CN110685286A - Deep foundation pit supporting construction process for adjacent road under complex geological condition - Google Patents

Deep foundation pit supporting construction process for adjacent road under complex geological condition Download PDF

Info

Publication number
CN110685286A
CN110685286A CN201911004456.4A CN201911004456A CN110685286A CN 110685286 A CN110685286 A CN 110685286A CN 201911004456 A CN201911004456 A CN 201911004456A CN 110685286 A CN110685286 A CN 110685286A
Authority
CN
China
Prior art keywords
foundation pit
rock
support
supporting
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911004456.4A
Other languages
Chinese (zh)
Inventor
邓利平
冉华
廖荣
胡宗峰
万轶
万昭
李伟
张骏程
李宇
康旆
王贝
廖勇
吴加洋
郭啸天
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd, Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN201911004456.4A priority Critical patent/CN110685286A/en
Publication of CN110685286A publication Critical patent/CN110685286A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/08Restraining of underground water by employing open ditches arranged below the level of the water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Abstract

The invention discloses a deep foundation pit supporting construction process of an adjacent road under a complex geological condition, which comprises the following steps: step 1, excavating a foundation pit beside a road to a rock layer, and performing slope releasing construction to form a first foundation pit; step 2, driving a first column pile along the edge of the bottom of the first foundation pit to form a first inclined column support; step 3, excavating a rock stratum at the bottom of the first foundation pit to form a second foundation pit, carrying out slope releasing construction, and then carrying out anchor rod support; and 4, drilling a second column pile along the edge of the bottom of the second foundation pit to form a second inclined column support. According to the invention, the deep foundation pit is supported by adopting the modes of the inclined column support, the anchor bolt support and the inclined column support, so that the problems of difficulty in supporting the deep foundation pit of the adjacent road under the complex geological condition, high construction cost, easiness in potential safety hazard and the like are solved, the deep foundation pit support construction of the adjacent road under the complex geological condition is realized, and successful practical experience is provided for the field of support construction.

Description

Deep foundation pit supporting construction process for adjacent road under complex geological condition
Technical Field
The invention relates to the technical field of foundation pit supporting construction, in particular to a deep foundation pit supporting construction process of an adjacent road under a complex geological condition.
Background
The foundation pit supporting is a temporary measure for supporting, reinforcing, protecting and controlling underground water, which is adopted for the side wall of the foundation pit and the surrounding environment in order to ensure the safety of the underground structure construction and the surrounding environment of the foundation pit, the foundation pit supporting engineering is a temporary engineering, the designed safety reserve is relatively small, but the construction cost is high, the number of the construction work is large, the technology is complex, the construction engineering is the most challenging technical difficulty in the building engineering, and meanwhile, the construction cost is reduced, and the key point of the engineering quality is ensured.
The foundation pit supporting forms mainly include row pile supporting, cement retaining walls, soil nailing walls, underground continuous wall supporting, reverse arch walls and the like, generally, the foundation pit supporting forms are different in application according to different depths of foundation pits, however, for deep foundation pit supporting under complex geological conditions, the geological conditions are basically soft and hard geological stratification and are always key points and difficulties of a construction party, and how to apply the foundation pit supporting forms, the foundation pit supporting forms need to be determined according to the specific complex geological conditions of the deep foundation pits. Taking the CLZF-2 standard engineering from the Cheng lan railway Cheng Du to the Chuan main temple as an example, when building the projects of Huangshengguan and Chuan main temple station houses, the site temporary site is narrow, the line distance between the excavation lines of the foundation pit and the site temporary road is about 50cm, the depth of the foundation pit exceeds 5m, the geological conditions are complex, the upper part of the stratum is a loose soil layer with high humidity, and the lower part is a hard and compact rock layer, if the conventional continuous vertical retaining plate support (the horizontal retaining plate is not suitable for the foundation pit with the depth of more than 5 m) is adopted, the vertical retaining plate can not effectively play a retaining role because the soil layer is only 2-3m and the reason of the adjacent road, the wall of the foundation pit is not suitable for being made into a vertical type, the soil body is easy to deform and collapse under the pressure, correspondingly, if the existing pile arranging structure is adopted, the shearing force borne by the concrete cast-in-situ pile, nor can an effective supporting function be formed. Therefore, the traditional single supporting form cannot form an effective supporting structure, and if a supporting form is used in combination, because no referential example exists, according to the characteristics of each supporting form, technical personnel can think that the problem is solved by adopting a continuous vertical retaining plate supporting and pile row supporting mode, however, the main defects of the mode are that a rock layer is not a vertical slope-laying structure, so that a large gap exists between a rock layer side slope and a pile row, a large amount of soil body needs to be backfilled for filling, the construction amount is large, the later-period cleaning is troublesome, meanwhile, because the depth is deeper, a cast-in-place pile with higher height needs to be manufactured, the construction cost is high, and when the side slope is broken and rolled stones occur, the shearing force of the pile row is too large to intercept, so that the potential safety hazard is easy to occur, therefore, the mode is not suitable for developing, and suitable for the complex geological conditions, especially under the condition that the side slope surface is close to the road, a construction process for deep foundation pit support.
Disclosure of Invention
The invention aims to: aiming at the existing problems, the invention provides a deep foundation pit supporting construction process of an adjacent road under a complex geological condition.
The technical scheme adopted by the invention is as follows: a deep foundation pit supporting construction process for an adjacent road under a complex geological condition is characterized by comprising the following steps:
step 1, excavating a foundation pit beside a road until the bottom of the foundation pit reaches a rock layer, and meanwhile, carrying out slope releasing construction on the formed foundation pit to form a first foundation pit;
step 2, driving a first column pile along the edge of the bottom of the first foundation pit, supporting a soil retaining plate on the inner side of the first column pile and supporting the soil retaining plate with a first inclined strut, and filling soil on the inner side of the soil retaining plate and tamping the soil retaining plate to form a first inclined strut;
step 3, excavating a rock layer at the bottom of the first foundation pit to form a second foundation pit, wherein the distance between an excavation starting point and the first inclined column support is 0.5-2m, the excavation depth is up to the design depth, meanwhile, slope releasing construction is carried out on the formed foundation pit, and then anchor rod support is carried out on the rock slope of the second foundation pit according to the existing anchor rod support construction standard;
and 4, driving a second column pile along the edge of the bottom of the second foundation pit, supporting a stone blocking plate on the inner side of the second column pile, and supporting by using a second inclined strut to form a second inclined strut support.
In the method, firstly, for the construction of a deep foundation pit with a soft and hard geological structure, a mode of excavating the foundation pit in layers is adopted for supporting, and the problem of different geological conditions is solved by a mode of supporting in layers, so that the defect that the same supporting structure cannot be suitable for different geological conditions is avoided, furthermore, by designing and adopting a mode of inclined column supporting, anchor rod supporting and inclined column supporting, inclined column supporting is adopted at the uppermost layer of the geology, side supporting is provided for a roadbed, the problem that loose foundation soil around the roadbed collapses under the action of heavy pressure and rainwater is avoided, the influence of the foundation pit on the strength of the roadbed of the road is reduced, the influence of the dispersed foundation soil falling into a second foundation pit is also prevented, good construction conditions are provided for forming a supporting structure of the second foundation pit, anchor rod supporting is adopted in a rock layer (hard layer), and the problems that the rock layer collapses and large rocks fall off are mainly prevented, meanwhile, the inclined column support is matched with the inclined column support at the bottom of the second foundation pit, so that the problem of second foundation pit support is solved, the mode of row pile support with a high-column pile structure is avoided, the backfilling soil amount and the construction cost are greatly reduced, potential safety hazards are eliminated, meanwhile, the problem that effective matching cannot be formed among all support structures when various support structures are combined and used is integrally solved, the deep foundation pit support construction close to a road under complex geological conditions is realized, and successful practical experience is provided for the field of support construction.
Furthermore, the rubble of considering the rock stratum side slope to roll off can form the impact to the stake of second batter post support, especially second stake and foundation ditch pit bottom junction, and the stress concentration degree that its formed is great, and the fill soil tamp forms the buffering soil layer between fender slabstone and rock stratum side slope to solve the rubble and strike second stake and cause the problem of junction stress concentration.
Furthermore, in consideration of the problems of convenience in tamping soil backfilling at the early stage and clearing away at the later stage, the backfilling height of the buffer soil layer is 2/5-3/5 of the height of the second column pile, so that the basic effect of the buffer soil layer can be guaranteed while the backfilling tamping soil amount is reduced as much as possible.
In the invention, because the deep foundation pit supporting construction is adopted, the problem of rock seepage can occur in the rock stratum part, in order to facilitate the removal of the part of water, a drainage ditch is dug at the joint of the rock stratum side slope and the pit bottom of the second foundation pit, the drainage ditch forms a ring along the joint, a cover plate with a through hole or a through groove is laid at the top of the drainage ditch, and the buffer soil layer is positioned on the cover plate. The infiltration of rock stratum side slope permeates to the escape canal in through buffer soil layer, then leads to drainage department through the escape canal, has solved the adverse effect of rock infiltration to the foundation ditch.
Further, in order to better perform the slope releasing construction of the second foundation pit, the slope releasing gradient of the slope releasing construction of the second foundation pit is 1: 0.25.
Further, in step 4, the anchor rod construction is preferably: drilling a hole on the vertical wall of the rock to a designed depth, placing a pull rod in the hole, pouring cement mortar to combine the cement mortar and the rock into an anchor rod with strong tensile resistance, wherein one end of the anchor rod is fixed on the rock wall, and the other end of the anchor rod is anchored in a rock layer, so that the anchor rod support is formed.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that: according to the invention, the deep foundation pit is supported by adopting the modes of the inclined column support, the anchor bolt support and the inclined column support, so that the problems of difficulty in supporting the deep foundation pit of the adjacent road under the complex geological condition, high construction cost, easiness in potential safety hazard and the like are solved, the deep foundation pit support construction of the adjacent road under the complex geological condition is realized, and successful practical experience is provided for the field of support construction.
Drawings
Fig. 1 is a schematic diagram of a deep foundation pit supporting structure of an adjacent road under a complex geological condition. The labels in the figure are: 1 is the road bed, 2 is first foundation ditch, 3 is the second foundation ditch, 4 is the rock layer, 5 is first batter post supports, 501 is first post stake, 502 is the fender breast board, 503 is first bracing, 504 is wooden vaulting pole, 6 is backfill layer, 7 is the bracing platform, 8 is anchor bolt support, 9 is second batter post support, 901 is the second post stake, 902 is the fender stone slab, 903 is the second bracing, 10 is the buffering soil layer, 11 is the escape canal, 12 is the foundation soil layer.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Examples
Taking CLZF-2 standard engineering from Chengdu railway Chengdu to Chuan main temple section accepted by an applicant as an example, the engineering comprises 5 station buildings including a Mao county station, a Zhenjiangguan station, a Pan station, a Chuan main temple station and a Huangshengguan station, wherein when the engineering of the Huangshengguan and the Chuan main temple station buildings is built, a site temporary site is narrow, a foundation pit excavation line is about 50cm away from the site temporary road, the depth of the foundation pit exceeds 5m, the geological condition is complex, the upper part of the stratum is a loose soil layer with high humidity, the lower part of the stratum is a hard and compact rock layer, and the traditional supporting structure cannot be applied, in order to solve the problem, as shown in figure 1, the deep foundation pit supporting construction process adopted by the invention comprises the following steps:
step 1, excavating a foundation pit beside a road subgrade 1 until the bottom of the foundation pit reaches a rock stratum 5, namely excavating 2-3m until a relatively soft foundation soil layer is excavated, and meanwhile, carrying out slope releasing construction on the formed foundation pit to form a first foundation pit 2, wherein the slope releasing construction is selected according to the slope gradient and the slope coefficient of the side slope according to the original design requirement, for example, the ratio of 1:0.5 can be adopted in the embodiment;
step 2, a first column pile 501 is arranged along the edge of the first foundation pit, a soil retaining plate 502 is erected on the inner side of the first column pile 501 and supported by a first inclined strut 503, soil is filled and tamped on the inner side of the soil retaining plate to form a first inclined column support 5, and a rammed soil layer forms a backfill layer 6;
step 3, excavating a rock layer 5 at the bottom of the first foundation pit 2 to form a second foundation pit 3, wherein the distance between an excavation starting point and a first inclined strut is 0.5-2m (in the embodiment, the distance between the excavation starting point and the first inclined strut is 1.5m is most appropriate), an inclined strut platform 7 is formed, the excavation depth of the second foundation pit 3 reaches the design depth of 3m, when the second foundation pit 3 is excavated, slope releasing construction needs to be carried out on the second foundation pit 3, and the slope releasing gradient of the slope releasing construction is 1: 0.25;
step 4, according to the existing anchor bolt support construction standard, performing anchor bolt support 8 on the rock vertical wall of the second foundation pit, namely drilling a hole on the rock vertical wall to a designed depth, placing a pull rod in the hole, pouring cement mortar and combining the cement mortar and the rock into a steel bar anchor bolt with strong tensile resistance, wherein one end of the steel bar anchor bolt is fixed on the rock wall, and the other end of the steel bar anchor bolt is anchored in the rock layer, and protecting the stability of the rock slope through anchor bolt support (the steel bar anchor bolt support is a preferred example, and other anchor bolt support structures, such as a steel wire rope mortar anchor bolt support or a pipe seam type anchor bolt support;
and 5, driving a second column 901 along the edge of the bottom of the second foundation pit 3, supporting a stone baffle plate 902 on the inner side of the second column 901, and supporting by using a second diagonal brace 903 to form a second diagonal brace 9.
In the above construction process, the first batter post support 5 adopted in the first foundation pit 2 is an existing and common batter post support structure, and the construction requirements and construction operations thereof are performed according to existing standards, that is, the soil retaining plate 902 is fixed on the inner side of the first post pile 501, the outer side of the first post pile 501 is supported by the first batter brace 503, the bottom end of the first batter brace 503 is on the wooden support pile 504, and the inner side of the soil retaining plate 502 is backfilled with soil, which will not be described in detail herein. Correspondingly, the second batter post support adopted in the second foundation pit 3 is also an existing common batter post support structure, and it is only required to be executed according to the existing construction standard. In order to better enable the second inclined column support to play a role of supporting the blocking stones, the blocking boards 502 are replaced by concrete or steel blocking boards 902 with higher material strength, and backfill forming a backfill layer 6 on the inner sides of the blocking boards 902 is not needed.
Further, considering that the crushed stones falling from the side slope of the rock layer 4 may impact the second piles 901 of the second batter post supports 9, and particularly, the stress concentration formed at the joints of the second piles 901 and the bottom of the foundation pit is relatively large, as shown in fig. 1, a buffer soil layer 10 is formed by filling and tamping soil between the stone blocking plate 902 and the side slope of the rock layer 4 to solve the problem of stress concentration at the joints caused by the crushed stones impacting the piles.
Further, in consideration of the problems of convenience in rammed soil backfilling at the early stage and clearing away at the later stage, the backfilling height of the buffer soil layer 10 is between 2/5 and 3/5 of the height of the second column pile 901, which can be 2/5, 5/10 or 3/5, and the specific value is selected according to the actual situation, so that the arrangement mode can reduce the backfilling ramming soil amount as much as possible and ensure the basic function of the buffer soil layer 10.
In the invention, because the deep foundation pit supporting construction is adopted, the problem of rock water seepage can occur at the rock layer 4 part, in order to remove the part of water, a drainage ditch 11 is dug at the joint of the rock layer 4 side slope and the pit bottom of the second foundation pit 3, the drainage ditch 11 forms a ring along the joint, a cover plate (not shown in the figure) with a through hole or a through groove is paved at the top of the drainage ditch 11, and the buffer soil layer 10 is positioned on the cover plate. The infiltration of 4 slopes on rock layer permeates to escape canal 11 in through buffer soil layer 10, then leads to drainage department through escape canal 11, has solved the adverse effect of rock infiltration to the foundation ditch.
In the construction process, the construction process is suitable for deep foundation pit supporting construction with two types of soft and hard stratum structures when a deep foundation pit is excavated, namely, when the rock layer in the embodiment is changed into a hard soil layer, the construction process is also suitable, the deep foundation pit is supported by adopting a mode of inclined column support, anchor rod support and inclined column support, the problems that the deep foundation pit of a near road under a complex geological condition is difficult to support, the construction cost is high, potential safety hazards are easy to occur and the like are solved, the deep foundation pit supporting construction of the near road under the complex geological condition is realized, and successful practical experience is provided for the supporting construction field.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (6)

1. A deep foundation pit supporting construction process for an adjacent road under a complex geological condition is characterized by comprising the following steps:
step 1, excavating a foundation pit beside a road until the bottom of the foundation pit reaches a rock layer, and meanwhile, carrying out slope releasing construction on the formed foundation pit to form a first foundation pit;
step 2, driving a first column pile along the edge of the bottom of the first foundation pit, supporting a soil retaining plate on the inner side of the first column pile and supporting the soil retaining plate with a first inclined strut, and filling soil on the inner side of the soil retaining plate and tamping the soil retaining plate to form a first inclined strut;
step 3, excavating a rock layer at the bottom of the first foundation pit to form a second foundation pit, wherein the distance between an excavation starting point and the first inclined column support is 0.5-2m, the excavation depth is up to the design depth, meanwhile, slope releasing construction is carried out on the formed foundation pit, and then anchor rod support is carried out on the rock slope of the second foundation pit according to the existing anchor rod support construction standard;
and 4, driving a second column pile along the edge of the bottom of the second foundation pit, supporting a stone blocking plate on the inner side of the second column pile, and supporting by using a second inclined strut to form a second inclined strut support.
2. The process of claim 1, wherein a buffer soil layer is formed between the stone blocking plate and the rock slope by filling and tamping.
3. A deep foundation pit supporting construction process for an adjacent road under complex geological conditions as claimed in claim 2, wherein the backfill height of the buffer soil layer is 2/5-3/5 of the height of the second column pile.
4. A deep foundation pit supporting construction process near roads under complex geological conditions as claimed in claim 1 or 3, wherein a drainage ditch is dug at the junction of the rock layer side slope and the bottom of the second foundation pit, a cover plate with through holes or through grooves is laid on the top of the drainage ditch, and the buffer soil layer is positioned on the cover plate.
5. A deep foundation pit supporting construction process for an adjacent road under complex geological conditions as claimed in claim 1, wherein the slope of the slope releasing construction of the second foundation pit is 1: 0.25.
6. A deep foundation pit supporting construction process for an adjacent road under complicated geological conditions as claimed in claim 1, wherein a hole is drilled to a designed depth in the vertical wall of the rock, a tie rod is placed in the hole, cement mortar is poured into the hole to combine with the rock into an anchor rod with strong tensile strength, one end of the anchor rod is fixed on the rock wall, and the other end of the anchor rod is anchored in the rock layer, thereby forming the anchor rod support.
CN201911004456.4A 2019-10-22 2019-10-22 Deep foundation pit supporting construction process for adjacent road under complex geological condition Pending CN110685286A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911004456.4A CN110685286A (en) 2019-10-22 2019-10-22 Deep foundation pit supporting construction process for adjacent road under complex geological condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911004456.4A CN110685286A (en) 2019-10-22 2019-10-22 Deep foundation pit supporting construction process for adjacent road under complex geological condition

Publications (1)

Publication Number Publication Date
CN110685286A true CN110685286A (en) 2020-01-14

Family

ID=69113662

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911004456.4A Pending CN110685286A (en) 2019-10-22 2019-10-22 Deep foundation pit supporting construction process for adjacent road under complex geological condition

Country Status (1)

Country Link
CN (1) CN110685286A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111101524A (en) * 2020-01-17 2020-05-05 龚大娇 Temporary supporting structure for foundation pit construction and temporary supporting construction method
CN111305237A (en) * 2020-03-05 2020-06-19 中煤科工集团重庆设计研究院有限公司 Slope supporting structure and construction method
CN112211199A (en) * 2020-04-06 2021-01-12 广东华星建设集团有限公司 Large deep foundation pit supporting construction structure and method thereof
CN112663622A (en) * 2020-12-16 2021-04-16 深圳市宏源建设工程有限公司 Anti-seepage construction method for anchor cable in deep foundation pit supporting engineering
CN112813984A (en) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN113668556A (en) * 2021-08-05 2021-11-19 深圳市盛业建筑科技(集团)有限公司 Double-row pile supporting method for adding connecting beams in soil layer

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202323960U (en) * 2011-11-23 2012-07-11 天津住宅集团建设工程总承包有限公司 Shallow foundation pit forming construction structure capable of ensuring slope stability
CN203741848U (en) * 2013-12-25 2014-07-30 深圳市工勘岩土工程有限公司 Steel tube plate type retaining structure
KR20160097486A (en) * 2015-02-09 2016-08-18 한국도로공사 Road drainage facility and construction methods accordingly
CN107419737A (en) * 2017-08-25 2017-12-01 中铁建设集团有限公司 A kind of steel tube for soil-nail slope retaining structure and method
CN108560572A (en) * 2018-04-12 2018-09-21 中铁上海工程局集团有限公司 A kind of construction method of extra-high support system
CN108842784A (en) * 2018-07-04 2018-11-20 上海建工七建集团有限公司 A kind of shallow foundation hole slope protecting device and means of defence excavated for slope
CN208136928U (en) * 2018-04-24 2018-11-23 河南建筑材料研究设计院有限责任公司 A kind of non-metal mine side slope soil-baffling structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202323960U (en) * 2011-11-23 2012-07-11 天津住宅集团建设工程总承包有限公司 Shallow foundation pit forming construction structure capable of ensuring slope stability
CN203741848U (en) * 2013-12-25 2014-07-30 深圳市工勘岩土工程有限公司 Steel tube plate type retaining structure
KR20160097486A (en) * 2015-02-09 2016-08-18 한국도로공사 Road drainage facility and construction methods accordingly
CN107419737A (en) * 2017-08-25 2017-12-01 中铁建设集团有限公司 A kind of steel tube for soil-nail slope retaining structure and method
CN108560572A (en) * 2018-04-12 2018-09-21 中铁上海工程局集团有限公司 A kind of construction method of extra-high support system
CN208136928U (en) * 2018-04-24 2018-11-23 河南建筑材料研究设计院有限责任公司 A kind of non-metal mine side slope soil-baffling structure
CN108842784A (en) * 2018-07-04 2018-11-20 上海建工七建集团有限公司 A kind of shallow foundation hole slope protecting device and means of defence excavated for slope

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111101524A (en) * 2020-01-17 2020-05-05 龚大娇 Temporary supporting structure for foundation pit construction and temporary supporting construction method
CN111305237A (en) * 2020-03-05 2020-06-19 中煤科工集团重庆设计研究院有限公司 Slope supporting structure and construction method
CN112211199A (en) * 2020-04-06 2021-01-12 广东华星建设集团有限公司 Large deep foundation pit supporting construction structure and method thereof
CN112663622A (en) * 2020-12-16 2021-04-16 深圳市宏源建设工程有限公司 Anti-seepage construction method for anchor cable in deep foundation pit supporting engineering
CN112663622B (en) * 2020-12-16 2022-02-08 深圳市宏源建设工程有限公司 Anti-seepage construction method for anchor cable in deep foundation pit supporting engineering
CN112813984A (en) * 2020-12-31 2021-05-18 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN112813984B (en) * 2020-12-31 2022-07-29 攀钢集团工程技术有限公司 Deep foundation pit construction method under complex geological condition
CN113668556A (en) * 2021-08-05 2021-11-19 深圳市盛业建筑科技(集团)有限公司 Double-row pile supporting method for adding connecting beams in soil layer

Similar Documents

Publication Publication Date Title
CN110685286A (en) Deep foundation pit supporting construction process for adjacent road under complex geological condition
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
US8898996B2 (en) Method for forming a retaining wall, and corresponding retaining wall
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN112554198B (en) Construction method of deep foundation pit protection structure adjacent to high-rise building
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
WO2023213117A1 (en) Widening structure and construction method for existing subgrade embankment wall section near river
CN110777836A (en) Reinforced concrete plate-anchor rod composite foundation and using method thereof
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN111576454A (en) Combined protective structure for side slope retaining wall and steel pipe pile and construction method thereof
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN110847207A (en) Structure and construction method for newly-built bridge with subway tunnel passing through existing bridge piles
CN101215840A (en) Airplane-type foundation reinforcement given-force construction method
CN211080248U (en) Deep foundation pit supporting structure of adjacent road under complex geological condition
CN111021378A (en) Highway subgrade slope broken line type anchoring pile retaining structure and construction method thereof
CN110939142A (en) Roadbed structure for side slope
CN211340742U (en) Anti-settlement foundation
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
CN210315650U (en) Anchor rod reinforced composite retaining wall
Mangushev et al. Construction of deep foundation ditch under a reconstructed multi-storey building on the main avenue of St. Petersburg

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination