DE1280759B - Grab excavator for making slots in the ground - Google Patents

Grab excavator for making slots in the ground

Info

Publication number
DE1280759B
DE1280759B DED42346A DED0042346A DE1280759B DE 1280759 B DE1280759 B DE 1280759B DE D42346 A DED42346 A DE D42346A DE D0042346 A DED0042346 A DE D0042346A DE 1280759 B DE1280759 B DE 1280759B
Authority
DE
Germany
Prior art keywords
guide
grab
excavator
masts
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DED42346A
Other languages
German (de)
Inventor
Dipl-Ing Paul Adams
Hans Benson
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wintershall Dea International AG
Original Assignee
Deutsche Erdoel AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Deutsche Erdoel AG filed Critical Deutsche Erdoel AG
Priority to DED42346A priority Critical patent/DE1280759B/en
Priority to AT723464A priority patent/AT252824B/en
Priority to NL6409632A priority patent/NL6409632A/xx
Publication of DE1280759B publication Critical patent/DE1280759B/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/40Dippers; Buckets ; Grab devices, e.g. manufacturing processes for buckets, form, geometry or material of buckets
    • E02F3/413Dippers; Buckets ; Grab devices, e.g. manufacturing processes for buckets, form, geometry or material of buckets with grabbing device
    • E02F3/4136Dippers; Buckets ; Grab devices, e.g. manufacturing processes for buckets, form, geometry or material of buckets with grabbing device with grabs mounted on a slidable or telescopic boom or arm
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/40Dippers; Buckets ; Grab devices, e.g. manufacturing processes for buckets, form, geometry or material of buckets
    • E02F3/413Dippers; Buckets ; Grab devices, e.g. manufacturing processes for buckets, form, geometry or material of buckets with grabbing device
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/46Dredgers; Soil-shifting machines mechanically-driven with reciprocating digging or scraping elements moved by cables or hoisting ropes ; Drives or control devices therefor
    • E02F3/47Dredgers; Soil-shifting machines mechanically-driven with reciprocating digging or scraping elements moved by cables or hoisting ropes ; Drives or control devices therefor with grab buckets

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Description

Greifbagger zum Herstellen von Schlitzen im Boden Die Erfindung betrifft einen Greifbagger zum Herstellen von Schlitzen im Boden mit einem Greifbaggergerüst und einem an einem Seil hängenden Schlitten, der an einer Führung gleitet und mit einem Greifer verbunden ist.Grab excavators for making slots in the ground The invention relates to a digger for making slots in the ground with a digger frame and a slide hanging on a rope that slides on a guide and with it is connected to a gripper.

Bei einem Greifbaggergerät bekannter Bauweise ist der Schöpflöffel mit einem Schlitten verbunden, der an einem Mast gleitend angeordnet ist. Der Löffel als grabendes Gerät führt in Längsrichtung des auszuhebenden Schlitzes eine etwa halbkreisförmige Schwenkung mit einem Radius von etwa 3,60 Meter aus, wobei die Kraft direkt auf den im Erdreich abgestützten Mast übertragen wird. Das Verfüllen der ausgehobenen Schlitzlänge von nur 3,60 Meter, beispielsweise mit Beton ist unpraktisch und für derartige kleine Abschnitte auch unwirtschaftlich. Eine Verbesserung läßt sich zumeist dadurch erzielen, daß das Gerät um einen Meter vorwärts versetzt wird, wodurch der zu verfüllende Abschnitt entsprechend verlängert wird. Hierbei stützt sich nun der die Kräfte aufnehmende Mast nicht mehr am Gebirge ab; er steht nur mit einer Spitze an der Sohle auf, wobei vornehmlich bei schwerem Boden oft eine Verbiegung des Mastes eintritt. Dies führt zu Unterbrechungen der Arbeit und zu umständlichen Reparaturen.In a grab excavator device of known construction, the ladle is connected to a carriage which is slidably arranged on a mast. As a digging device, the spoon performs an approximately semicircular pivot with a radius of about 3.60 meters in the longitudinal direction of the slot to be excavated, whereby the force is transmitted directly to the mast supported in the ground. Backfilling the excavated slot length of only 3.60 meters, for example with concrete, is impractical and also uneconomical for such small sections. An improvement can usually be achieved by moving the device forward by one meter, whereby the section to be filled is lengthened accordingly. Here, the mast that absorbs the forces is no longer supported on the mountain; he stands up only with one point on the sole, whereby a bending of the mast often occurs, especially on heavy ground. This leads to work interruptions and cumbersome repairs.

Bei einer anderen bekannten Konstruktion zur Herstellung von Schlitzen wird die Bodenaushebung mit einem Zweischalengreifer durchgeführt, der mit dem unteren Ende einer an einem Gerüst lotrecht oder schräg geführten Führungsstange starr verbunden ist. Die starre Verbindung zwischen dem Greifer und der Führungsstange bedingt, daß zu jeder Entleerung des Greifers auch die Führungsstange aus dem Schlitz herausgehoben und zur Seite geschwenkt werden muß. Außerdem kann bei dieser Konstruktion die Führungsstange nicht bis zur Schlitzsohle geführt und dort verankert werden, so daß besonders beim Ausheben tiefer Schlitze ein Abweichen der Führungsstange von der Vertikalen bzw. der gewünschten Richtung eintreten kann. Jedes derartige Abweichen kann ein Anschlagen des Greifers an die Schlitzwände und deren Nachfallen oder sogar deren Einstürzen verursachen.In another known construction for making slots the soil is excavated with a clamshell grab, the lower one with the Rigidly connected to the end of a guide rod that is guided vertically or diagonally on a scaffolding is. The rigid connection between the gripper and the guide rod requires that each time the gripper is emptied, the guide rod is also lifted out of the slot and must be swiveled to the side. In addition, the guide rod not to be guided to the slot sole and anchored there, so that especially when Digging deep slots, the guide rod deviates from the vertical or can occur in the desired direction. Any such deviation can be a hitting the gripper to the diaphragm walls and their falling or even their collapse cause.

Der Erfindung liegt die Aufgabe zugrunde, den Greifer derart zu führen, daß jegliche Abstützung der die Führung ausübenden Geräteteile am Gebirge überflüssig wird und somit ein beliebig langer Schlitz ausgehoben werden kann, ohne daß diese Arbeit durch abschnittweises Verfüllen unterbrochen werden muß. Ferner soll durch die Erfindung vermieden werden, daß der Greifer an die Schlitzwände anschlägt. Eine weitere Aufgabe der Erfindung besteht darin, eine Entleerung des Greifers zu ermöglichen, bei der die Führung nicht aus dem Schlitz herausgehoben werden muß. Auch soll das Umsetzen der Anlage durch die Erfindung vereinfacht werden.The invention is based on the object of guiding the gripper in such a way that that any support of the device parts exercising the leadership on the mountains is superfluous and thus any long slot can be excavated without this Work has to be interrupted by backfilling in sections. Furthermore, through the invention can be avoided that the gripper hits the slit walls. One Another object of the invention is to enable the gripper to be emptied, in which the guide does not have to be lifted out of the slot. That should too Implementation of the system can be simplified by the invention.

Die Lösung dieser Aufgaben wird nach der Erfindung darin gesehen, daß die Führung aus zwei Führungsmasten 4, 4' (F i g. 1) gebildet wird, der Schlitten 3 mittels Führungsbuchsen, Hydraulikzylindern 5 und Klemmvorrichtungen 6 mit den Führungsmasten verbindbar ist und diese ihrerseits unabhängig voneinander beweglich am Baggergerüst angeordnet sind.The solution to these problems is seen according to the invention in that the guide is formed from two guide masts 4, 4 '( Fig. 1) , the carriage 3 can be connected to the guide masts by means of guide bushings, hydraulic cylinders 5 and clamping devices 6 and these in turn are arranged independently movable on the excavator frame.

Dieser Greifbagger ermöglicht eine kontinuierliche Arbeitsweise zum Herstellen von Schlitzen im Boden. Während bei der ersten der beiden erwähnten bekannten Konstruktionen bei einem Aushub nur eine Schlitzlänge von 3,60 Meter erzielt werden kann, (die nur unter Gefährdung des Führungsmastes um einen Meter verlängert werden kann), und anschließend an diesen einen Aushub das Einfüllen des tragenden und/oder dichtenden Materials erfolgen muß, damit der Führungsmast sich beim nächsten Aushub wieder am Gebirge abstützen kann, wird bei dem Greifbagger nach der Erfindung nach Erreichen der gewünschten Schlitztiefe, also nach dem ersten Aushub, beim Weiterfahren der Maschine nur ein Führungsmast aus dem Schlitz herausgezogen, während der andere Führungsmast lediglich etwa einen Meter aufwärtsgefahren und anschließend zwischen Schlitzsohle und Greifbaggergerüst eingespannt wird. Dieser eingespannte Führungsmast ersetzt das Abstützen am Gebirge. Die Führung an zwei Führungsmasten verhindert jedes Abweichen des Greifers aus der Vertikalen, so daß der Greifer nicht durch seitliche Bewegungen an die Schlitzwände anschlagen kann. Zur Entleerung wird lediglich der Greifer mit Hilfe des Seils nach oben gezogen, und die Führungsmasten bleiben stehen.This grab excavator enables a continuous working method for making slots in the ground. While in the first of the two known constructions mentioned, only a slot length of 3.60 meters can be achieved during an excavation (which can only be lengthened by one meter if the guide mast is at risk), and then an excavation is followed by filling in the load-bearing and / or sealing material must be made so that the guide mast can be supported on the rock during the next excavation, only one guide mast is pulled out of the slot in the grab excavator according to the invention after reaching the desired slot depth, i.e. after the first excavation, when the machine continues , while the other guide mast is only moved up about a meter and then clamped between the bottom of the slot and the excavator frame. This clamped guide mast replaces support on the mountain. The guidance on two guide masts prevents the gripper from deviating from the vertical, so that the gripper cannot hit the slit walls by moving sideways. For emptying, the gripper is simply pulled up with the help of the rope and the guide masts stop.

Die Hydraulikzylinder und Klenunvorrichtungen zwischen dem Führungsschlitten und den Führungsmasten einerseits sowie solche zwischen den Führungsmasten und dem Greifbaggergerüst andererseits ermöglichen, daß das Gesamtgewicht der Maschine auf die in den Boden eindringenden Greiferschalen übertragen werden kann. Durch diese Verspannung der Führungsmasten sowohl mit dem Greifer als auch mit den übertägigen Greifbaggerteilen ergibt sich eine wesentliche Verstärkung der Aushubkraft des Greifers.The hydraulic cylinders and Klenun devices between the guide carriage and the guide masts on the one hand and those between the guide masts and the Grab diggers, on the other hand, allow the total weight of the machine to take up the gripper shells penetrating into the ground can be transferred. Through this Bracing of the guide masts both with the gripper and with the surface Grapple excavator parts result in a significant increase in the excavation force of the grapple.

Um den Führungsmasten auf der Schlitzsohle einen festen Halt zu geben, wird ferner vorgeschlagen, sie an ihren unteren Enden mit Spitzen zu versehen.To give the guide masts a firm hold on the slotted base, it is also proposed to tip them at their lower ends.

Um die Baggerarbeit des Greifers, insbesondere bei Gesteinsuntergrund oder festen Bodenartefi,durch die Masten wirksam zu unterstützen, können die Masten während des Hochziehens des gefüllten Greifers angehoben und auf die Sohle fallengelassen werden.About the digging work of the grab, especially on rocky subsoil or solid soil artefacts, which can be effectively supported by the masts, the masts raised while the filled gripper is being pulled up and dropped onto the sole will.

Die dadurch bewirkte Lockerung des Bodens kann nach einem weiteren Merkmal der Erfindung durch das Anbringen von Meißeln an den unteren Enden der Führungsmasten noch verstärkt werden.The loosening of the soil caused by this can after another Feature of the invention by attaching chisels to the lower ends of the guide masts to be strengthened.

Bei leicht angehobenen Masten können dann die Greiferschalen an den losgemeißelten Ansatzpunkten unterhalb der Führungsmasten die Aushubarbeit fortsetzen. In ähnlicher Weise kann auch das Losmeißeln in Längsrichtung des Schlitzes erfolgen, indem unter Weiterbewegung des Greifbaggers in der gewünschten Richtung die Sohle losgemeißelt und anschließend das gebrochene Material mit dem Greifer ausgebaggert wird.When the masts are slightly raised, the gripper shells can then be attached to the continue the excavation work with the chiseled attachment points below the guide masts. In a similar way, the chiseling can also be carried out in the longitudinal direction of the slot, by moving the digger in the desired direction chiseled loose and then the broken material is dredged with the grapple will.

In der Zeichnung ist ein Ausführungsbeispiel des Greifbaggers nach der Erfindung dargestellt. Es zeigt F i g. 1 den Greifbagger sowie einen Schnitt durch den Boden in Längsrichtung des auszuhebenden Schlitzes mit erstem Aushub, Fig.2 einen Schnitt durch den Boden in Querrichtung des Schlitzes, F i g. 3 das Umsetzen des Greifbaggers und F i g. 4 nochmals einen Schnitt durch den Boden in Längsrichtung des Schlitzes, jedoch in einem fortgeschrittenen Stadium des Aushebens.In the drawing, an embodiment of the grab excavator according to the invention is shown. It shows F i g. 1 the grab excavator and a section through the ground in the longitudinal direction of the trench to be excavated with the first excavation, FIG. 2 a section through the ground in the transverse direction of the trench, FIG . 3 the relocation of the grab excavator and F i g. 4 again a section through the floor in the longitudinal direction of the slot, but in an advanced stage of excavation.

Der mit dem Seil 1 (F i g. 1 und 2) in vertikaler Richtung bewegbare Greifer 2 ist am Schlitten 3 befestigt, der an den Führungsmasten 4 und 4' gleitend angeordnet ist. Durch hydraulische Zylinder 5 und Klemmvorrichtungen 6 können die Führungsmasten 4, 4' einerseits mit dem Greifer 2 (F i g. 1) und andererseits mit dem übertägigen Baggergerät (F i g. 2) fest verbunden werden. An ihrem unteren Ende sind die Führungsmasten 4, 4' mit einer Spitze 7 (F i g. 4) versehen, so - daß sie fest auf der Schlitzsohle verankert werden können. Diese Spitzen 7 können gegen Meißel 8 (F i g. 1 und 4) ausgewechselt werden, wenn die Führungsmasten 4, 4' zur Schaffung von Ansatzpunkten für die Greiferschalen oder zum Losmeißeln von Gestein auf der Schlitzsohle eingesetzt werden sollen.The gripper 2, which can be moved in the vertical direction with the rope 1 ( FIGS. 1 and 2), is attached to the carriage 3 , which is arranged to slide on the guide masts 4 and 4 '. By means of hydraulic cylinders 5 and clamping devices 6 , the guide masts 4, 4 'can be firmly connected on the one hand to the gripper 2 (FIG. 1) and on the other hand to the excavator device (FIG . 2). (. F i g 4) at its lower end, the guide poles 4, 4 'is provided with a tip 7 are so - that they can be firmly anchored to the slot sole. These tips 7 can be exchanged for chisels 8 ( FIGS. 1 and 4) if the guide masts 4, 4 'are to be used to create attachment points for the gripper shells or to chisel loose rock on the bottom of the slot.

Der Greifbagger kann als Ganzes auf einer Wandergleisbahn 9 (F i g. 3) fortbewegt und in Arbeitsstellung gebracht werden. Hierzu ist das Greifbaggergerüst 14, an dem die Führungsmasten 4 und 4' und der Greifer 2 mit Zubehör angeordnet sind, sowie der Maschinenrahmen 12 mit den auf einer Bühne untergebrachten 01 Arbeitselementen auf einem Fahrgestell 10 mit Kugeldrehkranz 11 befestigt. Zur Weiterbewegung und zur Richtungsänderung der Wandergleisbahn 9 kann der Greifbagger auf hydraulischen Stützen 13 abgesetzt, die so entlastete Wandergleisbahn 9 angehoben und in die gewünschte Richtung verfahren werden.The grab excavator can be moved as a whole on a touring track 9 ( FIG. 3) and brought into working position. For this purpose, the grab excavator frame 14, on which the guide masts 4 and 4 'and the grab 2 with accessories are arranged, as well as the machine frame 12 with the 01 working elements housed on a platform are attached to a chassis 10 with a slewing ring 11. To move on and change the direction of the touring track 9 , the grab excavator can be placed on hydraulic supports 13 , the thus relieved hiking track 9 can be raised and moved in the desired direction.

Mit diesem Greifbaggergerät lassen sich Bodenschlitze von beliebiger Länge mit einer Breite von minimal 0,4 Meter bis über 1 Meter und einer Tiefe bis zu etwa 30 Meter herstellen. Bei entsprechender Dimensionierung der Antriebselemente können auch größere Tiefen ausgehoben werden. Hierzu werden die Führungsmasten 4, 4' von Normallänge durch Anfügen von 2 Meter langen Schüssen abschnittsweise verlängert. Zur Stützung der Schlitzwände wird sofort nach dem Aushub eine Schwereflüssigkeit geeigneter Zusammensetzung, z. B. Bentonit, eingefüllt. Die anschließende Errichtung der Dichtungsschürze oder Tragwand erfolgt in Abschnitten bestimmter Länge, je nach der Trägfähigkeit der vorliegenden Bodenformation, indem die Schwereflüssigkeit durch geeignete Medien, beispielsweise Hydraton, Beton oder Stahlbeton, verdrängt wird.With this grab excavator, floor slots of any length with a width from a minimum of 0.4 meters to over 1 meter and a depth of up to about 30 meters can be created. If the drive elements are dimensioned accordingly, greater depths can also be excavated. For this purpose, the guide masts 4, 4 'of normal length are lengthened in sections by adding 2 meter long sections. To support the diaphragm walls, a heavy liquid of a suitable composition, e.g. B. bentonite filled. The subsequent construction of the sealing skirt or supporting wall takes place in sections of a certain length, depending on the carrying capacity of the existing soil formation, in that the heavy fluid is displaced by suitable media, for example hydraton, concrete or reinforced concrete.

In der F i g. 4 ist der linke Teil des Schlitzes ein derartiger Abschnitt. Er ist vom rechten Teil des Schlitzes durch eine senkrechte, nicht bezeichnete Abdichtvorrichtung getrennt.In FIG. 4 the left part of the slot is one such section. It is separated from the right part of the slot by a vertical, unspecified sealing device.

Claims (2)

Patentansprüche: 1. Greifbagger zum Herstellen von Schlitzen im Boden mit einem Baggergerüst, einem an einem Seil hängenden Schlitten, der an einer Führung gleitet und mit einem Greifer verbunden ist, dadurch gekennzeichnet, daß der Schlitten (3) mittels Führungsbuchsen, Hydraulikzylindem (5) und Klemmvorrichtungen (6) mit der Führung verbindbar ist, die ihrerseits von zwei am Greifbaggergertist (14) angeordneten, unabhängig voneinander beweglichen Führungsmasten (4, 4') gebildet ist. Claims: 1. Grab excavator for making slots in the ground with an excavator frame, a slide hanging on a rope, which slides on a guide and is connected to a gripper, characterized in that the slide (3) by means of guide bushes, hydraulic cylinders (5) and clamping devices (6) can be connected to the guide, which in turn is formed by two independently movable guide masts (4, 4 ') arranged on the grab excavator (14). 2. Greifbagger nach Anspruch 1, dadurch gekennzeichnet, daß die Führungsmasten (4, und 4") an ihren unteren Enden mit Spitzen (7) versehen sind. 3. Greifbagger nach Anspruch 1, dadurch gekennzeichnet, daß die Führungsmasten (4 und 4) an ihren unteren Enden mit Meißeln (8) versehen sind. In Betracht gezogene Druckschriften-. Deutsches Gebrauchsmuster Nr. 1813 993; belgische Patentschrift Nr. 571844.2. Grab excavator according to claim 1, characterized in that the guide masts (4, and 4 ") are provided with points (7 ) at their lower ends. 3. Grab excavator according to claim 1, characterized in that the guide masts (4 and 4) are provided with chisels (8) at their lower ends. Relevant publications - German utility model No. 1813 993; Belgian patent specification No. 571 844.
DED42346A 1963-08-28 1963-08-28 Grab excavator for making slots in the ground Pending DE1280759B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
DED42346A DE1280759B (en) 1963-08-28 1963-08-28 Grab excavator for making slots in the ground
AT723464A AT252824B (en) 1963-08-28 1964-08-20 Grab excavator for the continuous creation of slots in the ground
NL6409632A NL6409632A (en) 1963-08-28 1964-08-20

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DED42346A DE1280759B (en) 1963-08-28 1963-08-28 Grab excavator for making slots in the ground

Publications (1)

Publication Number Publication Date
DE1280759B true DE1280759B (en) 1968-10-17

Family

ID=7046771

Family Applications (1)

Application Number Title Priority Date Filing Date
DED42346A Pending DE1280759B (en) 1963-08-28 1963-08-28 Grab excavator for making slots in the ground

Country Status (3)

Country Link
AT (1) AT252824B (en)
DE (1) DE1280759B (en)
NL (1) NL6409632A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4265036A (en) * 1979-03-23 1981-05-05 Staats William J Bucket dredging and conveying system
DE4225217C2 (en) * 1992-07-30 2001-08-02 Porr Technobau Ag Recovery device

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CS237125B1 (en) * 1983-07-04 1985-07-16 Anton Panacek Apparatus for excavating wells or ditches

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE571844A (en) *
DE1813993U (en) * 1960-05-03 1960-06-23 Polensky & Zoellner Bauunterne EXCAVATOR.

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE571844A (en) *
DE1813993U (en) * 1960-05-03 1960-06-23 Polensky & Zoellner Bauunterne EXCAVATOR.

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4265036A (en) * 1979-03-23 1981-05-05 Staats William J Bucket dredging and conveying system
DE4225217C2 (en) * 1992-07-30 2001-08-02 Porr Technobau Ag Recovery device

Also Published As

Publication number Publication date
NL6409632A (en) 1965-03-01
AT252824B (en) 1967-03-10

Similar Documents

Publication Publication Date Title
DE1225118B (en) Spoon excavator for digging trenches
EP0412477A1 (en) Grab bucket provided with anchoring means to the trench wall
DE4142369A1 (en) PLANE ARRANGEMENTS ON A WATER VEHICLE, IN PARTICULAR SWIMMING EXCAVATORS
DE1280759B (en) Grab excavator for making slots in the ground
DE3445062C2 (en)
DE4111604A1 (en) METHOD FOR PRODUCING CONCRETE AND CEMENT BODIES IN THE FLOOR
DE2550595C3 (en) A ram and a pipe having device for the production of earth bores and in these arranged piles made of poured or compacted concrete
DE68918516T2 (en) Locking device for rotational reaction force.
EP0103706A1 (en) Shoring apparatus for the shoring of trenches
DE2406215A1 (en) DEVICE AND METHOD FOR LAYING LARGE VOLUME PIPES, IN PARTICULAR PIPELINES
DE1484592A1 (en) Device for taking soil samples
EP2801668A1 (en) Excavation device for producing a trench in the ground
DE2438956A1 (en) Hydraulic shaft tubbing machine as excavator attachment - has rotating cylinder acting as shell guide and vibration production source
DE2420570C2 (en) Device for expanding earth boreholes
DE4140755C1 (en) Vertical shaft excavator for digging, loosening and/or loading - has holding bake with bracket with vertical main axis, round which swivels slewing arm
AT123907B (en) Method and device for the production of concrete bored piles.
DE29705899U1 (en) Shaft excavator
DE2347478C3 (en) Rotary drilling rig for subsoil investigations and the production of deep boreholes
DE1708575C (en) Device for underground laying of pipelines or the like
AT214374B (en) Backhoe
DE2913771C3 (en) Boom equipped with a pulling device for hydraulic excavators
DE3338135A1 (en) Foundation pile for a drilling and/or production platform for deep water
DE3020570A1 (en) Deviation measuring system for trench construction - uses inserted rod with hollow guide cage and two measured inclination angles
DE19511798A1 (en) Bracing support for cable winding vehicle
DE1708572C3 (en) Shaft facility