DE2836488A1 - Air supported hangar anchoring system - has pipes containing explosive set off after driving into ground - Google Patents
Air supported hangar anchoring system - has pipes containing explosive set off after driving into groundInfo
- Publication number
- DE2836488A1 DE2836488A1 DE19782836488 DE2836488A DE2836488A1 DE 2836488 A1 DE2836488 A1 DE 2836488A1 DE 19782836488 DE19782836488 DE 19782836488 DE 2836488 A DE2836488 A DE 2836488A DE 2836488 A1 DE2836488 A1 DE 2836488A1
- Authority
- DE
- Germany
- Prior art keywords
- ground
- pipe
- driving
- pipes
- anchoring system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/806—Ground anchors involving use of explosives
Abstract
Description
Verankerung von luftgetragenen Hallen und flexiblen KonstruktionenAnchoring of airborne halls and flexible constructions
Ein wesentlicher konstruktiver Bestandteil von Traglufthallen ist die Verankerung, die im Unterschied zu massiven Hallen nicht nur Wind- , Schnee- und Eigengewichtskräfte aufnehmen muß, sondern auch die aus dem die Halle stabilisierenden Innendruck herrührenden Kräfte. Dazu kommt, daß häufig luftgetragene Hallen umgesetzt werden, so daß eine teure feste Verankerung, die stationär im Boden bleibt, hohe Folgekosten durch stetigen Ersatz hervorruft.An essential constructive component of air domes is the anchoring, which, in contrast to massive halls, not only and self-weight forces, but also from the stabilizing the hall Forces resulting from internal pressure. In addition, airborne halls are often implemented so that an expensive fixed anchorage that remains stationary in the ground is high Resulting in follow-up costs through constant replacement.
Bekannte Verankerungen sind Betonfundamente mit Spreizankern oder Dübeln, die wegen der großen Auftriebskräfte der Hallen sehr teuer sind. Sie benötigen neben Betonmengen bis zu 1 cbm pro lfm Hallenumfang je nach Spannweite und Höhe der Halle noch starke Eisenbewehrungen. Weiter sind Schlaganker aus Winkeleisen bekannt, die als Ankerpaare gesetzt werden und neben relativ hohen Herstellkosten besonders bei steinigem Boden oder festen Bodenschichten (z.B. Ortstein) schwierig und zeitaufwendig zu montieren sind.Well-known anchors are concrete foundations with expansion anchors or Dowels, which are very expensive because of the great buoyancy of the halls. you need In addition to concrete quantities of up to 1 cbm per running meter of hall circumference, depending on the span and height the hall still has strong iron reinforcement. Drop anchors made from angle iron are also used known, which are set as anchor pairs and in addition to relatively high manufacturing costs Difficult especially on stony ground or solid soil layers (e.g. local stone) and are time-consuming to assemble.
Eine weitere bekannte Form der Verankerung stellt der Drehanker dar, der heute am verbreitetsten ist, um luftgetragene Hallen, Masten, flexible Konstruktionen usw zu verankern. Neben den relativ hohen Kosten liegt ein Nachteil darin, daß die Stabilität von den jeweiligen Bodenverhältnissen abhängt. Das Einschrauben bei nicht steinfreien Böden führt häufig zu Schwierigkeiten, und der Drehanker wirkt bei falschen Schraubgeschwindigkeiten als Bohrer, wodurch die Belastbarkeit wesentlich gesenkt wird, da der Boden am Bohrloch aufgelockert wird.Another well-known form of anchoring is the rotating anchor, which is most common today to airborne halls, masts, flexible constructions to anchor etc. In addition to the relatively high cost, there is a disadvantage that the Stability depends on the respective soil conditions. The screwing in at no Stone-free soils often lead to difficulties, and the swivel anchor works with wrong ones Screw speeds than a drill, which significantly reduces the load capacity because the soil at the borehole is loosened.
Schließlich sind noch Anker bekannt, die senkrecht in den Boden geschlagen werden und aus Rohr bestehen. In einer Ausführung sind diese Rohre am unteren Ende geschlitzt und werden nach dem Einbringen durch eine Zugstange, die mit Hilfe eines hydraulischen Spreizgerätes nach oben gezogen wird, gespreizt. Da nur eine bedingte Spreizung möglich ist, müssen verhältnismäßig lange Rohre verwendet werden und die Ausziehfestigkeit ist begrenzt. Zusätzlich ist das Gewinde der zum Spreizen verwendeten Gewindestange häufig zu erneuern, da die Gewindestange beim Eintreiben des Rohres als Rammstange verwendet wird und die Rammschläge auf das Ankerrohr weiterleitet.Finally, anchors are known that are hammered vertically into the ground and are made of pipe. In one embodiment, these tubes are at the lower end are slotted and after being inserted by a pull rod that is operated with the help of a hydraulic spreader is pulled up, spread. Since only a conditional Spreading is possible, relatively long pipes must be used and the Pull-out strength is limited. In addition, the thread is the one used for spreading Threaded rod to be renewed frequently as the threaded rod is driven in of the pipe is used as a ramming rod and forwards the ramming hits to the anchor pipe.
Ein zweiter bekannter Rohranker wird aus Quadratrohr hergestellt, das seitlich im unteren Bereich waagrechte Schlitze enthält, durch die nach dem Einschlagen Winkeleisen durch Hammerschläge auf eine Spreizstange seitlich horizontal ausgetrieben werden.A second known pipe anchor is made from square pipe, which laterally in the lower area contains horizontal slots through which after the Hammer in angle iron by hitting a spreader bar with a hammer to the side and horizontally be driven out.
Dies wird für jedes Ankerteil im Rohr wiederholt, wobei kein Ankerteil breiter als das Rohrdickenmaß sein kann, wodurch relativ geringe Breitenwirkung im Boden entsteht.This is repeated for each anchor part in the pipe, with no anchor part Can be wider than the pipe thickness, creating a relatively small width effect arises in the ground.
Befe hier erwähnten Rohranker zeichnen sich durch aufwendige Spitzenkonstruktion und Rohrschlitzarbeiten aus.The pipe anchors mentioned here are characterized by an elaborate tip construction and pipe slitting work.
Die Erfindung vermeidet diese Nachteile und ermöglicht dabei besonders preisgünstige Verankerungen. Die Verankerung erfolgt durch ein Rohr, das in Zugrichtung in die Erde geschlagen wird.The invention avoids these disadvantages and makes it possible in particular inexpensive anchorages. The anchoring is done by a tube that is pulled in the direction of pull is hammered into the ground.
Damit keine Erde in das Rohr eindringen kann, wird es am unteren Ende zusammengedrückt (z.B-. durch Stanzen). Es bekommt dadurch gleichzeitig eine Spitze, die das Eintreiben in den Erdboden wesentlich vereinfacht.So that no earth can penetrate the pipe, it is at the lower end pressed together (e.g. by punching). It gets a tip at the same time, which significantly simplifies driving into the ground.
Nach dem Eintreiben wird das Rohr durch einz genau dosierte SprengladungVgespreizt. Die Sprengpatrone wird in dem Rohr herabgelassen und das Rohr bevorzugt durch Wasser gefüllt, so daß die Druckwirkung nicht nach oben verpufft. Durch die Sprengung wird das untere Rohrende bis zum fünffachen seines alten Durchmessers gespreizt. *) oder einen anderen geeigneten Treibsatz Nach der Sprengung wird ein festwerdender Stoff, vorzugsweise Beton, in das Rohr gefüllt, der den am Rohrende durch die Sprengung entstandenen Hohlraum ausfüllt und ein Zusammenziehen des gespreizten Rohrendes unter Belastung verhindert. Dabei wird die Auflagefläche gegen das Erdreich vergrößert.After driving in, the pipe is expanded by a precisely dosed explosive charge. The explosive cartridge is lowered into the tube and the tube is preferably lowered through water filled so that the pressure does not fizzle out upwards. The demolition will the lower end of the pipe spread up to five times its old diameter. *) or another suitable propellant After the blast, a solidifying substance, preferably concrete, filled into the pipe, the one at the end of the pipe by the blast resulting cavity fills and a contraction of the spread pipe end prevented under stress. This increases the contact surface against the ground.
Folgende Vorteile zeichnen die neue Verankerung aus: a) Einfachste Rohrankerherstellung und einfachste Montage.The new anchoring has the following advantages: a) Easiest Pipe anchor production and easy assembly.
b) Sehr große Spreizwirkung und daher hohe Auszugsfestigkeit. b) Very large expansion effect and therefore high pull-out strength.
c) Verdichtung des Bodens am Ankergrund und dadurch zusoätzliche Steigerung iezn fçtAgkeit. c) Compaction of the soil at the anchorage and thus additional Increase in fitness.
d) Durch b) und c) bedingt relativ kurze Rohrlängen ausreichend. d) Due to b) and c), relatively short pipe lengths are sufficient.
e) Aus a) bis d) folgend gegenüber allen bekannten Verankerungsarten besonders billige Herstellung und schnelle Montage. e) Following from a) to d) for all known types of anchoring particularly cheap production and quick assembly.
Zweckmäßig ist es ferner, vor dem Einschlagen des Rohres in das Erdreich auf dem Bohrkopf eine beispièlsweise aus Blei bestehende Schutzhaube anzubringen, die Verformungen des Rohrkopfes.verhindert.It is also useful before the pipe is hammered into the ground to attach a protective hood made of lead, for example, to the drill head, prevents deformation of the pipe head.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19782836488 DE2836488A1 (en) | 1978-08-21 | 1978-08-21 | Air supported hangar anchoring system - has pipes containing explosive set off after driving into ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19782836488 DE2836488A1 (en) | 1978-08-21 | 1978-08-21 | Air supported hangar anchoring system - has pipes containing explosive set off after driving into ground |
Publications (1)
Publication Number | Publication Date |
---|---|
DE2836488A1 true DE2836488A1 (en) | 1980-03-06 |
Family
ID=6047532
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19782836488 Ceased DE2836488A1 (en) | 1978-08-21 | 1978-08-21 | Air supported hangar anchoring system - has pipes containing explosive set off after driving into ground |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE2836488A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4445422A1 (en) * | 1994-12-20 | 1996-06-27 | Fischer Artur Werke Gmbh | Anchor bolts that can be anchored by an explosive charge |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1634272A1 (en) * | 1966-10-03 | 1970-10-01 | Bauunternehmung Mast Gmbh | Device for the underground production of an extended anchor foot for tie rods for anchoring components in the ground |
DE1484484B1 (en) * | 1964-04-17 | 1971-03-25 | Harvey Aluminum Inc | Method for producing a ground anchor and ground anchor for carrying out this method |
-
1978
- 1978-08-21 DE DE19782836488 patent/DE2836488A1/en not_active Ceased
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1484484B1 (en) * | 1964-04-17 | 1971-03-25 | Harvey Aluminum Inc | Method for producing a ground anchor and ground anchor for carrying out this method |
DE1634272A1 (en) * | 1966-10-03 | 1970-10-01 | Bauunternehmung Mast Gmbh | Device for the underground production of an extended anchor foot for tie rods for anchoring components in the ground |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4445422A1 (en) * | 1994-12-20 | 1996-06-27 | Fischer Artur Werke Gmbh | Anchor bolts that can be anchored by an explosive charge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2101236A1 (en) | Corrosion-protected tie rods for anchoring components in the ground as well as a method for producing tension anchors with corrosion-protected tie rods | |
DE2545572A1 (en) | BUILDING ANCHORING | |
DE3445965A1 (en) | COMPACTING DEPTH, METHOD AND DEVICE FOR PRODUCING THE SAME | |
DE2432708A1 (en) | TUBULAR PILE AND PROCEDURE FOR ITS GROUND IN A DRILLED HOLE | |
EP0976873A1 (en) | Injection- or prestressed ground anchor | |
EP1922449B1 (en) | Method for consolidating soils and stabilizing foundations | |
DE2034662A1 (en) | Method for attaching an anchor in the ground and the like and anchors for carrying out this method | |
DE2354764C3 (en) | Method and device for the watertight implementation of a built-in component to be introduced into the ground through a building wall or excavation pit wall or floor | |
EP0151389B1 (en) | Method and apparatus for constructing building elements in the soil like piles, injection anchorages, cut-off walls or similar | |
DE3838880C1 (en) | Method of producing a grouted anchor, and grouted anchor for carrying out the method | |
DE2836488A1 (en) | Air supported hangar anchoring system - has pipes containing explosive set off after driving into ground | |
DE2631745A1 (en) | FLOOR NAILING PROCEDURE | |
DE102005029364B4 (en) | Precast pile and associated method for building foundation | |
DE3926787C2 (en) | Method and device for inserting and anchoring a tensile pile | |
DE4026781A1 (en) | Multipart ground anchor assembly - has anchoring foot on steel bar with four flanges and leaf springs | |
CH374819A (en) | Process for the production of prestressed anchors for structures such as retaining walls, excavation securing devices and the like and prestressing anchors produced according to this process | |
EP2808449B1 (en) | Pile driven by drilling | |
DE19740032C2 (en) | Device for anchoring a rebar and method for anchoring a sealing base | |
AT269002B (en) | Injection tension anchoring in the ground and process for their production | |
DE1944644C3 (en) | Process for the production of a reinforced concrete pile from in-situ concrete used for the foundation of a corner post and steel pipe for the implementation of the process | |
DE3400741C2 (en) | ||
DE3332519A1 (en) | Impact-driven pile and foundation method with the use of the impact-driven pile | |
DE1271045B (en) | Method for producing ground anchors | |
DE2047018C3 (en) | Method for reducing subsidence and device for producing prestressing | |
DE102021003798A1 (en) | Ground peg for an industrial tent |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
OAM | Search report available | ||
OC | Search report available | ||
8110 | Request for examination paragraph 44 | ||
8131 | Rejection |