also be several explosive charges arranged at different points in the depth of the hole be arranged within the shell 2. The sheath 2 is also expedient still filled with an incompressible medium, e.g. water, to prevent the explosion caused by the blast to condemn generated force, respectively. this force on more or less evenly to let the entire inside of the shell 2 act. After widening this will be Of course, the water is pumped out again.

Die Hülle 2 könnte auch auf hydraulischem Wege aufgeweitet werden, was natürlich einen guten Verchluss der oberen Oeffnung während dem Aufweitungsvorgang erfordern würde. The shell 2 could also be expanded hydraulically, which of course means a good closure of the upper opening during the expansion process would require.

Die erforderlichen Druckerzeugungsaggregate könnten, wie schon die Bohr- oder Raumgeräte, auf einem Fahrzeug angeordnet sein.The required pressure generating units could, like the Drilling or space equipment, be arranged on a vehicle.

Fig. ld zeigt schliesslich einen fertig gebauten Hohlraum 6 mit oberer Oeffnung 7, die z.B. als Einstiegslucke mit Deckel ausgebildet werden kann. Die besonders seitwärts aufgeweitete Hülle 2 wird während dem Aufweiten die umliegende Erde besonders in den Zonen A stark verdichten, was einen weiteren erwünschten Effekt darstellt. Finally, FIG. 1d shows a finished cavity 6 with an upper one Opening 7, which can be designed, for example, as an access hatch with a cover. the sleeve 2 that is widened laterally becomes the surrounding one during the widening Strongly compact soil, especially in zones A, which is another desirable effect represents.

Sollte die Erde an der für den Bau eines solchen Hohlraumes vorgesehenen Stelle zu stark verdichtet sein, könnten rund um das zentrale, zur Aufnahme der Hülle bestimmte Loch eine Anzahl Hilfslöcher in die Erde vorgetrieben werden, die sich beim Aufweiten der Hülle dann von selbst wieder schliessen würden. Der Aufwand für das Anbringen solcher Hilfslöcher ist sehr gering. Should the earth at the intended for the construction of such a cavity Place too much condensed, could be around the central, to accommodate the Sheath certain hole a number of auxiliary holes are driven into the earth that would then close again by themselves when the envelope is expanded. The effort for making such auxiliary holes is very small.

Ein z.B. nach Fig. ld ausgebildeter Hohlraum 6 könnte auch als Fundament für die Verankerung von Masten oder dgl. verwendet werden. Ein Mast könnte dabei entweder am oberen Rand der Hülle 2, die eventuell sogar über der Erde vorsteht, oder am Verstärkungsring 4 befestigt werden. Selbstverständlich könnte der Mast auch einfach durch die Oeffnung 7 in den Hohlraum 6 eingesteckt und dann der verbleibende Hohlraum mit Beton aufgefüllt werden. A cavity 6 formed, for example, according to FIG. 1d could also be used as a foundation Used for anchoring masts or the like. A mast could be used either at the upper edge of the shell 2, which may even protrude above the ground, or attached to the reinforcement ring 4. Of course the mast could also simply inserted through the opening 7 into the cavity 6 and then the remaining one Cavity to be filled with concrete.

Claims (11)

Patentansprüche Claims verfahren zum Bau von unter der Erde liegenden Hohlräumen, dadurch gekennzeichnet, dass zuerst ein Loch bis zur gewünschten Tiefe in die Erde vorgetrieben, dann eine aufweitbare Hülle in das Loch gesteckt, und schliesslich die Hülle von innen her zum Aufweiten gebracht wird, und dabei die Hülle, sich an die umliegende Erde anlegend, letztere verdrängt.method of building underground cavities, thereby marked that first a hole was driven into the earth to the desired depth, then put an expandable sleeve into the hole, and finally the sleeve of inside is brought to expand, and in doing so, the shell is attached to the surrounding area Laying earth, the latter displaced. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass das genannte Loch durch Bohren oder Rammen in die Erde vorgetrieben wird. 2. The method according to claim 1, characterized in that said Hole is driven into the earth by drilling or ramming. 3. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass eine Hülle aus Metall verwendet wird, wobei diese vorerst entsprechend der angestrebten Hohlraumform ausgebildet und dann soweit zusammengefaltet wird, dass sie sich in das genannte-Loch einbringen lässt. 3. The method according to claim 1, characterized in that a shell made of metal is used, this initially corresponding to the desired cavity shape is formed and then folded up to the extent that it fits into said hole bring in. 4. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass eine Hülle aus Streckmetall verwendet wird. 4. The method according to claim 1, characterized in that a shell made of expanded metal is used. 5. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass zum Aufweiten der Hülle in deren Innerem wenigstens eine Sprengladung angebracht und gezündet wird. 5. The method according to claim 1, characterized in that for expanding the shell attached and detonated at least one explosive charge inside the shell will. 6. Verfahren nach Anspruch 5, dadurch gekennzeichnet, dass die Hülle vor dem Zünden der Sprengladung mit einem inkompressiblen Druckübertragungsmedium, z.B. mit einer Flüssigkeit, gefüllt wrd. 6. The method according to claim 5, characterized in that the shell before igniting the explosive charge with an incompressible pressure transmission medium, e.g. filled with a liquid. 7. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass die Hülle auf hydraulischem Wege zum Aufweiten gebracht wird. 7. The method according to claim 1, characterized in that the shell is brought to expand hydraulically. 8. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass nach der Bildung des Hohlraumes durch Aufweiten der Hülle ein Mast oder dgl. im Hohlraum verankert wird. 8. The method according to claim 1, characterized in that according to the Formation of the cavity by expanding the shell, a mast or the like. In the cavity is anchored. 9. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass im Abstand um das genannte erste Loch eine Anzahl die Erde lockernde Hilfslöcher in die Erde vorgetrieben werden. 9. The method according to claim 1, characterized in that at a distance around said first hole a number the Earth loosening auxiliary holes be propelled into the earth. 10. Verfahren nach Anspruch 1, dadurch gekennzeichnet, dass der obere Hüllenrand verstärkt wird, z.B. mittels eines den entsprechenden Hüllenteil umgebenden Ringes. 10. The method according to claim 1, characterized in that the upper Envelope edge is reinforced, e.g. by means of a surrounding the corresponding envelope part Ring. 11. Verfahren nach Anspruch 2, bei welchem das Loch durch Rammen vorgetrieben wird, dadurch gekennzeichnet, dass die Hülle als äussere Schale des gerammten Körpers beim Vortrieb des Loches in dieses eingebracht wird. 11. The method of claim 2, wherein the hole is rammed is advanced, characterized in that the shell as the outer shell of the rammed body is introduced into this when driving the hole. L e e r s e i t eL e r s e i t e
DE19712130927 1970-06-23 1971-06-22 Method for building underground cavities Pending DE2130927A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH951370A CH526686A (en) 1970-06-23 1970-06-23 Method of building underground cavities

Publications (1)

Publication Number Publication Date
DE2130927A1 true DE2130927A1 (en) 1971-12-30

Family

ID=4352783

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19712130927 Pending DE2130927A1 (en) 1970-06-23 1971-06-22 Method for building underground cavities

Country Status (2)

Country Link
CH (1) CH526686A (en)
DE (1) DE2130927A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4625680A (en) * 1983-07-27 1986-12-02 Hogan Lawrence J Water conservation means
FR3042209A1 (en) * 2015-10-09 2017-04-14 Stephane Ulvoas SEALING RESERVATION

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3348301C2 (en) * 1983-01-13 1994-11-17 Stump Bohr Gmbh Consolidation of zones or holes in ground
DE3300971A1 (en) * 1983-01-13 1984-07-19 Stump Bohr Gmbh, 8045 Ismaning Method of producing stabilised or compacted zones or holes in the earth and device for carrying out the method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4625680A (en) * 1983-07-27 1986-12-02 Hogan Lawrence J Water conservation means
FR3042209A1 (en) * 2015-10-09 2017-04-14 Stephane Ulvoas SEALING RESERVATION

Also Published As

Publication number Publication date
CH526686A (en) 1972-08-15

Similar Documents

Publication Publication Date Title
US4060994A (en) Process for providing a foundation pile for alternating compressive and tractive stresses and a pile thus provided
DE2158764A1 (en) Method for producing an underground wall
DE2434200C3 (en) Process for the production of underground cavities
DE2444576A1 (en) COMPOSITE SUPPORT AND FOUNDATION PILLAR FOR VARIOUS STRUCTURES, AND METHOD OF MANUFACTURING THESE
DE2011823A1 (en) Method of creating watertight barriers
DE2233732A1 (en) PROCEDURE FOR SOLIDIZING LOOSE EARTH AND PROCESSING FASTENING PILES
DE3615601C1 (en) Pipe support screed for a combined sheet pile
DE2130927A1 (en) Method for building underground cavities
EP0069817B1 (en) Bulk blasting
DE3248430A1 (en) METHOD FOR FRAMING STEEL PROFILES IN A STONE SUBSTRATE
DE2630979A1 (en) DISMANTLING PROCEDURES
DE3228198A1 (en) Method of improving the keying of a reinforced-concrete root pile which forms a root pile wall preferably with other root piles of the same type
DE4307396A1 (en) Method of lining of shaft with concrete sections - has sections cast in-situ in circular forms which are re-used as lower sections harden and are driven down
DE693918C (en) Method for fastening an anchor in the ground for the purpose of absorbing tensile forces
DE1910556A1 (en) Process for the production of foundation piles from in-situ concrete with extensions of the pile shaft and the pile base, as well as internal formwork for carrying out the process
DE3507730C2 (en)
DE3625129C2 (en) Manhole expansion with cast iron ring elements for deep freeze shafts in the mining industry
DE3307392A1 (en) METHOD FOR CONSTRUCTION OF CONCRETE LINED UNDER CONCRETE
AT265981B (en) Pressure tunnel armor and process for making such
DE2407874C3 (en) Device for explosively enlarging the pile base of an in-situ concrete pile
DE3501252A1 (en) Method of producing a cast-in-situ concrete pile
DD275502A1 (en) PROCEDURE FOR INTRODUCING CONSTRUCTION BODIES INTO THE TERRITORY
DE2836488A1 (en) Air supported hangar anchoring system - has pipes containing explosive set off after driving into ground
DE1064887B (en) Process for the production of a composite pile for foundations and a steel driven pile for carrying out this process
CH670669A5 (en) Concrete foundation constructing method - uses hollow perforated drill to inject binder into sloping holes to form anchorage cores for lining blocks