CN206844138U - A kind of bar construction of domatic isolated footing - Google Patents
A kind of bar construction of domatic isolated footing Download PDFInfo
- Publication number
- CN206844138U CN206844138U CN201720712581.0U CN201720712581U CN206844138U CN 206844138 U CN206844138 U CN 206844138U CN 201720712581 U CN201720712581 U CN 201720712581U CN 206844138 U CN206844138 U CN 206844138U
- Authority
- CN
- China
- Prior art keywords
- domatic
- isolated footing
- bar
- stirrup
- vertical bars
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Foundations (AREA)
Abstract
The utility model discloses a kind of bar construction of domatic isolated footing, including the blinding layer positioned at bottom, the basic net sheet being laid on blinding layer, and it is vertically provided at the foundation columns joint bar in the middle part of the basic net sheet, it is characterized in that, also include being vertically provided at the vertical bars at the corner of domatic isolated footing to be poured, and be centered around the rectangular positioning stirrup set on the outside of the foundation columns joint bar, diagonal bar is connected between the corner and the top of the corresponding vertical bars of the positioning stirrup;The vertical distance of top, positioning stirrup and the diagonal bar of the vertical bars to the forming surface of domatic isolated footing to be poured is consistent, and is all higher than minimal protection thickness degree.The utility model has the requirement that can be reduced to worker's technical merit, is advantageous to improve the quality and uniformity of concreting;Ensure domatic isolated footing molding effect, improve domatic isolated footing pouring molding speed, reduce the advantages that domatic isolated footing pours labor intensity.
Description
Technical field
Technical field of building construction is the utility model is related to, in particular to a kind of bar construction of domatic isolated footing.
Background technology
In the design of concrete isolated footing, to reduce cost, compared to the square-section isolated footing of routine, shelving
Section isolated footing can more save concrete, and can reduce foundation forms on the premise of basic stress requirement is met
Dosage, so using than wide.But domatic isolated footing difficulty of construction is larger, and construction Difficulties are concreting and shaping
Quality is difficult to control.At present, in general construction way is that heap slope pours, and the method poured using common heap slope, although operation
Simply, but concrete formation poor quality controls, and basic sectional dimension is not easy to ensure, the particularly control of corner angle line position, more
It is that difficulty is very big.The casting method is excessively horizontal by the operation of concrete worker, and single foundation construction quality is uneven.
Utility model content
For above-mentioned the deficiencies in the prior art, technical problem to be solved in the utility model is:How a kind of knot is provided
Structure is simple, and installation operation is convenient, advantageously reduces the difficulty of construction of worker, ensures the reinforcing bar of the domatic isolated footing of construction quality
Structure, it is advantageously ensured that domatic basis shaping physical dimension and molding effect, meet the force request of basic engineering, and build
The requirement of thing function safe to use.
In order to solve the above-mentioned technical problem, the utility model employs following technical scheme:
A kind of bar construction of domatic isolated footing, including the blinding layer positioned at bottom, are laid on blinding layer
Basic net sheet, and it is vertically provided at the foundation columns joint bar in the middle part of the basic net sheet, it is characterised in that also including vertically arranged
Vertical bars at the corner of domatic isolated footing to be poured, and be centered around the rectangular of setting on the outside of the foundation columns joint bar and determine
Position stirrup, diagonal bar is connected between the corner and the top of the corresponding vertical bars of the positioning stirrup;The top of the vertical bars,
It is consistent to position the vertical distance of stirrup and diagonal bar to the forming surface of domatic isolated footing to be poured, and is all higher than minimal protection layer
Thickness.
Using said structure so that the diagonal bar being connected between the corner of positioning stirrup and corresponding vertical bars is independent along domatic
The domatic broken line direction on basis is set.Again due to the top of vertical bars, positioning stirrup and diagonal bar to domatic isolated footing to be poured
Forming surface vertical distance it is consistent, and be all higher than minimal protection thickness degree.So, when casting concrete, Gong Renke
To be controlled by diagonal bar to the thickness of concrete, the difficulty of concreting is advantageously reduced.Moreover, there is the auxiliary of diagonal bar
Help so that requirement of the concrete pouring construction to worker's technical merit is relatively low, is advantageous to improve the quality of concreting
And uniformity;Ensure domatic isolated footing molding effect, improve domatic isolated footing pouring molding speed, reduce domatic independence base
Plinth pours labor intensity.Said structure is simple, and installation operation is convenient.
Further, the vertical bars are implanted into the blinding layer, or are welded on the basic net sheet.
So, the installation of vertical bars can be made easier, installation is more reliable.
Further, multiple brace rods are additionally provided between the diagonal bar and the basic net sheet.
So, the intensity of diagonal bar can be increased, when avoiding diagonal bar long, middle part can bend, and influence the mixed of later stage
Coagulate native pouring quality.
Further, the forming surface of the top of the vertical bars, positioning stirrup and diagonal bar to domatic isolated footing to be poured
Vertical distance be 20~30mm.
So, in the case where meeting the requirement of minimal protection thickness degree, reduce the distance as far as possible, be easy to worker constructing
When can preferably control the Forming Quality of concreting.
Further, multiple reinforcing hoops for being used to reinforce the foundation columns joint bar are additionally provided with the foundation columns joint bar
Muscle.
So, the intensity of foundation columns joint bar can be increased, improve the Forming Quality and intensity of domatic isolated footing.
Further, the stirrup of reinforcing includes the embedded division reinforcing stirrup in domatic isolated footing, positioned at domatic
The encrypted area of the top area of isolated footing reinforces stirrup, and reinforces stirrup positioned at the non-encrypted area on foundation columns joint bar top.
In summary, the utility model, which has, enables to requirement of the concrete pouring construction to worker's technical merit relative
It is relatively low, be advantageous to improve the quality and uniformity of concreting;Ensure domatic isolated footing molding effect, it is independent to improve domatic
Basic pouring molding speed, reduce the advantages that domatic isolated footing pours labor intensity.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model embodiment.
Embodiment
With reference to embodiment, the utility model is described in further detail.
During specific implementation:As shown in figure 1, a kind of bar construction of domatic isolated footing, including the base mat positioned at bottom
Layer 1, the basic net sheet 2 being laid on blinding layer, and the foundation columns joint bar 3 at the middle part of basic net sheet 2 is vertically provided at,
Also include being vertically provided at the vertical bars 4 at the corner of domatic isolated footing to be poured, and be centered around the outside of foundation columns joint bar 3
The rectangular positioning stirrup 5 set, it is connected between the corner and the top of the corresponding vertical bars 4 of the positioning stirrup 5
Diagonal bar 6;The tops of the vertical bars 4, positioning stirrup 5 and diagonal bar 6 to the forming surface of domatic isolated footing to be poured it is vertical away from
From consistent, and it is all higher than minimal protection thickness degree.
Using said structure so that the diagonal bar being connected between the corner of positioning stirrup and corresponding vertical bars is independent along domatic
The domatic broken line direction on basis is set.Again due to the top of vertical bars, positioning stirrup and diagonal bar to domatic isolated footing to be poured
Forming surface vertical distance it is consistent, and be all higher than minimal protection thickness degree.So, when casting concrete, Gong Renke
To be controlled by diagonal bar to the thickness of concrete, the difficulty of concreting is advantageously reduced.Moreover, there is the auxiliary of diagonal bar
Help so that requirement of the concrete pouring construction to worker's technical merit is relatively low, is advantageous to improve the quality of concreting
And uniformity;Ensure domatic isolated footing molding effect, improve domatic isolated footing pouring molding speed, reduce domatic independence base
Plinth pours labor intensity.Said structure is simple, and installation operation is convenient.
During implementation, the vertical bars 4 are implanted into the blinding layer 1, or are welded on the basic net sheet 2.
So, the installation of vertical bars can be made easier, installation is more reliable.
During implementation, multiple brace rods are additionally provided between the diagonal bar 6 and the basic net sheet 2.
So, the intensity of diagonal bar can be increased, when avoiding diagonal bar long, middle part can bend, and influence the mixed of later stage
Coagulate native pouring quality.
During implementation, the top of the vertical bars 4, stirrup 5 and diagonal bar 6 are positioned to the forming surface of domatic isolated footing to be poured
Vertical distance be 20~30mm.
So, in the case where meeting the requirement of minimal protection thickness degree, reduce the distance as far as possible, be easy to worker constructing
When can preferably control the Forming Quality of concreting.
During implementation, multiple reinforcing hoops for being used to reinforce the foundation columns joint bar 3 are additionally provided with the foundation columns joint bar 3
Muscle.
So, the intensity of foundation columns joint bar can be increased, improve the Forming Quality and intensity of domatic isolated footing.
During implementation, the stirrup of reinforcing includes the embedded division reinforcing stirrup in domatic isolated footing, only positioned at domatic
The encrypted area for founding the top area on basis reinforces stirrup, and reinforces stirrup positioned at the non-encrypted area on the top of foundation columns joint bar 3.
Embodiment:
1st, reinforcement fabrication
The surface of reinforcing bar should be clean, and oil stain, the outer skin that paints dirt and can be peeled off when pounding with a hammer, iron rust etc. should be clear before use
Except clean.Conscientiously it is familiar with drawing before blanking, establishment material table, should avoids during fracture with short dipstick metering length material, preventing from producing in amount material
Raw cumulative errors.In cutting-off process, such as find that reinforcing bar has splitting, drop-head or serious elbow to cut off.Vertical bars termination
Processing, preferably using emery wheel cuts, electric arc must not be used to cut, port surface should smooth out, and notching edge must not have crackle, root face and lack
Rib.Positioning stirrup is processed into closed ring type and constructs its structure, and reinforcing bar preferably uses two-sided overlap welding or single welding, the lap of splice >=5d
Or >=10d, joint welding thickness >=0.3d, weld width >=0.8d;In construction, reinforcement welding answers pre-bending, to ensure that two connect
On an axis, 2 points are fixed head, and tack weld should should start from more than overlapping end 20mm, striking in overlap joint one end, receive arc
Should be on overlap joint termination, arc crater fills up.First layer weld seam should have enough fusion penetrations, main weld and tack weld, particularly fixed
The top and terminal of position weld seam, it should fuse good.
2nd, reinforcement installation
Positioning stirrup is welded in outside basic coupling beam longitudinal reinforcement top or foundation columns joint bar;Vertical bars are implanted into blinding layer four
At angle or it is welded in basic net sheet muscle edge;Diagonal bar prolongs the knuckle line arrangement at domatic basis four sides, top and bottom, is respectively welded
In positioning stirrup angle point bending place and vertical bars top of supply line, apparent distance length increase in middle part is with diameter support reinforcing bar and welds jail
Gu.Above reinforcement welding technique uses arc welding, and before welding, the scale at solder joint should be removed totally, in welding process and
When scarfing cinder, face of weld is smooth, and weld seam is attractive in appearance.
3rd, the most suitable slump of concrete is determined
The slump of concrete should according to structure section, reinforcing bar content, transportation range, pour mode, means of transportation, vibrate
The conditional decision such as ability and weather, shelving isolated footing concrete slump preferably select 160mm ± 20mm.The test side of slump
Method:With the slump bucket that a 100mm suitable for reading, lower mouth 200mm, high 300mm are horn-like, consolidate after penetration concrete, then pull out
Bucket is played, concrete is because deadweight produces slump phenomenon, with bucket height(300mm)The height of concrete peak after slump is subtracted, if
Difference is 160mm, then slump is 160.Concrete supply side should have strict quality assurance system, and deliverability should meet company
The requirement of continuous pumping.The performance of concrete should still meet existing national standards in addition to it should meet design requirement《Ready-mixed concrete》
GB/T 14902 pertinent regulations.
4th, concreting
It should be layered and be carried out continuously during casting concrete, placement layer by layer thickness cannot be greater than 300mm.Pour for the first time to basis
Poured for the second time again behind footing position, about 0.5h.Period should often observe template and positioning stirrup whether there is and walks about, shifts feelings
Condition, when discovery has deformation, walks about or shift, stop pouring immediately, and amendment and reinforcing template in time, then it is further continued for pouring
Build.In concreting process, when concrete loses flowability and possesses certain plastic, using the chi side more than key dimension,
Prolong positioning stirrup to strike off and make basic moulding;Before concrete initial set, then prolong basic four sides with wooden float and rub flat receipts face with the hands, and ensure
Minimal protective cover thickness.
5th, concrete curing
The concrete poured, should be covered in 12h rear films or water seasoning, normal temperature maintenance are no less than 7d.If special messenger
Check and implement, prevent from, due to conserving not in time, causing concrete surface crack.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not using the utility model as limitation
All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model
Protection domain within.
Claims (6)
1. a kind of bar construction of domatic isolated footing, including the blinding layer positioned at bottom(1), it is laid on blinding layer
Basic net sheet(2), and it is vertically provided at the basic net sheet(2)The foundation columns joint bar at middle part(3), it is characterised in that also wrap
Include the vertical bars being vertically provided at the corner of domatic isolated footing to be poured(4), and it is centered around the foundation columns joint bar(3)Outside
The rectangular positioning stirrup set(5), the positioning stirrup(5)Corner and the corresponding vertical bars(4)Top between
It is connected with diagonal bar(6);The vertical bars(4)Top, positioning stirrup(5)And diagonal bar(6)To domatic isolated footing to be poured
The vertical distance of forming surface is consistent, and is all higher than minimal protection thickness degree.
2. the bar construction of domatic isolated footing as claimed in claim 1, it is characterised in that the vertical bars(4)It is implanted into the base
Plinth bed course(1)It is interior, or it is welded on the basic net sheet(2)On.
3. the bar construction of domatic isolated footing as claimed in claim 1, it is characterised in that the diagonal bar(6)With the base
Plinth mesh sheet(2)Between be additionally provided with multiple brace rods.
4. the bar construction of domatic isolated footing as claimed in claim 1, it is characterised in that the vertical bars(4)Top, fixed
Position stirrup(5)And diagonal bar(6)Vertical distance to the forming surface of domatic isolated footing to be poured is 20~30mm.
5. the bar construction of domatic isolated footing as claimed in claim 1, it is characterised in that the foundation columns joint bar(3)On
It is additionally provided with multiple for reinforcing the foundation columns joint bar(3)Reinforcing stirrup.
6. the bar construction of domatic isolated footing as claimed in claim 5, it is characterised in that the reinforcing stirrup includes being located at
Embedded division in domatic isolated footing reinforces stirrup, and stirrup is reinforced positioned at the encrypted area of the top area of domatic isolated footing, with
And positioned at foundation columns joint bar(3)The non-encrypted area on top reinforces stirrup.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720712581.0U CN206844138U (en) | 2017-06-19 | 2017-06-19 | A kind of bar construction of domatic isolated footing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720712581.0U CN206844138U (en) | 2017-06-19 | 2017-06-19 | A kind of bar construction of domatic isolated footing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206844138U true CN206844138U (en) | 2018-01-05 |
Family
ID=60800943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720712581.0U Active CN206844138U (en) | 2017-06-19 | 2017-06-19 | A kind of bar construction of domatic isolated footing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206844138U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109763508A (en) * | 2019-01-26 | 2019-05-17 | 中煤地建设工程有限公司 | A kind of domatic isolated footing structure |
CN111877384A (en) * | 2020-08-06 | 2020-11-03 | 广州协安建设工程有限公司 | One-step forming construction method for stepped independent extension foundation |
CN115341596A (en) * | 2022-09-21 | 2022-11-15 | 深圳市清华苑工程结构鉴定有限公司 | Implementation method for bilateral additional construction of slope-shaped independent foundation |
-
2017
- 2017-06-19 CN CN201720712581.0U patent/CN206844138U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109763508A (en) * | 2019-01-26 | 2019-05-17 | 中煤地建设工程有限公司 | A kind of domatic isolated footing structure |
CN111877384A (en) * | 2020-08-06 | 2020-11-03 | 广州协安建设工程有限公司 | One-step forming construction method for stepped independent extension foundation |
CN115341596A (en) * | 2022-09-21 | 2022-11-15 | 深圳市清华苑工程结构鉴定有限公司 | Implementation method for bilateral additional construction of slope-shaped independent foundation |
CN115341596B (en) * | 2022-09-21 | 2024-01-23 | 深圳市清华苑工程结构鉴定有限公司 | Implementation method for double-side additional construction of slope-shaped independent foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105649113B (en) | The structure and construction method of a kind of basement post-pouring zone | |
CN206844138U (en) | A kind of bar construction of domatic isolated footing | |
CN207616844U (en) | Foundation platform precast concrete side form and molding machine | |
CN105275097A (en) | A post-cast strip water-stop steel plate and demolition-free template net installing method | |
CN109577377A (en) | Basement post-pouring zone structure and its construction method | |
CN109208790A (en) | Circular arc shear wall single side formwork construction method | |
CN204456224U (en) | A kind of structure of basement post-pouring zone | |
CN106948504A (en) | Assembled wallboard water seepage prevention vertical abutment joint structure and its construction method | |
CN102116092A (en) | Method for constructing reinforcing band for compensating contraction of concrete and preventing cracks | |
CN104594633B (en) | The construction method and its formwork structure of umbrella shape space curved surface clear-water concrete | |
CN107191006B (en) | Dismantling and repairing method for refractory concrete layer of diversion trench | |
CN104805864B (en) | The cementing Waterproof Construction Technique that closes of basement top-down method exterior wall tongue and groove and sealing | |
CN110080438A (en) | A kind of incorporation basalt fibre regeneration concrete wall and apply method | |
CN210685019U (en) | Anti-bank structure with stagnant water steel sheet | |
CN110761562A (en) | Auxiliary tool for pouring concrete and using method | |
CN209040348U (en) | A kind of assembled double steel plate combined shear wall construction with ribbing | |
CN207348280U (en) | A kind of novel precast floor slab | |
CN216075741U (en) | Anti-crack structure at joint of filler wall and shear wall | |
CN206189449U (en) | Soleplate with lead integrated plank sheathing system of wall | |
CN108005400A (en) | A kind of construction method of existing building structure integral replacement | |
CN108130889A (en) | Pump lock main body bottom plate and flow channel layer side wall step construction joint method for production | |
CN212453264U (en) | Anti reinforcing apparatus that floats of hollow superstructure mandrel of cast in situ concrete | |
CN201288339Y (en) | Leakage-proof structure of foundation bedplate back-pouring band | |
CN207647172U (en) | A kind of sealing is returned template reinforcing device | |
CN210152287U (en) | Multifunctional floor split heads |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200622 Address after: No.1 Tengfei Road, Junliang City, Dongli District, Tianjin Patentee after: MCC Construction Engineering Group (Tianjin) Construction Engineering Co., Ltd Address before: No. 1 West Road 400084 Dadukou District of Chongqing Patentee before: CHINA METALLURGICAL CONSTRUCTION ENGINEERING GROUP Co.,Ltd. |