CN105970993B - The construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap - Google Patents
The construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap Download PDFInfo
- Publication number
- CN105970993B CN105970993B CN201610505940.5A CN201610505940A CN105970993B CN 105970993 B CN105970993 B CN 105970993B CN 201610505940 A CN201610505940 A CN 201610505940A CN 105970993 B CN105970993 B CN 105970993B
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- pile
- cushion cap
- pile crown
- diameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
Abstract
The invention discloses the underwater connection structures and its construction method of a kind of prefabricated pile and prefabricated cushion cap, the prefabricated cushion cap is fixedly connected on the top of prefabricated pile, the top of prefabricated pile has pile crown, the diameter of the pile crown is less than pile crown prefabricated pile diameter below, the prefabricated cushion cap is equipped with the through-hole connecting with pile crown, the diameter of the through-hole is greater than the diameter of pile crown, but it is less than pile crown prefabricated pile diameter below, to concrete perfusion between through-hole and pile crown by way of subaqueous concreting, it is fixed together prefabricated pile with prefabricated cushion cap.
Description
Technical field
The present invention relates to a kind of underwater pile structures, further relate to the construction method of this underwater pile structure.
Background technique
In the foundation engineerings such as bridge, harbour, harbour, hydraulic engineering, pile foundation of bearing platform plinth is common base form.When applying
When cushion cap is located at the water surface or less between duration, generally constructed using cofferdam method, but the at high cost of cofferdam construction, the period is long, technology is difficult
Degree is big, is also possible to will affect navigation.Currently, precast assembly structure uses more and more widely, if pile foundation of bearing platform plinth is adopted
With precast construction, on-site consolidation can then remove cofferdam construction process from, substantially reduce construction cost and shorten the construction period.Precast assembly
Pile foundation of bearing platform plinth, key node is how to handle the underwater connecting node of stake and cushion cap, but in the prior art, prefabricated pile
It is also unreasonable with the underwater connection structure of prefabricated cushion cap, have the shortcomings that difficulty of construction is big, reliability is low.
Summary of the invention
The technical problem to be solved in the present invention is to provide it is a kind of convenient for rapid construction, effect reliable prefabricated pile with it is prefabricated
The underwater connection structure of cushion cap, to overcome the drawbacks described above of the prior art.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme that:A kind of water of prefabricated pile and prefabricated cushion cap
Lower connection structure, the prefabricated cushion cap are fixedly connected on the top of prefabricated pile, and the top of prefabricated pile has pile crown, the pile crown
Diameter is less than pile crown prefabricated pile diameter below, and the prefabricated cushion cap is equipped with the through-hole that connect with pile crown, the through-hole it is straight
Diameter is greater than the diameter of pile crown, but is less than pile crown prefabricated pile diameter below, mixed by underwater grouting between the through-hole and pile crown
Solidifying soil is fixed together.
Preferably, the prefabricated pile is concrete square pile, concrete circular pile or concrete tubular pile.
Preferably, the prefabricated pile is equipped with the bulb adjacent with pile crown, and bulb is located at pile crown hereinafter, described pre-
The diameter of through-hole is less than the diameter of bulb on cushion cap processed.
It preferably, is identical in pile crown prefabricated pile diameter below.
Preferably, the prefabricated pile is solid concrete stake, constitutes and is embedded with reinforcing bar, steel in the concrete of the prefabricated pile
Muscle beam or steel pipe, the reinforcing bar, tendon or steel pipe expose from the top of prefabricated pile and form the pile crown.
Preferably, shear key is additionally provided on the pile crown.
The invention solves another technical problem be to provide the construction method of above-mentioned connection structure.
This approach includes the following steps:
A, prefabricated pile is installed in place under water first;
B, prefabricated cushion cap is then lifted into prefabricated pile top, matches the through-hole on prefabricated cushion cap with pile crown, and
Toroidal cavity is formed between pile crown and through-hole wall;
C, by subaqueous concreting technique into the toroidal cavity between pile crown and through-hole wall concrete perfusion, will
Prefabricated pile and prefabricated cushion cap are connected and fixed.
Compared with prior art, the invention has the advantages that.
The present invention has carried out reasonable design to the structure of prefabricated pile and the underwater connecting node of prefabricated cushion cap, in prefabricated pile
Toroidal cavity is formed between pile crown and the through-hole wall of prefabricated cushion cap, and passes through the subaqueous concreting into the toroidal cavity
Mode is connected and fixed prefabricated pile and prefabricated cushion cap.This underwater connection type simple structure, easy for construction, low-cost, company
Reliable in quality is connect, and construction period can be greatly shortened, there is huge economic benefit and important realistic meaning.
Detailed description of the invention
Fig. 1 is the elevational schematic view of underwater the first embodiment of connection structure of prefabricated pile of the present invention and prefabricated cushion cap.
Fig. 2 is the elevational schematic view of second of embodiment of underwater connection structure of prefabricated pile of the present invention and prefabricated cushion cap.
Fig. 3 is the elevational schematic view of underwater the third embodiment of connection structure of prefabricated pile of the present invention and prefabricated cushion cap.
Fig. 4 is the top plan view of the underwater connection structure of prefabricated pile of the present invention and prefabricated cushion cap.
In figure:
1, prefabricated cushion cap 2, prefabricated pile 3, subaqueous concreting
11, through-hole 21, pile crown 22, bulb
23, reinforcing bar, tendon or steel pipe
Specific embodiment
Specific embodiments of the present invention will be described in further detail with reference to the accompanying drawing.These embodiments are only used for
Illustrate the present invention, and not limitation of the present invention.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase
Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can
To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also can be indirectly connected through an intermediary
Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood as the case may be
Concrete meaning in the present invention.
In addition, in the description of the present invention, unless otherwise indicated, the meaning of " plurality " is two or more.
As shown in Figure 1, being the first embodiment of the invention, the underwater connection structure packet of the prefabricated pile and prefabricated cushion cap
Prefabricated cushion cap 1 and Duo Gen prefabricated pile 2 are included, the top of prefabricated pile 2 has pile crown 21, and it is below pre- that the diameter of pile crown 21 is less than pile crown
The diameter of stake 2 processed, 2 diameter of prefabricated pile below of pile crown 21 is all identical.It is equipped on prefabricated cushion cap 1 and is connected with pile crown 21
Through-hole 11, the diameter of through-hole 11 is greater than the diameter of pile crown 21, but is less than pile crown 2 diameter of prefabricated pile below, therefore, prefabricated to hold
Platform 1 can be located in the top of prefabricated pile 2, and be formed between the pile crown of prefabricated pile 21 and the through-hole wall of prefabricated cushion cap 1
Toroidal cavity (as shown in Figure 4), by way of subaqueous concreting into the toroidal cavity concrete perfusion 3, make prefabricated
Cushion cap 1 and prefabricated pile 2 are fixed together.2 one side of prefabricated pile can play the role of the prefabricated cushion cap 1 of support, another party
Face can double as the bed die of subaqueous concreting.Above-mentioned prefabricated pile 2 can be concrete square pile, concrete circular pile or concrete
Tubular pole etc., for square pile, above-mentioned diameter should be understood as the circumscribed circle diameter of square-section.
As shown in Fig. 2, be second of embodiment of the invention, unlike the first embodiment, pile crown 21 with
Under the diameter of prefabricated pile 2 be not impartial.The bulb 22 adjacent with pile crown 21, bulb are equipped on prefabricated pile 2
22 be located at pile crown 21 hereinafter, and the diameter of bulb 22 be greater than the diameter at the other positions of prefabricated pile 2, and through-hole on prefabricated cushion cap
11 diameter is less than the diameter of bulb 22.In this way, bulb 22 can support prefabricated cushion cap 1, and double as underwater grouting coagulation
The bed die of soil., can be identical as the diameter of pile crown 21 as the diameter of the prefabricated pile 2 below of bulb 22, pile crown can also be compared
21 diameter is big.
In above-mentioned two embodiment, the partial structurtes such as shear key can also be increased, on pile crown 21 further to mention
The reliability that high prefabricated cushion cap 1 is bonded with pile crown 21.
As shown in figure 3, be the third embodiment of the invention, unlike above two embodiment, pile crown 21
It is not concrete structure.Prefabricated pile 2 is solid concrete stake, constitutes in the concrete of prefabricated pile 2 and is embedded with reinforcing bar, tendon
Or steel pipe 23, the reinforcing bar, tendon or steel pipe 23 expose from the concrete on 2 top of prefabricated pile, and form the pile crown 21.
That is, pile crown 21 is made of the reinforcing bar, tendon or steel pipe upwardly extended from concrete.Work as subaqueous concreting
After the completion of 3 constructions, these exposed reinforcing bar, tendon or steel pipes are just integrated in concrete, and by prefabricated cushion cap 1 and prefabricated pile
2 are linked together.
Above-mentioned connection structure can construct according to the following steps.
A, each prefabricated pile 2 is installed in place under water first;
B, then prefabricated cushion cap 1 is lifted into 2 top of prefabricated pile and is covered on pile crown 21, make through-hole on prefabricated cushion cap with
Pile crown 21 matches, and forms toroidal cavity between pile crown 21 and the inner wall of through-hole 11;
C, coagulation is perfused into the toroidal cavity between 11 inner wall of pile crown 21 and through-hole by subaqueous concreting technique
Prefabricated pile 2 and prefabricated cushion cap 1 are connected and fixed by soil.
The invention avoids traditional cofferdam construction methods, realize precast construction with mature subaqueous concreting technique
Underwater connection, simple structure, easy for construction, low-cost, quality of connection is reliable, there is huge economic benefit.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the technical principles of the invention, several improvement and replacement can also be made, these are improved and replacement
Also it should be regarded as protection scope of the present invention.
Claims (1)
1. a kind of construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap, the prefabricated cushion cap(1)It is fixedly connected on
Prefabricated pile(2)Top, prefabricated pile(2)Top have pile crown(21), the pile crown(21)Diameter be less than pile crown it is below
Prefabricated pile(2)Diameter, the prefabricated cushion cap(1)It is equipped with and pile crown(21)The through-hole of connection(11), the through-hole(11)It is straight
Diameter is greater than pile crown(21)Diameter, but be less than pile crown(21)Prefabricated pile below(2)Diameter, the through-hole(11)With pile crown(21)
Between pass through subaqueous concreting(3)It is fixed together, characterized in that include the following steps:
A, prefabricated pile is installed in place under water first;
B, prefabricated cushion cap is then lifted into prefabricated pile top, matches the through-hole on prefabricated cushion cap with pile crown, and in pile crown
Toroidal cavity is formed between through-hole wall;
C, by subaqueous concreting technique into the toroidal cavity between pile crown and through-hole wall concrete perfusion, will be prefabricated
Stake and prefabricated cushion cap are connected and fixed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610505940.5A CN105970993B (en) | 2016-06-30 | 2016-06-30 | The construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610505940.5A CN105970993B (en) | 2016-06-30 | 2016-06-30 | The construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105970993A CN105970993A (en) | 2016-09-28 |
CN105970993B true CN105970993B (en) | 2018-11-27 |
Family
ID=56954930
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610505940.5A Withdrawn - After Issue CN105970993B (en) | 2016-06-30 | 2016-06-30 | The construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105970993B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059774A (en) * | 2017-05-27 | 2017-08-18 | 中交第三航务工程勘察设计院有限公司 | A kind of assembled high-rise pile cap revetment structure and construction method |
CN107059773A (en) * | 2017-05-27 | 2017-08-18 | 中交第三航务工程勘察设计院有限公司 | Assembled integral revetment structure and its construction method on a kind of soft soil foundation |
CN108265737B (en) * | 2018-03-27 | 2024-03-08 | 淮海工学院 | Assembled concrete bearing platform and micro pile combined foundation and construction method |
CN109183827A (en) * | 2018-09-18 | 2019-01-11 | 何文峰 | Underwater reinforced concrete foundation construction operation engineering method |
CN109797765B (en) * | 2018-12-25 | 2019-11-22 | 广州市市政集团设计院有限公司 | It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device |
CN109989415B (en) * | 2019-05-06 | 2021-05-28 | 河南绿建建筑科技有限公司 | Construction method of fabricated foundation |
CN110158475A (en) * | 2019-05-21 | 2019-08-23 | 北京工业大学 | A kind of prefabricated assembled bridge substructure and its construction method |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100744693B1 (en) * | 2005-10-24 | 2007-08-01 | (주) 선암기술연구소 | Concrete-steel house and pile foundation footing construction method using thereof |
CN103711139A (en) * | 2012-09-29 | 2014-04-09 | 上海中技桩业股份有限公司 | Semi-rigid connection structure between pile foundation and bearing platform |
CN103628504B (en) * | 2013-11-28 | 2016-01-20 | 广州市恒盛建设工程有限公司 | The method of attachment of a kind of pin-connected panel prefabricated reinforced concrete platform structure node under water |
JP6379554B2 (en) * | 2014-03-20 | 2018-08-29 | ジャパンパイル株式会社 | Ready-made piles and support methods for ready-made piles |
CN204456160U (en) * | 2014-12-12 | 2015-07-08 | 中交公路规划设计院有限公司 | A kind of bridge prefabrication cushion cap |
CN204919635U (en) * | 2015-09-18 | 2015-12-30 | 贵州省公路局 | Bridge foundation reinforced structure |
CN205857219U (en) * | 2016-06-30 | 2017-01-04 | 上海勘测设计研究院有限公司 | Prefabricated pile and the attachment structure under water of prefabricated cushion cap |
-
2016
- 2016-06-30 CN CN201610505940.5A patent/CN105970993B/en not_active Withdrawn - After Issue
Also Published As
Publication number | Publication date |
---|---|
CN105970993A (en) | 2016-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105970993B (en) | The construction method of the underwater connection structure of prefabricated pile and prefabricated cushion cap | |
CN104790424B (en) | The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof | |
CN103628504B (en) | The method of attachment of a kind of pin-connected panel prefabricated reinforced concrete platform structure node under water | |
CN109555151A (en) | Precast concrete column combines connecting structure and construction method with the steel reinforced concrete of cushion cap | |
CN106930277A (en) | A kind of construction of manual-excavation cast-in-place pile method | |
WO2017084573A1 (en) | Upheaval-resisting support structure | |
CN105544593A (en) | Wind power generation tower foundation with prefabricated foundation prestressed beams and slab | |
CN108360678A (en) | A kind of assembled beam-column node tenon connection structure | |
CN105926775A (en) | Novel concrete-filled steel tube beam column joint | |
CN107435338A (en) | Overhead transmission line concrete precast pipe pile cushion cap attachment means | |
CN205857219U (en) | Prefabricated pile and the attachment structure under water of prefabricated cushion cap | |
CN205875394U (en) | Antidetonation concrete beam column that dry process is connected | |
CN209260897U (en) | Assembly concrete beam column sleeve combination connecting node | |
CN106193644B (en) | Basement reconstruction structure with raft foundation building | |
CN212317544U (en) | A post connection structure about newly-built basis for expanding underground space | |
CN209703418U (en) | Assembled flood-control wall | |
CN207194001U (en) | A kind of new overhead transmission line concrete precast pipe pile cushion cap foundation | |
CN106592586B (en) | Additional cuff back-up sand building stones prefabricated pile and its construction method | |
CN212294679U (en) | Combined lattice column-concrete precast pile inclined support structure | |
CN213896714U (en) | Prefabricated beam type arch bridge | |
CN213773339U (en) | Tubular pile with large bearing capacity | |
CN209585028U (en) | A kind of open caisson applies broken pile | |
CN209384243U (en) | A kind of prestressing force support pile and piling wall | |
CN208803631U (en) | Light steel grating concrete superposed column | |
CN206902719U (en) | Preassembling support beam combines support system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20181127 Effective date of abandoning: 20220329 |
|
AV01 | Patent right actively abandoned |
Granted publication date: 20181127 Effective date of abandoning: 20220329 |