CN218060693U - Assembled steel construction building - Google Patents
Assembled steel construction building Download PDFInfo
- Publication number
- CN218060693U CN218060693U CN202221737678.4U CN202221737678U CN218060693U CN 218060693 U CN218060693 U CN 218060693U CN 202221737678 U CN202221737678 U CN 202221737678U CN 218060693 U CN218060693 U CN 218060693U
- Authority
- CN
- China
- Prior art keywords
- connecting axle
- floorbar
- assembled steel
- back timber
- jack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses an assembled steel construction building, including the floorbar, stand and back timber, first connecting axle and second connecting axle are installed respectively to the stand both ends, and first connecting axle both ends slide to be inserted and establish at the floorbar both ends, and second connecting axle both ends are articulated with the one end of back timber, and the inside telescopic link that is equipped with of inserting of back timber, extension board are installed to the floorbar downside, and floorbar internally mounted has the bottom plate, installs the curb plate between two stands, and the slide opening has been seted up at the floorbar both ends, and first connecting axle both ends slide to set up in the slide opening, the utility model discloses a first connecting axle and second connecting axle are installed respectively to the stand both ends, and first connecting axle both ends slide to be inserted and establish at the floorbar both ends, and second connecting axle both ends are articulated with the one end of back timber, are convenient for constitute the outer framework of building fast, then insert in proper order and establish the installation baffle for simple to operate is swift, and assembly structure stability is higher.
Description
Technical Field
The utility model relates to an assembly type structure technical field specifically is an assembly type steel construction building.
Background
The assembly type building can be divided into two major types, namely an assembly type concrete building and an assembly type steel structure building, wherein the assembly type concrete building is formed by prefabricating and forming building maintenance structures such as wallboards, floor slabs, beams and columns and main body structures in a factory and assembling and constructing on site; the integrated assembly type steel structure building takes a steel structure as a main structure, and maintenance structures such as wallboards, floor slabs and the like adopt light steel systems or concrete slabs and the like. Buildings assembled from prefabricated parts at the site are called fabricated buildings. The building block is divided into five types, namely a block building, a plate building, a box building, a framework plate building, a rising-rise building and the like according to the form and the construction method of the prefabricated part.
An assembled steel structural building of prior art application number CN202121444907.9 comprising: the bottom surface of the fixing plate is provided with a plurality of positioning piles; the bottom plate is detachably connected with the top surface of the fixed plate; one end of each upright post is detachably connected with the bottom plate, and a waterproof side plate is clamped between every two adjacent upright posts; the two cross columns are detachably connected with the other ends of the plurality of upright columns, and are positioned vertically above the bottom plate; the top beam is positioned between the two transverse columns, the top beam is connected with the two transverse columns through a plurality of top columns, and a top plate is clamped between every two adjacent top columns; and the waterproof sun-proof plate is covered between the top beam and the two cross columns. The using length of the top beam cannot be adjusted, so that the assembly, use and treatment of top beams with different lengths are met, the installation is complex, and the use is inconvenient for cooling.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an assembled steel construction building to solve the service length that can not adjust the back timber among the prior art, thereby satisfy the back timber assembly use of different length and handle, the installation is complicated, the problem of the use of taking a cool not being convenient for.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an assembled steel construction building, includes floorbar, stand and back timber, first connecting axle and second connecting axle are installed respectively to the stand both ends, first connecting axle both ends slide to be inserted and establish at the floorbar both ends, second connecting axle both ends are articulated with the one end of back timber, the inside telescopic link that is equipped with of inserting of back timber, the extension board down is installed to the floorbar downside, floorbar internally mounted has the bottom plate, installs the curb plate between two stands.
Furthermore, sliding holes are formed in two ends of the bottom beam, and two ends of the first connecting shaft are arranged in the sliding holes in a sliding mode.
Furthermore, the slide hole is set to be a U-shaped hole, and one end of the first connecting shaft is fixedly connected through a limiting nut.
Furthermore, the two ends of the telescopic rod are inserted into the two posts of the top beam in a sliding manner, and the upper side of the top beam is provided with a fastening bolt.
Furthermore, a first jack is formed in the upright post, two ends of the side plate are slidably clamped in the first jack, a second jack is formed in the bottom beam, and two ends of the bottom plate are slidably inserted in the second jack.
Furthermore, a hanging ring is installed on the outer side of the lower end of the top beam, and a curtain is installed on the hanging ring through a hook.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a first connecting axle and second connecting axle are installed respectively to the stand both ends, and first connecting axle both ends slide to be inserted and establish at the floorbar both ends, and second connecting axle both ends are articulated with the one end of back timber, are convenient for constitute the outer framework of building fast, then insert in proper order and establish the installation baffle for simple to operate is swift, and assembly structure stability is higher.
2. The utility model discloses and be equipped with the telescopic link through inside inserting of back timber, inside two posts of establishing the back timber are inserted in the slip of telescopic link both ends, and the back timber upside installs fastening bolt for insert through adjusting the telescopic link and establish the inside degree of depth of two posts, thereby can adjust the use length of back timber, thereby satisfy the assembly use processing of different length, be convenient for enjoy the cool use.
3. The utility model discloses a link is installed in the back timber lower extreme outside, the curtain that hangs down is installed through the couple to the link, is convenient for shelter from the processing to the exit around the building of assembled, is favorable to improving the travelling comfort that the cool was used.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic view of a first assembly structure of the present invention;
FIG. 2 is a second assembly view of the present invention;
fig. 3 is a schematic view of the structure of the bottom beam of the present invention.
In the figure: 1. a bottom beam; 2. a slide hole; 3. a first connecting shaft; 4. a column; 5. a top beam; 6. a second connecting shaft; 7. a telescopic rod; 8. a first jack; 9. a side plate; 10. Fastening a bolt; 11. a second jack; 12. a base plate; 13. a drapery; 14. hanging a ring; 15. a limit nut; 16. and a lower support plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Please refer to fig. 1, fig. 2, fig. 3, in the embodiment of the present invention, an assembly type steel structure building, including floorbar 1, stand 4 and back timber 5, first connecting axle 3 and second connecting axle 6 are installed respectively to stand 4 both ends, 3 both ends of first connecting axle are slided and are inserted and establish 1 both ends of floorbar, 6 both ends of second connecting axle are articulated with the one end of back timber 5, be convenient for constitute the outer framework of building fast, then insert in proper order and establish the erection baffle, accomplish the assembly of building, make simple to operate swift, the assembly structure stability is higher, back timber 5 is inside to be inserted and is equipped with telescopic link 7, make and insert the inside degree of depth of establishing two posts through adjusting telescopic link 7, thereby can adjust the service length of back timber 5, thereby satisfy the assembly use processing of different length, extension board 16 is installed to floorbar 1 downside, floorbar 1 internally mounted has bottom plate 12, install curb plate 9 between two stands 4, be convenient for shelter from the processing to the building side.
Preferably, the slide opening 2 has been seted up at floorbar 1 both ends, and 3 both ends of first connecting axle slide to set up in slide opening 2, are convenient for slide-articulate 4 lower extremes of stand inside floorbar 1 both ends for can incline to adjust to use the processing to stand 4.
Preferably, the slide hole 2 is set to be a U-shaped hole, and one end of the first connecting shaft 3 is fixedly connected through a limiting nut 15, so that the sliding limiting treatment is conveniently carried out on one end of the first connecting shaft 3.
Preferably, the two ends of the telescopic rod 7 are slidably inserted into the two posts of the top beam 5, the fastening bolt 10 is installed on the upper side of the top beam 5, the telescopic rod 7 is conveniently adjusted to insert the depth of the two posts, so that the use length of the top beam 5 can be adjusted, and the assembly use treatment with different lengths is met.
Preferably, the upright column 4 is internally provided with a first jack 8, the two ends of the side plate 9 are slidably clamped in the first jack 8, the bottom beam 1 is internally provided with a second jack 11, the two ends of the bottom plate 12 are slidably inserted in the second jack 11, the bottom plate 12 and the side plate 9 are conveniently installed and positioned, and the positioning stability and the dismounting are convenient and quick.
Preferably, the outer side of the lower end of the top beam 5 is provided with a hanging ring 14, the hanging ring 14 is provided with a vertical curtain 13 through a hook, shielding treatment is conveniently carried out on front and rear outlets of the fabricated building, and improvement of comfort of use in cool enjoying is facilitated.
The utility model discloses a theory of operation and use flow: the two ends of the upright post 4 are respectively provided with the first connecting shaft 3 and the second connecting shaft 6, the two ends of the first connecting shaft 3 are inserted at the two ends of the bottom beam 1 in a sliding manner, the two ends of the second connecting shaft 6 are hinged with one end of the top beam 5, so that an outer framework of a building can be conveniently and quickly formed, and then the installation baffles are sequentially inserted to complete the assembly of the building, so that the installation is convenient and quick, and the stability of an assembly structure is high; and through some telescopic links 7 of inserting inside the back timber 5, and the back timber 5 upside installs fastening bolt 10 for insert the inside degree of depth of establishing two posts through adjusting telescopic link 7, thereby can adjust the use length of back timber 5, thereby satisfy the assembly use of different length and handle.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (6)
1. The utility model provides an assembled steel construction building, includes floorbar (1), stand (4) and top beam (5), its characterized in that: first connecting axle (3) and second connecting axle (6) are installed respectively to stand (4) both ends, slide at first connecting axle (3) both ends and insert and establish at floorbar (1) both ends, second connecting axle (6) both ends are articulated with the one end of back timber (5), back timber (5) inside is inserted and is equipped with telescopic link (7), extension board (16) down are installed to floorbar (1) downside, floorbar (1) internally mounted has bottom plate (12), installs curb plate (9) between two stands (4).
2. An assembled steel structural building according to claim 1, wherein: slide holes (2) are formed in the two ends of the bottom beam (1), and the two ends of the first connecting shaft (3) are arranged in the slide holes (2) in a sliding mode.
3. An assembled steel structural building according to claim 2, wherein: the sliding hole (2) is arranged to be a U-shaped hole, and one end of the first connecting shaft (3) is fixedly connected through a limiting nut (15).
4. An assembled steel structure building according to claim 1, wherein: two ends of the telescopic rod (7) are inserted into the two posts of the top beam (5) in a sliding manner, and the upper side of the top beam (5) is provided with a fastening bolt (10).
5. An assembled steel structural building according to claim 1, wherein: the novel floor is characterized in that a first jack (8) is formed in the upright column (4), two ends of the side plate (9) are slidably clamped in the first jack (8), a second jack (11) is formed in the bottom beam (1), and two ends of the bottom plate (12) are slidably inserted in the second jack (11).
6. An assembled steel structural building according to claim 1, wherein: and a hanging ring (14) is installed on the outer side of the lower end of the top beam (5), and a vertical curtain (13) is installed on the hanging ring (14) through a hook.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221737678.4U CN218060693U (en) | 2022-07-07 | 2022-07-07 | Assembled steel construction building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221737678.4U CN218060693U (en) | 2022-07-07 | 2022-07-07 | Assembled steel construction building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218060693U true CN218060693U (en) | 2022-12-16 |
Family
ID=84435667
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221737678.4U Active CN218060693U (en) | 2022-07-07 | 2022-07-07 | Assembled steel construction building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218060693U (en) |
-
2022
- 2022-07-07 CN CN202221737678.4U patent/CN218060693U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215803108U (en) | Attached beam type hanging basket | |
CN218060693U (en) | Assembled steel construction building | |
CN109132843A (en) | The installation method of super-section metal bellows in a kind of vertical shaft | |
CN215564746U (en) | Assembled steel structure ladder cage | |
CN113152658B (en) | Large-span corridor with comprehensive curtain wall at bottom and construction method | |
CN214462394U (en) | High-altitude overhanging scaffold | |
CN211622543U (en) | Hanging basket control device | |
CN208604911U (en) | A kind of novel suspention beam bracket | |
CN217205217U (en) | Scaffold for house construction | |
CN216276814U (en) | Building machine walkway plate connecting assembly | |
CN214738726U (en) | Steel construction vestibule with electromechanical installation gallows | |
CN215291304U (en) | A installation device that is used for building enclosure outer wall rock wool battenboard | |
CN216276813U (en) | Building machine walkway plate connecting assembly | |
CN215889310U (en) | Connecting component and platform for mounting and constructing ceiling decorative plate | |
CN215630633U (en) | Assembled elevator derrick | |
CN218668433U (en) | Operating platform for building construction of anti-video wall of house | |
CN220599110U (en) | Movable bridge type operation platform | |
CN216276815U (en) | Connecting assembly for hanging frame of building machine | |
CN218234259U (en) | Combined folding scaffold | |
CN210369830U (en) | Folding detachable scaffold | |
CN221031323U (en) | Movable hoistway construction device | |
CN220978763U (en) | Electric hanging basket erecting device | |
CN215564253U (en) | Vertical frame structure of building construction scaffold | |
CN213548524U (en) | Three-dimensional greening structure | |
CN221119147U (en) | Mounting platform of elevator well |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |