CN217923513U - Foundation pile for civil engineering - Google Patents

Foundation pile for civil engineering Download PDF

Info

Publication number
CN217923513U
CN217923513U CN202221831342.4U CN202221831342U CN217923513U CN 217923513 U CN217923513 U CN 217923513U CN 202221831342 U CN202221831342 U CN 202221831342U CN 217923513 U CN217923513 U CN 217923513U
Authority
CN
China
Prior art keywords
carbon fiber
pile body
pouring
civil engineering
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221831342.4U
Other languages
Chinese (zh)
Inventor
宁静
范海林
李传辉
陈先桐
董文文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yulin Jianye Xintong Construction Engineering Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202221831342.4U priority Critical patent/CN217923513U/en
Application granted granted Critical
Publication of CN217923513U publication Critical patent/CN217923513U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a foundation pile that civil engineering foundation pile technical field's civil engineering used, including the bottom pile body, upper pile body and cushion cap, upper pile body and bottom pile body are located cushion cap top and bottom respectively, the bottom pile body comprises carbon fiber reinforcement frame, carbon fiber reinforcement frame comprises four vertical carbon fiber reinforcement and a plurality of layers of carbon fiber reinforcement ring, it is solid to make the bottom pile body need not to carry out watering of plank encapsulation and concrete, can make carbon fiber reinforcement frame reach the condition that prevents moisture erosion, can guarantee the firm and intensity of the bottom pile body of foundation pile on the one hand, on the other hand can effectively solve the problem of moisture erosion, reduce the process simultaneously, reduce the engineering volume, its simple structure simultaneously, be fit for promoting on a large scale.

Description

Foundation pile for civil engineering
Technical Field
The utility model relates to a civil engineering foundation pile technical field specifically is foundation pile that civil engineering used.
Background
The foundation pile is a foundation formed by a pile and a bearing platform connected to the top of the pile. If the pile body is completely buried in the soil and the bottom surface of the bearing platform is contacted with the soil body, the pile body is called a low bearing platform pile foundation; when the upper part of the pile body is exposed out of the ground and the bottom of the pile cap is positioned above the ground, the pile body is called a high pile cap pile foundation. Building pile foundations are typically low cap pile foundations.
In the existing civil engineering foundation pile, a bottom pile body for embedding the ground bottom is usually driven into a rock stratum or a hard soil layer by steel bars, the whole foundation pile is grabbed and attached to the ground, and because the underground soil is wet, the steel bars are usually required to be packaged by boards, and simultaneously concrete is poured, so that the steel bars are protected, the process is complicated, and the engineering quantity is large, so that the foundation pile for civil engineering is urgently required to be developed to meet the actual use requirement.
Disclosure of Invention
The utility model aims at solving above defect, provide the foundation pile that civil engineering used.
In order to solve the technical problem, the utility model discloses a following technical scheme:
foundation pile that civil engineering used, including the bottom pile body, upper pile body and cushion cap, upper pile body and bottom pile body are located cushion cap top and bottom respectively, the bottom pile body comprises carbon fiber reinforcing bar frame, carbon fiber reinforcing bar frame comprises four vertical carbon fiber reinforcing bars and a plurality of layers of carbon fiber reinforcing bar ring, carbon fiber reinforcing bar ring comprises four horizontal carbon fiber reinforcing bars, the both ends of horizontal carbon fiber reinforcing bar all are equipped with the installation trepanning, end to end between the horizontal carbon fiber reinforcing bar, form closed loop structure, vertical carbon fiber reinforcing bar pegs graft into the inside in installation trepanning, fixed connection is carried out with the bottom of cushion cap in the top of carbon fiber reinforcing bar frame.
In the above description, as a further scheme, the upper layer pile body is composed of a steel bar frame and a pouring column body, the steel bar frame is composed of four longitudinal steel bar columns and a plurality of transverse steel bar columns, the bottoms of the longitudinal steel bar columns are fixed on the top of the bearing platform, the transverse steel bar columns are bent inwards for multiple times to be connected end to end, and the bent positions and the middle parts of the longitudinal steel bar columns are welded and fixed.
In the above description, as a further scheme, the pouring column is composed of four pouring wood plates, the pouring wood plates respectively surround the periphery of the steel bar frame, a pouring cavity is formed between the pouring wood plates and the steel bar frame, and concrete is poured into the pouring cavity to form a concrete pouring layer.
In the above description, as a further alternative, the bearing platform is constructed by concrete pouring.
In the above description, as a further scheme, two sides of the mounting sleeve holes near the opening are provided with welding plates, the welding plates are in an annular structure, and two adjacent mounting sleeve holes are welded and fixed through the welding plates.
In the above description, as a further aspect, the welding plate is made of a stainless steel plate.
The utility model discloses produced beneficial effect as follows:
the utility model provides a foundation pile for civil engineering adopts the carbon fiber reinforcing bar frame that comprises the carbon fiber reinforcing bar at the bottom pile body, make the bottom pile body need not to carry on the plank encapsulation and concrete water admittedly, can make the carbon fiber reinforcing bar frame reach the condition that prevents the moisture erosion, can guarantee the firm and intensity of the bottom pile body of foundation pile on the one hand, on the other hand can effectively solve the problem of moisture erosion, reduce the process simultaneously, reduce the engineering volume, its simple structure simultaneously, be fit for promoting on a large scale.
Drawings
Fig. 1 is a schematic view of the internal structure of a foundation pile for civil engineering of the present invention;
fig. 2 is a schematic structural view of a carbon fiber reinforcing cage in a foundation pile for civil engineering of the present invention;
FIG. 3 is a schematic view of a portion of the enlarged structure of A in FIG. 2;
in the figure: 1-bottom layer pile body, 2-bearing platform, 3-upper layer pile body, 4-pouring wood plate, 5-steel bar main body frame, 6-concrete pouring layer, 101-transverse carbon fiber steel bar, 102-longitudinal carbon fiber steel bar, 103-welding plate, 104-mounting trepanning, 501-longitudinal steel bar column, 502-transverse steel bar column and 503-pouring cavity.
Detailed Description
In order to facilitate understanding of those skilled in the art, the present invention will be further described with reference to the following examples and drawings, which are not intended to limit the present invention. The present invention will be described in detail with reference to the accompanying drawings.
Referring to fig. 1-3, the foundation pile for civil engineering includes a bottom pile body 1, an upper pile body 3 and a pile cap 2, the upper pile body 3 and the bottom pile body 1 are respectively located at the top and the bottom of the pile cap 2, the bottom pile body 1 is composed of a carbon fiber reinforcement frame, the carbon fiber reinforcement frame is composed of four longitudinal carbon fiber reinforcements 102 and a plurality of carbon fiber reinforcement rings, the carbon fiber reinforcement rings are composed of four transverse carbon fiber reinforcements 101, both ends of the transverse carbon fiber reinforcements 101 are provided with mounting holes 104, the transverse carbon fiber reinforcements 101 are connected end to form a closed ring structure, the longitudinal carbon fiber reinforcements 102 are inserted into the mounting holes 104, and the top of the carbon fiber reinforcement frame is fixedly connected with the bottom of the pile cap 2.
The upper layer pile body 3 is composed of a reinforcing frame 5 and a pouring column body, the reinforcing frame 5 is composed of four longitudinal reinforcing columns 501 and a plurality of transverse reinforcing columns 502, the bottoms of the longitudinal reinforcing columns 501 are fixed to the top of the bearing platform 2, the transverse reinforcing columns 502 are bent inwards for multiple times to be connected end to end, and the bent positions and the middle parts of the longitudinal reinforcing columns 501 are welded and fixed.
The pouring column body is composed of four pouring wood plates 4, the pouring wood plates 4 respectively surround the periphery of the reinforcing steel bar frame 5, a pouring cavity 503 is formed between the pouring wood plates 4 and the reinforcing steel bar frame 5, concrete is poured into the pouring cavity 503 to form a concrete pouring layer 6, and the bearing platform 2 is formed by pouring concrete.
The both sides that the mounting trepan boring 104 is close to the opening part are equipped with welded plate 103, and welded plate 103 is the loop configuration, carries out welded fastening through welded plate 103 between two adjacent mounting trepan boring 104, and welded plate 103 comprises the stainless steel sheet.
The above description is only for the preferred embodiment of the present invention, and the present invention is not limited to the above description, and although the present invention is disclosed in the preferred embodiment, it is not limited to the above description, and any person skilled in the art can make some changes or modifications to equivalent embodiments without departing from the scope of the present invention, but all the technical solutions of the present invention are within the scope of the present invention.

Claims (6)

1. Foundation pile that civil engineering used, including bottom pile body, upper pile body and cushion cap, upper pile body and bottom pile body are located cushion cap top and bottom, its characterized in that respectively: the bottom pile body comprises the carbon fiber reinforcing bar frame, and the carbon fiber reinforcing bar frame comprises four vertical carbon fiber reinforcing bars and a plurality of layers of carbon fiber reinforcing bar ring, and the carbon fiber reinforcing bar ring comprises four horizontal carbon fiber reinforcing bars, and the both ends of horizontal carbon fiber reinforcing bar all are equipped with the installation trepanning, and end to end between the horizontal carbon fiber reinforcing bar forms closed ring structure, and vertical carbon fiber reinforcing bar pegs graft into the inside in installation trepanning, and fixed connection is carried out with the bottom of cushion cap in the top of carbon fiber reinforcing bar frame.
2. Foundation pile for civil engineering according to claim 1, characterized in that: the pile body on the upper layer is composed of a reinforcing steel frame and a pouring column body, the reinforcing steel frame is composed of four longitudinal reinforcing steel columns and a plurality of transverse reinforcing steel columns, the bottoms of the longitudinal reinforcing steel columns are fixed to the top of the bearing platform, the transverse reinforcing steel columns are bent inwards for multiple times to be connected end to end, and the bent positions and the middle parts of the longitudinal reinforcing steel columns are welded and fixed.
3. Foundation pile for civil engineering according to claim 2, characterized in that: the pouring column body is composed of four pouring wood plates, the pouring wood plates surround the periphery of the reinforcing steel bar frame respectively, a pouring cavity is formed between the pouring wood plates and the reinforcing steel bar frame, and concrete is poured into the pouring cavity to form a concrete pouring layer.
4. Foundation pile for civil engineering according to claim 1, characterized in that: the bearing platform is formed by pouring concrete.
5. Foundation pile for civil engineering according to any one of claims 1 to 4, characterised in that: the both sides that the mounting trepanning is close to the opening part are equipped with the welded plate, and the welded plate is the loop configuration, carries out welded fastening through the welded plate between two adjacent mounting trepanning.
6. Foundation pile for civil engineering according to claim 5, characterized in that: the welding plate is made of stainless steel plates.
CN202221831342.4U 2022-07-17 2022-07-17 Foundation pile for civil engineering Active CN217923513U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221831342.4U CN217923513U (en) 2022-07-17 2022-07-17 Foundation pile for civil engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221831342.4U CN217923513U (en) 2022-07-17 2022-07-17 Foundation pile for civil engineering

Publications (1)

Publication Number Publication Date
CN217923513U true CN217923513U (en) 2022-11-29

Family

ID=84189170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221831342.4U Active CN217923513U (en) 2022-07-17 2022-07-17 Foundation pile for civil engineering

Country Status (1)

Country Link
CN (1) CN217923513U (en)

Similar Documents

Publication Publication Date Title
CN105089061B (en) Ultra-deep foundation pit supporting method
CN101440622B (en) CFG pile, pipe pile embankment reinforcement system and construction method thereof
CN105970993B (en) The construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap
CN205975658U (en) Steel platform tower crane foundation
CN106088120B (en) A kind of cofferdam decentralization construction method
CN110258593A (en) Friction pile for slope treatment
CN207525758U (en) A kind of reinforced Structure About Soldier Pile
CN204780990U (en) Combined type retaining wall structure
CN114086586A (en) Pile foundation construction method and structure for installing photovoltaic panel on steep slope
CN106013834A (en) Device and method for storey addition of basement
CN217923513U (en) Foundation pile for civil engineering
CN107227741A (en) Basement supporting construction
CN111622234A (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
CN106400814A (en) Foundation pit supporting method
CN207728018U (en) The building structure of skyscraper is built suitable for tier building set
CN203603525U (en) Reinforcing structure with clamp plate girder and clamp plate column externally arranged for stone structure
CN105569329A (en) Unilateral formwork support basement construction method and basement
CN212533950U (en) Ecological bank protection in river course
CN205917726U (en) Stake girder construction integral type tower crane foundation structure
CN213477808U (en) Structure is found fast to steel construction underground garage
CN212052780U (en) Oblique supporting type deep foundation pit supporting structure
CN107916798A (en) The building structure of skyscraper is built suitable for tier building set
CN209339172U (en) A kind of novel peg board composite foundation
CN210529716U (en) Adjacent foundation pit soil body supporting construction
CN209723230U (en) The connecting node of steel plate combined shear wall and not equal higher baselines

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240428

Address after: No. 157, Middle Section of Binhe Avenue, Mingzhou Town, Suide County, Yulin City, Shaanxi Province, 719000

Patentee after: Yulin Jianye Xintong Construction Engineering Co.,Ltd.

Country or region after: China

Address before: Room 102, Unit 1, Building 14, Tixiang Flower House, No. 866, Lingxi South Street, Handan District, Handan City, Hebei Province, 056000

Patentee before: Ning Jing

Country or region before: China