CN217536985U - Foundation pit enclosure structure - Google Patents

Foundation pit enclosure structure Download PDF

Info

Publication number
CN217536985U
CN217536985U CN202123217575.3U CN202123217575U CN217536985U CN 217536985 U CN217536985 U CN 217536985U CN 202123217575 U CN202123217575 U CN 202123217575U CN 217536985 U CN217536985 U CN 217536985U
Authority
CN
China
Prior art keywords
pile
region
cast
foundation pit
excavating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123217575.3U
Other languages
Chinese (zh)
Inventor
孙海忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai General Construction Engineering Research Institute Co ltd
Original Assignee
Shanghai General Construction Engineering Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai General Construction Engineering Research Institute Co ltd filed Critical Shanghai General Construction Engineering Research Institute Co ltd
Priority to CN202123217575.3U priority Critical patent/CN217536985U/en
Application granted granted Critical
Publication of CN217536985U publication Critical patent/CN217536985U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model provides a foundation pit retaining structure, include: the method comprises the following steps of firstly excavating a region and a later excavating region, wherein the later excavating region is positioned in the central region of a foundation pit, and the first excavating region is positioned in the peripheral region of the later excavating region; arranging a cast-in-situ bored pile and a triaxial mixing pile at the periphery of a prior excavation area, wherein the cast-in-situ bored pile and the triaxial mixing pile are arranged adjacently, and the triaxial mixing pile is arranged at the outer side of the cast-in-situ bored pile; the steel pipe piles are arranged on the periphery of the rear excavation area; and the upright pile is arranged between the steel pipe pile and the cast-in-situ bored pile. The utility model has the advantages of as follows: the construction quality is stable, and the pile forming quality of the pile foundation is good; the construction is convenient, the construction period is short, and the construction progress is fast; the building envelope has low construction cost, utilizes the reserved soil area and has greater economy; the construction feasibility and the operability are strong, and the adaptability to the site and similar stratums is strong.

Description

Foundation pit enclosure structure
Technical Field
The utility model relates to a foundation ditch retaining structure.
Background
With the development of economy and science and technology, underground engineering is being developed on a large scale, the required performance is higher and higher, and the requirements on the research of deep soil bodies and the development and modification of underground spaces are higher and higher. The construction of underground building structures is undoubtedly ultimately dependent on the interaction of their structure with the surrounding geotechnical media. The foundation pit engineering creates conditions for the smooth construction of underground engineering, and the existing deep and large foundation pit support mode in soft soil areas mainly combines a plate type support system enclosure wall with a support structure. The process has the problems of large construction difficulty, large engineering quantity, high construction cost, poor enclosure effect and the like in the enclosure of deep and large foundation pits in soft soil areas.
The plate type supporting system supporting wall mainly comprises: underground continuous wall, cast-in-place pile row, section steel cement mixing pile, steel sheet pile and concrete sheet pile. The supporting structure mainly adopts steel supports, reinforced concrete supports or the combination of the steel supports and the reinforced concrete supports.
(1) The steel support system is a structural system formed by welding steel components or splicing bolts in a foundation pit. The foundation pit excavation method has the advantages of simple structure, relatively uniform node forms, high erection and dismantling speed, repeated and cyclic use and the like, but is mainly suitable for excavation of foundation pits with common excavation depth and regular shapes at present. The rigidity of the steel support is relatively small, and the unidirectional steel bar support is too long, so that the splicing nodes are more prone to accumulating to form large construction displacement, and the large-area foundation pit deformation control and the surrounding environment protection are not facilitated.
(2) The reinforced concrete support has the characteristics of high rigidity, good integrity, flexible planar arrangement form and the like. However, the supporting form of the device is often provided with the problems of dense supporting rod pieces, large engineering quantity, small unearthed space, low speed and the like. Meanwhile, the requirements on the management and technical capacity of construction units are relatively high.
(3) The steel and concrete combined support adopts a steel and concrete combined support form, and the characteristics of two materials are fully utilized, so that the support form is widely applied to engineering, but the complex support node has the defects of high construction difficulty in site, high construction cost, difficulty in controlling construction quality due to on-site pouring and maintenance, and certain limitation in the application range.
When the existing support form is used for a deep foundation pit in a deep soft soil area, the conventional arrangement of the supports and the columns according to the plane of the whole foundation pit is huge engineering quantity, and meanwhile, the construction period is long, the requirement on construction at the nodes is high, and the condition of stress concentration can be generated, so that the support structure is bent to generate large deflection deformation. Therefore, the method for designing and constructing the novel ultra-large-area foundation pit support in the deep soft soil area has very important engineering practical significance.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a foundation ditch envelope.
In order to solve the above problem, the utility model provides a foundation pit retaining structure, include:
the method comprises the following steps of firstly excavating a region and a later excavating region, wherein the later excavating region is positioned in the central region of a foundation pit, and the first excavating region is positioned in the peripheral region of the later excavating region;
arranging a cast-in-situ bored pile and a triaxial mixing pile at the periphery of a prior excavation area, wherein the cast-in-situ bored pile and the triaxial mixing pile are arranged adjacently, and the triaxial mixing pile is arranged at the outer side of the cast-in-situ bored pile;
the steel pipe piles are arranged on the periphery of the rear excavation area;
and the upright pile is arranged between the steel pipe pile and the cast-in-situ bored pile.
Further, among the above-mentioned foundation ditch envelope, still include:
the purlin is arranged on the inner side of the top of the cast-in-situ bored pile;
the concrete cap is arranged at the top of the steel pipe pile;
one end of the supporting beam is connected with the surrounding purlin, the other end of the supporting beam is connected with the reinforced concrete capping beam, and the middle of the supporting beam is connected with the top of the upright post pile.
Further, among the above-mentioned foundation ditch envelope, still include:
the profile steel force transmission belt is arranged on the side, close to the pre-excavation region, of the steel pipe pile;
one end of the foundation bottom plate is connected with one end of the cast-in-situ bored pile, and the other end of the foundation bottom plate is connected with the profile steel force transmission belt, wherein the foundation bottom plate is arranged at the lower part of the support beam in parallel;
the section steel trades and props, the section steel trades the one end that props with the bored concrete pile is connected, the section steel trades the other end that props with soleplate connects.
Compared with the prior art, the utility model discloses at first to a fender pile, interior support and excavation subregion arrange and carry out optimal design, support in order to replace the large tracts of land through the method that divides the hole in the foundation ditch setting more than 50m square staying native district. And then carrying out earth excavation of the prior area, and construction of a foundation slab and a support replacing structure. The horizontal inner support is then removed. And then performing the operations of earth excavation, steel pipe pile recovery, construction and maintenance of the foundation slab and the like of the later implementation area. And finally, completing the back construction of the basement structure and the dismantling work of the temporary support replacement.
The utility model has the advantages of as follows:
(1) The construction quality is stable, and the pile forming quality of the pile foundation is good;
(2) The construction is convenient, the construction period is short, and the construction progress is fast;
(3) The building envelope has low construction cost, utilizes the reserved soil area and has greater economy;
(4) The construction feasibility and the operability are strong, and the adaptability to the site and similar stratums is strong.
Drawings
Fig. 1 is a schematic plan view of a foundation pit supporting structure in an earth excavation stage of a foundation pit advanced region according to an embodiment of the present invention;
fig. 2 is a schematic plan view of a foundation pit supporting structure in an earth excavation stage of a post-foundation-pit implementation area of the present invention;
fig. 3 is a schematic view of the cross-sectional structure of the foundation pit of fig. 1 and 2;
wherein: 1. the cast-in-situ bored pile comprises a bored pile, 2 three-axis stirring piles, 3 steel pipe piles, 4 upright posts, 5 purlins, 6 reinforced concrete capping beams, 7 supporting beams, 8 excavation areas, 9 profile steel force transmission belts, 10 profile steel support changing, 11 foundation bottom plates, 12 excavation areas after soil is left in pits, 13 reinforced concrete force transmission belts, 14 basement one-layer floor slabs, 15 wall boards.
Detailed Description
In order to make the aforementioned objects, features and advantages of the present invention more comprehensible, the present invention is described in detail with reference to the accompanying drawings and the following detailed description.
As shown in fig. 1-3, the utility model provides a construction method of foundation pit support structure, including:
step S1, dividing a foundation pit into a first excavation area 8 and a second excavation area 12, wherein the second excavation area is located in the central area of the foundation pit, and the first excavation area 8 is located in the peripheral area of the second excavation area 12;
s2, arranging a bored pile 1 and a triaxial mixing pile 2 which are adjacent to each other at the periphery of the excavation area 8, wherein the triaxial mixing pile 2 is arranged on the outer side of the bored pile 1; arranging a steel pipe pile 3 at the periphery of the rear excavation area; arranging a vertical column pile 4 in the area between the steel pipe pile 3 and the cast-in-situ bored pile 1;
in the method, a cast-in-situ bored pile 1, a triaxial mixing pile 2, a steel pipe pile 3 and a stand column pile 4 form a supporting wall,
s3, arranging a surrounding purlin 5 on the inner side of the top of the cast-in-situ bored pile 1, arranging a reinforced concrete capping beam 6 on the top of the steel pipe pile 3, connecting one end of a supporting beam 7 with the surrounding purlin 5, connecting the other end of the supporting beam 7 with the reinforced concrete capping beam 6, and connecting the middle part of the supporting beam 7 with the top of the upright pile 4;
after the earth is excavated to the bottom elevation positions of the enclosing purlin 5 to be formed, the reinforced concrete capping beam 6 and the horizontal inner support 7, a reinforced concrete horizontal inner support system consisting of the enclosing purlin 5, the supporting beam 7 and the reinforced concrete capping beam 6 is constructed, the steel-reinforced concrete horizontal inner support system is maintained to reach 80% of the design strength, the combined action of the earth-reserved rear excavation area 12, the steel pipe piles 3, the supporting beam 7 and the like is realized, and the peripheral cast-in-place piles 1 of the foundation pit are supported. Preferably, each node of the support wall and each node of the reinforced concrete horizontal inner support system are rigidly connected by adopting a mode of steel bar binding welding and concrete common pouring.
Step S4, firstly excavating earthwork of the area 8, after the earthwork of the area 8 is excavated to the elevation of the substrate, arranging a section steel force transfer belt 9 on the side, close to the area 8, of the steel pipe pile 3, connecting one end of a foundation bottom plate 11 and one end of the cast-in-situ bored pile with the cast-in-situ bored pile 1, and connecting the other end of the foundation bottom plate 11 and the section steel force transfer belt 9, wherein the foundation bottom plate 11 is arranged at the lower part of the support beam 7 in parallel;
after the construction of the surrounding purlin 5, the reinforced concrete capping beam 6 and the support 7 is finished and the maintenance reaches 80% of the design strength, earth excavation of an excavation-first area 8 at the lower layer can be carried out, and the earth is manually repaired at the local depths of a ground beam, a bearing platform and the like which are 30cm above the elevation of the pit bottom;
preferably, 1m wide construction joints are arranged on the foundation slab 11 and the steel pipe pile 3, and the section steel force transmission belt 9 is arranged in the construction joints;
preferably, one end of the section steel force transmission belt 9 is embedded in a steel bar of the foundation slab 11, the other end of the section steel force transmission belt is welded in the steel pipe pile 3, and then the concrete of the foundation slab 11 is poured to complete the connection between the foundation slab 11 and the steel pipe pile 3;
step S5, connecting one end of a section steel support changing 10 with the cast-in-situ bored pile 1, and connecting the other end of the section steel support changing 10 with the foundation slab 11;
after a support replacing system consisting of the section steel force transmission belt 9, the section steel support replacing 10 and the foundation bottom plate 11 is installed and constructed, the foundation bottom plate 11 is maintained to reach 100% of the design strength, and the supporting beam 7 can be conveniently detached in the follow-up process;
preferably, one end of the profile steel replacement support 10 is welded with a reinforcement cage hanging rib of the cast-in-situ bored pile 1, the other end of the profile steel replacement support 10 is embedded in the foundation slab 11, and then the foundation slab 11 is poured to complete the connection between the foundation slab 11 and the cast-in-situ bored pile 1;
preferably, during the concrete pouring of the foundation slab 11, the gap between the foundation slab 11 and the cast-in-situ bored pile 1 is filled with concrete of the same strength grade as that of the foundation slab 11;
s6, removing the horizontal support beams 7 and the vertical column piles 4, excavating the earthwork of the rear excavation area 12, removing the reinforced concrete capping beams 6, and removing the steel pipe piles 3;
here, after the maintenance foundation sole plate 11 reaches 100% of the design strength, the horizontal support beams 7 are removed.
Preferably, after the earthwork of the post-excavation area 12 is excavated to 1.5m above the ground surface, the reinforced concrete cap 6 is broken, and the steel pipe pile 3 is pulled out;
and S7, continuing to construct the basement structure: the method comprises the steps that a wall plate 15 is arranged on the side, close to a cast-in-situ bored pile 1, of a foundation bottom plate 11, one end of a first floor slab 14 of the basement is connected with the wall plate 15, one end of a reinforced concrete force transmission belt is connected with the cast-in-situ bored pile 1, the other end of the reinforced concrete force transmission belt 13 is connected with the first floor slab 14 of the basement and the wall plate 15 respectively, and the section steel support changing 10 is detached when the construction of the first floor slab 14 of the basement and the reinforced concrete force transmission belt 13 is completed and the maintenance reaches 100% of the design strength.
Here, a construction joint may be provided between the first poured foundation slab 11 and the later poured foundation slab.
The utility model discloses an eliminate when current support form is under construction to its adverse effect that produces of deep weak soil area super large area foundation ditch, carry out optimal design to excavation supporting structure and excavation scheme. The utility model discloses to deep weak soil area super large area foundation ditch, make enclosure effect reach the construction quality requirement, when to the foundation ditch effect reinforcing for the time limit for a project, save the cost.
The utility model discloses at first to a fender pile, interior support and excavation subregion arrange and carry out optimal design, support in order to replace the large tracts of land through the method that divides the hole in the foundation ditch setting more than 50m square soil remaining district. And then carrying out earth excavation of the advanced area, and construction of a foundation slab and a support replacing structure. The horizontal inner support is then removed. And then performing the works of earth excavation, steel pipe pile recovery, foundation slab construction and maintenance and the like of the later implementation area. And finally, completing the back construction of the basement structure and the dismantling work of the temporary support replacement.
The utility model has the advantages of as follows:
(1) The construction quality is stable, and the pile forming quality of the pile foundation is good;
(2) The construction is convenient, the construction period is short, and the construction progress is fast;
(3) The building envelope has low construction cost, utilizes the reserved soil area and has greater economy;
(4) The construction feasibility and the operability are strong, and the adaptability to the site and similar stratums is strong.
As shown in fig. 1-3, according to the utility model discloses an on the other hand still provides a foundation ditch envelope, include:
the method comprises the following steps of firstly excavating a region 8 and a later excavating region 12, wherein the later excavating region is located in the central region of a foundation pit, and the firstly excavating region 8 is located in the peripheral region of the later excavating region 12;
the cast-in-situ bored pile comprises a cast-in-situ bored pile 1 and a triaxial mixing pile 2 which are arranged on the periphery of an excavation area 8, wherein the cast-in-situ bored pile 1 and the triaxial mixing pile 2 are arranged adjacently, and the triaxial mixing pile 2 is arranged on the outer side of the cast-in-situ bored pile 1;
the steel pipe pile 3 is arranged on the periphery of the rear excavation area;
and the upright post pile 4 is arranged between the steel pipe pile 3 and the cast-in-situ bored pile 1.
The utility model discloses an in the foundation ditch envelope structure embodiment, still include:
the purlin 5 is arranged on the inner side of the top of the cast-in-situ bored pile 1;
a concrete cap 6 arranged on the top of the steel pipe pile 3;
one end of the supporting beam 7 is connected with the surrounding purlin 5, the other end of the supporting beam 7 is connected with the reinforced concrete capping beam 6, and the middle of the supporting beam 7 is connected with the top of the upright post pile 4.
The utility model discloses an in the foundation ditch envelope structure embodiment, still include:
the section steel force transmission belt 9 is arranged on the side, close to the excavation region 8, of the steel pipe pile 3;
one end of the foundation slab 11 is connected with one end of the cast-in-situ bored pile 1, and the other end of the foundation slab 11 is connected with the profile steel force transmission belt 9, wherein the foundation slab 11 is arranged on the lower part of the support beam 7 in parallel;
the section steel trades and props, the section steel trades the one end that props 10 with bored concrete pile 1 is connected, the section steel trades the other end that props 10 with soleplate 11 is connected.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other.
It will be apparent to those skilled in the art that various changes and modifications may be made in the invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (7)

1. A foundation pit support structure is characterized by comprising:
the method comprises the following steps of firstly excavating a region and a later excavating region, wherein the later excavating region is positioned in the central region of a foundation pit, and the first excavating region is positioned in the peripheral region of the later excavating region;
arranging a cast-in-situ bored pile and a triaxial stirring pile at the periphery of a prior excavation area, wherein the cast-in-situ bored pile and the triaxial stirring pile are arranged adjacently, and the triaxial stirring pile is arranged on the outer side of the cast-in-situ bored pile;
the steel pipe piles are arranged on the periphery of the rear excavation area;
and the upright pile is arranged between the steel pipe pile and the cast-in-situ bored pile.
2. The foundation pit enclosure of claim 1 further comprising:
and the purlin is arranged on the inner side of the top of the cast-in-situ bored pile.
3. The foundation pit enclosure of claim 2 further comprising:
and the reinforced concrete capping beam is arranged at the top of the steel pipe pile.
4. The foundation pit enclosure of claim 3 further comprising:
one end of the supporting beam is connected with the surrounding purlin, the other end of the supporting beam is connected with the reinforced concrete capping beam, and the middle of the supporting beam is connected with the top of the upright post pile.
5. The foundation pit enclosure of claim 4 further comprising:
and the section steel force transmission belt is arranged on the side, close to the excavation region, of the steel pipe pile.
6. The foundation pit enclosure of claim 5 further comprising:
the one end of soleplate, soleplate with drilling bored concrete pile one end with drilling bored concrete pile connects, soleplate's the other end with shaped steel biography power area is connected, wherein, soleplate parallel arrangement in the lower part of a supporting beam.
7. The foundation pit enclosure of claim 6 further comprising:
the section steel trades and props, the section steel trades the one end that props with the bored concrete pile is connected, the section steel trades the other end that props with soleplate connects.
CN202123217575.3U 2021-12-21 2021-12-21 Foundation pit enclosure structure Active CN217536985U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123217575.3U CN217536985U (en) 2021-12-21 2021-12-21 Foundation pit enclosure structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123217575.3U CN217536985U (en) 2021-12-21 2021-12-21 Foundation pit enclosure structure

Publications (1)

Publication Number Publication Date
CN217536985U true CN217536985U (en) 2022-10-04

Family

ID=83417059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123217575.3U Active CN217536985U (en) 2021-12-21 2021-12-21 Foundation pit enclosure structure

Country Status (1)

Country Link
CN (1) CN217536985U (en)

Similar Documents

Publication Publication Date Title
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN108005399A (en) Add the construction method for building multi-layer underground space under a kind of existing building group
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
US11959243B2 (en) Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction
CN111441343A (en) Mountain photovoltaic support micropore cast-in-place pile foundation system, construction method and application
CN111236952A (en) Full-recovery assembly type rectangular pipe-jacking working well steel structure supporting device and construction method of working well
CN105064711A (en) Method for constructing underground garage between residential buildings
CN108385693B (en) Equal-generation anchor bolt supporting method and system for staged basement supporting
CN100443673C (en) Method of construction
CN112682045A (en) Bearing structure of underground tunnel ultra-shallow buried underpass highway and construction method
CN209941754U (en) High-voltage power pipe culvert in-situ protection structure
CN210195766U (en) Underground structure is built in same direction as digging to hunch lid
CN111549789A (en) Reinforcing structure for foundation pit support and construction method thereof
CN217536985U (en) Foundation pit enclosure structure
CN110924404A (en) Construction method for deep backfill filling wall foundation
CN110847188A (en) Ultra-deep foundation pit earth excavation platform structure and construction method thereof
CN207597914U (en) Add the construction stress structure for building multi-layer underground space under a kind of existing building group
CN116289979A (en) Deep foundation pit supporting construction method for underground forward and reverse synchronous construction
CN114922195A (en) Construction method of soft soil deep and large foundation pit adjacent to protected object
CN112627002B (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN212052780U (en) Oblique supporting type deep foundation pit supporting structure
CN114263185A (en) Foundation pit support structure and construction method thereof
CN211395691U (en) Structure for improving vertical supporting node
CN217734046U (en) Supporting pile and supporting plate combined supporting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant