CN220596815U - Assembled building materials hoisting device - Google Patents

Assembled building materials hoisting device Download PDF

Info

Publication number
CN220596815U
CN220596815U CN202321839350.8U CN202321839350U CN220596815U CN 220596815 U CN220596815 U CN 220596815U CN 202321839350 U CN202321839350 U CN 202321839350U CN 220596815 U CN220596815 U CN 220596815U
Authority
CN
China
Prior art keywords
fixedly connected
rope
wallboard
connecting rod
outer side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321839350.8U
Other languages
Chinese (zh)
Inventor
裴晓鹏
吴亚柱
汤高荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202321839350.8U priority Critical patent/CN220596815U/en
Application granted granted Critical
Publication of CN220596815U publication Critical patent/CN220596815U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an assembled building material lifting device, which relates to the technical field of green buildings and comprises a connecting frame, wherein the top surfaces of two ends of the connecting frame are fixedly connected with second vertical arms, the outer sides of the two second vertical arms are respectively provided with a first vertical arm, the outer side walls of the two first vertical arms are fixedly connected with connecting plates, the side walls of the connecting plates are rotationally connected with a rope collecting roller, the outer side walls of the rope collecting roller are fixedly connected with movable ropes, and the movable ropes are rotated by the first connecting rods, so that the first connecting rods are rotated and moved downwards along racks, the movable ropes are driven to be hooked downwards by the first connecting rods, pass through second directional wheels and drive fixed hooks to move upwards, so that one side of a wallboard is pulled upwards, the whole wallboard is vertically placed, the effect of vertical overturning after the wallboard is improved is realized, the problem of complex operation of the overturning wallboard in high-place operation is avoided, and the portability of the wallboard after being lifted is installed is improved.

Description

Assembled building materials hoisting device
Technical Field
The utility model relates to the technical field of green buildings, in particular to an assembled building material lifting device.
Background
The fabricated building is a building which is fabricated by transferring a large amount of field operation work in a traditional building mode to a factory, processing and manufacturing building components and accessories (such as floors, wallboards, stairs, balconies and the like) in the factory, transporting to a building construction site, assembling and installing the building accessories on site through a reliable connection mode, and after the building accessories are transported to the site, installing the accessories on site is needed, and for the installation of a high-rise building, transporting the accessories to a designated position by means of lifting equipment is needed.
In the prior art, as disclosed in chinese patent CN217808575U, "a building material hoisting device for green assembly type building construction", the on-line screen storage device comprises a base, the base symmetry is provided with the frame, adjacent slidable is provided with the carriage between the frame, install building material spacing frame on the carriage, compare the mode of fixing after binding by the hoist machine again with conventional rope, the assembly building material can be stably spacing in the carriage, and the upper and lower slip of carriage is driven by hydraulic cylinder, and two sets of hydraulic cylinder drive in the drive process.
However, in the prior art, the building wallboard is generally transported in a horizontal state for improving the stability during moving, and is generally placed vertically during building processing, so that the lifted wallboard is directly transported, and after being lifted to a designated height, the wallboard is required to be turned over to a vertical state, so that the high-altitude operation is inconvenient.
Disclosure of Invention
The utility model aims to solve the problem that the wallboard is inconvenient to operate at a high place because the wallboard needs to be turned to be in a vertical state after being lifted to a specified height in the prior art by directly carrying and lifting the wallboard.
In order to achieve the above purpose, the present utility model adopts the following technical scheme: the utility model provides an assembled building materials hoisting device, includes the link, the equal fixedly connected with second perpendicular arm of both ends top surface of link, two the outside of the perpendicular arm of second all is provided with first perpendicular arm, two the equal fixedly connected with connecting plate of lateral wall of the perpendicular arm of first, the lateral wall rotation of connecting plate is connected with receipts rope roller, the lateral wall fixedly connected with activity rope of receipts rope roller, the top of activity rope is provided with the head rod, the lateral wall fixedly connected with of receipts rope roller is heightened the rope, heighten the rope with the equal fixedly connected with fixed hook in bottom of activity rope, the bottom fixedly connected with first directional wheel of first perpendicular arm, the bottom fixedly connected with second directional wheel of the perpendicular arm of second.
Preferably, the casters are fixedly connected to the four corner positions at the bottom end of the connecting frame, and gears are fixedly connected to the two ends of the first connecting rod.
Preferably, the outer side of the gear is meshed with a rack, and the outer side wall of the rack is fixedly connected with a guide rail.
Preferably, the first connecting rod is in sliding connection with the guide rail, and the outer sides of the gears are fixedly connected with round baffles.
Preferably, the outer side wall of the connecting frame is coated with an antirust agent, and the inner side wall of the guide rail is coated with a lubricant.
Preferably, a second connecting rod is fixedly connected between the two rope collecting rollers, the outer side wall of the height-adjusting rope is in sliding connection with the first directional wheel, and the outer side wall of the movable rope is in sliding connection with the second directional wheel.
Compared with the prior art, the utility model has the advantages and positive effects that:
1. according to the utility model, the first connecting rod is rotated to enable the first connecting rod to move downwards along the rack, the first connecting rod drives the movable rope to hook downwards, the movable rope passes through the second directional wheel and drives the fixed hook to move upwards, so that one side of the wallboard is pulled upwards, the whole wallboard is vertically placed, the effect of vertical overturning after the wallboard is improved is achieved, the problem of complex operation of overturning the wallboard during high-place operation is avoided, and the portability of installation of the wallboard after the wallboard is lifted is improved.
2. According to the utility model, the guide rail is fixedly connected between the first vertical arm and the second vertical arm, so that the first connecting rod moves under the limit of the guide rail, meanwhile, the rack is arranged in the guide rail, the gears are fixed at the two ends of the first connecting rod, and the gears are meshed with the rack, so that the stability of the height adjustment of the first connecting rod is improved, and the wallboard can be turned more stably.
Drawings
Fig. 1 is a schematic perspective view of an assembled building material lifting device according to the present utility model;
fig. 2 is a schematic perspective view of a first vertical arm and a second vertical arm in an assembled building material lifting device according to the present utility model;
FIG. 3 is a schematic perspective view of a movable rope in an assembled building material lifting device according to the present utility model;
fig. 4 is an enlarged view of the partial structure at a in fig. 3.
Legend description: 1. a connecting frame; 2. a first vertical arm; 3. a second vertical arm; 4. a first steering wheel; 5. a second orientation wheel; 6. a fixed hook; 7. a height-adjusting rope; 8. a guide rail; 9. a rack; 10. a round baffle; 11. a rope collecting roller; 12. a connecting plate; 13. a first connecting rod; 14. a gear; 15. a movable rope; 16. a second connecting rod; 17. casters.
Detailed Description
In order that the above objects, features and advantages of the utility model will be more clearly understood, a further description of the utility model will be rendered by reference to the appended drawings and examples. It should be noted that, in the case of no conflict, the embodiments of the present application and the features in the embodiments may be combined with each other.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present utility model, however, the present utility model may be practiced otherwise than as described herein, and therefore the present utility model is not limited to the specific embodiments of the disclosure that follow.
Example 1
As shown in fig. 1-4, the utility model provides an assembled building material lifting device, which comprises a connecting frame 1, wherein the top surfaces of two ends of the connecting frame 1 are fixedly connected with second vertical arms 3, the outer sides of the two second vertical arms 3 are respectively provided with a first vertical arm 2, the outer side walls of the two first vertical arms 2 are fixedly connected with a connecting plate 12, the side walls of the connecting plate 12 are rotatably connected with a rope collecting roller 11, the outer side walls of the rope collecting roller 11 are fixedly connected with movable ropes 15, a first connecting rod 13 is arranged above the top ends of the movable ropes 15, the outer side walls of the rope collecting roller 11 are fixedly connected with height adjusting ropes 7, the bottom ends of the height adjusting ropes 7 and the movable ropes 15 are fixedly connected with fixed hooks 6, the bottom surfaces of the first vertical arms 2 are fixedly connected with first directional wheels 4, and the bottom ends of the second vertical arms 3 are fixedly connected with second directional wheels 5.
In the following, the specific setting and action of this embodiment will be described specifically, when in use, the building wall is placed above the connecting frame 1, and the four fixing hooks 6 are aligned with the four corners of the wallboard, the fixing hooks 6 are fixed with the wallboard, in the first stage, the rope collecting roller 11 at the corners of the first vertical arm 2 and the connecting frame 1 is rotated, the rope collecting roller 11 rotates, the height of the fixing hooks 6 is raised by the height-adjusting rope 7 through the first directional wheel 4, the whole height of the wallboard is raised by the movable rope 15 through the second directional wheel 5, and after the whole height of the wallboard is raised to the designated height, the second stage, the first connecting rod 13 is moved downwards, so that the movable rope 15 is hooked downwards by the first connecting rod 13, the movable rope 15 passes through the second directional wheel 5, and drives the fixing hooks 6 to move upwards, so that one side of the wallboard is pulled upwards, and the whole wallboard is vertically placed.
Example two
As shown in fig. 1-4, casters 17 are fixedly connected to the four corners of the bottom end of the connecting frame 1, and gears 14 are fixedly connected to the two ends of the first connecting rod 13. The outer side of the gear 14 is meshed with a rack 9, and the outer side wall of the rack 9 is fixedly connected with a guide rail 8. The first connecting rod 13 is in sliding connection with the guide rail 8, and the outer sides of the gears 14 are fixedly connected with round baffles 10. The outer side wall of the connecting frame 1 is coated with an antirust agent, and the inner side wall of the guide rail 8 is coated with a lubricant. A second connecting rod 16 is fixedly connected between the two rope collecting rollers 11, the outer side wall of the height-adjusting rope 7 is in sliding connection with the first directional wheel 4, and the outer side wall of the movable rope 15 is in sliding connection with the second directional wheel 5.
The effect that its whole embodiment reached is, through fixed connection guide rail 8 between first perpendicular arm 2 and second perpendicular arm 3, make head rod 13 remove under the spacing of guide rail 8, simultaneously, set up rack 9 in the inside of guide rail 8, fixed gear 14 at the both ends of head rod 13, the meshing has realized the location effect of gear 14 between gear 14 and rack 9, when needing to reciprocate head rod 13, rotate head rod 13, thereby make head rod 13 rotate down along rack 9 and remove, thereby make the dead hook 6 of here upwards pull up, when being convenient for promote the wallboard, adjust vertical wallboard angle.
The application method and the working principle of the device are as follows: when in use, the building wall is placed above the connecting frame 1, and the four fixing hooks 6 are aligned with the four corners of the wallboard, and the fixing hooks 6 are fixed with the wallboard;
then, the rope collecting roller 11 at the corner of the first vertical arm 2 and the connecting frame 1 is rotated, the rope collecting roller 11 rotates, the height-adjusting rope 7 and the movable rope 15 are contained in the outer side wall of the rope collecting roller 11, the height of the fixed hook 6 is lifted by the height-adjusting rope 7 through the first directional wheel 4, the height of the fixed hook 6 is lifted by the movable rope 15 through the second directional wheel 5, and therefore the whole height of the wallboard is lifted;
finally, the first connecting rod 13 is rotated, so that the first connecting rod 13 moves downwards along the rack 9, the first connecting rod 13 drives the movable rope 15 to hook downwards, the movable rope 15 passes through the second directional wheel 5 and drives the fixed hook 6 to move upwards, and one side of the wallboard is pulled upwards, so that the wallboard is vertically placed.
The present utility model is not limited to the above-mentioned embodiments, and any equivalent embodiments which can be changed or modified by the technical content disclosed above can be applied to other fields, but any simple modification, equivalent changes and modification made to the above-mentioned embodiments according to the technical substance of the present utility model without departing from the technical content of the present utility model still belong to the protection scope of the technical solution of the present utility model.

Claims (6)

1. The utility model provides an assembled building materials hoisting device, includes link (1), its characterized in that: the utility model discloses a rope winding device for the automobile, including link (1), connecting frame, rope winding roller, connecting rod (11), connecting rod (15), connecting rod (13) are provided with on the top of rope winding roller (11), outer lateral wall fixedly connected with height-adjusting rope (7) of rope winding roller (11), height-adjusting rope (7) with fixed hook (6) are all provided with in the outside of second perpendicular arm (3), the bottom fixedly connected with first directional wheel (4) of bottom fixedly connected with of first perpendicular arm (2), the bottom fixedly connected with second directional wheel (5) of second perpendicular arm (3) in the outside wall of connecting frame (1).
2. The fabricated building material lifting device of claim 1, wherein: caster (17) are fixedly connected to four corner positions at the bottom end of the connecting frame (1), and gears (14) are fixedly connected to two ends of the first connecting rod (13).
3. The fabricated building material lifting device of claim 2, wherein: the outer side of the gear (14) is meshed with a rack (9), and the outer side wall of the rack (9) is fixedly connected with a guide rail (8).
4. A modular building material lifting device as claimed in claim 3, wherein: the first connecting rod (13) is in sliding connection with the guide rail (8), and the outer sides of the gears (14) are fixedly connected with round baffles (10).
5. A modular building material lifting device as claimed in claim 3, wherein: the outer side wall of the connecting frame (1) is coated with an antirust agent, and the inner side wall of the guide rail (8) is coated with a lubricant.
6. The fabricated building material lifting device of claim 1, wherein: a second connecting rod (16) is fixedly connected between the two rope collecting rollers (11), the outer side wall of the height-adjusting rope (7) is in sliding connection with the first directional wheel (4), and the outer side wall of the movable rope (15) is in sliding connection with the second directional wheel (5).
CN202321839350.8U 2023-07-13 2023-07-13 Assembled building materials hoisting device Active CN220596815U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321839350.8U CN220596815U (en) 2023-07-13 2023-07-13 Assembled building materials hoisting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321839350.8U CN220596815U (en) 2023-07-13 2023-07-13 Assembled building materials hoisting device

Publications (1)

Publication Number Publication Date
CN220596815U true CN220596815U (en) 2024-03-15

Family

ID=90178213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321839350.8U Active CN220596815U (en) 2023-07-13 2023-07-13 Assembled building materials hoisting device

Country Status (1)

Country Link
CN (1) CN220596815U (en)

Similar Documents

Publication Publication Date Title
CN110821149B (en) Mold taking device and mold taking method applied to house slip form forming device
CN214062281U (en) Building platform for outdoor building and indoor decoration
CN108797992A (en) A kind of climbing frame for assembled architecture
CN115402909A (en) Super high-rise inclined double-layer special-shaped curtain wall construction device
CN113089894B (en) Method for mounting prefabricated wall panel of prefabricated building
CN220596815U (en) Assembled building materials hoisting device
WO2023184882A1 (en) Material lifting device
CN216945812U (en) Prevent door type hoisting equipment that scatters and bear device with hoist and mount
JPH0673892A (en) Fitting method for outer facing plate material of building and device therefor
CN111502294B (en) Automatic installation method of movable precast concrete wallboard
JPH0319567Y2 (en)
CN110409847B (en) Curtain wall assembling equipment for constructional engineering and working method thereof
JPH06263369A (en) Elevator
CN219158452U (en) Curtain wall installation auxiliary device
CN217711798U (en) Handling frame suitable for ALC slat outer wall installation
CN219156359U (en) Self-climbing construction crane for elevator steel structure well
CN220245491U (en) Functional foot rest
CN211998556U (en) Rotary lifting machine tool on balcony beam
CN220412648U (en) Lifting appliance for building construction
CN213231298U (en) Hoisting accessory is used in building engineering construction
CN214935438U (en) Assembled building wallboard hoist device
CN212503686U (en) Construction equipment of prefabricated building based on BIM
CN219507479U (en) Building engineering material lifting machine
CN216613816U (en) Universal curtain wall and quick hoisting device for components thereof
CN220705095U (en) Suspension for construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant