Verfahren zur Erfassung von Steinen und anderen Fremdkörpern im Fördergut auf Gurtbandförderern, dadurch gekennzeichnet, daß an einem Punkt des Gurtbandförderers (1) gleichzeitig die Meterlast und das Fördervolumen des Fördergutes (7) ermittelt, die Meßwertpaare verglichen und aus Abweichungen der Meßwertpaare zueinander unter Berücksichtigung der korrelierenden Meßwertdynamik ein Meßwert gewonnen und einer Signaleinrichtung und/oder Einrichtung zur Aushaltung der Steine und/oder Notabschalteeinrichtung zugeführt wird.Method for detecting stones and other foreign objects in the conveyed on belt conveyors, characterized in that at a point of the belt conveyor (1) at the same time determines the meter load and the delivery volume of the conveyed material (7), compared the Meßwertpaare and deviations of Meßwertpaare each other taking into account correlated measured value dynamics obtained a measured value and a signal device and / or device for holding the stones and / or Notabschalteeinrichtung is supplied.
HierzuFor this
2 Seiten Zeichnungen2 pages drawings
Anwendungsgebiet der ErfindungField of application of the invention
Die Erfindung betrifft ein Verfahren zur Erfassung von Steinen und anderen Fremdkörpern im Fördergut auf Gurtbandförderern, welche zu Beschädigungen bzw. zu erhöhtem Verschleiß der Förderanlage führen. Wesentliches Anwendungsgebiet Lt die Steinaushaltung auf Förderanlagen des Braunkohlentagebaues.The invention relates to a method for detecting stones and other foreign bodies in the conveyed on belt conveyors, which lead to damage or increased wear of the conveyor system. Main field of application Lt the Steinaushaltung on conveyors of lignite opencast mining.
Charakteristik des bekannten Standes der TechnikCharacteristic of the known state of the art
Dem Problem der Erfassung von Steinen und anderen Fremdkörpern, welche zur Beschädigung von Fördereinrichtungen insbesondere des Tagebaubetriebes führen können, wird seit langer Zeit eine besondere Aufmerksamkeit geschenkt. Neben der Ortung derartiger Fremdkörper im Gebirge selbst, also noch vor der Förderung, für die seismische, gravimetrisch und radiometrische Untersuchungsverfahren bekannt wurden, kommt der Erfassung dieser Fremdkörper auf den Fördereinrichtungen selbst eine hohe Bedeutung zu, da in diesem Bereich schwerwiegende Schäden, insbesondere an den Fördergurten entstehen können. Als gelöst kann die Erfassung metallischer Fremdkörper angesehen werden, da für diesen Zweck Meßverfahren zur Verfügung stehen, welche auf der Grundlage der Veränderung der magnetischen Eigenschaften im Bereich der Lage des Fremdkörpers im Förderstrom basieren.The problem of the detection of stones and other foreign bodies, which can lead to the damage of conveyors in particular of open pit mining, has long been given special attention. In addition to the location of such foreign objects in the mountains themselves, so even before the promotion, were known for the seismic, gravimetric and radiometric examination method, the detection of foreign bodies on the conveyors themselves is of great importance, since in this area serious damage, especially to the Conveyor belts may arise. The detection of metallic foreign bodies can be regarded as solved since measuring methods are available for this purpose which are based on the change in the magnetic properties in the region of the position of the foreign body in the delivery flow.
Schwierigkeiten hingegen bestehen nach wie vor im Erkennen von Steinen, insbesondere dann, wenn sie im Fördergutstrom verborgen, also optisch nicht erkannt werden können. Durch die DD-PS 227538 wurde bereits eine Lösung bekannt, nach welcher verborgene Steine im oberflächennahen Bereich in Tagebauen durch Erfassung des anomalen thermischen Potentialfeldes, hervorgerufen durch Dichteinhomogenitäten, geortet werden sollen. Dieses Meßverfahren eignet sich jedoch nur für Gestein von sehr großen Abmessungen. Kleinere Steine, die jedoch die Gurtbandförderer zu beschädigen imstande sind — in der Praxis sind das bereits Steine mit einer Kantenlänge von größer als 400mm — die bereits im Fördergutstrom enthalten sind, besitzen nur ein gering vom übrigen Fördergut abweichendes thermisches Potentialfeld, das nicht mehr geortet werden kann. Auch das Erfassen von Steinen auf dem Gurtbandförderer mit einer Isotopenmeßanlage, wie durch DD-PS 123703 vorgeschlagen, konnte in der Praxis keinen Eingang finden, da bei der erforderlichen Durchstrahlung bereits Gurtstöße die Dichtebostimmungen verfälschen und damit fortwährende Fehlortungen die Folge sind. Aus diesem Grund hat sich bis heute die visuelle Kontrolle des Gurtbandförderers auf ankommende Steine durchgesetzt. Sie versagt jedoch, wenn diese Steine vom übrigen Fördergut verdeckt sind, weshalb bereits Versuche unternommen wurden, mit Hilfe von in den Fördergutstrom greifende mechanische Γ aster Notabschaltungen zu veranlassen. Ein derartiges Ortungssystem behindert natürlicherweise den Fördergutstrom, insbesondere Anbackungen und Anfrierungen im Winterbetrieb, so daß sich auch derartige Einrichtungen nicht durchsetzen konnten.However, difficulties still exist in the detection of stones, especially when they are hidden in the flow of conveyed material, that is to say they can not be visually recognized. By DD-PS 227538 a solution has already been known, according to which hidden stones in the near-surface area in opencast mines to be located by detecting the anomalous thermal potential field, caused by density inhomogeneities. However, this measurement method is only suitable for rocks of very large dimensions. Smaller stones, however, which are capable of damaging the belt conveyors - in practice, these are already stones with an edge length of greater than 400mm - which are already contained in Fördergutstrom, have only a little deviating from the rest of Fördergut thermal potential field, which are no longer located can. Also, the detection of stones on the belt conveyor with a Isotopenmeßanlage, as proposed by DD-PS 123703, could find no input in practice, since in the required radiation already Gurtstöße falsify the density standards and thus ongoing faulty locations are the result. For this reason, the visual inspection of the belt conveyor on incoming stones has prevailed to this day. However, it fails if these stones are covered by the other conveyed, which is why attempts have been made to initiate with the help of engaging in the Fördergutstrom mechanical Γ aster emergency shutdowns. Such a location system naturally obstructs the Fördergutstrom, especially caking and frostbite in winter operation, so that even such facilities could not prevail.
Ziel der ErfindungObject of the invention
Ziel der Erfindung ist es, zuverlässig Steine und andere Fremdkörper im Fördergut auf Gurtbandförderern mit einfachen meßtechnischen Mitteln zu orten und ein Signal für Maßnahmen der Schadensverhütung am Gurtbandförderer durch die Fremdkörper bereitzustellen.The aim of the invention is to reliably locate stones and other foreign matter in the conveyed on webbing conveyors with simple metrological means and to provide a signal for measures of damage prevention on Gurtbandförderer by the foreign body.
Das Wesen der ErfindungThe essence of the invention
Der Erfindung liegt die Aufgabe zugrunde, ein Meßverfahren zu entwickeln, welches Inhomogenitäten des Fördergutstromes eindeutig zu erfassen gestattet und Meßwerte zur Verfügung stellt, welche einen Rückschluß auf die Art des Fremdkörpers im Fördergutstrom zulassen.The invention has for its object to develop a measuring method which clearly allows to detect inhomogeneities of Fördergutstromes and provides readings available, which allow a conclusion on the type of foreign body in Fördergutstrom.
Diese Aufgabe wird erfindungsgemäß gelöst, indem auf einer Basislänge des Gurtbandförderers von beispielsweise = 1 m gleichzeitig eine Massen- und Volumenbestimmung des Fördergutstromes erfolgt und daraus die Dichte des Fördergutstromabschnittes ermittelt wird. Zweckmäßig geschieht die Massenbestimmung mit Hilfe einer Einrollenbandwaage, die aus an den Tragrollen angeordneten Kraftmeßdosen besteht und einer Fördervolumenmeßanlage auf HF-Basis. Die Bestimmung der Dichte erfolgt durch eine geeignete Schaltung mit Hilfe der Quotientenbildung aus beiden gewonnenen Meßwerten. Dia Signnlgewinnung erfolgt damit durch Ermittlung von Abweichungen der Meßwertpaare zueinander und unter Berücksichtigung der korrelierenden Meßwertdynamik. Rasche Anstiege der Dichte kennzeichnen grundsätzlich eine Gefahrensitum'in, so daß das Signal der Dichte unmittelbar zur Auflösung eines Signals für das Gerätepersonal, einer Zwangsabschaltung des Gurtbandförderers oder aber Mitteln zur Auehaltung der Steine genutzt werden kann.This object is achieved by a mass and volume determination of Fördergutstromes carried out on a base length of the webbing conveyor of, for example = 1 m at the same time and from the density of Fördergutstromabschnittes is determined. Suitably, the mass determination is done by means of a Einrollengurtwaage, which consists of arranged on the support rollers load cells and a Fördervolumenmeßanlage on HF basis. The density is determined by means of a suitable circuit with the help of the quotient formation from the two measured values obtained. Dia Signnlgewinnung done so by determining deviations of the measured value pairs to each other and taking into account the correlated measured value dynamics. Rapid increases in density are generally indicative of danger, so that the signal of density can be used directly to resolve a signal to the equipment personnel, a forced shutdown of the belt conveyor or means to hold the stones.