CN218522232U - Pipeline bracket root closing-up die device - Google Patents

Pipeline bracket root closing-up die device Download PDF

Info

Publication number
CN218522232U
CN218522232U CN202222827484.XU CN202222827484U CN218522232U CN 218522232 U CN218522232 U CN 218522232U CN 202222827484 U CN202222827484 U CN 202222827484U CN 218522232 U CN218522232 U CN 218522232U
Authority
CN
China
Prior art keywords
scute
main
pipeline
homonymy
die device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222827484.XU
Other languages
Chinese (zh)
Inventor
张齐东
齐新权
张平
赵忠峰
刘军宏
王少清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB Fifth Engineering Co Ltd
Original Assignee
CCCC SHB Fifth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB Fifth Engineering Co Ltd filed Critical CCCC SHB Fifth Engineering Co Ltd
Priority to CN202222827484.XU priority Critical patent/CN218522232U/en
Application granted granted Critical
Publication of CN218522232U publication Critical patent/CN218522232U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The application relates to the technical field of building pipeline construction, and discloses pipeline bracket root binding off die set, including two main scute and pipeline, two side scute, two have all been welded at the both ends of main scute the side scute forms the flute profile setting with homonymy main scute plate, and homonymy two the side scute is connected with the clamping mechanism jointly, two main scute and four side scute all lie in the outside cover of pipeline and establish, two the equal common fixedly connected with arc steel sheet of junction inner wall of two side scutes of main scute and homonymy. The inconvenient phenomenon of operation that traditional operation personnel's manual daubing binding off was protected the mound and is brought can be solved to this application to and adopt the simple and easy preparation mould of bamboo offset plate to bring protect mound fracture, not aesthetic problem, can realize quick installation, demolish fast, processing is simple, and is with low costs, can realize having enough to meet the need reuse, can be convenient for simultaneously with the even cover of mould after the block establish with the pipeline outside.

Description

Pipeline bracket root closing-up die device
Technical Field
The application relates to the technical field of building pipeline construction, in particular to a pipeline bracket root closing-up die device.
Background
After the initial installation of the building pipeline is completed, the pipeline root needs to be subjected to closing-up pier protection treatment by adopting fine aggregate concrete, so that the purposes of preventing water, rust, collision and the like for the pipeline root are achieved, and the connection strength between the pipeline root and the ground is improved.
In the process of implementing the application, the inventor finds that at least the following problems exist in the technology, and the traditional mode for treating the protection pier at the root of the pipeline is generally that after an operator directly smears the closing-in protection pier through concrete prepared on site manually or adopts building materials such as bamboo plywood and the like to simply make a mold, the closing-in protection pier is made through the simple mold, but on one hand, the manual direct preparation has high requirements on the making technology of workers, otherwise, the made closing-in protection pier is not only not attractive, but also the phenomenon of uneven closing-in protection pier can occur, the strength of the simple mold made of the bamboo plywood is very low, and when concrete is poured, the concrete closing-in protection pier is easy to expand outwards, so that the prepared protection pier is cracked, and therefore, the device for the closing-in mold at the root of the pipeline support is provided.
SUMMERY OF THE UTILITY MODEL
The purpose of this application is in order to solve among the prior art generally by the direct concrete of operating personnel through field preparation and hand daub the binding off protect the mound or adopt building material such as bamboo offset plate simple and easy preparation mould after, back is through simple and easy mould carrying out binding off protect mound preparation, but on the one hand manual direct preparation is higher to workman's preparation technical requirement, otherwise the binding off of producing protect the mound not only beautifully, still can appear binding off and protect the uneven phenomenon of mound, and the simple and easy mould intensity of bamboo offset plate preparation is very low, when carrying out concrete placement, concrete binding off protects the mound and easily expands outward, lead to the problem that the mound that protects after the preparation easily ftractures, and a pipeline support root binding off mould device that proposes.
In order to achieve the purpose, the following technical scheme is adopted in the application:
the utility model provides a pipeline support root binding off die set, includes two main scute and pipeline, two the both ends of main scute all weld have the side scute, two the side scute forms flute profile with homonymy main scute shape and sets up, and the homonymy is two the side scute is connected with the clamping mechanism jointly, two the outside cover that main scute and four side scutes all lie in the pipeline is established, two the equal common fixedly connected with arc steel sheet of junction inner wall of main scute and two side scutes of homonymy.
Preferably, two connecting blocks are fixedly arranged at the two ends of the main angle plate and the end faces of the two side angle plates at the same side, the side walls of the two connecting blocks at the same side are rotatably connected with rotating blocks through pin rods, and positioning rods are fixedly arranged at one ends, close to the pipeline, of the rotating blocks.
Preferably, two clamping mechanism all includes the fixed plate that sets up in two side scute knecks one side of homonymy, the equal fixedly connected with joint pole in tip both sides of fixed plate, two the joint groove has all been seted up to one side that the pipeline was kept away from to the one end in opposite directions of lateral wall of side scute.
Preferably, two main standing grooves have all been seted up to the terminal surface of main scute, and main balancing weight has all been placed to the inside of two main standing grooves, each vice standing groove has all been seted up to the terminal surface of side scute, and vice balancing weight has all been placed to the inside of each vice standing groove, two the lower extreme of main scute and two side scutes of homonymy all fixes jointly and is equipped with the sealed filler strip of U-shaped.
Preferably, two magnetic blocks are embedded into two ends of the side wall of one opposite side of the two fixing plates, and each magnetic block is magnetically connected with the side corner plate at the same side.
Preferably, two connecting ropes are fixedly arranged between the two main balancing weights and the two auxiliary balancing weights on the same side.
Compared with the prior art, the application provides a pipe support root binding off die set possesses following beneficial effect:
1. this pipe bracket root binding off die set, through two main scute that are equipped with, four side scute and latch mechanism's cooperation, can enclose the peripheral fender that closes two recess shapes, when carrying out the preparation of pipeline root binding off fender mound, can enclose to close in the pipeline outside and form binding off fender mound mould, holistic structural strength is high, the shaping of pipeline root binding off fender mound is very simple, the inconvenient phenomenon of operation that traditional operation personnel manual daub binding off fender mound brought has been solved, and adopt the easy preparation mould of bamboo plywood to bring to protect the mound fracture, unattractive problem, can realize quick installation, demolish fast, the processing is simple, low cost, can realize turnover reuse.
2. This pipe bracket root binding off die set through the cooperation of the connecting block that is equipped with, rotatory piece and locating lever, can make the mould central point after the block keep coaxial with the pipeline when carrying out die holding, does benefit to the binding off after the shaping and protects the mound at pipeline outside evenly distributed, does benefit to the atress evenly.
The device is not involved the part all the same with prior art or can adopt prior art to realize, and the inconvenient phenomenon of operation that traditional operation personnel manual daub binding off and protect the mound and bring can be solved to this application to and adopt the simple and easy preparation mould of bamboo plywood to bring to protect the mound fracture, not aesthetic problem, can realize quick installation, demolish fast, processing is simple, and is with low costs, can realize having enough to meet the need reuse, simultaneously can be convenient for with the even cover of mould after the block establish with the pipeline outside.
Drawings
Fig. 1 is a schematic structural diagram of a pipe support root closing-up die device according to the present application;
FIG. 2 is a schematic view of the connection between the U-shaped gasket strip and the side gusset of FIG. 1.
In the figure: 1. a main gusset; 2. a pipeline; 3. a side gusset; 4. an arc-shaped steel plate; 5. connecting blocks; 6. rotating the block; 7. positioning a rod; 8. a fixing plate; 9. a clamping and connecting rod; 10. a main counterweight block; 11. a secondary balancing weight; 12. a U-shaped sealing gasket strip; 13. a magnetic block; 14. and connecting ropes.
Detailed Description
The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only a part of the embodiments of the present application, and not all of the embodiments.
Referring to fig. 1-2, a pipeline support root binding off die set, including two main scute 1 and pipeline 2, the both ends of two main scute 1 all weld have side scute 3, two side scute 3 and homonymy main scute 1 form the recess shape setting, two side scutes 3 of homonymy are connected with latch mechanism jointly, two main scutes 1 and four side scutes 3 all are located the outside cover of pipeline 2 and establish, two main scutes 1 and the equal common fixedly connected with arc steel sheet 4 of junction inner wall of two side scutes 3 of homonymy, main scute 1 and side scute 3 all adopt steel to make.
The both ends of two main scute 1 and the terminal surface of two side scutes of homonymy 3 are all fixed and are equipped with connecting block 5, the lateral wall of two connecting blocks of homonymy 5 all rotates through the pin rod and is connected with rotatory piece 6, the one end that each rotatory piece 6 is close to pipeline 2 is all fixed and is equipped with locating lever 7, after the side scute 3 block with both sides is in the same place, turn up four locating levers 7 rotation, make it be the level form, and make locating lever 7 offset with the outer wall of pipeline 2, can make main scute 1 this moment, the die cavity central point that side scute 3 encloses the synthetic type keeps same axis setting with pipeline 2, do benefit to the even arrangement of mould.
Two latch mechanisms all include the fixed plate 8 that sets up in 3 knecks one side of two side gussets of homonymy, and the equal fixedly connected with joint pole 9 in tip both sides of fixed plate 8, and the joint groove has all been seted up to one side that pipeline 2 was kept away from to the one end in opposite directions to the lateral wall of two side gussets 3, inserts the joint pole 9 through fixed plate 8 and inserts the joint inslot that corresponds, can make two 3 mutual blocks of side gussets of homonymy, and follow-up split is convenient.
Main standing groove has all been seted up to the terminal surface of two main scutches 1, and main balancing weight 10 has all been placed to the inside of two main standing grooves, vice standing groove has all been seted up to the terminal surface of each side scutches 3, and vice balancing weight 11 has all been placed to the inside of each vice standing groove, the sealed filler strip 12 of U-shaped that all fixes being equipped with jointly of the lower extreme of two main scutches 1 and two side scutches 3 of homonymy, through main balancing weight 10 and vice balancing weight 11, can be convenient for carry out the counter weight to main scutches 1 and side scutches 3 and sticis, the sealed filler strip 12 of cooperation U-shaped can keep sufficient compactness between mould bottom side and the ground this moment, thereby can prevent that the water liquid in the garrulous stone concrete of pouring from overflowing from the mould bottom side.
The magnetic blocks 13 are embedded into two opposite side wall ends of the two fixing plates 8, each magnetic block 13 is magnetically connected with the corner plate 3 on the same side, and stability of the fixing plates 8 during clamping can be improved in an auxiliary mode through the magnetic blocks 13.
Two main balancing weight 10 and two vice balancing weight 11 of homonymy between all fixed two are connected rope 14 that are equipped with jointly, through connecting rope 14, can be convenient for connect stably between main balancing weight 10 and the vice balancing weight 11.
In this application, during the use, after the installation of pipeline 2 is accomplished, two recess shape structures that 2 formation of two main scute 1 and two side scutes of homonymy are established from the position cover of 2 both sides of pipeline, and insert joint pole 9 through fixed plate 8 and the joint inslot that corresponds, utilize fixed plate 8 and joint pole 9 can make the recess shape stable in structure joint of both sides fixed, this moment at main scute 1, pour rubble concrete between side scute 3 and arc steel sheet 4, wait for rubble concrete preliminary cooling shaping after, can take joint pole 9 out through fixed plate 8, can turn to next pipeline 2 department with the mould this moment and reuse, because main scute 1, joint strength between side scute 2 is higher, the difficult fracture of binding off fender pier after the shaping, simultaneously through arc steel sheet 4, can make four outer angle departments of binding off fender pier after the shaping be the arc setting, and is pleasing to the eye.
The above description is only for the preferred embodiments of the present application, but the scope of the present application is not limited thereto, and any person skilled in the art should be considered to be within the scope of the present application, and all equivalent substitutions and changes according to the technical solutions and the inventive concepts of the present application should be covered by the scope of the present application.

Claims (6)

1. The utility model provides a pipeline support root binding off die set, includes two main scute (1) and pipeline (2), its characterized in that, two side scute (3), two are all welded at the both ends of main scute (1) side scute (3) and homonymy main scute (1) formation recess shape setting, homonymy two side scute (3) are connected with clamping mechanism, two jointly main scute (1) and four side scute (3) all are located the outside cover of pipeline (2) and establish, two the equal common fixedly connected with arc steel sheet (4) of junction inner wall of two side scutes (3) of main scute (1) and homonymy.
2. The pipe support root closing-in die device according to claim 1, wherein two ends of two main angle plates (1) and end surfaces of two side angle plates (3) on the same side are both fixedly provided with connecting blocks (5), side walls of the two connecting blocks (5) on the same side are both rotatably connected with rotating blocks (6) through pin rods, and one end of each rotating block (6) close to the pipe (2) is fixedly provided with a positioning rod (7).
3. The pipe support root closing-in die device according to claim 1, wherein the two clamping mechanisms respectively comprise a fixing plate (8) arranged on one side of a joint of two side angle plates (3) on the same side, clamping rods (9) are fixedly connected to two sides of the end portion of the fixing plate (8), and clamping grooves are formed in one sides, away from the pipe (2), of the opposite ends of the side walls of the two side angle plates (3).
4. The pipe support root closing-up die device according to claim 1, wherein main placing grooves are formed in the end surfaces of the two main corner plates (1), main balancing weights (10) are placed inside the two main placing grooves, auxiliary placing grooves are formed in the end surfaces of the side corner plates (3), auxiliary balancing weights (11) are placed inside the auxiliary placing grooves, and U-shaped sealing gaskets (12) are fixedly arranged at the lower ends of the two main corner plates (1) and the two side corner plates (3) on the same side.
5. The pipe support root closing-up die device according to claim 3, wherein two ends of the side wall of one opposite side of the two fixing plates (8) are embedded with magnetic blocks (13), and each magnetic block (13) is magnetically connected with the side angle plate (3) on the same side.
6. The pipe support root closing-up die device according to claim 4, wherein two connecting ropes (14) are fixedly arranged between the two main balance weights (10) and the two auxiliary balance weights (11) on the same side.
CN202222827484.XU 2022-10-26 2022-10-26 Pipeline bracket root closing-up die device Active CN218522232U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222827484.XU CN218522232U (en) 2022-10-26 2022-10-26 Pipeline bracket root closing-up die device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222827484.XU CN218522232U (en) 2022-10-26 2022-10-26 Pipeline bracket root closing-up die device

Publications (1)

Publication Number Publication Date
CN218522232U true CN218522232U (en) 2023-02-24

Family

ID=85249870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222827484.XU Active CN218522232U (en) 2022-10-26 2022-10-26 Pipeline bracket root closing-up die device

Country Status (1)

Country Link
CN (1) CN218522232U (en)

Similar Documents

Publication Publication Date Title
CN209443766U (en) Pouring model for building
CN206971732U (en) A kind of doubly-linked beam forms pouring structure
CN109057339A (en) A kind of one-time-concreting construction method of the anti-bank in toilet
CN109914644A (en) A kind of assembled heat insulation masonry wall and preparation method thereof
CN215331463U (en) Roofing pipeline concrete protection mound forming die
CN218522232U (en) Pipeline bracket root closing-up die device
CN206844138U (en) A kind of bar construction of domatic isolated footing
CN105951683B (en) Gate pier bracket Joint Re-bar Construction
CN209397712U (en) The connection structure of antidetonation steel pipe in a kind of shear wall
CN207750651U (en) A kind of concrete pump pipe temporary blocking device
CN208702139U (en) A kind of construction template structure of toilet wall
CN211250567U (en) Pouring die for balcony
CN204899217U (en) Concrete is vertical to meet template bracket reinforcing apparatus that batch position pour
CN209619997U (en) A kind of steel pipe combination skeleton slip casting solution cavity interstitital texture with holes
CN206736950U (en) A kind of special-shaped anchor ear applied to glass steel formwork
CN207513167U (en) The template system of the convex template component of arcuate building, concave template component and its composition
CN207513153U (en) The beam column cast-in-place node dedicated aluminium alloy template of assembly concrete frame structure
CN208163928U (en) A kind of producing device of stiffened column
CN207003720U (en) A kind of assembled integral concrete shear force wall attachment structure
CN207331771U (en) A kind of energy-efficient plugging structure of poured band of outer wall of basement
CN206376545U (en) A kind of dual bracing means of external angle formwork
CN206655482U (en) A kind of servicing unit for outer wall template installation
CN210421612U (en) Integral assembly type heat-insulation and decoration integrated light wall board
CN217106117U (en) Opening-closable steel formwork for construction of main structure of super high-rise building
CN208803484U (en) A kind of piping lane of fixed water-stop glue band pours mold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant