CN110130399A - Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure - Google Patents

Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure Download PDF

Info

Publication number
CN110130399A
CN110130399A CN201910407545.7A CN201910407545A CN110130399A CN 110130399 A CN110130399 A CN 110130399A CN 201910407545 A CN201910407545 A CN 201910407545A CN 110130399 A CN110130399 A CN 110130399A
Authority
CN
China
Prior art keywords
piping lane
main body
section
jurisdiction
trapezoidal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910407545.7A
Other languages
Chinese (zh)
Inventor
刁钰
郭勇志
郑刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201910407545.7A priority Critical patent/CN110130399A/en
Publication of CN110130399A publication Critical patent/CN110130399A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/08Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against transmission of vibrations or movements in the foundation soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to ground and basic engineering construction technical fields, disclose a kind of trapezoidal piping lane system and construction method that inclination supporting is combined with main structure, in the area using cut and cover tunneling, first squeeze into two rows of taper piles, two rows of taper piles are separately connected by crown beam of constructing again, soil layer between two rows of taper piles is excavated into open type foundation pit after carrying out taper pile supporting, tamps place;Then flute profile section of jurisdiction and/or folding shape section of jurisdiction are spliced to form trapezoidal piping lane main body, the gap between the oblique side wall of piping lane main body two and taper pile is filled with cement mortar, finally earthen backfill.The present invention combines the inclination supporting that slope uses with the oblique side wall of piping lane two of trapezoid cross section, inclination supporting can reduce piping lane side wall stress, help to mitigate piping lane long-term settlement, help to improve piping lane anti-seismic performance, the oblique side wall in trapezoid cross section two coincides with slope, backfill can be reduced, construction volume is reduced;And the contradiction between stress and space utilization rate has also been better balanced in the design of trapezoid cross section.

Description

Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure
Technical field
The invention belongs to ground and basic engineering construction technical fields, in particular to a kind of novel piping lane body System and its construction method.
Background technique
With China's rapid economic development, urbanization rate is substantially improved, and existing urban infrastructure is sent out with city The paces of exhibition are lacked of proper care, and pipe gallery construction in the case becomes most important.The structure design of pipe gallery engineering uses year Limit should be determining according to the reasonable using period of permanent structure, and not preferably less than 100 years.But in actual use, long-term settlement Piping lane joint can be made to be easy to happen leakage, infiltration can make piping lane accelerated sedimentation again, influence durability.In addition, piping lane is in earthquake Also it is easy to happen destruction under effect, since piping lane is embedded in underground, will result in heavy economic losses once occurring to destroy.Therefore right For piping lane construction, how to balance cost, stress, space utilization rate, durability is particularly important.
Pipe gallery cross-sectional form and property, capacity, geology, topographic features and construction according to receiving pipeline at present Mode, piping lane system can be divided into round and two kinds of section forms of box.Conventional circular section has respective with conventional rectangular section Advantage, but be all difficult to balance all aspects, it is mainly manifested in the following aspects:
First, in soft clay area, shallow embedding piping lane generally selects cut and cover tunneling.For conventional circular and rectangular section piping lane All it is first to be excavated with Vertical Pile supporting, again, inner support is set when excavating, by bracing demolition after piping lane installation, most Afterwards by earthen backfill.And inner support installation will expend huge human and material resources, but only play a role, using in the construction process Effect is unobvious in journey.
Second, although the piping lane of circular cross-section is advantageous in terms of stress performance, space utilization rate is low, coverage Greatly, speed of application is slow.
Third, the piping lane of rectangular section is compared to circular cross section, and space utilization rate is high, coverage is small, speed of application Fastly;But stress performance is poor, the stress at four angles is concentrated particularly evident.
Summary of the invention
What the present invention puted forth effort to solve is the underutilization of conventional rectangular, circular cross-section piping lane in service stage to vertical supporting And it is poor with shock resistance to cause long-term settlement larger, and the installation Yu dismounting of inner support will cause into cut and cover tunneling The technical issues of this waste, provides a kind of trapezoidal piping lane system and its construction method for tilting supporting in conjunction with main structure, The inclination supporting that slope uses is combined with the oblique side wall in piping lane bottom two of trapezoid cross section, inclination supporting can reduce piping lane side Wall stress helps to mitigate piping lane long-term settlement, helps to improve piping lane anti-seismic performance, the oblique side wall in trapezoid cross section two and slope phase It is overlapped, it is possible to reduce backfill reduces construction volume;And stress and space utilization rate has also been better balanced in the design of trapezoid cross section Between contradiction.
In order to solve the above-mentioned technical problem, the present invention is achieved by technical solution below:
A kind of trapezoidal piping lane system that inclination supporting is combined with main structure, including piping lane main body and inclination supporting;
The section of the piping lane main body be top margin be greater than bottom edge isosceles trapezoid, the piping lane main body in the longitudinal direction by Multiple segments are spliced, each segment be by two to four flute profile sections of jurisdiction and/or folding shape pipe sheet assembling at frame structure;
The inclination supporting includes the taper pile that piping lane main body two sides are arranged in, and two rows of taper piles are in piping lane main body two Side is symmetrical arranged and is close proximity to the oblique side wall of the piping lane main body two;It is filled between the taper pile and the oblique side wall of the piping lane main body two There is cement mortar;Crown beam is connected at the top of taper pile described in each row;
Before the piping lane main body construction, the soil layer between two rows of taper piles is dug out, and is excavated into open foundation pit;The piping lane master After body construction, earthen backfill between the oblique side wall of the piping lane main body two and the taper pile.
Further, the flute profile section of jurisdiction of the two neighboring segment of the piping lane main body and/or the folding shape section of jurisdiction are wrong Seam connection installation.
Further, the flute profile section of jurisdiction and/or the folding shape section of jurisdiction pass through track bolt lateral connection and longitudinally connected.
Further, the length of each segment of the piping lane main body is 2-3m.
Further, the trapezoidal top margin overall length in the section of the piping lane main body is 1.8-2.2 times of trapezoidal bottom edge overall length.
Further, water proof rubber pad is used between the two neighboring segment of the piping lane main body.
Further, the section of the piping lane main body is the isosceles trapezoid that upper and lower base angle is respectively 60 ° and 120 °, the pipe Each segment of corridor main body is assembled by two different flute profile sections of jurisdiction.
Further, the stake diameter of the taper pile is 600-800mm;The width of the crown beam is not less than the stake of the taper pile Diameter, the hat depth of beam are not less than 0.6 times of crown beam width.
A kind of construction method of trapezoidal piping lane system that the inclination supporting is combined with main structure, this method according to Lower step carries out:
(1) position for determining two rows of taper piles is designed according to piping lane, further according to tube lane dimension, with designing buried depth, the hydrology Matter condition estimates the buried depth and size of the taper pile, after carrying out setting-out, the two rows of taper piles of construction;
(2) assembling reinforcement, formwork are carried out according to design requirement on the basis of the reinforcing bar reserved at the top of the taper pile described in each row Plate pours the crown beam;
(3) excavation of foundation pit is carried out between two rows of taper piles, digs good compacting place later;
(4) the flute profile section of jurisdiction and/or the folding shape section of jurisdiction to foundation pit bottom are lifted, by the flute profile section of jurisdiction and/or described It rolls over shape section of jurisdiction and the piping lane main body is spliced by the track bolt;The piping lane main body is in the longitudinal direction by multiple segments Be spliced, each segment by two to four flute profile sections of jurisdiction and/or folding shape pipe sheet assembling at frame structure, the frame structure Section is the isosceles trapezoid that top margin is greater than bottom edge;
(5) cement bonded sand is injected in the gap between the oblique side wall of the piping lane main body two and the taper pile that assembly is completed Slurry, makes the piping lane main body combine closely with the taper pile;
(6) backfill construction is carried out between the piping lane body top and the taper pile.
The beneficial effects of the present invention are:
(1) present invention can be achieved to reduce long-term settlement: since pattern foundation pit supporting structure uses taper pile, and below taper pile insertion piping lane, In the long-term use, taper pile plays Unloading Effect, therefore can reduce the long-term settlement of piping lane, enhances the impervious of piping lane Ability improves the durability of piping lane.
(2) present invention can be achieved to improve piping lane anti-seismic performance: since piping lane and taper pile are close together, and taper pile is inserted Enter below piping lane, piping lane and taper pile can form an entirety, and the taper pile on both sides approximately forms a up-side down triangle, enhances The stability of piping lane system;When earthquake, piping lane and taper pile mass motion reduce the opposite changing of the relative positions of piping lane, to reduce earthquake Destruction.
(3) since foundation pit uses taper pile supporting, inner support, and taper pile conduct the achievable save the cost of the present invention: are eliminated Permanent supporting can share load for piping lane, reduce the stress of piping lane main structure side wall, to reduce workload, save Cost.
(4) contradiction between stress and space utilization rate, piping lane has been better balanced using trapezoid cross section piping lane in the present invention Main body uses trapezoid cross section, and more flat under same area, so buried depth is small, cost is substantially reduced.
Detailed description of the invention
Fig. 1 is the front view of trapezoidal piping lane system provided by a kind of optional embodiment of the invention;
Fig. 2 is the top view of trapezoidal piping lane system provided by a kind of optional embodiment of the invention;
Fig. 3 is the bolt of two kinds of flute profile sections of jurisdiction in trapezoidal piping lane system provided by a kind of optional embodiment of the invention Hole arrangement schematic diagram;(a) it is the flute profile section of jurisdiction 3 of one of them, is (b) two flute profile section of jurisdiction 3 wherein;
Fig. 4 is the connection schematic diagram of trapezoidal piping lane system center tap bolt provided by the present invention.
In above-mentioned figure: 1- taper pile, 2- crown beam, 3- flute profile section of jurisdiction, 4- cement mortar, 5- track bolt.
Specific embodiment
Below by specific embodiment, the present invention is described in further detail, and following embodiment can make this profession The present invention, but do not limit the invention in any way is more completely understood in technical staff.
As depicted in figs. 1 and 2, a kind of trapezoidal piping lane system for tilting supporting in conjunction with main structure is present embodiments provided And its construction method first squeezes into two rows of taper piles 1, then crown beam 2 of constructing divides two rows of taper piles 1 in the area using cut and cover tunneling It does not connect, is dug out the soil layer between two rows of taper piles 1 with excavator after carrying out 1 supporting of taper pile, excavate the foundation pit at open type, so Rear screed real field.Then it carries out flute profile section of jurisdiction 3 and/or rolls over the lifting and installation of shape section of jurisdiction, be spliced to form trapezoidal piping lane main body; Gap between the oblique side wall of piping lane main body two and taper pile 1 is filled with cement mortar 4, finally again earthen backfill.Flute profile section of jurisdiction as a result, 3 and/or folding shape section of jurisdiction constitute trapezoidal piping lane main body, taper pile 1 plays unloading effect to piping lane main body.
A kind of trapezoidal piping lane system of inclination supporting of the invention in conjunction with main structure includes piping lane main body and inclination branch Shield.The section of piping lane main body is the isosceles trapezoid that top margin is greater than bottom edge, and in general, the trapezoidal top margin in the section of piping lane main body is total 1.8-2.2 times of a length of trapezoidal bottom edge overall length.Piping lane main body is spliced by multiple segments in the longitudinal direction, each segment Length is 2-3m.Each segment of piping lane main body be by two to four flute profile sections of jurisdiction 3 and/or folding shape pipe sheet assembling at trapezoidal section Face frame structure.Fissure of displacement connection installation is answered in the two neighboring segment of piping lane main body, flute profile section of jurisdiction 3 and/or folding shape section of jurisdiction.
Flute profile section of jurisdiction 3 and folding shape section of jurisdiction are prefabricated component, are specifically designed according to the structure of trapezoidal piping lane main body, can be used two 3 assembly of flute profile section of jurisdiction or four folding shape pipe sheet assemblings or a flute profile section of jurisdiction 3 plus two folding shape pipe sheet assemblings;Flute profile section of jurisdiction 3 Long side, short side and side by constituting continuous broken line are constituted, and folding shape section of jurisdiction is made of the long side and short side for constituting broken line.Channel pipe Piece 3 and folding shape section of jurisdiction should be preset with hand hole in section of jurisdiction interior sidewall surface when prefabricated, are reserved in each hand hole and are connected to channel pipe 3 section of piece or the bolt hole for rolling over shape section of jurisdiction section, for laterally being connected flute profile section of jurisdiction 3 and/or folding shape section of jurisdiction by track bolt 5 Connect with it is longitudinally connected, the setting direction of track bolt 5 is parallel with flute profile section of jurisdiction 3 or folding shape section of jurisdiction surface.
Between the two neighboring segment of piping lane main body should use water proof rubber pad, and the precompression of water proof rubber pad do not answer it is small In 3MPa.Also, subsiding crack is arranged between two neighboring segment every 40-60 meters in piping lane main body.
The inclination supporting of unloading is played by being respectively arranged at two rows of taper piles 1 of piping lane main body two sides and every to piping lane main body The crown beam 2 connected at the top of one row's taper pile 1 is constituted.
Piping lane main body two sides are respectively arranged with row's taper pile 1, and two rows of taper piles 1 are symmetrical set in piping lane main body two sides. Taper pile 1 is close proximity to two oblique side walls of piping lane main body as far as possible, and essentially identical with two oblique sidewall slope angles of piping lane main body.It is two rows of Soil layer between taper pile 1 is dug out, and is excavated into open foundation pit.Ordinary circumstance is not required to carry out combined bolting and shotcrete to foundation pit, such as strong drop Situations such as rainy day gas or underground water are gushed out carries out combined bolting and shotcrete to foundation pit.The stake diameter of taper pile 1 is typically no less than 600mm, preferably For within the scope of 600-800mm, and the spacing of taper pile 1 should meet code requirement.For taper pile 1 in construction, reserved steel bar side is answered at top Just it is connect with crown beam 2.Gap between piping lane main body and taper pile 1 is filled with cement mortar 4, and strength of cement mortar should be greater than 10MPa。
The top of two rows of taper piles 1 is attached by crown beam 2 respectively, and the width (horizontal direction) of crown beam 2 is not preferably less than taper pile 1 Stake diameter, the height (vertical direction) of crown beam 2 is not preferably less than 0.6 times of 2 width of crown beam.The strength grade of concrete of crown beam 2 is suitable Greater than C25, and crown beam 2 should disconnect setting subsiding crack at a certain distance.
As depicted in figs. 1 and 2, in a kind of optional embodiment of the invention, the section of piping lane main body is upper bottom Angle is respectively the isosceles trapezoid of 60 ° and 120 °, and each segment of piping lane main body is assembled by two different flute profile sections of jurisdiction 3. Prefabricated 3 shape of flute profile section of jurisdiction is different, the flute profile section of jurisdiction 3 of one of them, and top margin length is the 1/3 of trapezoidal total top margin, bottom edge Length is the 2/3 of trapezoidal total bottom edge, and side is identical with trapezoidal total bottom edge length, and the angle of top margin and side is 60 °, side and bottom The angle on side is 120 °.The flute profile section of jurisdiction 3 of two wherein, top margin length are the 2/3 of trapezoidal total top margin, and bottom edge length is trapezoidal total The 1/3 of bottom edge, side is identical with trapezoidal total bottom edge length, and the angle of top margin and side is 60 °, the angle on side and bottom edge is 120°。
In this optional embodiment, the lateral connection of flute profile section of jurisdiction 3 is two flute profile sections of jurisdiction 3 in same segment It is assemblied into trapezoid cross section frame structure, the longitudinally connected of flute profile section of jurisdiction 3 is two neighboring above-mentioned trapezoid cross section frame structure Fissure of displacement connection.As shown in figure 3, the bolt hole for 3 lateral connection of flute profile section of jurisdiction is usually preset in 3 longitudinal direction of flute profile section of jurisdiction At intermediate and two back gauge edge 200-300mm, and the center for the bolt hole being correspondingly connected on two neighboring flute profile section of jurisdiction 3 away from For 300-400mm.The section for being usually reserved in flute profile section of jurisdiction 3 for rolling over the longitudinally connected bolt hole in shape section of jurisdiction 3, length are shorter Bottom edge or reserved one (centrally located) of top surface, the longer bottom edge of length or reserved two of top surface (are located at away from folding Position at angle 1/4 and at 3/4), side is two reserved (being located at two trisection point positions).Flute profile section of jurisdiction 3 spell it is good after according to Reserved bolt hole is attached, as shown in Figure 4 by track bolt 5.
The construction method of trapezoidal piping lane system of the above-mentioned inclination supporting in conjunction with main structure, specifically in accordance with the following steps into Row:
One, taper pile 1 positions
The position for determining taper pile 1 is designed according to piping lane, is come further according to tube lane dimension, design buried depth, hydrogeologic condition pre- The buried depth and size for estimating two rows of taper piles 1, finally carry out setting-out.
Two, taper pile 1 is constructed
First rigging up is overlapped drilling rod center, and gradient is adjusted by the design requirement of trapezoidal piping lane main body.Boring procedure Using normal circulation slewing drilling machine into construction technology, soil is suitably thrown less in clay layer, by creeping into voluntarily pulping, is then increased in sandy soils Concentration of hydraulic mixture Gu Bi.Borehole cleaning is carried out after drilling, is removed sediment all, is engaged concrete with basement rock intact, To improve stake bottom bearing capacity.The steel reinforcement cage integral hoisting that will be made again, casting concrete, steel reinforcement cage enter Kong Houzhi and pour coagulation The time that soil finishes is no more than 4 hours.
Three, crown beam 2 is constructed
Unwrapping wire is measured according to design requirement, then excavates groove, then digs 1 pile crown of taper pile, 1 pile crown of taper pile is cleared up and is done Only.Assembling reinforcement, formwork supporting plate are carried out according to design requirement on the basis of the reinforcing bar that taper pile 1 is reserved, then pours crown beam 2.
Four, excavation of foundation pit
Before excavation of foundation pit, pipe well points precipitation is set.According to design requirement, excavation of foundation pit is carried out between two rows of taper piles 1, It is excavated within top layer 6m with high-front shovel, 6m earthwork employment force-fitting excavator dress below;Dig good compacting place later. Situations such as ordinary circumstance is not required to carry out combined bolting and shotcrete to foundation pit, and such as heavy rainfall weather or underground water are gushed out, to foundation pit progress Combined bolting and shotcrete.
Five, flute profile section of jurisdiction 3 and/or the lifting of folding shape section of jurisdiction, assembly
The flute profile section of jurisdiction 3 being placed in beside foundation pit and/or folding shape section of jurisdiction are lifted to foundation pit bottom using crane, lifting is completed Flute profile section of jurisdiction 3 and/or folding shape section of jurisdiction are stitched together with track bolt 5 at reserved bolt hole afterwards.Each segment by two to Four flute profile sections of jurisdiction 3 and/or the splicing of folding shape section of jurisdiction, the piping lane principal length of each segment are 2-3m.Piping lane main body is longitudinal by more A segment is spliced, and water proof rubber pad should be arranged in the junction between segment, and the precompression of water proof rubber pad is no less than 3MPa.Subsiding crack is arranged between two neighboring segment every 40-60 meters in piping lane main body.
Six, gap slip casting
Cement mortar 4 is injected with conduit in gap between the oblique side wall of piping lane main body two and taper pile 1 that assembly is completed, is made Piping lane main body is combined closely with taper pile 1;The maximum pressure of slip casting is generally higher than 4MPa.
Seven, backfill
Backfill construction is carried out between piping lane body top and taper pile 1, the compactness to be met of banketing, moisture content etc. are wanted It asks, with earth scraper, scraper etc. to the method spread out and put on using layering of banketing, the thickness of every layer of paving soil should be according to soil property, compactness It is required that being determined with machine performance.When rolling, wheel (rammer) mark is mutually lapped, and anti-leak-stopping pressure, leakage are rammed.
Although the preferred embodiment of the present invention is described above in conjunction with attached drawing, the invention is not limited to upper The specific embodiment stated, the above mentioned embodiment is only schematical, be not it is restrictive, this field it is common Technical staff under the inspiration of the present invention, without breaking away from the scope protected by the purposes and claims of the present invention, may be used also By make it is many in the form of specific transformation, within these are all belonged to the scope of protection of the present invention.

Claims (9)

1. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure, which is characterized in that including piping lane main body and incline Oblique supporting;
The section of the piping lane main body is the isosceles trapezoid that top margin is greater than bottom edge, and the piping lane main body is in the longitudinal direction by multiple Segment is spliced, each segment be by two to four flute profile sections of jurisdiction and/or folding shape pipe sheet assembling at frame structure;
The inclination supporting includes the taper pile that piping lane main body two sides are arranged in, and two rows of taper piles are in piping lane main body two sides pair Claim setting and is close proximity to the oblique side wall of the piping lane main body two;Water is filled between the taper pile and the oblique side wall of the piping lane main body two Cement mortar;Crown beam is connected at the top of taper pile described in each row;
Before the piping lane main body construction, the soil layer between two rows of taper piles is dug out, and is excavated into open foundation pit;The piping lane main body is applied After work, earthen backfill between the oblique side wall of the piping lane main body two and the taper pile.
2. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure according to claim 1, feature exist In the flute profile section of jurisdiction of the two neighboring segment of the piping lane main body and/or folding shape section of jurisdiction fissure of displacement connection installation.
3. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure according to claim 1, feature exist Pass through track bolt lateral connection and longitudinally connected in, the flute profile section of jurisdiction and/or the folding shape section of jurisdiction.
4. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure according to claim 1, feature exist In the length of each segment of the piping lane main body is 2-3m.
5. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure according to claim 1, feature exist In the trapezoidal top margin overall length in the section of the piping lane main body is 1.8-2.2 times of trapezoidal bottom edge overall length.
6. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure according to claim 1, feature exist In using water proof rubber pad between the two neighboring segment of the piping lane main body.
7. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure according to claim 1, feature exist In the section of the piping lane main body is the isosceles trapezoid that upper and lower base angle is respectively 60 ° and 120 °, each section of the piping lane main body Section is assembled by two different flute profile sections of jurisdiction.
8. a kind of trapezoidal piping lane system that inclination supporting is combined with main structure according to claim 1, feature exist In the stake diameter of the taper pile is 600-800mm;The width of the crown beam is not less than the stake diameter of the taper pile, the height of the crown beam Degree is not less than 0.6 times of crown beam width.
9. a kind of trapezoidal piping lane system that the inclination supporting as described in any one of claim 1-8 is combined with main structure is applied Work method, which is characterized in that this method follows the steps below:
(1) position for determining two rows of taper piles is designed according to piping lane, further according to tube lane dimension, design buried depth, hydrogeological item Part estimates the buried depth and size of the taper pile, after carrying out setting-out, the two rows of taper piles of construction;
(2) assembling reinforcement, formwork supporting plate are carried out according to design requirement on the basis of the reinforcing bar reserved at the top of the taper pile described in each row, is poured Build the crown beam;
(3) excavation of foundation pit is carried out between two rows of taper piles, digs good compacting place later;
(4) the flute profile section of jurisdiction and/or the folding shape section of jurisdiction to foundation pit bottom are lifted, by the flute profile section of jurisdiction and/or the folding shape Section of jurisdiction is spliced into the piping lane main body by the track bolt;The piping lane main body is spliced by multiple segments in the longitudinal direction It forms, each segment is by two to four flute profile sections of jurisdiction and/or folding shape pipe sheet assembling at frame structure, the section of the frame structure It is greater than the isosceles trapezoid on bottom edge for top margin;
(5) cement mortar is injected in the gap between the oblique side wall of the piping lane main body two and the taper pile that assembly is completed, made The piping lane main body is combined closely with the taper pile;
(6) backfill construction is carried out between the piping lane body top and the taper pile.
CN201910407545.7A 2019-05-15 2019-05-15 Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure Pending CN110130399A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910407545.7A CN110130399A (en) 2019-05-15 2019-05-15 Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910407545.7A CN110130399A (en) 2019-05-15 2019-05-15 Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure

Publications (1)

Publication Number Publication Date
CN110130399A true CN110130399A (en) 2019-08-16

Family

ID=67574606

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910407545.7A Pending CN110130399A (en) 2019-05-15 2019-05-15 Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure

Country Status (1)

Country Link
CN (1) CN110130399A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110700649A (en) * 2019-09-08 2020-01-17 宁波西沃工程科技有限公司 Construction method of buried transformer substation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485351A (en) * 2013-09-30 2014-01-01 中国建筑股份有限公司 Inclined pile vertical anchor rod supporting structure for foundation pit supporting and construction method thereof
CN103882869A (en) * 2014-03-21 2014-06-25 郭永 Inclined supporting pile structure for foundation pit support and construction method thereof
WO2018076499A1 (en) * 2016-10-31 2018-05-03 浙江鑫宙竹基复合材料科技有限公司 Pipe segment connecting component suitable for comprehensive bamboo composite pipe gallery
CN208857818U (en) * 2018-08-14 2019-05-14 四川农业大学 A kind of trapezoidal channel hole steel sheep pile support structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485351A (en) * 2013-09-30 2014-01-01 中国建筑股份有限公司 Inclined pile vertical anchor rod supporting structure for foundation pit supporting and construction method thereof
CN103882869A (en) * 2014-03-21 2014-06-25 郭永 Inclined supporting pile structure for foundation pit support and construction method thereof
WO2018076499A1 (en) * 2016-10-31 2018-05-03 浙江鑫宙竹基复合材料科技有限公司 Pipe segment connecting component suitable for comprehensive bamboo composite pipe gallery
CN208857818U (en) * 2018-08-14 2019-05-14 四川农业大学 A kind of trapezoidal channel hole steel sheep pile support structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110700649A (en) * 2019-09-08 2020-01-17 宁波西沃工程科技有限公司 Construction method of buried transformer substation

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104452809B (en) A kind of super shallow tunnel cover and cut construction method
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN105862930B (en) A kind of protection structure to creating existing tunnel below underground engineering
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN106958256A (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN102359046A (en) High fill subgrade connection method
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN102995659B (en) Method for constructing from central area to periphery of ultra-large type underground engineering
CN104895111B (en) The construction method of integrated pipe canal in weak soil ground
CN110685286A (en) Deep foundation pit supporting construction process for adjacent road under complex geological condition
CN109538246A (en) Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN107023027A (en) A kind of building concentration zones large-scale well-sinking construction method
CN101597888B (en) Construction method of municipal drainage culvert sinking trough
CN111042053A (en) Permanent temporary combined retaining wall structure in urban hydraulic engineering and construction method thereof
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN112064751A (en) Deep groove construction method for drainage pipeline
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN108457289A (en) A kind of open caisson construction method of complex condition
CN107165173A (en) A kind of foundation pit supporting system and its construction method
CN104712341B (en) Bed shallow covering shield driving stratum consolidation system and its construction method
CN209324377U (en) Ledge method tunneling subway station arch springing ruggedized construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190816

WD01 Invention patent application deemed withdrawn after publication