DE102004031198A1 - Material processing method for e.g. canal construction involves placing sheeting over material placed in channel on ground - Google Patents
Material processing method for e.g. canal construction involves placing sheeting over material placed in channel on ground Download PDFInfo
- Publication number
- DE102004031198A1 DE102004031198A1 DE200410031198 DE102004031198A DE102004031198A1 DE 102004031198 A1 DE102004031198 A1 DE 102004031198A1 DE 200410031198 DE200410031198 DE 200410031198 DE 102004031198 A DE102004031198 A DE 102004031198A DE 102004031198 A1 DE102004031198 A1 DE 102004031198A1
- Authority
- DE
- Germany
- Prior art keywords
- revetment
- channel
- transport
- ground
- processing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/12—Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
- E02B3/121—Devices for applying linings on banks or the water bottom
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/18—Making embankments, e.g. dikes, dams
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Revetment (AREA)
Abstract
Description
Mit diesem Patent soll ein Verfahren zur/zum Aufarbeitung, Transport und Verarbeitung von Materialien mit Hilfe eines entwickelten Verbaugerätes im Bereich des Kanalbaus (Deckwerk) sowie in der Böschungssicherung und im Bereich des Bergbaus gesichert/patentiert werden.With This patent is a process for / for processing, transport and processing of materials using a developed equipment in the field the sewer construction (revetment) as well as in the slope protection and in the area secured / patented by the mining industry.
Wichtig bei diesen Einsatzbereichen (Kanalbau, Böschungssicherung und Bergbau) ist es, dass das Material in den einzubringenden Anwendungsbereichen sämtliche Hohlräume ausfüllt. Dadurch muss es möglich sein, dass das Material ohne Unterbrechung und Pause mit hohen Druck und großer Kraft sozusagen verbaut bzw. verpresst wird. Dazu muss das Material eine hundertprozentig gleichbleibende Konsistenz aufweisen, das bedeutet dieses einzubringende Material muss gleichbleibend fließend sein und parallel keine Unterschiede aufweisen in Hinsicht der Bestandteile im selben Volumen. Insbesondere ist darauf zu achten, dass gleiche Anteile von Wasser und Material vorhanden sind und bis zum Verbau immer vermischt sind. Wäre das nicht der Fall, würde beim Verbau des Materials nicht garantiert werden können, dass sämtliche Hohlräume ausgefüllt werden können.Important in these applications (sewer construction, slope stabilization and mining) it is that the material in the application areas to be introduced all cavities fills. This must make it possible be that the material without interruption and break with high pressure and great power is installed or pressed, so to speak. This requires a material 100% consistent consistency, that means this material to be introduced must be constantly flowing and have no parallel differences in terms of components in the same volume. In particular, care must be taken that same Shares of water and material are present and up to the shoring always mixed. Would that would not be the case in the construction of the material can not be guaranteed that all cavities filled out can be.
Diese Bedingung/Notwendigkeit lässt sich nur erreichen, wenn das Material ohne Verzögerung nach der Mischung sofort verbaut wird. Würde dieses Material nicht sofort verbaut werden, würde sich der Mischzustand wieder umkehren. Das bedeutet, die Bestandteile Wasser und Material würden wieder ihre Vermischung aufgeben. Dies darf aber nicht geschehen, da mit Hilfe des Wassers die Fließbarkeit des Materials garantiert wird.These Condition / need leaves Only reach if the material immediately after mixing without delay is installed. Would This material would not be installed immediately, the mixed state would be back turning back. This means the components of water and material would be back give up their mixing. But this must not happen because with Help of the water the flowability of the material is guaranteed.
Aus diesem Grund wurde es notwendig, ein Verfahren zu entwickeln, welches diese ganzen Bedingungen garantiert. Somit entstand eine Anlage, die das Material über eine Siebung entsprechend aussiebt, wie z.B. zu große Körnungen, Wurzelwerk usw., dieses Material danach mit Wasser mischt. Als Hauptformel kann dort angegeben werden 1/3 Wasser und 2/3 Material. Danach wird das Material mittels Pumpen (zum größten Teil Betonpumpen) mit Hilfe von Schläuchen oder Rohren und eines eigen entwickelten Verbaugerätes verbaut (siehe dazu Flussschema zur/zum Materialaufarbeitung, -transport und -verarbeitung/-einbau „Zeichnung 4 in der Anlage"; eigen entwickeltes Verbaugerät „Zeichnung 11" inklusive beiliegender Nummerierungserläuterungen). Diese Anlage ist auf Grundlage ihrer Einsatzgebiete sehr vielseitig einsetzbar. Dazu ist es erforderlich, für den reibungslosen Direkteinsatz sowohl vom Wasser, vom unwegsamen Gelände sowie von der Straße aus die Anlagen direkt zum Einbauort zu bringen. Aus diesem Grund können Anlagen verschieden verbaut werden. Die günstigste Anwendung wäre in Containern, da die Container universal umsetzbar sind und damit vielseitig einsetzbar. Sie können aber auch fest montiert sein. Einige Anregungen wurden in der Zeichnung 5 in der Anlage inklusive der beiliegenden Nummerierungserläuterung aufgezeigt. Somit sind die Anlagen sowohl auf Schiffen, Lkws, Anhängern und Abrollcontainern montier- bzw. einsetzbar.Out For this reason, it became necessary to develop a method which these whole conditions are guaranteed. Thus, a plant was created, the the material over sifting out a sieve, e.g. too large grain sizes, Root system, etc., then mix this material with water. As a main formula can be specified there 1/3 water and 2/3 material. After that will the material by means of pumps (for the most part concrete pumps) with the help of hoses or pipes and a self-developed Verbaugerätes installed (See the flow chart for material reconditioning, transport and processing / installation "Drawing 4 in the annex "; self-developed assembly unit "Drawing 11" including enclosed Numbering explanations). This plant is very versatile based on its applications used. For this it is necessary for the smooth direct employment from the water, from the rough terrain as well as from the road the To bring plants directly to the installation site. Because of this, plants can be installed differently. The cheapest application would be in containers, because the containers are universally implementable and therefore versatile. You can but also be firmly mounted. Some suggestions were in the drawing 5 in the annex including the enclosed numbering explanation demonstrated. Thus, the facilities are on both ships, trucks, trailers and Roll-off containers can be mounted or used.
Im Bereich des Kanalbaus (Deckwerk) lässt sich der Einsatz des Verfahrens am Besten mit Hilfe von bildhaften Darstellungen gut beschreiben (siehe dazu Zeichnung 1; Zeichnung 2 und Zeichnung 3 inklusive der beiliegenden Nummerierungserläuterung). In diesen Zeichnungen sind unterschiedlichste Kanalböschungsaufbauten (Querschnitt des Kanals) aufgezeigt. Beim Verbau dieses Materials mittels des Verbaugerätes sind aber besondere Notwendigkeiten zu beachten. Es ist notwendig, das Verbaugerät soweit als möglich in das Deckwerk hineinzuführen, Damit das Material nicht nur im oberen Teil des Deckwerkes verbaut wird. Mit Hilfe der bereits angesprochenen Druckverbauung wird das Material eingepresst und garantiert eine komplette Hohlraumverfüllung im Deckwerk. Eine bildhafte Darstellung ist in Zeichnung 6 inklusive der beiliegenden Nummerierungserläuterung ersichtlich. Die Vor- und Nachheransicht des Deckwerkes ist zur Veranschaulichung in Zeichnung 10 „Teilzeichnung 1 + Teilzeichnung 2" inklusive der beiliegenden Nummerierungserläuterung verdeutlicht worden.in the Area of the sewer construction (revetment) can be the use of the method best described best with the help of pictorial representations (See drawing 1, drawing 2 and drawing 3 including the enclosed numbering explanation). In these drawings are different Kanalböschungsaufbauten (Cross section of the channel) shown. When installing this material by means of the Verbaugerätes but special needs to be considered. It is necessary, the Verbaugerät so far as possible into the revetment into it The material is not only installed in the upper part of the revetment. With the help of the already mentioned Druckverbauung the material Pressed in and guarantees a complete cavity filling in the Revetment. A pictorial representation is included in drawing 6 the enclosed numbering explanation. The pros and subsequent view of the revetment is shown in the drawing for illustrative purposes 10 "part drawing 1 + part drawing 2 "included the enclosed numbering explanation has been clarified.
Ein weiterer Anwendungsbereich des Verfahrens inklusive des Verbaugerätes ist die Böschungssicherung. In dieser Anwendung werden in die bestehende Böschung Holzpflöcke geschlagen, die die Aufgabe haben, den aufzubringenden Oberboden zu halten. Zeichnerische Erläuterungen finden Sie dazu in der Zeichnung 8 der Anlage inklusive der Teilzeichnung 1–3 und der beiliegenden Nummerierungserläuterung. Die bildhafte Darstellung des Verbaus wird in Zeichnung 7 in der Anlage inklusive der beiliegenden Nummerierungserläuterung ersichtlich.One Another application of the method including the Verbaugerätes is the slope protection. In this application, wooden pegs are struck into the existing embankment, the have the task of holding the topsoil to be applied. Graphical Explanations Please refer to drawing 8 of the annex including the part drawing 1-3 and the enclosed numbering explanation. The pictorial representation of the Verbaus is shown in drawing 7 in the annex including the enclosed numbering Explanation seen.
Darauf hingewiesen werden muss noch, dass beim Verbau von Materialien im Bereich des Kanalbaus (Deckwerk) und auch im Bereich der Böschungssicherung das Material nicht plan abgezogen werden darf, sondern grobe Unebenheiten aufweisen muss. Dadurch wird verhindert, dass z.B. beigemischter Samen im Material (z.B. Oberboden) nicht ausgeschwemmt oder weggespült wird. Weitere Besonderheiten der zu belassenen groben Unebenheiten auf der Oberfläche sind, dass bei Regenfällen Wasser Zeit hat, sich auch auf Böschungen zu sammeln, um in die Böschungsoberfläche einzudringen. Dies ist notwendig, damit der Boden nicht austrocknet und das der notwendige Pflanzenwachstum für eine dauerhafte Böschungssicherung gedeihen kann.It must also be pointed out that when installing materials in the area of the sewer construction (revetment) and also in the area of the slope protection, the material must not be removed flat, but must have rough unevenness. This prevents eg mixed seeds in the material (eg topsoil) from being washed out or washed away. Other peculiarities of the rough surface unevenness are that during rainfall, water has time to collect on embankments to penetrate the slope surface. This is necessary so that the soil does not dry out and that the necessary plant growth can flourish for a permanent slope protection.
Ein weiterer Anwendungsbereich ist die Verfüllung von Hohlräumen im Bereich des Bergbaus. Dieses wird immer wieder notwendig, da alte Bergwerksstollen einstürzen und Gefährdungen für Mensch und Tier hervorrufen. Hier wird es aber in bestimmten Fällen notwendig werden, das manuelle Verbaugerät durch ein ferngesteuertes Verbaugerät zu ersetzen, damit die Gefährdung für die Personen im Bereich des Verbaus gering gehalten wird. Weiterhin ist in diesem Anwendungsbereich zu beachten, dass 90% des zu verfüllenden Hohlraumes – wie bereits in den beiden vorherigen Anwendungsbereichen beschrieben – verfüllt und das Material aufgearbeitet wird. In den letzten 10% muss dem Material das Produkt Füma zugemischt werden (Produktbezeichnung, z.B. 4702, 4701). Dieses Material hat die Aufgabe/die Funktion/die Eigenschaft aufzuquellen, um nach dem Verbau des Materials sämtliche Hohlräume auszufüllen. Somit kann garantiert werden, dass keinerlei Hohlräume nach dem Verbau mehr vorhanden sind und gefährdete Gebiete nicht mehr vom Einsturz bedroht sind (siehe dazu Zeichnung 9 inklusive beiliegender Nummerierungserläuterung).One Another application is the filling of cavities in the Area of mining. This is necessary again and again, because old Collapse of mine tunnels and threats for human and cause animal. But here it is necessary in certain cases become the manual installer to be replaced by a remote controlled device, so that the danger to the persons in the Area of the Verbaus is kept low. Furthermore, in this Scope of application to note that 90% of the to be filled Cavity - like already described in the two previous application areas - filled and the material is worked up. In the last 10% of the material has the Product Füma (product name, e.g., 4702, 4701). This Material has the task / function / property to swell after the installation of the material all cavities fill. Thus it can be guaranteed that no cavities after there are more and less vulnerable areas and no longer endangered areas Collapse are threatened (see drawing 9 including enclosed Numbering explanation).
Erläuterungen zu Zeichnung 1:Explanatory notes to drawing 1:
(Querschnitt im Kanal)
- 1
- Versickerungsmulde
- 2
- 3
- Boden aufgefüllt
- 4
- abgestufter Kornfilter nach MAK
- 5
- Betriebsweg (in diesem Fall wie folgt aufgebaut)
- – 1 cm Deckschicht, Splitt 2/5 mm
- – 10 cm Schotterrasen (15% Oberboden; 85% Schotter 32/45 mm)
- – 15 cm Tragschicht, Schotter 0/45 mm
- 6
- Knickpunkt zur Verjüngung des Deckwerkes
- 7
- Abschluss Deckwerk
- 8
- Beginn des zu verfüllenden Deckwerkes mit Oberboden
- 9
- loses Deckwerk (Schüttsteine in diesem Fall Klasse II)
- 10
- Vollverguss
- 11
- Geotextiler Filter
- 12
- Hohlräume im Deckwerk mit Oberboden ausgefüllt mittels des zu patentierenden Verfahrens
- 13
- Wasserstand im Kanal
- 1
- depression in
- 2
- 3
- Soil filled up
- 4
- Graded grain filter according to MAK
- 5
- Operating path (in this case constructed as follows)
- - 1 cm top layer, chippings 2/5 mm
- - 10 cm gravel grass (15% topsoil, 85% gravel 32/45 mm)
- - 15 cm base course, gravel 0/45 mm
- 6
- Kink point for the rejuvenation of the revetment
- 7
- Completion revetment
- 8th
- Beginning of the revetment to be filled with topsoil
- 9
- loose revetment (Schüttsteine in this case class II)
- 10
- Full Encapsulation
- 11
- Geotextile filter
- 12
- Cavities in the revetment filled with topsoil by means of the patented process
- 13
- Water level in the canal
Erläuterungen zu Zeichnung 2:Explanatory notes to drawing 2:
Querschnitt im Kanal)
- 1
- 10 cm Oberbodenabdeckung
- 2
- mit Boden verfüllen
- 3
- obere Böschungskante vom Kanal
- 4
- Hohlräume im Deckwerk mit Oberboden ausgefüllt mittels des zu patentierenden Verfahrens
- 5
- Beginn des zu verfüllenden Deckwerks mit Oberboden
- 6
- Betriebsweg (in diesem Fall wie folgt aufgebaut)
- a. 1 cm Deckschicht Splitt 2/5 cm
- b. 10 cm Schotterrasen (15% Oberboden; 85% Schotter 32/45 mm)
- c. 15 cm Tragschicht 0/45 mm
- 7
- 5 cm Oberbodenabdeckung
- 8
- 2 stufiger ungebundener Kornfilter
- 9
- Loses Deckwerk Schüttsteine K1. II
- 10
- Wasserstand im Kanal
- 11
- Abschluss Deckwerk
- 12
- Knickpunkt zur Verjüngung des Deckwerkes
- 1
- 10 cm top cover
- 2
- fill with soil
- 3
- upper slope edge of the canal
- 4
- Cavities in the revetment filled with topsoil by means of the patented process
- 5
- Beginning of the revetment to be filled with topsoil
- 6
- Operating path (in this case constructed as follows)
- a. 1 cm cover layer chippings 2/5 cm
- b. 10 cm gravel grass (15% topsoil, 85% gravel 32/45 mm)
- c. 15 cm base layer 0/45 mm
- 7
- 5 cm top cover
- 8th
- 2-stage unbound grain filter
- 9
- Loose revetment of loose stones K1. II
- 10
- Water level in the canal
- 11
- Completion revetment
- 12
- Kink point for the rejuvenation of the revetment
Erläuterung zu Zeichnung 3:Explanation to drawing 3:
(Querschnitt im Kanal)
- 1
- Verankerung
- 2
- Ein- oder zweistufiger Kornfilter nach MAK
- 3
- Spundwand
- 4
- Geotexfiltermatte
- 5
- 6
- Spundwandoberkante
- 7
- Holm
- 8
- Oberkante Holm
- 9
- Loses Deckwerk Klasse II auszufüllen mit Oberboden mittels des zu patentierenden Verfahrens
- 10
- Oberkante Böschung
- 11
- Oberboden mittels patentierten Verfahren aufgebracht
- 12
- Oberboden mittels patentierten Verfahren aufgebracht
- 13
- Wasserstand im Kanal
- 1
- anchoring
- 2
- One or two-stage grain filter according to MAK
- 3
- bulkhead
- 4
- Geotexfiltermatte
- 5
- 6
- Sheet piling top
- 7
- Holm
- 8th
- Top edge spar
- 9
- Complete revetment class II filled with topsoil by means of the patented process
- 10
- Top edge of embankment
- 11
- Topsoil applied by patented process
- 12
- Topsoil applied by patented process
- 13
- Water level in the canal
Erläuterung zu Zeichnung 5:
- 1
- Technik zur/zum Materialaufarbeitung, -transport und -verarbeitung/-einbau verbaut auf einem Glattdeckleichter
- 2
- Technik zur/zum Materialaufarbeitung, -transport und -verarbeitung/-einbau verbaut auf einem Sattelauflieger
- 3
- Technik zur/zum Materialaufarbeitung, -transport und -verarbeitung/-einbau verbaut auf einem Drehschemelanhänger
- 4
- Technik zur/zum Materialaufarbeitung, -transport und -verarbeitung/-einbau verbaut auf einem Vierachsfahrgestell (Nach StVZO Gesamtzuggewicht maximal 32 to.)
- 5
- Technik zur/zum Materialaufarbeitung, -transport und -verarbeitung/-einbau verbaut auf einem Lkw (zwei- oder dreiachsig) variabel auf Baustellenfahrzeugen „Altrad" oder normalen Straßenlastkraftwagen)
- 6
- Technik zur/zum Materialaufarbeitung, -transport und verarbeitung/-einbau verbaut auf einem
- Abrollcontainer
- 1
- Technology for material processing, transport and processing / installation installed on a smooth flat roofer
- 2
- Technology for material reconditioning, transport and processing / installation installed on a semi-trailer
- 3
- Technique for material processing, transport and processing installed on a turntable trailer
- 4
- Technique for / material processing, transport and processing / installation installed on a four-axle chassis (according to StVZO gross vehicle weight maximum 32 tons.)
- 5
- Technology for material reconditioning, transport and processing / installation mounted on a truck (two- or three-axle) variable on construction vehicles "Altrad" or normal road trucks)
- 6
- Technology for / material processing, transport and processing / installation installed on one
- abrollcontainer
Erläuterung zu Zeichnung 6:Explanation to drawing 6:
(Verbau des aufgearbeiteten bzw. verarbeiteten Materials mit Hilfe eines entwickelten Verbaugerätes im Bereich des Deckwerkes „Kanalbau")
- 1
- arbeitende Person
- 2
- Schlauch oder Rohr für die Materialzuführung des aufgearbeiteten Materials
- 3
- Einbau/Verbaugerät für das aufgearbeitete Material
- 4
- Verbautes aufgearbeitetes Material
- 5
- Deckwerk im Kanalbau (Schüttsteine Klasse 2)
- 1
- working person
- 2
- Hose or tube for the material supply of the reclaimed material
- 3
- Installation / removal unit for the reclaimed material
- 4
- Deployed refurbished material
- 5
- Revetment in sewer construction (Schüttsteine class 2)
Erläuterungen zu Zeichnung 7:Explanatory notes to drawing 7:
(Verbau des aufgearbeiteten bzw. verarbeiteten Materials mit Hilfe eines entwickelten Verbaugerätes im Bereich der Böschungsbefestigung)
- 1
- Schlauch oder Rohr für die Materialzuführung des aufgearbeiteten Materials
- 2
- Einbau/Verbaugerät für das aufgearbeitete Material
- 3
- Verbautes aufgearbeitetes Material (Oberboden)
- 4
- Profil der vorhandenen Böschung, die gesichert werden muss (vor dem Abrutschen)
- 5
- Holzpflöcke zum Halten des aufgebrachten Materials
- 6
- Arbeitende Person
- 1
- Hose or tube for the material supply of the reclaimed material
- 2
- Installation / removal unit for the reclaimed material
- 3
- Used refurbished material (topsoil)
- 4
- Profile of the existing embankment, which must be secured (before slipping)
- 5
- Wooden pegs for holding the applied material
- 6
- Working person
Erläuterung zu Zeichnung 8:
- Teilzeichnung 1 = Draufsicht auf die Böschungsschräge mit Holzpflöcken. Die Anzahl der Holzpflöcke richtet sich nach der Schräge der Böschung. Somit variiert die Anzahl der einzubauenden Holzpflöcke zwischen 8 und 20 Stück/m2.
- 1
- Oberkante der zu sichernden Böschungsebene
- 2
- Holzpflöcke (je m2 zwischen 8 und 20 Stück)
- Teilzeichnung 2 = Querschnitt der zu sichernden Böschung mit Holzpflöcken.
- 3
- Böschungsfläche
- 4
- Holzpflöcke
- Teilzeichnung 3 = Querschnitt der zu sichernden Böschung mit Holzpflöcken und aufgebrachten Oberboden
- 5
- aufgebrachter Oberboden mittels Verbaugerät (es ist darauf zu achten, dass eine Deckung oberhalb der Holzpflöcke von mindestens 5cm erforderlich ist und die Holzpflöcke in der Böschung um mindestens 15cm versenkt sind und mindestens 10cm aus der Böschung zum Halten des Oberbodens noch herausschauen.
- 6
- Böschungsfläche
- 7
- Oberfläche des aufgebrachten Oberbodens (nicht eben, sondern stark aufgeraut, damit sich Wasser bilden kann und in das Erdreich versickern kann bei Niederschlag)
- 8
- Oberkante der herausschauenden Holzpflöcke
- 9
- Fläche auf dem der Oberboden aufgetragen wird
- 10
- Holzpflöcke
- Partial drawing 1 = top view of the slopes with wooden pegs. The number of wooden pegs depends on the incline of the embankment. Thus, the number of wooden pegs to be installed varies between 8 and 20 pieces / m 2 .
- 1
- Top edge of the embankment level to be secured
- 2
- Wooden pegs (per m 2 between 8 and 20 pieces)
- Partial drawing 2 = Cross section of the embankment to be secured with wooden pegs.
- 3
- slope face
- 4
- wooden stakes
- Partial drawing 3 = Cross section of the embankment to be secured with wooden pegs and applied topsoil
- 5
- Applied topsoil by means of an installer (make sure that a cover above the wooden pegs of at least 5cm is required and the pegs are sunk in the embankment by at least 15cm and still at least 10cm from the embankment to hold the top floor still look out.
- 6
- slope face
- 7
- Surface of the applied topsoil (not flat, but heavily roughened, so that water can form and seep into the soil during precipitation)
- 8th
- Top of the outward looking wooden pegs
- 9
- Surface on which the topsoil is applied
- 10
- wooden stakes
Erläuterung zu Zeichnung 9:Explanation to drawing 9:
(Querschnitt von Hohlraumverfüllungen im Bereich des Bergbaues)
- 1
- Schlauch bzw. Rohr zum Transport des aufgearbeiteten Materials
- 2
- Anlage zur Aufarbeitung und Verarbeitung des zu verfüllenden Materials
- 3
- Bebauung
- 4
- Zu verfüllender Hohlraum (90% des zu verfüllenden Hohlraumes)
- 5
- Bebauung
- 6
- Zu verfüllender Hohlraum, dem zu verfüllenden Material wird das Produkt Fyma beigefügt (Produktbezeichnung, z.B. 4702, 4701). Dieses Material hat die Aufgabe, aufzuquellen, um nach dem Verbau des Materials sämtliche Hohlräume auszufüllen. Somit wird garantiert, dass keinerlei Hohlräume mehr vorhanden sind und gefährdete Gebiete nicht mehr vom Einsturz bedroht sind.
- 7
- Bebauung
- 8
- Bepflanzung
- 1
- Hose or tube for transporting the reclaimed material
- 2
- Plant for processing and processing of the material to be filled
- 3
- building
- 4
- Cavity to be filled (90% of the cavity to be filled)
- 5
- building
- 6
- To be filled cavity, the material to be filled is the product Fyma attached (product name, eg 4702, 4701). This material has the task of swelling to fill after filling the material all cavities. This guarantees that no cavities are left and endangered areas are no longer threatened by collapse.
- 7
- building
- 8th
- planting
Erläuterung zu Zeichnung 10:
- Teilzeichnung 1 = Deckwerk (beim Kanalbau) vor der Verfüllung
- 1
- Schüttsteine Klasse 2
- 2
- Unterbau
- Teilzeichnung 2 = Deckwerk nach der Verfüllung/Verpressung mit Oberboden oder Beton
- 3
- Schüttsteine Klasse 2
- 4
- Verfülltes/verpresstes Material
- 5
- Unterbau
- Partial drawing 1 = revetment (during sewer construction) before backfilling
- 1
- Schüttsteine class 2
- 2
- substructure
- Partial drawing 2 = revetment after backfilling / grouting with topsoil or concrete
- 3
- Schüttsteine class 2
- 4
- Backfilled / pressed material
- 5
- substructure
Erläuterungen zu Zeichnung 11:Explanatory notes to drawing 11:
Verbaugerät)
- 1
- Schlauch/Rohr zur Materialzuführung
- 2
- Haltegriffe für Person zum halten des Gerätes
- 3
- Schlauch
- 4
- Haltegestell
- 5
- Versteifungsgestell
- 6
- Verbindungsschellen
- 1
- Hose / tube for material supply
- 2
- Handles for person to hold the device
- 3
- tube
- 4
- holding frame
- 5
- stiffening frame
- 6
- connection clamps
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE200410031198 DE102004031198A1 (en) | 2004-06-28 | 2004-06-28 | Material processing method for e.g. canal construction involves placing sheeting over material placed in channel on ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE200410031198 DE102004031198A1 (en) | 2004-06-28 | 2004-06-28 | Material processing method for e.g. canal construction involves placing sheeting over material placed in channel on ground |
Publications (1)
Publication Number | Publication Date |
---|---|
DE102004031198A1 true DE102004031198A1 (en) | 2006-01-19 |
Family
ID=35508001
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE200410031198 Withdrawn DE102004031198A1 (en) | 2004-06-28 | 2004-06-28 | Material processing method for e.g. canal construction involves placing sheeting over material placed in channel on ground |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE102004031198A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110647039A (en) * | 2019-10-08 | 2020-01-03 | 黄河勘测规划设计研究院有限公司 | Synchronous control self-adaptive balance scheduling method for long-distance open channel water delivery project |
-
2004
- 2004-06-28 DE DE200410031198 patent/DE102004031198A1/en not_active Withdrawn
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110647039A (en) * | 2019-10-08 | 2020-01-03 | 黄河勘测规划设计研究院有限公司 | Synchronous control self-adaptive balance scheduling method for long-distance open channel water delivery project |
CN110647039B (en) * | 2019-10-08 | 2022-03-25 | 黄河勘测规划设计研究院有限公司 | Synchronous control self-adaptive balance scheduling method for long-distance open channel water delivery project |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE29824577U1 (en) | Dike, network structure of vehicle tires and assembly platform | |
EP3696328B1 (en) | Method for installing vertical grids against burrowing animals | |
AT352639B (en) | SHORE SHORING | |
DE102004031198A1 (en) | Material processing method for e.g. canal construction involves placing sheeting over material placed in channel on ground | |
DE102007056408B4 (en) | System and method for building a roadway | |
DE102012004980A1 (en) | Method for stabilizing subsoil of road and building, for use in removal of e.g. building load in stable region, involves compressing and moving jacket tube to floor material installation site, while holding sheath at lower end of soil | |
AT519819B1 (en) | METHOD FOR SUBSEQUENT SOIL CONSOLIDATION | |
EP0691437A1 (en) | Method for stabilising slopes | |
EP0141772B1 (en) | Ventilation plate for sanitizing or planting trees | |
DE3521434A1 (en) | Injection method and apparatus for soil stabilisation | |
DE102014101334A1 (en) | Slope protection device, thus created embankment structure, and method for producing such a slope structure | |
CH661078A5 (en) | METHOD FOR GROUNDING AND / OR STABILIZING A SOIL. | |
DE3716292A1 (en) | Method and arrangement for constructing a diaphragm wall | |
EP3134581B1 (en) | Method and soil-stabilizing means | |
AT518483B1 (en) | Mobile tensioning device | |
DE102008001109A1 (en) | Drainage of a shotcrete shell with drainage pipes | |
AT330672B (en) | INFLATABLE WEIR FOR WATER COURSES AND PROCEDURE FOR ERECTING SUCH WEIR | |
DE102005010495A1 (en) | Device for producing of barrage or similar involves a pressure tight container that is either single or double-walled and has a filler opening, connector and anchor to fix the device underground | |
DE1534383C (en) | Process for the production of viable trench fillings after excavations in traffic routes using a mobile device | |
DE69715779T2 (en) | Device and method for generating permeability in a diaphragm wall | |
DE3410469A1 (en) | Method of restoring or replanting trees | |
DE10037320C2 (en) | Method and devices for laying a pipe string consisting of a number of pipes in a channel at the bottom of a body of water | |
DE8332080U1 (en) | TREE VENTILATION PLATE FOR THE RENOVATION OR REPLANTING OF TREES | |
EP0257382A2 (en) | Method for stabilizing the soil | |
EP1125029B1 (en) | Infiltration drainage fitting or infiltration drainage conduit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8139 | Disposal/non-payment of the annual fee |