CN218924173U - Movable building rubbish recycling device - Google Patents
Movable building rubbish recycling device Download PDFInfo
- Publication number
- CN218924173U CN218924173U CN202222055632.0U CN202222055632U CN218924173U CN 218924173 U CN218924173 U CN 218924173U CN 202222055632 U CN202222055632 U CN 202222055632U CN 218924173 U CN218924173 U CN 218924173U
- Authority
- CN
- China
- Prior art keywords
- fixedly connected
- crushing box
- fixed plate
- electromagnet
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02W—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
- Y02W30/00—Technologies for solid waste management
- Y02W30/50—Reuse, recycling or recovery technologies
- Y02W30/58—Construction or demolition [C&D] waste
Landscapes
- Processing Of Solid Wastes (AREA)
Abstract
The utility model discloses a movable building rubbish recycling device, which comprises a crushing box body and a control panel, wherein the top of the crushing box body is fixedly connected with a hopper inlet, the top of the crushing box body is positioned below the hopper inlet and is rotationally connected with a double-roller crusher, and the inner side of the crushing box body is positioned below the double-roller crusher and is fixedly connected with a second fixing plate, so that the movable building rubbish recycling device has the beneficial effects that: according to the utility model, a large amount of dust can be caused by crushing the roller crusher, the surrounding and working personnel are influenced, the water pump can be started, the water in the pipeline and the spray head extraction water tank is utilized to carry out dust falling operation on the upper part of the roller crusher, the spreading of the dust is effectively reduced, the garbage falling down after crushing finally falls onto the conveying belt due to the inclination of the second fixing plate, and the metal substances mixed in the garbage are maximally absorbed through the layer-by-layer screening of the first electromagnet, the second electromagnet and the third electromagnet, so that the roller crusher is simple and practical.
Description
Technical Field
The utility model relates to the technical field of building waste recovery, in particular to a movable building waste recovery device.
Background
The construction waste refers to the general terms of dregs, waste concrete, waste masonry, waste plastic, waste metal, waste bamboo and other waste generated by people in the production activities of construction industry such as removing, building, finishing, repairing and the like, and can be classified according to the generation sources, the construction waste can be classified into engineering dregs, finishing garbage, removing garbage, engineering slurry and the like, the materials are not helpful to the construction, the site selection of most urban construction waste places has random to a great extent, and a plurality of potential safety hazards are left,
substances produced during construction need to be treated correspondingly, so that the ideal effect can be achieved
The engineering project construction is an integral process, and the consideration of links is more important.
However, the conventional construction waste recycling device cannot effectively separate metal objects in construction waste to obtain resource recycling, cannot separate soil and other types of waste to obtain more resource recycling effects, saves a large amount of resources and manually sorted funds, generates a large amount of dust during recycling, cannot reduce dust, collects the construction waste to a place where the construction waste is processed and cannot be conveniently moved and recycled, and therefore the movable construction waste recycling device is needed.
Disclosure of Invention
The present utility model is directed to a mobile construction waste recycling device, which solves the problems set forth in the background art.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a portable building rubbish recovery unit, includes crushing box and control panel, the top fixedly connected with funnel import of crushing box, the top of crushing box just is located funnel import below and rotates and be connected with the pair roller breaker, the inboard of crushing box just is located the below fixedly connected with second fixed plate of pair roller breaker, the inside of second fixed plate is equipped with first cylinder, the output fixedly connected with first electro-magnet of first cylinder, the inside of crushing box just is located the below fixedly connected with third fixed plate of second fixed plate, the third
The top of three fixed plates is equipped with first conveyer belt, the bottom of third fixed plate is equipped with the third cylinder, the output fixedly connected with third electro-magnet of third cylinder, one side of smashing the box inner wall is equipped with the second cylinder, the output fixedly connected with second electro-magnet of second cylinder, the inner wall fixedly connected with first fixed plate of smashing the box, the top of first fixed plate is equipped with the second conveyer belt, the bottom of smashing the box is equipped with the third conveyer belt, the inside of smashing the box and the one end that is located the third conveyer belt are equipped with the second export.
As a novel preferred scheme of this experiment, the bottom fixedly connected with swash plate of smashing the box, smash the inboard of box and be located two diaphragms of top fixedly connected with of swash plate, two the top fixedly connected with two springs of diaphragm, two the top fixedly connected with plate of spring, be equipped with a plurality of hole on the plate piece, the central point of the bottom of plate is equipped with vibrating motor, smash the inside of box and be located one side of swash plate and be equipped with first export.
As a novel preferred scheme of this experiment, one side fixedly connected with water tank of smashing the box, the top of water tank is equipped with the water filling port, the inside of water tank is equipped with the water pump, the delivery port of water pump is connected with the pipeline, the inboard of smashing the box just is located one side of twin roll breaker and is equipped with the shower nozzle, pipeline and shower nozzle fixed connection.
As a novel preferred scheme of this experiment, the surface of first conveyer belt is equipped with a plurality of fixed block strip.
As a novel preferred scheme of this experiment, control panel and first electro-magnet, third electro-magnet and second electro-magnet electric connection.
As a novel preferred scheme of this experiment, first conveyer belt is whole all to be 35 degrees contained angles with the horizontal direction, the second fixed plate is whole all to be 35 degrees contained angles with the horizontal direction.
As a novel preferred scheme of this experiment, smash the bottom fixedly connected with universal wheel of box.
Compared with the prior art, the utility model has the beneficial effects that: the utility model firstly causes a large amount of dust by crushing the roller crusher, has influence on the periphery and staff, and can start water
The pump utilizes the water in pipeline and the shower nozzle extraction water tank to carry out the dust fall work to the top of pair roller breaker, the effectual spread of dust that reduces, the rubbish that drops down after smashing is finally dropped to the conveyer belt because of the inclination of second fixed plate, through first electro-magnet, the screening layer by layer of second electro-magnet and third electro-magnet, the metal substance that is mingled with in rubbish is absorbed to the maximize, and be equipped with the fixed block strip on the first conveyer belt and prevent to go up because of the transportation of inclination rubbish, and vibrating motor carries out the output vibration against the plate, the plate is because of the existence of the spring of bottom, vibration by a wide margin, the existence such as dregs in the screening rubbish, after smashing, can utilize control panel to control first electro-magnet, second electro-magnet and third electro-magnet lose magnetic force, make metal substance rubbish drop on the conveyer belt again and carry the recovery, as far as possible separate the dress to get, a large amount of manpower has been reduced, and the bottom is equipped with the universal wheel and can remove everywhere at any time and retrieve, it is simple and practical.
Drawings
FIG. 1 is a schematic view of the internal structure of the present utility model;
FIG. 2 is a schematic perspective view of a first conveyor belt according to the present utility model;
FIG. 3 is a schematic view of the three-dimensional structure of the plate of the present utility model;
fig. 4 is an enlarged view of fig. 1 at a in accordance with the present utility model.
In the figure: 1. crushing a box body; 2. a control panel; 3. a first cylinder; 4. a first electromagnet; 5. a first conveyor belt; 6. a third cylinder; 7. a third electromagnet; 8. a plate; 9. a spring; 10. a cross plate;
11. a vibration motor; 12. a first outlet; 13. a sloping plate; 14. a third conveyor belt; 15. a second outlet;
16. a first fixing plate; 17. a second conveyor belt; 18. a second electromagnet; 19. a second cylinder; 20. a hole; 21. a second fixing plate; 22. a water pump; 23. a pipe; 24. a water filling port; 25. a water tank; 26. a spray head; 27. a twin roll crusher; 28. a funnel inlet; 29. a fixed block strip; 30. a third fixing plate;
31. and a universal wheel.
Detailed Description
The technical solutions of the embodiments of the present utility model will be clearly and completely described below with reference to the drawings in the embodiments of the present utility model, and it is apparent that the described embodiments are only a part of the present utility model
Embodiments are intended, and not all embodiments are intended. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 4, the present utility model provides a technical solution: the movable construction waste recycling device comprises a crushing box body 1 and a control panel 2, wherein the top of the crushing box body 1 is fixedly connected with a hopper inlet 28, waste to be crushed can be poured into the crushing box body, a pair roller crusher 27 is rotatably connected to the top of the crushing box body 1 and positioned below the hopper inlet 28, the poured waste is crushed, a second fixed plate 21 is fixedly connected to the inner side of the crushing box body 1 and positioned below the pair roller crusher 27, a first air cylinder 3 is arranged in the second fixed plate 21, a first electromagnet 4 at one end can be started to move for working, the output end of the first air cylinder 3 is fixedly connected with a first electromagnet 4, metal substances in the waste can be sucked, the inside of the crushing box body 1 is fixedly connected with a third fixed plate 30 positioned below the second fixed plate 21, the bearing effect of the first conveyor belt 5 is achieved, the crushed waste is transported and enabled to fall onto a second conveyor belt 17 through the first metal suction, the third air cylinder 6 is arranged at the bottom end of the third fixed plate 3, the second electromagnet 6 is connected with the second air cylinder 19 through the first air cylinder 6, the third electromagnet 19 is started to move to the second air cylinder 19 at one end of the second air cylinder 6, the third electromagnet 19 is connected with the third electromagnet 19 at one end of the third air cylinder 6 is started to move through the third air cylinder 19 at the third air cylinder 6, the garbage in the falling scattered state is recovered once, the first fixed plate 16 is fixedly connected with the inner wall of the crushing box body 1, the bearing effect on the second conveying belt 17 is achieved, the second conveying belt 17 is arranged at the top of the first fixed plate 16, the garbage which is recovered through three times of metal is transported and finally falls onto the plate 8, the third conveying belt 14 is arranged at the bottom end of the crushing box body 1, finally, the rest garbage is screened and transported to the second outlet 15 through the third conveying belt 14, the second outlet 15 is arranged at the inner part of the crushing box body 1 and at one end of the third conveying belt 14, and finally, a part of garbage is collected and treated together through the second outlet 15.
Further, the bottom end of the crushing box body 1 is fixedly connected with an inclined plate 13, so that fallen garbage can be automatically discharged
Going to first export 12 one side motion and retrieving, smash the inboard of box 1 and being located two diaphragms 10 of top fixedly connected with of swash plate 13, bear and fix spring 9, the top fixedly connected with of two diaphragms 10 two springs 9, the top fixedly connected with plate 8 of two springs 9, because there is spring 9's existence in plate 8 bottom, make plate 8 increase the range after vibrating more, be equipped with a plurality of hole 20 on the plate 8, only can pass through rubbish such as dregs, through the screening fall down thereby through the vibration, the central point of the bottom of plate 8 is equipped with vibrating motor 11, start vibrating motor 11 can make plate 8 produce the vibration and carry out screening rubbish, smash the inside of box 1 and be located one side of swash plate 13 and be equipped with first export 12, finally a portion dregs class rubbish is handled together by the cell-phone from this.
Further, one side fixedly connected with water tank 25 of smashing box 1, the top of water tank 25 is equipped with water filling port 24, the inside of water tank 25 is equipped with water pump 22, can carry out the extraction to the water in the water tank 25 and use, the delivery port of water pump 22 is connected with pipeline 23, the inboard of smashing box 1 and lie in one side of pair roller breaker 27 and be equipped with shower nozzle 26, pipeline 23 and shower nozzle 26 fixed connection, the dust that produces in the crushing process of pair roller breaker 27 is handled to the water of water pump 22 through pipeline 23 and shower nozzle 26.
Further, the outer surface of the first conveyor belt 5 is provided with a plurality of fixing block strips 29, so that garbage cannot be transported due to the inclination of the first conveyor belt 5.
Further, the control panel 2 is electrically connected with the first electromagnet 4, the third electromagnet 7 and the second electromagnet 18, and the magnetic force on the first electromagnet 4, the third electromagnet 7 and the second electromagnet 18 can be controlled by using the control panel 2.
Further, the whole first conveyor belt 5 is inclined at 35 degrees, and the falling process is increased by adjusting the height
Additionally, the second electromagnet 18 has higher efficiency, the whole second fixing plate 21 is inclined at 35 degrees, and crushed garbage can automatically fall onto the first conveying belt 5 due to the inclination of the second fixing plate 21.
Further, the universal wheel 31 is fixedly connected to the bottom of the crushing box body 1, and the crushing box body 1 can not be moved at any time to work.
When the utility model is used, firstly, the garbage to be recovered is poured into the hopper from the hopper inlet 28, the double-roller crusher 27 is started to crush the garbage entering the crushing box body 1, and the water pump 22 is started to crush the garbage
The water in the water tank 25 is pumped, dust falling is carried out above the crushing by the pipeline 23 and the spray nozzle 26, the crushed garbage falls onto the first conveying belt 5 due to the slope of the second fixing plate 21, the crushed garbage reaches the lower part of the first electromagnet 4 through the transportation of the first conveying belt 5, the first cylinder 3 is started to lower the first electromagnet 4 to absorb and recycle metal substances in the garbage, one end of the garbage reaching the first conveying belt 5 drops downwards, the garbage is in a dispersed state in the dropping process, the second cylinder 19 is started to drive the second electromagnet 18 to absorb and recycle the garbage secondarily, and finally the garbage falling onto the second conveying belt 17 reaches the lower part of the third electromagnet 7 through the transportation, the third cylinder 6 is started to reduce the third electromagnet 7 to absorb the garbage which is turned over once in the falling process, then the garbage falls onto the plate 8, the vibrating motor 11 is started to output vibration to the plate 8, the vibration is greatly generated by the existence of the spring 9, the existence of the hole 20 on the plate 8, the existence of the muck and the like falls onto the sloping plate 13 in the vibration, the garbage which is not sieved in the vibration falls onto the third conveying belt 14 to be transported away due to the slope of the plate 8, finally the first electromagnet 4, the second electromagnet 18 and the third electromagnet 7 are controlled by the control panel 2 to lose magnetic force after the crushing is finished, and the metal substances fall onto the conveying belt again to be transported and recovered, so that the operation is simple.
In the description of the present utility model, it should be understood that the terms "coaxial," "bottom," "one end," "top," "middle," "other end," "upper," "one side," "top," "inner," "front," "center," "two ends," etc. indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, are merely for convenience in describing the present utility model and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and therefore should not be construed as limiting the present utility model.
Furthermore, the terms "first," "second," "third," "fourth," and the like are used for descriptive purposes only and are not to be construed as indicating or implying a relative importance or implying a number of such features in order to be construed as indicating the indicated technical feature, whereby features defining "first," "second," "third," "fourth" may explicitly or implicitly include at least one such feature.
In the present utility model, unless explicitly specified and limited otherwise, the terms "mounted," "configured," "connected," "secured," "screwed," and the like are to be construed broadly and may be, for example, a secured connection
The connection can be detachable connection or integrated; can be mechanically or electrically connected; either directly or indirectly through intermediaries, or by communication between two elements or interaction between two elements, unless explicitly defined otherwise, the meaning of the terms in this disclosure will be understood by those of ordinary skill in the art.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations may be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.
Claims (7)
1. The utility model provides a movable construction waste recovery device, its characterized in that includes crushing box (1) and control panel (2), the top fixedly connected with funnel import (28) of crushing box (1), the top of crushing box (1) just is located funnel import (28) below and rotates and be connected with pair roller breaker (27), the inboard of crushing box (1) just is located the below fixedly connected with second fixed plate (21) of pair roller breaker (27), the inside of second fixed plate (21) is equipped with first cylinder (3), the output fixedly connected with first electro-magnet (4) of first cylinder (3), the inside of crushing box (1) just is located the below fixedly connected with third fixed plate (30) of second fixed plate (21), the top of third fixed plate (30) is equipped with first conveyer belt (5), the bottom of third fixed plate (30) is equipped with third cylinder (6), the output fixedly connected with third electro-magnet (7) of third cylinder (6), the second cylinder (19) are connected with second fixed plate (19) of second fixed plate (19), the top of first fixed plate (16) is equipped with second conveyer belt (17), the bottom of smashing box (1) is equipped with third conveyer belt (14), the inside of smashing box (1) just is located the one end of third conveyer belt (14) and is equipped with second export (15).
2. The mobile construction waste recycling apparatus according to claim 1, wherein: the utility model discloses a crushing box, including crushing box (1), baffle (13) are smashed to the bottom fixedly connected with of crushing box (1), the inboard of smashing box (1) just is located two diaphragm (10) of top fixedly connected with of baffle (13), two the top fixedly connected with of diaphragm (10) two springs (9), two the top fixedly connected with plate (8) of spring (9), be equipped with a plurality of hole (20) on plate (8), the central point of the bottom of plate (8) is put and is equipped with vibrating motor (11), the inside of smashing box (1) just is located one side of baffle (13) and is equipped with first export (12).
3. The mobile construction waste recycling apparatus according to claim 1, wherein: one side fixedly connected with water tank (25) of smashing box (1), the top of water tank (25) is equipped with water filling port (24), the inside of water tank (25) is equipped with water pump (22), the water outlet of water pump (22) is connected with pipeline (23), the inboard of smashing box (1) just is located one side of pair roller breaker (27) and is equipped with shower nozzle (26), pipeline (23) and shower nozzle (26) fixed connection.
4. The mobile construction waste recycling apparatus according to claim 1, wherein: the outer surface of the first conveying belt (5) is provided with a plurality of fixed block strips (29).
5. The mobile construction waste recycling apparatus according to claim 1, wherein: the control panel (2) is electrically connected with the first electromagnet (4), the third electromagnet (7) and the second electromagnet (18).
6. The mobile construction waste recycling apparatus according to claim 1, wherein: the whole first conveyer belt (5) all is 35 degrees contained angles with the horizontal direction, the whole second fixed plate (21) all is 35 degrees contained angles with the horizontal direction.
7. The mobile construction waste recycling apparatus according to claim 1, wherein: the bottom of the crushing box body (1) is fixedly connected with a universal wheel (31).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222055632.0U CN218924173U (en) | 2022-08-05 | 2022-08-05 | Movable building rubbish recycling device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222055632.0U CN218924173U (en) | 2022-08-05 | 2022-08-05 | Movable building rubbish recycling device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218924173U true CN218924173U (en) | 2023-04-28 |
Family
ID=86087282
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222055632.0U Active CN218924173U (en) | 2022-08-05 | 2022-08-05 | Movable building rubbish recycling device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218924173U (en) |
-
2022
- 2022-08-05 CN CN202222055632.0U patent/CN218924173U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206444710U (en) | Environment-friendly type building decoration refuse disposal installation | |
CN208133269U (en) | A kind of civil engineering work waste material recycling device | |
CN109926145A (en) | A kind of municipal administration construction waste crushing device with dedusting function | |
CN108993736B (en) | New-type breaker for building | |
CN108940419A (en) | A kind of construction site building waste processing recycling and reusing device | |
CN106733098A (en) | A kind of environment-friendly type building decoration refuse disposal installation | |
CN211216845U (en) | Waste recovery device for building block processing | |
CN215029915U (en) | Construction discarded object broken handle equipment of environmental protection | |
CN207552897U (en) | A kind of Portable broken-stone material distributing machine for road pavement defect treatment | |
CN209866276U (en) | Mining engineering mine opens and adopts broken screening plant | |
CN210079629U (en) | Stone crusher for building site | |
CN208711786U (en) | Building site is with construction waste treatment recovery device of recycling | |
CN208661251U (en) | A kind of construction site garbage pulverator | |
CN218924173U (en) | Movable building rubbish recycling device | |
CN112570077A (en) | Waste material treatment device for building construction and use method thereof | |
CN204747057U (en) | Dustproof construction waste processing equipment | |
CN208661242U (en) | A kind of inorganic chemistry test particle reagents grinding device | |
CN217663733U (en) | Waste recovery device is used in road engineering construction | |
CN214975594U (en) | Concrete waste recycling device | |
CN212120139U (en) | Automatic processing apparatus of building rubbish | |
CN211329537U (en) | Civil engineering construction waste treatment device | |
CN209531689U (en) | Building concrete refuse disposal installation | |
CN207204316U (en) | A kind of sandstone production line | |
CN211612856U (en) | Stone crusher | |
CN218637471U (en) | Environment-friendly dust-free stone crushing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |