Prior art keywords
building
skyscraper
column
cross members
truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711404153.2A
Other languages
Chinese (zh)
Inventor
习朝位
史永健
蒋义平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Architectural Design Research Institute LLC
Original Assignee
Hebei Architectural Design Research Institute LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Architectural Design Research Institute LLC filed Critical Hebei Architectural Design Research Institute LLC
Priority to CN201711404153.2A priority Critical patent/CN107916798A/en
Publication of CN107916798A publication Critical patent/CN107916798A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266Enlarging
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts

Abstract

The present invention provides a kind of building structure that skyscraper is built suitable for tier building set, belong to building set and build technical field, including the braced frame system skyscraper being located above Old building, braced frame system includes frame column, base cross members are arranged on the truss crossbeam above base cross members with several, frame column is arranged on Old building surrounding, base cross members are arranged on above Old building, between base cross members truss crossbeam adjacent thereto, dagger is equipped between two neighboring truss crossbeam, cross-brace is set close to both sides frame column, truss upright-column is equipped between base cross members and bottommost truss crossbeam.By building skyscraper in Old building overcoat, the frame column of skyscraper is located at the surrounding of Old building, base cross members, truss crossbeam, truss upright-column and the cross-brace of top form braced frame system, in the case of meeting Old building normal use, realize that set is built by braced frame system on Old building and add layer, achieve the purpose that original place increasing layer enlarging, local integration.

Description

The building structure of skyscraper is built suitable for tier building set
Technical field
The invention belongs to fixed buildings set to build technical field, is to be related to one kind to be suitable for tier building more specifically Set builds the building structure of skyscraper.
Background technology
With the fast development of China's economy, the paces of urbanization are accelerated, and skyscraper is rised sheer from level ground like the mushrooms after rain, Cause the soil of downtown urban land fewer and fewer.There are at present in China city substantial amounts of 90 years and its former generation build 4 layers or so of old masonry house, with the development of the city and improvement of living standard, these Old buildings and appearance of city and people Demand produce gap, there are the defects of function is poor, shock resistance is poor, cannot meet the needs of social development.
In Old City Reconstruction, since some Old buildings are not up to service life, but progress comprehensive reformation is needed to carry Rise.If being removed to these Old buildings newly-built, necessarily bring building waste nowhere to discharge, strange land Relocation and Settlement the problems such as, this with Build Green Development, the objective of harmonious society is not inconsistent.
The content of the invention
It is existing to solve it is an object of the invention to provide a kind of building structure that skyscraper is built suitable for tier building set There is the dismounting of Old building present in technology is newly-built to cause building waste processing hardly possible, the technical problem of strange land Relocation and Settlement hardly possible.
To achieve the above object, the technical solution adopted by the present invention is:One kind is provided and builds high level suitable for tier building set The building structure of building, including be arranged on the skyscraper above Old building, the skyscraper are braced frame system, institute State braced frame system include frame column, base cross members and several be arranged at truss crossbeam above base cross members, it is described Frame column is arranged at Old building surrounding, and the base cross members are arranged above Old building, base cross members purlin adjacent thereto Between frame crossbeam, cross-brace is equipped between adjacent two truss crossbeams, the cross-brace is set close to both sides frame column, the bottom Truss upright-column is equipped between portion's crossbeam and bottommost truss crossbeam.
Further, the basis instrument of the adjacent foundation Old building of the skyscraper, the basis of the Old building is ash Earth foundation, the basis of the skyscraper is multiple bored concrete piles, and the bored concrete pile is extended downward into dirt ground beneath soil layer, The frame column is arranged on the top of the bored concrete pile.
Further, the bored concrete pile is club-footed pile, and the club-footed pile includes base expanding and base expanding portion, straight section portion and pile cover portion, described The bottom absolute altitude in pile cover portion is not less than the dirt bottom of foundation.
Further, the maximum outer edge in the base expanding and base expanding portion of the club-footed pile is without departing from grey earth foundation inner edge;The dirt The width on basis is a, and straight section minister's degree H of the club-footed pile is more than 2a.
Further, the frame column medial surface is equipped with the Preserved node for being used for continuing part with the later stage and be connected, described pre- Node is stayed to be arranged on below base cross members.
Further, it is equipped with and the corresponding connecting node of truss upright-column, the connecting node below the base cross members Pier is connected including being arranged at the concrete below base cross members, the connection pier bottom portion is equipped with downward for continuing part with the later stage The pre-embedded steel slab that column is connected, the pre-embedded steel slab are connected by connection structure with the truss upright-column of top and the downward column of lower section.
Further, the connection structure includes dowel and bar planting, and one end of the dowel is arranged in the connection pier, The other end of the dowel runs through the pre-embedded steel slab and fixation;One end of the bar planting is arranged in the downward column, described The other end of bar planting is through the pre-embedded steel slab and is implanted into the connection pier and truss upright-column.
Further, the dowel is arranged in the middle part of the pre-embedded steel slab for multiple and spacing parallel arranging;The bar planting is more Surrounding that is a and being arranged at the downward column.
Further, the vertical muscle in the truss upright-column is weldingly fixed on the pre-embedded steel slab after the connection pier Upper surface;Vertical muscle in the downward column is weldingly fixed on pre-embedded steel slab lower surface after the bending of pre-embedded steel slab bottom surface.
Further, perfusion is early between the top of the pre-embedded steel slab and connection pier, between lower section and downward column mends by force Repay shrinkage concrete.
The beneficial effect of the building structure provided by the invention for building skyscraper suitable for tier building set is:With it is existing Technology is compared, and the building structure that the present invention builds skyscraper suitable for tier building set is built by building high level in Old building overcoat Build, the frame column of skyscraper is arranged on the surrounding of Old building, base cross members, truss crossbeam, truss upright-column and the diagonal brace of top Column forms braced frame system, meets in the case of Old building normal use, passes through frame truss knot on Old building Structure system realizes that set is built and adds layer, achievees the purpose that original place increasing layer enlarging, local integration.
Brief description of the drawings
To describe the technical solutions in the embodiments of the present invention more clearly, below will be to embodiment or description of the prior art Needed in attached drawing be briefly described, it should be apparent that, drawings in the following description be only the present invention some Embodiment, for those of ordinary skill in the art, without having to pay creative labor, can also be according to these Attached drawing obtains other attached drawings.
Fig. 1 is the structural representation of the building structure provided in an embodiment of the present invention that skyscraper is built suitable for tier building set Figure;
Fig. 2 builds Old building base the building structure of skyscraper to be provided in an embodiment of the present invention suitable for tier building set The location diagram of plinth and Tall Building Foundation;
Fig. 3 is the A-A sectional views in Fig. 2;
Fig. 4 builds connecting node the building structure of skyscraper to be provided in an embodiment of the present invention suitable for tier building set Usage state diagram;
Fig. 5 is the surface structure figure of built-in fitting in Fig. 4;
Fig. 6 is the lower surface configuration figure of built-in fitting in Fig. 4;
Wherein, each reference numeral in figure:
1- Old buildings, 2- frame columns, 3- base cross members, 4- cross-braces, 5- truss upright-columns, 6- skyscrapers, 7- truss are horizontal Beam, 8- ash earth foundations, 9- bored concrete piles, 10- Preserved nodes, 12- connection piers, the downward columns of 13-, 14- pre-embedded steel slabs, 15- dowels, 16- bar plantings, 17- indulge muscle one, and 18- indulges muscle two;80- bottom surfaces, 81- inner edges, 90- base expanding and base expandings portion, 91- straight sections portion, 92- pile covers portion, The initial segment is excavated in 93- maximum outer edges, 94- base expanding and base expandings portion.
Embodiment
In order to which technical problems, technical solutions and advantages to be solved are more clearly understood, tie below Accompanying drawings and embodiments are closed, the present invention will be described in further detail.It should be appreciated that specific embodiment described herein is only To explain the present invention, it is not intended to limit the present invention.
It should be noted that when element is referred to as " being fixed on " or " being arranged at " another element, it can be directly another On one element or it is connected on another element.When an element is known as " being connected to " another element, it can To be directly to another element or be indirectly connected on another element.
It is to be appreciated that term " length ", " width ", " on ", " under ", "front", "rear", "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " top ", " bottom " " interior ", " outer " are to be closed based on orientation shown in the drawings or position System, is for only for ease of and describes the present invention and simplify description, rather than indicates or imply that signified device or element must have Specific orientation, with specific azimuth configuration and operation, therefore be not considered as limiting the invention.
In addition, term " first ", " second " are only used for description purpose, and it is not intended that instruction or hint relative importance Or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can be expressed or Implicitly include one or more this feature.In the description of the present invention, " multiple " are meant that two or more, Unless otherwise specifically defined.
Referring to Fig. 1, existing say the building structure provided by the invention that skyscraper is built suitable for tier building set It is bright.It is described to build the building structure of skyscraper suitable for tier building set, including the skyscraper 6 of the top of Old building 1 is arranged on, The skyscraper 6 is braced frame system, the braced frame system include frame column 2, base cross members 3 and several It is arranged at the truss crossbeam 7 of the top of base cross members 3, several truss crossbeams 7 of base cross members 3 and its top are parallel to each other interval Set, the frame column 2 is arranged at 1 surrounding of Old building, and the base cross members 3 are arranged at the top of Old building 1, the base cross members Cross-brace 4 is equipped between 3 truss crossbeams 7 adjacent thereto, between adjacent two truss crossbeams 7, the cross-brace 4 is close to both sides Frame column 2 is set, and truss upright-column 5 is equipped between the base cross members 3 and bottommost truss crossbeam 7.Wherein, base cross members and thereon The truss crossbeam of side is the identical girder truss of structure.The old of original masonry structure is built in by using braced frame system set More than building, built-loading and geological process can be born, be divided into two independent structures with the Old building of original masonry structure Unit.
The building structure provided by the invention that skyscraper is built suitable for tier building set, compared with prior art, not On the premise of removing existing tier building and normal use, creatively propose sandwich construction set and build high-rise technology, by Old building overcoat builds skyscraper, and the frame column of skyscraper is arranged on the surrounding of Old building, and the base cross members of top, truss are horizontal Beam, truss upright-column and cross-brace form braced frame system, meet in the case of Old building normal use, in Old building On by braced frame system realize that set is built plus layer, achieve the purpose that original place increasing layer enlarging, local integration.Utilize the present invention Solve the problems, such as to remove and the building waste that brings and found a room in the strange land, reduce investment outlay, meet the theory of Green Development, economic benefit society Can remarkable benefit.
When existing Old building depth is larger, braced frame system needs to apply prestressing force, to reduce structure section.
Further, also referring to Fig. 2,3, skyscraper is built suitable for tier building set as provided by the invention A kind of embodiment of building structure, the basis instrument of the adjacent foundation Old building 1 of the skyscraper 6 are described old to build The basis for building 1 is grey earth foundation 8, and the basis of the skyscraper 6 is multiple bored concrete piles 9, and the bored concrete pile 9 extends downward into ash In 8 lower section soil layer of earth foundation, the frame column 2 is arranged on the top of the bored concrete pile 9, ensures the strong of tall buildings basis Degree and rigidity.
Further, referring to Fig. 3, as the building knot provided by the invention that skyscraper is built suitable for tier building set A kind of embodiment of structure, the bored concrete pile 9 are club-footed pile, and the club-footed pile includes base expanding and base expanding portion 90, straight section portion 91 and stake Cap portion 92, the bottom absolute altitude in the pile cover portion 92 are not less than grey 8 bottom surface of earth foundation.It is also right while bored concrete pile stability is ensured Grey earth foundation plays build-in effect of contraction.
The maximum outer edge 93 in the base expanding and base expanding portion 90 of the club-footed pile ensures ash without departing from grey 8 inner edge of earth foundation, with this The stability of earth foundation;The width of the ash earth foundation 8 is a, and the 91 length H of straight section portion of the club-footed pile is more than 2a, by adding The length in big club-footed pile straight section portion, to reduce interference of the club-footed pile to grey earth foundation;The axis C of 1 wall of Old building and height Distance L between the axis D of layer 6 wall of building is 1500mm, can obtain the maximization of land use.
It should be noted in club-footed pile work progress:When excavating base expanding and base expanding pile foundation, along the bar shaped ash soil matrix of existing Old building Plinth, which excavates club-footed pile, to be needed to be spaced at least two position excavation, can be carried out after the pile foundation construction of the club-footed pile of excavation The pile foundation of adjacent club-footed pile is excavated and keeps the two stake positions in interval.The construction procedure of club-footed pile is as follows:
It is excavated to the bottom in club-footed pile base expanding and base expanding portion vertically first, i.e., at the 93 place plane of maximum outer edge in base expanding and base expanding portion;So The cone for carrying out the base expanding and base expanding portion immediately below bar shaped ash earth foundation afterwards is excavated, i.e. longitudinal section is the base expanding and base expanding portion of right angled triangle in Fig. 2 Excavate the initial segment 94;After surrounding's foundation soil acceptance(check) of the initial segment is excavated in base expanding and base expanding portion, the conical section and its surrounding of excavation protect Circle carries out casting concrete;When the strength grade of concrete of above-mentioned cast reaches design strength 50%-70%, it can continue by figure Paper excavates the remainder in base expanding and base expanding portion, after excavating acceptance(check), descending reinforcing cage and casting concrete.
Club-footed pile casting and constructing should be noted:For each several part of club-footed pile pour by several times, the concrete poured by several times Interface is answered dabbing and is cleaned out, and base expanding and base expanding portion should reserve interface when excavating the initial segment construction and connect short muscle.
Further, referring to Fig. 1, as the building knot provided by the invention that skyscraper is built suitable for tier building set A kind of embodiment of structure, 2 medial surface of frame column are equipped with the Preserved node 10 for being used for continuing part with the later stage and be connected, The Preserved node 10 is arranged on the lower section of base cross members 3., it is necessary to be continued below base cross members after lower section Old building is removed Build, can ensure the integral strength of skyscraper by Preserved node.
Further, also referring to Fig. 4-6, skyscraper is built suitable for tier building set as provided by the invention A kind of embodiment of building structure, the lower section of the base cross members 3 be equipped with 5 corresponding connecting node of truss upright-column, The connecting node includes being arranged at the concrete connection pier 12 of the lower section of base cross members 3, and 12 bottom of the connection pier, which is equipped with, to be used for The pre-embedded steel slab 14 that the downward column 13 in part is connected is continued with the later stage, the pre-embedded steel slab 14 passes through connection structure and the truss of top Column 5 and the downward column 13 of lower section are connected.Pre-embedded steel slab realizes that the connection with frame column and downward column is fixed by connection structure, Meet the design requirement of tall buildings antidetonation stress.
Further, also referring to Fig. 4-6, skyscraper is built suitable for tier building set as provided by the invention A kind of embodiment of building structure, the connection structure include dowel 15 and bar planting 16, and one end of the dowel 15 is set It is placed in the connection pier 12, the other end of the dowel 15 through the pre-embedded steel slab 14 and is fixed;The one of the bar planting 16 End is arranged in the downward column 13, and the other end of the bar planting 16 through the pre-embedded steel slab 14 and is implanted into the connection pier 12 And in truss upright-column 5.Realize that built-in fitting realizes pre-embedded steel slab and lower section with being connected the connection of pier, while using bar planting using dowel The connection of downward column, ensure that the downward stress conductive performance continued at downward column connected node of frame column is good.
Wherein, the length L ' that the bar planting 16 is extended into truss upright-column 5 is 120mm, can effectively ensure that truss upright-column With the bonding strength of downward column, the integral strengths of tall buildings is improved.
Further, also referring to Fig. 5,6, skyscraper is built suitable for tier building set as provided by the invention A kind of embodiment of building structure, the dowel 15 are arranged in the pre-embedded steel slab 14 for multiple and spacing parallel arranging Portion;The bar planting 16 is multiple and is arranged in the four corners position of the downward column 13.Dowel 15 is three in Fig. 5, in Fig. 6 Bar planting 16 is four, and the particular number of dowel and bar planting can also be determined according to actual conditions, ensures to connect by dowel and bar planting Being reliably connected for pier and downward column and pre-embedded steel slab is connect, while also ensure that the uniform conductive of bearing up-down force.
Further, also referring to Fig. 5,6, skyscraper is built suitable for tier building set as provided by the invention A kind of embodiment of building structure, the vertical muscle 1 in the truss upright-column 5 weld solid after the connection pier 12 It is scheduled on the upper surface of the pre-embedded steel slab 14;Vertical muscle 2 18 in the downward column 13 welds after 14 bottom surface bending of pre-embedded steel slab It is fixed on 14 lower surface of pre-embedded steel slab.It is welded and fixed after vertical muscle one end or bending with built-in fitting upper surface, indulges two end of muscle folding It is welded and fixed after curved with built-in fitting lower surface, is 110mm using two-sided welding, welding length, vertical power transmission is effectively ensured The integrality of connectivity and structure.
Further, a kind of tool as the building structure provided by the invention that skyscraper is built suitable for tier building set Body embodiment, perfusion is early between the top of the pre-embedded steel slab 14 and connection pier 12, between lower section and downward column 13 mends by force Repay shrinkage concrete.Early stage of the pre-embedded steel slab with being connected pier, downward intercolumniation concrete is improved by early strong expansive concrete Intensity, while can effectively prevent concrete cracking.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement made within refreshing and principle etc., should all be included in the protection scope of the present invention.

Claims (10)

1. the building structure of skyscraper is built suitable for tier building set, it is characterised in that:Including being arranged on above Old building Skyscraper, the skyscraper are braced frame system, the braced frame system include frame column, base cross members and Several are arranged at the truss crossbeam above base cross members, and the frame column is arranged at Old building surrounding, and the base cross members are set It is placed in above Old building, is equipped between base cross members truss crossbeam adjacent thereto, between adjacent two truss crossbeams tiltedly Dagger, the cross-brace are set close to both sides frame column, and truss upright-column is equipped between the base cross members and bottommost truss crossbeam.
2. the building structure of skyscraper is built suitable for tier building set as claimed in claim 1, it is characterised in that:The height The basis instrument of the adjacent foundation Old building of layer building, the basis of the Old building are grey earth foundation, the base of the skyscraper Plinth is multiple bored concrete piles, and the bored concrete pile is extended downward into dirt ground beneath soil layer, and the frame column is arranged on the filling Note the top of stake.
3. the building structure of skyscraper is built suitable for tier building set as claimed in claim 2, it is characterised in that:The filling Note stake is club-footed pile, and the club-footed pile includes base expanding and base expanding portion, straight section portion and pile cover portion, and the bottom absolute altitude in the pile cover portion is not less than dirt The bottom of foundation.
4. the building structure of skyscraper is built suitable for tier building set as claimed in claim 3, it is characterised in that:The expansion The maximum outer edge in the base expanding and base expanding portion of bottom stake is without departing from grey earth foundation inner edge;The width of the ash earth foundation is a, the club-footed pile Straight section minister's degree H be more than 2a.
5. the building structure of skyscraper is built suitable for tier building set as claimed in claim 1, it is characterised in that:The frame Trestle medial surface is equipped with the Preserved node for being used for continuing part with the later stage and be connected, and the Preserved node is arranged under base cross members Side.
6. such as claim 1-5 any one of them is suitable for the building structure that tier building set builds skyscraper, its feature exists In:Be equipped with below the base cross members includes being arranged at bottom with the corresponding connecting node of truss upright-column, the connecting node The concrete connection pier of below the crossbeam, the connection pier bottom portion is equipped with the pre-buried steel for being used for continuing the downward column in part with the later stage and be connected Plate, the pre-embedded steel slab are connected by connection structure with the truss upright-column of top and the downward column of lower section.
7. the building structure of skyscraper is built suitable for tier building set as claimed in claim 6, it is characterised in that:The company Binding structure includes dowel and bar planting, and one end of the dowel is arranged in the connection pier, and the other end of the dowel runs through institute State pre-embedded steel slab and fixation;One end of the bar planting is arranged in the downward column, and the other end of the bar planting is through described pre- Bury steel plate and be implanted into the connection pier and truss upright-column.
8. the building structure of skyscraper is built suitable for tier building set as claimed in claim 7, it is characterised in that:The anchor Muscle is arranged in the middle part of the pre-embedded steel slab for multiple and spacing parallel arranging;The bar planting is multiple and be arranged at the downward column Surrounding.
9. the building structure of skyscraper is built suitable for tier building set as claimed in claim 6, it is characterised in that:The purlin Erect the upper surface that the vertical muscle one in column is weldingly fixed on the pre-embedded steel slab after the connection pier;In the downward column Vertical muscle two is weldingly fixed on pre-embedded steel slab lower surface after the bending of pre-embedded steel slab bottom surface.
10. the building structure of skyscraper is built suitable for tier building set as claimed in claim 7, it is characterised in that:It is described Early strong expansive concrete is irrigated between the top of pre-embedded steel slab and connection pier, between lower section and downward column.
CN201711404153.2A 2017-12-22 2017-12-22 The building structure of skyscraper is built suitable for tier building set Pending CN107916798A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711404153.2A CN107916798A (en) 2017-12-22 2017-12-22 The building structure of skyscraper is built suitable for tier building set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711404153.2A CN107916798A (en) 2017-12-22 2017-12-22 The building structure of skyscraper is built suitable for tier building set

Publications (1)

Publication Number Publication Date
CN107916798A true CN107916798A (en) 2018-04-17

Family

ID=61893933

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711404153.2A Pending CN107916798A (en) 2017-12-22 2017-12-22 The building structure of skyscraper is built suitable for tier building set

Country Status (1)

Country Link
CN (1) CN107916798A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653534A (en) * 2019-02-18 2019-04-19 河北建筑设计研究院有限责任公司 Set building club-footed pile strip footing straining beam and set building
CN111502323A (en) * 2020-04-23 2020-08-07 璐句附 Building structure suitable for multi-storey building set-up high-rise building

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5174085A (en) * 1988-12-13 1992-12-29 Chinese Building Technology Services Corp. Ltd. Method of adding additional stories to an existing storied building
CN1759222A (en) * 2003-03-20 2006-04-12 株式会社天奇三公司 Anti-seismic reinforcement and expansion method for building and anti-seismically reinforced and expanded building
CN102140850A (en) * 2011-02-28 2011-08-03 东北石油大学 Frame with floors of composite grid structure and construction method thereof
EP2610418A1 (en) * 2011-12-27 2013-07-03 Neapo Oy Method for renovating a building and a building
CN103669598A (en) * 2013-12-30 2014-03-26 合肥工业大学 Layer added steel framework column base node on top of multi-layer concrete framework structure and construction method thereof
WO2015060807A1 (en) * 2013-10-21 2015-04-30 Kukharev Dmytro Ihorovych A secondary structure
CN207728018U (en) * 2017-12-22 2018-08-14 河北建筑设计研究院有限责任公司 The building structure of skyscraper is built suitable for tier building set

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5174085A (en) * 1988-12-13 1992-12-29 Chinese Building Technology Services Corp. Ltd. Method of adding additional stories to an existing storied building
CN1759222A (en) * 2003-03-20 2006-04-12 株式会社天奇三公司 Anti-seismic reinforcement and expansion method for building and anti-seismically reinforced and expanded building
CN102140850A (en) * 2011-02-28 2011-08-03 东北石油大学 Frame with floors of composite grid structure and construction method thereof
EP2610418A1 (en) * 2011-12-27 2013-07-03 Neapo Oy Method for renovating a building and a building
WO2015060807A1 (en) * 2013-10-21 2015-04-30 Kukharev Dmytro Ihorovych A secondary structure
CN103669598A (en) * 2013-12-30 2014-03-26 合肥工业大学 Layer added steel framework column base node on top of multi-layer concrete framework structure and construction method thereof
CN207728018U (en) * 2017-12-22 2018-08-14 河北建筑设计研究院有限责任公司 The building structure of skyscraper is built suitable for tier building set

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘慧珊等: "高层建筑桩基础工程技术", 中国建筑工业出版社, pages: 196 - 198 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109653534A (en) * 2019-02-18 2019-04-19 河北建筑设计研究院有限责任公司 Set building club-footed pile strip footing straining beam and set building
CN111502323A (en) * 2020-04-23 2020-08-07 璐句附 Building structure suitable for multi-storey building set-up high-rise building

Similar Documents

Publication Publication Date Title
CN102182325B (en) Storey adding method for existing building basement with frame structure and independent foundation
CN108487252A (en) A kind of deep foundation pit open cutting is suitable to make construction method
CN103321231A (en) Construction method of foundation pit support
CN101614019A (en) The multilayer underground structure next to existing building self-supporting construction method
CN108005399A (en) Add the construction method for building multi-layer underground space under a kind of existing building group
CN109944250A (en) The foundation pit of impermanent vertical support system is along inverse combining construction method
CN112982481B (en) Structure construction method for crossing subway intersection node on pipe gallery
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
CN108277996A (en) The construction method of multi-storey basement is extended under a kind of protection groups of building
CN105089670A (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN109403654A (en) A kind of underpinning method of existing building structure
CN104652444A (en) Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation
CN113482011B (en) Large-diameter PHC pipe pile and cast-in-situ bored pile combined foundation pit supporting structure and method
CN207728018U (en) The building structure of skyscraper is built suitable for tier building set
CN107916798A (en) The building structure of skyscraper is built suitable for tier building set
CN111622234B (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
CN110952563A (en) Temporary anti-floating structure for excavation of foundation pit above existing subway tunnel
CN207597914U (en) Add the construction stress structure for building multi-layer underground space under a kind of existing building group
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction
CN215483004U (en) Expansive soil stratum ultra-deep shaft supporting structure
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure
CN208981334U (en) Go along with sb. to guard him ruggedized construction in underground
CN110130399A (en) Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure
CN110130397A (en) Tilt hexagon piping lane system and its construction method of the supporting in conjunction with main structure
CN214460436U (en) Reinforced cushion layer supporting system for reinforcing local deep pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination