CN209723230U CN201920222518.8U CN201920222518U CN209723230U CN 209723230 U CN209723230 U CN 209723230U CN 201920222518 U CN201920222518 U CN 201920222518U CN 209723230 U CN209723230 U CN 209723230U
Authority
CN
China
Prior art keywords
steel plate
shear wall
combined shear
plate combined
baselines
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201920222518.8U
Other languages
Chinese (zh)
Inventor
余周
薛尚铃
罗福盛
陶修
程振宇
沈琪雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CISDI Engineering Co Ltd
Original Assignee
CISDI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CISDI Engineering Co Ltd filed Critical CISDI Engineering Co Ltd
Priority to CN201920222518.8U priority Critical patent/CN209723230U/en
Application granted granted Critical
Publication of CN209723230U publication Critical patent/CN209723230U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The connecting node of higher baselines is not waited the utility model discloses a kind of steel plate combined shear wall and, higher baselines are not waited including steel plate combined shear wall and, the second basis that there is the not equal higher baselines first foundation and absolute altitude to be higher than first foundation, elevation location corresponding with second basis is connected with connecting plate on the steel plate combined shear wall, and the connecting plate passes through the first anchor bolts with the second basis of higher baselines is not waited;Elevation location corresponding with the first foundation is connected with end plate on the steel plate combined shear wall, and the first foundation of the end plate and not grade higher baselines passes through the second anchor bolts.The utility model, by end plate and connecting plate and not, equal higher baselines pass through anchor bolts to steel plate combined shear wall, realize the connection between steel plate combined shear wall and not equal higher baselines, base top mark height is reduced without whole, reduce foundation depth and excavated volume, anti-floating head and precipitation difficulty are reduced, project cost has been saved.

Description

The connecting node of steel plate combined shear wall and not equal higher baselines
Technical field
The utility model belongs to structural engineering field, and in particular to a kind of steel plate combined shear wall and not equal higher baselines Connecting node.
Background technique
Shear wall is widely used in skyscraper as effective lateral resistant member, especially by peripheral steel plate and Nei Bao The double steel plate combined concrete shear wall that concrete efficient combination is formed together is currently to greatly develop assembled architecture research Hot spot.The connecting node on steel plate combined shear wall used at present and basis mainly has exposed, outer-enwraped type and flush type, but For basic top surface the same absolute altitude the case where.
Often arrange that raft foundation or pile-raft foundation, steel plate combined shear wall are often arranged in core in skyscraper under Core Walls Structure Cylinder elevator foundation pit periphery forms steel plate combination and cuts so that the basic top surface absolute altitude of steel plate combined shear wall two sides is inconsistent The connectivity problem of power wall and not equal higher baselines.General processing mode is that raft foundation top surface absolute altitude is down to elevator foundation pit bottom, complete At terrace absolute altitude is backfilled to plain concrete again after steel plate combined shear wall and the connection construction on basis, which leads to raft Plate board bottom absolute altitude increases according to the high corresponding reduction of base top mark, i.e. foundation depth, increases deep excavation project amount, increase anti-floating water Head and precipitation difficulty, while bottom shear wall computed altitude is also increased, cause project cost to increase.
Utility model content
In view of the foregoing deficiencies of prior art, the purpose of this utility model is to provide a kind of steel plate combined shear walls With the connecting node between not equal higher baselines, do not reduce integrally raft foundation base top mark it is high in the case where, it can be achieved that steel plate group Connection between combination shearing wall and not equal higher baselines.
A kind of connecting node of steel plate combined shear wall and not equal higher baselines, including steel plate combined shear wall and not contour base Plinth, the second basis that there is the not equal higher baselines first foundation and absolute altitude to be higher than first foundation, in the steel plate combined shear Elevation location corresponding with second basis is connected with connecting plate, the connecting plate and the second basis for not waiting higher baselines on wall Pass through the first anchor bolts;Elevation location corresponding with the first foundation is connected with end plate on the steel plate combined shear wall, The first foundation of the end plate and not equal higher baselines passes through the second anchor bolts.
Using the above structure, steel plate combined shear wall is by end plate and connecting plate and not equal higher baselines pass through anchor bolts, The connection between steel plate combined shear wall and not equal higher baselines is realized, it is high without the whole base top mark that reduces, reduce foundation pit depth Degree and excavated volume, reduce anti-floating head and precipitation difficulty, have saved project cost.
Optionally, the connecting plate and end plate are welded with the steel plate of the steel plate combined shear wall respectively.
Optionally, the steel plate combined shear wall lower end is supported on the first foundation, and the end plate passes through described the Two anchor bolts are fixed on first foundation top surface, and the connecting plate is fixed on the second basic top surface by first anchor bolt.
Optionally, stiffener is connected on the outside of the connecting plate and steel plate combined shear wall.
Optionally, the steel plate combined shear wall includes the steel plate of periphery and the concrete of Nei Bao, and the steel plate inside is right The high cursor position of connecting plate described in Ying Yu is welded with dowel, and the dowel protrudes into the concrete.
The globality for enhancing connecting plate and steel plate combined shear wall in the utility model, is being correspondingly connected with Board position It is provided with dowel on the inside of steel plate combined shear wall, the horizontal force of connecting plate can be effectively applied on steel plate combined shear wall, and And the setting of dowel will not influence steel plate combined shear wall inner concrete pour it is closely knit.
Optionally, there is gap between the steel plate combined shear wall and not equal higher baselines, the gap uses microlith The closely knit formation pouring layer of concreting.
Optionally, the side of close not equal higher baselines is provided with peg on the steel plate combined shear wall, and the peg buries Enter in the pouring layer.
Optionally, the peg in the position on steel plate combined shear wall between connecting plate and end plate, the peg It is welded with the steel plate of steel plate combined shear wall.
Optionally, pouring hole is offered on the connecting plate.
Optionally, the end plate connection is connected to steel plate combination and cuts in steel plate combined shear wall lower end surface, the connecting plate The side of the close not equal higher baselines of power wall.
The beneficial effects of the utility model are: the utility model, realize steel plate combined shear wall and not equal higher baselines it Between connection, it is high without the whole base top mark that reduces, reduce foundation depth and excavated volume, reduce anti-floating head and precipitation is difficult Degree, has saved project cost.
Detailed description of the invention
Fig. 1 is the steel plate combined shear wall of the utility model and the connecting node sectional view of not equal higher baselines;
Fig. 2 and Fig. 3 is the perspective view of the utility model steel plate combined shear wall different directions.
Piece mark explanation
1- steel plate combined shear wall;2- connecting plate;3- end plate;The not equal higher baselines of 4-;41- first foundation;The second base of 42- Plinth;The first anchor bolt of 5a-;The second anchor bolt of 5b-;6- stiffener;7- dowel;8- pouring layer;9- peg;10- pouring hole.
Specific embodiment
The embodiments of the present invention is illustrated by particular specific embodiment below, those skilled in the art can be by this Content disclosed by specification understands other advantages and effect of the utility model easily.
It should be clear that the term of such as "upper", "lower", "left", "right", " centre " and " one " cited in this specification, also Only being illustrated convenient for narration, rather than to limit the enforceable range of the utility model, relativeness is altered or modified, Under the content of no substantial changes in technology, when being also considered as the enforceable scope of the utility model.
As shown in Figure 1 to Figure 3, the utility model provides the connection section of a kind of steel plate combined shear wall and not equal higher baselines Point, including steel plate combined shear wall 1 and not equal higher baselines 4, wherein do not wait higher baselines 4 that there is relatively low first foundation 41 It is higher than the second basis of first foundation 41, that is, the basis for having height different with absolute altitude;Connect on the steel plate combined shear wall 1 It is connected to connecting plate 2, the connecting plate 2 is corresponding with the elevation location on second basis 42, and connecting plate 2 and not grade higher baselines 4 Second basis 42 passes through multiple first anchor bolt 5a connections;1 lower end of steel plate combined shear wall is connected with end plate 3, end plate 3 and institute The elevation location for stating first foundation 41 is corresponding, and the first foundation 41 of end plate 3 and not equal higher baselines 4 passes through multiple second anchor bolt 5b Connection.
By end plate 3 and connecting plate 2 and not, equal higher baselines 4 realize steel plate by anchor bolts to steel plate combined shear wall 1 Connection between compound shear wall 1 and not equal higher baselines 4, it is high without the whole base top mark that reduces, reduce foundation depth and excavation Amount, reduces anti-floating head and precipitation difficulty, has saved project cost.
Wherein, the steel plate combined shear wall 1 includes the steel plate of periphery and the concrete of Nei Bao, in an embodiment In, the connecting plate 2 and end plate 3 are connect with the steel plate of the steel plate combined shear wall 1 by welding respectively.The steel 1 lower end of board group combination shearing wall is supported on the first foundation 41, the steel plate lower end of the end plate 3 and steel plate combined shear wall 1 Outer wall welding, and end plate 3 is fixed on 41 top surface of first foundation by multiple second anchor bolt 5b;The outer wall of connecting plate 2 and steel plate welds It connects, and is fixed on the second basic 42 top surfaces by multiple first anchor bolt 5a.
In one embodiment, multiple stiffeners 6 are connected on the outside of the connecting plate 2 and steel plate combined shear wall 1.It should Stiffener 6 is connected with connecting plate 2 and steel plate outer wall simultaneously, such as is connected by the way of welding.Reinforced by stiffener 6 Processing, improves the intensity and stability of structure.
In one embodiment, the high cursor position for connecting plate 2 being corresponded on the inside of the steel plate is welded with dowel 7, described Dowel 7 protrudes into the concrete.It is provided with dowel 7 on the inside of the steel plate combined shear wall 1 for being correspondingly connected with 2 position of plate, can incite somebody to action The horizontal force of connecting plate 2 is effectively applied on steel plate combined shear wall 1, and the setting of dowel 7 will not influence steel plate combination and cut 1 inner concrete of power wall pours closely knit.And enhance the globality of connecting plate 2 Yu steel plate combined shear wall 1, prevent steel plate because It is separated by lateral force with the concrete of interior packet.
In one embodiment, the side of the close not equal higher baselines 4 of the steel plate combined shear wall 1 and not contour base There is gap, gap pours closely knit formation pouring layer 8 using pea gravel concreten between plinth 4.It is mixed that microlith is poured in the gap Solidifying soil, is filled closely knit.Enhance anchoring ability of the steel plate combined shear wall 1 in basis.
In one embodiment, it is provided on the steel plate combined shear wall 1 close to the side of grade higher baselines 4 multiple Peg 9, for peg 9 in the position on steel plate combined shear wall 1 between connecting plate 2 and end plate 3, peg 9 is embedded to described pour In layer 8, enhance the globality that steel plate combined shear wall 1 is connect with pouring layer 8.Wherein, the peg 9 and steel plate combined shear wall Welding on the outside of 1 steel plate.
In one embodiment, multiple pouring holes 10 to be offered on the connecting plate 2 convenient for pouring.
In one embodiment, the anchoring stability between higher baselines 4 is waited for enhancing steel plate combined shear wall 1 and not, The end plate 3 is connect with 1 lower end surface of steel plate combined shear wall, i.e., the steel plate lower end surface of end plate 3 and steel plate combined shear wall 1 is welded It connects, and end plate 3 is a monolith, the integrated support of steel plate combined shear wall 1 improves stability of strutting system on end plate 3;Wherein, it connects Plate 2 is connected to the side of the close not equal higher baselines 4 of steel plate combined shear wall 1.
The utility model realizes that process is as follows, in corresponding second basic (i.e. the eminence position) for not waiting higher baselines 4, in steel plate Connecting plate 2 with stiffener 6 and pouring hole 10 is set on the outside of compound shear wall 1, and dowel 7 is arranged in inside;In the not contour base of correspondence End plate 3 is arranged in the first foundation (i.e. lower position) of plinth 4 on steel plate combined shear wall 1, and by anchor bolt respectively by connecting plate 2 and end plate 3 be anchored on not equal higher baselines 4, finally again by the gap microlith of steel plate combined shear wall 1 and not equal higher baselines 4 Concreting is closely knit, and peg 9 is embedded in the pea gravel concreten at this time.
The beneficial effects of the utility model are: the utility model, realizes steel plate combined shear wall 1 and not equal higher baselines 4 Between connection, it is high without the whole base top mark that reduces, reduce foundation depth and excavated volume, reduce anti-floating head and precipitation is difficult Degree, has saved project cost.
Dowel 7 is provided in the utility model on the inside of the steel plate combined shear wall 1 for being correspondingly connected with 2 position of plate, can will be connected The horizontal force of fishplate bar 2 is effectively applied on steel plate combined shear wall 1, and the setting of dowel 7 will not influence steel plate combined shear 1 inner concrete of wall pours closely knit.Enhance the globality of connecting plate 2 Yu steel plate combined shear wall 1.
The above embodiments are only illustrative of the principle and efficacy of the utility model, and not for limitation, this is practical new Type.Any person skilled in the art can all carry out above-described embodiment under the spirit and scope without prejudice to the utility model Modifications and changes.Therefore, such as those of ordinary skill in the art without departing from the revealed essence of the utility model All equivalent modifications or change completed under mind and technical idea, should be covered by the claim of the utility model.

Claims (10)

1. the connecting node of a kind of steel plate combined shear wall and not equal higher baselines, including steel plate combined shear wall and not contour base Plinth, the second basis that there is the not equal higher baselines first foundation and absolute altitude to be higher than first foundation, it is characterised in that: in the steel Elevation location corresponding with second basis is connected with connecting plate, the connecting plate and not equal higher baselines on board group combination shearing wall Second basis pass through the first anchor bolts;Elevation location corresponding with the first foundation connects on the steel plate combined shear wall It is connected to end plate, the first foundation of the end plate and not grade higher baselines passes through the second anchor bolts.
2. the connecting node of steel plate combined shear wall according to claim 1 and not equal higher baselines, it is characterised in that: described Connecting plate and end plate are welded with the steel plate of the steel plate combined shear wall respectively.
3. the connecting node of steel plate combined shear wall according to claim 1 and not equal higher baselines, it is characterised in that: described Steel plate combined shear wall lower end is supported on the first foundation, and the end plate is fixed on first foundation by second anchor bolt Top surface, the connecting plate are fixed on the second basic top surface by first anchor bolt.
4. the connecting node of steel plate combined shear wall according to claim 1 and not equal higher baselines, it is characterised in that: described Stiffener is connected on the outside of connecting plate and steel plate combined shear wall.
5. the connecting node of steel plate combined shear wall according to claim 1 and not equal higher baselines, it is characterised in that: described Steel plate combined shear wall includes the steel plate of periphery and the concrete of Nei Bao, and the high standard of the connecting plate is corresponded on the inside of the steel plate Position is welded with dowel, and the dowel protrudes into the concrete.
6. steel plate combined shear wall described in -5 any one and the connecting node for not waiting higher baselines according to claim 1, special Sign is: having gap between the steel plate combined shear wall and not equal higher baselines, the gap is poured using pea gravel concreten Build closely knit formation pouring layer.
7. the connecting node of steel plate combined shear wall according to claim 6 and not equal higher baselines, it is characterised in that: described Close to not waiting side of higher baselines to be provided with peg on steel plate combined shear wall, the peg is embedded in the pouring layer.
8. the connecting node of steel plate combined shear wall according to claim 7 and not equal higher baselines, it is characterised in that: described Peg in the position on steel plate combined shear wall between connecting plate and end plate, the steel of the peg and steel plate combined shear wall Plate welding.
9. the connecting node of steel plate combined shear wall according to claim 6 and not equal higher baselines, it is characterised in that: described Pouring hole is offered on connecting plate.
10. the connecting node of steel plate combined shear wall according to claim 1 and not equal higher baselines, it is characterised in that: institute End plate connection is stated in steel plate combined shear wall lower end surface, the connecting plate is connected to the close not equal higher baselines of steel plate combined shear wall Side.
CN201920222518.8U 2019-02-22 2019-02-22 The connecting node of steel plate combined shear wall and not equal higher baselines Withdrawn - After Issue CN209723230U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920222518.8U CN209723230U (en) 2019-02-22 2019-02-22 The connecting node of steel plate combined shear wall and not equal higher baselines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920222518.8U CN209723230U (en) 2019-02-22 2019-02-22 The connecting node of steel plate combined shear wall and not equal higher baselines

Publications (1)

Publication Number Publication Date
CN209723230U true CN209723230U (en) 2019-12-03

Family

ID=68683660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920222518.8U Withdrawn - After Issue CN209723230U (en) 2019-02-22 2019-02-22 The connecting node of steel plate combined shear wall and not equal higher baselines

Country Status (1)

Country Link
CN (1) CN209723230U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853748A (en) * 2019-02-22 2019-06-07 中冶赛迪工程技术股份有限公司 The connecting node of steel plate combined shear wall and not equal higher baselines

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853748A (en) * 2019-02-22 2019-06-07 中冶赛迪工程技术股份有限公司 The connecting node of steel plate combined shear wall and not equal higher baselines
CN109853748B (en) * 2019-02-22 2024-02-06 中冶赛迪工程技术股份有限公司 Connecting node of steel plate combined shear wall and unequal-height foundation

Similar Documents

Publication Publication Date Title
CN109356173A (en) A kind of pin-connected panel anchor bolt frame girder construction and its construction method
CN206376287U (en) Subway station main body and the float Structure of accessory structure interface
CN111236258A (en) Prefabricated pile wall supporting structure with stiffening rib wall and unloading platform and construction method thereof
CN203334270U (en) Mountable buried type prefabricated hollow underground diaphragm wall
CN205935195U (en) Prefabricated building concrete beam column shaped steel built -up connection node construction
CN209723230U (en) The connecting node of steel plate combined shear wall and not equal higher baselines
CN102493439A (en) Building fundamental pile constructional element
CN210117712U (en) Stirring grooving insertion type prefabricated combined box foundation structure
CN207878458U (en) Interim steel trestle with resistance to plucking auxiliary pile
CN212294679U (en) Combined lattice column-concrete precast pile inclined support structure
CN109853748A (en) The connecting node of steel plate combined shear wall and not equal higher baselines
CN209620049U (en) A kind of pin-connected panel anchor bolt frame girder construction
CN210194604U (en) Stirring grooving insertion type combined prefabricated special-shaped section composite foundation structure
CN206376251U (en) Steel plate concrete prefabricated parts and face forever and descend retaining design in combination
CN205529847U (en) Landing stage structure that combination smw worker method was gone along with sb. to guard him
CN200946270Y (en) Sinking pipe bottom-expanding pile
CN201924342U (en) Cast-in-place concrete cylindrical sheet connecting pile
CN108330986A (en) Back-pressure de-bowed type pile slab supporting structure and construction method after stake
CN216156604U (en) Multi-connected-cylinder rectangular assembled well wall structure
CN220080031U (en) Structural member with ring frame beam serving as enclosing purlin
CN217128240U (en) Novel stagnant water envelope
CN213867612U (en) Install novel prefabricated shore protection device fast
CN210918326U (en) Processing structure for arranging tie beam and reinforcing beam column joint between layers when column is overlong
CN201137063Y (en) High bearing capacity pipe caisson pouring club-footed pile
CN200955147Y (en) High-rise building sink-pipe bored concrete pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20191203

Effective date of abandoning: 20240206

AV01 Patent right actively abandoned

Granted publication date: 20191203

Effective date of abandoning: 20240206