CN116289979A - Construction Method of Deep Foundation Pit Supporting Underground Simultaneous Construction - Google Patents
Construction Method of Deep Foundation Pit Supporting Underground Simultaneous Construction Download PDFInfo
- Publication number
- CN116289979A CN116289979A CN202310189215.1A CN202310189215A CN116289979A CN 116289979 A CN116289979 A CN 116289979A CN 202310189215 A CN202310189215 A CN 202310189215A CN 116289979 A CN116289979 A CN 116289979A
- Authority
- CN
- China
- Prior art keywords
- basement
- foundation pit
- construction
- underground
- structural beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明的地下顺逆同步施工的深基坑支护施工方法,针对地下室顶板与地面不位于同一水平面时,需在基坑内设置横向支撑加强支护,降低了施工效率的问题。步骤如下:采用顺作法先期施工中心岛区域,将中心岛区域土体放坡开挖至地下室第二道结构梁板标高下方,浇筑地下室第二道结构梁板的中心部分;在压顶梁与地下室第二道结构梁板之间间隔设置并固接多根斜抛撑;挖除基坑周边区域并浇筑施工地下室第二道结构梁板,待地下室第二道结构梁板达到要求强度后,拆除斜抛撑,采用顺作法施工地下一层结构及地上各层结构,同步开挖地下室第二道结构梁板下方土体并采用逆作法按序施工地下各层结构。
The deep foundation pit supporting construction method of underground forward and reverse simultaneous construction of the present invention is aimed at the problem that when the basement roof and the ground are not located on the same horizontal plane, it is necessary to set transverse supports in the foundation pit to strengthen the support, which reduces the construction efficiency. The steps are as follows: use the straight method to construct the central island area in advance, excavate the soil in the central island area to the level below the second structural beam slab in the basement, and pour the central part of the second structural beam slab in the basement; The second structural beams and slabs are arranged at intervals and fixed with multiple diagonal throwing braces; the surrounding area of the foundation pit is excavated and the second structural beams and slabs of the basement are poured. After the second structural beams and slabs of the basement reach the required strength, they are removed Diagonal throwing bracing, using the sequential method to construct the underground structure and the structures of the above-ground layers, simultaneously excavating the soil below the second structural beam slab in the basement and using the reverse method to construct the underground structures in sequence.
Description
技术领域technical field
本发明涉及岩土工程基坑支护技术领域,特别涉及一种地下顺逆同步施工的深基坑支护施工方法。The invention relates to the technical field of geotechnical engineering foundation pit support, in particular to a deep foundation pit support construction method for underground forward and reverse simultaneous construction.
背景技术Background technique
近年来,随着城市化进程的加速,地下空间的开发和利用程度不断加大,基坑深度越来越深,支护结构的施工空间也越发有限。顺作法操作简单、速度快、造价低,支撑构架单纯,工期易掌握、工程质量易控制,但对周边环境破坏较大;逆作法是将地下主体结构的梁、板、柱作为挡土墙的横向支撑,能够大幅度缩短工期,减少了土方量,提高施工的安全性,但地下结构中墙柱的混凝土接搭质量较难控制。In recent years, with the acceleration of urbanization, the development and utilization of underground space has been increasing, the depth of foundation pits has become deeper and deeper, and the construction space of support structures has become more and more limited. The forward method is simple in operation, fast in speed, low in cost, simple in the supporting structure, easy to grasp the construction period, and easy to control the project quality, but it will cause great damage to the surrounding environment; the reverse method uses the beams, slabs, and columns of the main underground structure as the retaining wall Lateral support can greatly shorten the construction period, reduce the amount of earthwork, and improve the safety of construction, but the quality of concrete bonding of wall columns in underground structures is difficult to control.
目前,在顺逆同步施工的建筑工程中,通常将地下室顶板作为首道支撑,地下室顶板以上采用顺作法施工地上各层结构,地下室顶板以下采用逆作法施工地下各层结构,然而,当地下室顶板与地面并不位于同一水平面时,地下室顶板无法作为围护结构提供支撑,基坑在开挖过程中,围护结构因悬臂过长导致其变形增大,需通过在基坑内大面积设置横向支撑加强支护,降低了施工效率,且增大了工程成本。At present, in construction projects with simultaneous forward and reverse construction, the basement roof is usually used as the first support. When it is not at the same level as the ground, the roof of the basement cannot provide support as an enclosure structure. During the excavation of the foundation pit, the enclosure structure will deform due to the excessively long cantilever. It is necessary to set up horizontal supports in a large area in the foundation pit. Strengthening the support reduces the construction efficiency and increases the engineering cost.
发明内容Contents of the invention
针对地下室顶板与地面不位于同一水平面时,需通过在基坑内大面积设置横向支撑加强支护,降低了施工效率,且增大了工程成本的问题。本发明的目的是提供一种地下顺逆同步施工的深基坑支护施工方法。When the roof of the basement is not at the same level as the ground, it is necessary to set up a large area of lateral support in the foundation pit to strengthen the support, which reduces the construction efficiency and increases the project cost. The object of the invention is to provide a deep foundation pit support construction method for underground forward and reverse simultaneous construction.
本发明解决其技术问题所采用的技术方案是:一种地下顺逆同步施工的深基坑支护施工方法,步骤如下:The technical solution adopted by the present invention to solve the technical problem is: a deep foundation pit support construction method of underground forward and reverse synchronous construction, the steps are as follows:
S1:施工基坑围护结构,基坑内采用竖向连接的立柱桩和格构桩作为竖向支撑,将地下一层土体划分为中心岛区域及围合于其外侧的周边区域,采用顺作法先期施工中心岛区域,将中心岛区域土体放坡开挖至地下室第二道结构梁板标高下方,浇筑地下室第二道结构梁板的中心部分,割除影响地下室第二道结构梁板和结构柱施工的部分格构桩,使得格构桩顶部位于地下室第二道结构梁板的底部;S1: Construct the foundation pit enclosure structure. Vertically connected column piles and lattice piles are used as vertical supports in the foundation pit. The method is to construct the central island area in advance. The soil in the central island area is sloped and excavated to below the level of the second structural beam and slab in the basement, and the central part of the second structural beam and slab in the basement is poured. Part of the lattice pile for structural column construction, so that the top of the lattice pile is located at the bottom of the second structural beam slab in the basement;
S2:在压顶梁与地下室第二道结构梁板的中心部分之间间隔设置并固接多根斜抛撑,割除影响斜抛撑设置的部分格构桩;S2: Set and fasten multiple diagonal braces at intervals between the top beam and the central part of the second structural beam slab in the basement, and cut off some lattice piles that affect the installation of diagonal braces;
S3:挖除基坑周边区域预留土坡并继续浇筑施工地下室第二道结构梁板,待地下室第二道结构梁板达到设计要求的强度后,拆除斜抛撑,采用顺作法施工地下一层结构及地上各层结构,同步开挖地下室第二道结构梁板下方土体并采用逆作法按序施工地下各层结构。S3: Excavate the reserved soil slope in the surrounding area of the foundation pit and continue to pour the second structural beam slab in the basement. After the second structural beam slab in the basement reaches the strength required by the design, remove the oblique struts and use the straight method to construct the first underground structure. Layer structure and the structure of each layer above the ground, the soil below the second structural beam slab in the basement is excavated simultaneously, and the structure of each underground layer is constructed sequentially by using the reverse method.
本发明的地下顺逆同步施工的深基坑支护施工方法,首先,将基坑地下一层土体划分为中心岛区域及周边区域,采用顺作法先期施工中心岛区域,放坡开挖地下一层土体并浇筑地下室第二道结构梁板的中心部分,在压顶梁与地下室第二道结构梁板之间安装斜抛撑,接着,挖除基坑周边区域预留土坡并完成地下室第二道结构梁板的浇筑施工,待地下室第二道结构梁板达到设计要求的强度后,拆除斜抛撑并采用顺作法施工地下一层及其上部各层结构,同步开挖地下室第二道结构梁板下方土体并采用逆作法按序施工地下各层结构;本发明的地下顺逆同步施工的深基坑支护施工方法至少具有如下有益效果:In the deep foundation pit support construction method of underground forward and reverse simultaneous construction of the present invention, firstly, the underground layer of foundation pit soil is divided into a central island area and surrounding areas, the central island area is constructed in advance by the forward method, and the underground is excavated by sloping. A layer of soil and pouring the central part of the second structural beam slab in the basement, installing diagonal throw braces between the top beam and the second structural beam slab in the basement, and then excavating the reserved soil slope around the foundation pit and completing the basement For the pouring construction of the second structural beam and slab, after the second structural beam and slab of the basement reaches the strength required by design, the oblique throwing braces will be removed and the structure of the first basement and its upper floors will be constructed by the sequential method, and the second basement will be excavated simultaneously. The soil mass under the beam slab of the road structure and the structure of each underground layer are sequentially constructed by using the reverse method; the deep foundation pit support construction method of the underground forward and backward simultaneous construction of the present invention has at least the following beneficial effects:
1、与现有逆作法将地下室第一道结构梁板作为首道水平支撑不同,该施工方法先期施工中心岛区域并浇筑地下室第二道结构梁板中心部分,并在压顶梁和地下室第二道结构梁板之间增设斜抛撑,使得围护结构、斜抛撑、格构桩及部分主体结构相互连接共同构成一完整的支护结构受力体系,以抵抗周边水土压力及施工荷载等,基坑内支撑构架得以简化,不但提高了施工效率,缩短了工期,避免了常规顺作法施工因搭设及拆除水平支撑所带来的工期长、环境污染等不利因素,而且,斜抛撑后期可拆除回收再利用,有效节约了工程造价,实现了绿色化施工;1. Different from the existing top-down method, which uses the first structural beam and slab of the basement as the first horizontal support, this construction method constructs the center island area in advance and pours the center part of the second structural beam and slab in the basement. Diagonal braces are added between the beams and slabs of the road structure, so that the enclosure structure, diagonal braces, lattice piles and part of the main structure are connected to each other to form a complete supporting structure force system to resist surrounding water and soil pressure and construction loads, etc. , the support structure in the foundation pit can be simplified, which not only improves the construction efficiency, shortens the construction period, but also avoids the disadvantages of long construction period and environmental pollution caused by the erection and removal of horizontal supports in conventional construction. Dismantle, recycle and reuse, effectively saving the project cost and realizing green construction;
2、由于将地下室第二道结构梁板作为逆作法首道水平支撑,即在地面以下就进行顺逆结合上、下同步施工,减少了逆作施工的层数,降低了施工难度,并缩短了等待结构梁板达到设计强度的时间,加快了施工效率,降低了工程成本;2. Since the second structural beam slab in the basement is used as the first horizontal support of the top-down method, that is, the up-and-down simultaneous construction is carried out below the ground, which reduces the number of layers of upside-down construction, reduces the construction difficulty, and shortens the construction time. The time spent waiting for the structural beam and slab to reach the design strength is shortened, the construction efficiency is accelerated, and the project cost is reduced;
3、现有逆作法以地下室第一道结构梁板作为首道水平支撑,为了满足一柱一桩竖向承载力的要求,格构桩的截面尺寸往往大于地下室结构柱,导致结构柱无法包住格构桩,本技术方案由于将地下室第二道结构梁板作为首道支撑,一柱一桩的竖向承载力变小,格构桩的截面尺寸也相应地缩小,便于结构柱包住格构柱实现两者的可靠连接,避免了结构柱无法包住大截面尺寸的格构桩的情况。3. The existing upside-down method uses the first structural beam and slab in the basement as the first horizontal support. In order to meet the vertical bearing capacity requirements of one column and one pile, the cross-sectional size of the lattice pile is often larger than the structural column in the basement, resulting in that the structural column cannot contain In the case of lattice piles, this technical solution uses the second structural beam slab in the basement as the first support, the vertical bearing capacity of one column and one pile becomes smaller, and the cross-sectional size of the lattice piles is also reduced accordingly, which is convenient for the structural columns to enclose The lattice column realizes the reliable connection between the two, avoiding the situation that the structural column cannot cover the lattice pile with a large cross-sectional size.
优选的,所述步骤S1中,所述基坑围护结构的施工方法如下:在地下连续墙所处槽段两侧设置三轴水泥土搅拌桩进行槽壁加固,并通过大直径高压旋喷桩对地下连续墙接缝处进行止水,在位于外侧的三轴水泥土搅拌桩顶部形成“L”型整浇式的混凝土导墙,混凝土导墙一端设置于三轴水泥土搅拌桩内侧,其另一端位于三轴水泥土搅拌桩顶部,在地下连续墙顶部施工压顶梁并设有预留主筋。Preferably, in the step S1, the construction method of the foundation pit enclosure structure is as follows: install three-axis cement-soil mixing piles on both sides of the groove section where the underground diaphragm wall is located to reinforce the groove wall, and use large-diameter high-pressure rotary grouting The pile seals the water at the joints of the underground diaphragm wall, and an "L"-shaped concrete guide wall is formed on the top of the three-axis cement-soil mixing pile located on the outside. One end of the concrete guide wall is set inside the three-axis cement-soil mixing pile. The other end is located on the top of the three-axis cement-soil mixing pile, and a top beam is constructed on the top of the underground diaphragm wall and a reserved main reinforcement is provided.
优选的,所述步骤S1中,基坑地下一层土体的周边区域以放坡平台宽度≥3m,放坡坡度不大于1:1.5的方式开挖,坡面铺设混凝土面板,混凝土面板内设钢筋网,且内设锚筋和插筋进行护坡。Preferably, in the step S1, the surrounding area of the soil body of the basement layer of the foundation pit is excavated in such a way that the width of the grading platform is ≥ 3m, and the grading slope is not greater than 1:1.5. Reinforced mesh, with anchor bars and insert bars inside for slope protection.
优选的,所述砼支座固接于地下室第二道结构梁板中心部分边缘顶部和结构柱之间的交接部位,钢支座铆接于压顶梁侧面,斜抛撑一端焊接在钢支座上,其另一端通过锚板铆接于砼支座。Preferably, the concrete support is fixed at the intersection between the edge top of the center part of the second structural beam slab in the basement and the structural column, the steel support is riveted to the side of the top beam, and one end of the slanting brace is welded on the steel support , the other end of which is riveted to the concrete support through the anchor plate.
优选的,所述地下室第二道结构梁板中心部分端部施工缝处设有预留主筋,预留主筋与后期施工的周边区域的第二道结构梁板的结构主筋进行连接。Preferably, the construction joints at the ends of the central part of the second structural beam slab in the basement are provided with reserved main reinforcement, and the reserved main reinforcement is connected with the structural main reinforcement of the second structural beam slab in the surrounding area of the later construction.
附图说明Description of drawings
图1为本发明的地下顺逆同步施工的深基坑支护施工方法一实施例的中心岛区域顺作开挖的示意图;Fig. 1 is the schematic diagram of excavation in the central island area of an embodiment of the deep foundation pit support construction method of underground forward and reverse synchronous construction of the present invention;
图2为本发明的地下顺逆同步施工的深基坑支护施工方法一实施例中在地下室第一道结构梁板和压顶梁之间设置斜抛撑的示意图。Fig. 2 is a schematic diagram of the installation of diagonal braces between the first structural beam slab and the top beam in the basement in an embodiment of the deep foundation pit support construction method of underground forward and reverse simultaneous construction according to the present invention.
图3为本发明的地下顺逆同步施工的深基坑支护施工方法一实施例的顺逆同步施工的示意图。Fig. 3 is a schematic diagram of forward and reverse simultaneous construction of an embodiment of the deep foundation pit support construction method of underground forward and reverse simultaneous construction according to the present invention.
图中标号如下:The numbers in the figure are as follows:
立柱桩1;格构桩2;混凝土面板3;插筋4;锚筋5;地下连续墙11;三轴水泥土搅拌桩12;高压旋喷桩14;混凝土导墙15;压顶梁16;预留主筋17;地下室第一道结构梁板21;地下室第二道结构梁板22;结构柱25;砼支座26;钢支座27;斜抛撑28。
具体实施方式Detailed ways
以下结合附图和具体实施例对本发明作进一步详细说明。需说明的是,附图均采用非常简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本发明实施例的目的。为叙述方便,下文中所述的“上”、“下”与附图的上、下的方向一致,但这不能成为本发明技术方案的限制。The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that all the drawings are in very simplified form and use inaccurate scales, and are only used to facilitate and clearly assist the purpose of illustrating the embodiments of the present invention. For the convenience of description, the "up" and "down" described below are consistent with the directions of up and down in the drawings, but this should not be a limitation of the technical solution of the present invention.
本实施例中,地下室顶板(即地下室第一道结构梁板21)位于整平地面以上,下面结合图1至图3说明本发明的地下顺逆同步施工的深基坑支护施工方法,具体步骤如下:In this embodiment, the basement roof (i.e., the first
S1:如图1所示,施工基坑围护结构,基坑内采用竖向连接的立柱桩1和格构桩2(即一柱一桩)作为竖向支撑,将地下一层土体划分为中心岛区域及围合于其外侧的周边区域,采用顺作法先期施工中心岛区域,图1中点划线标示区域即为中心岛区域,将中心岛区域土体放坡开挖至地下室第二道结构梁板22标高下方,浇筑地下室第二道结构梁板22的中心部分,如图2所示,割除影响地下室第二道结构梁板22和结构柱25施工的部分格构桩2,即图2中虚线框线且斜线填充的部分格构桩2,使得格构桩2顶部位于地下室第二道结构梁板22的底部;S1: As shown in Figure 1, the foundation pit enclosure structure is constructed, and vertically connected
S2:如图2所示,在压顶梁16与地下室第二道结构梁板22的中心部分之间间隔设置并固接多根斜抛撑28,割除影响斜抛撑28设置的部分格构桩2;S2: As shown in Figure 2, a plurality of
S3:如图3所示,挖除基坑周边区域预留土坡并继续浇筑施工地下室第二道结构梁板22,待地下室第二道结构梁板22达到设计要求的强度后,拆除斜抛撑28,采用顺作法施工地下一层结构及其上部各层结构,同步开挖地下室第二道结构梁板22下方土体并采用逆作法按序施工地下二层结构、地下三层结构等地下各层结构。S3: As shown in Figure 3, excavate the reserved soil slope in the surrounding area of the foundation pit and continue to pour the second
本发明的地下顺逆同步施工的深基坑支护施工方法,首先,将基坑地下一层土体划分为中心岛区域及周边区域,采用顺作法先期施工中心岛区域,放坡开挖地下一层土体并浇筑地下室第二道结构梁板22的中心部分,在压顶梁16与地下室第二道结构梁板22之间安装斜抛撑28,接着,挖除基坑周边区域预留土坡并完成地下室第二道结构梁板22的浇筑施工,待地下室第二道结构梁板22达到设计要求的强度后,拆除斜抛撑28并采用顺作法施工地下一层及其上部各层结构,同步开挖地下室第二道结构梁板22下方土体并采用逆作法按序施工地下各层结构;本发明的地下顺逆同步施工的深基坑支护施工方法至少具有如下有益效果:In the deep foundation pit support construction method of underground forward and reverse simultaneous construction of the present invention, firstly, the underground layer of foundation pit soil is divided into a central island area and surrounding areas, the central island area is constructed in advance by the forward method, and the underground is excavated by sloping. A layer of soil is poured into the central part of the second
1、与现有逆作法将地下室第一道结构梁板21作为首道水平支撑不同,该施工方法先期施工中心岛区域并浇筑地下室第二道结构梁板22中心部分,并在压顶梁16和地下室第二道结构梁板22之间增设斜抛撑28,使得围护结构、斜抛撑28、格构桩2及部分主体结构相互连接共同构成一完整的支护结构受力体系,以抵抗周边水土压力及施工荷载等,基坑内支撑构架得以简化,不但提高了施工效率,缩短了工期,避免了常规顺作法施工因搭设及拆除水平支撑所带来的工期长、环境污染等不利因素,而且,斜抛撑28后期可拆除回收再利用,有效节约了工程造价,实现了绿色化施工;1. Unlike the existing top-down method, which uses the first
2、由于将地下室第二道结构梁板22作为逆作法首道水平支撑,即在地面以下就进行顺逆结合上、下同步施工,减少了逆作施工的层数,降低了施工难度,并缩短了等待结构梁板达到设计强度的时间,加快了施工效率,降低了工程成本;2. Since the second
3、现有逆作法以地下室第一道结构梁板21作为首道水平支撑,为了满足一柱一桩竖向承载力的要求,格构桩2的截面尺寸往往大于地下室结构柱25,导致结构柱25无法包住格构桩2,本技术方案由于将地下室第二道结构梁板22作为首道支撑,一柱一桩的竖向承载力变小,格构桩2的截面尺寸也相应地缩小,便于结构柱25包住格构柱2实现两者的可靠连接,避免了结构柱2无法包住大截面尺寸的格构桩2的情况。3. The existing upside-down method uses the first
如图1所示,本实施例中基坑围护结构的施工方法,步骤如下:在地下连续墙11所处槽段两侧设置三轴水泥土搅拌桩12进行槽壁加固,以确保地下连续墙11成槽安全,并通过RJP大直径高压旋喷桩14对地下连续墙11接缝处进行止水;在位于外侧的三轴水泥土搅拌桩12顶部形成“L”型整浇式的混凝土导墙15,混凝土导墙15一端设置于三轴水泥土搅拌桩12内侧,其另一端位于三轴水泥土搅拌桩12顶部,在地下连续墙11顶部施工压顶梁16并预留主筋17,以便与后期施工的地下室外墙主筋进行连接。As shown in Figure 1, the construction method of the foundation pit enclosure structure in this embodiment, the steps are as follows: install three-axis cement-soil mixing piles 12 on both sides of the groove section where the
请继续参考图1,基坑地下一层土体以放坡平台宽度≥3m,放坡坡度不大于1:1.5的方式开挖,坡面铺设80mm厚C20混凝土面板3,混凝土面板3内设6.5@200×200钢筋网(图中未示出),且内设φ48×3.5锚筋5和φ20插筋4进行护坡。Please continue to refer to Figure 1. The ground floor of the foundation pit is excavated with a grading platform width ≥ 3m and a grading slope of no more than 1:1.5. The 80mm thick C20
如图2所示,砼支座26固接于地下室第二道结构梁板22中心部分边缘顶部和结构柱25之间的交接部位,钢支座27铆接于压顶梁16侧面,斜抛撑28一端焊接在钢支座27上,其另一端通过锚板铆接于砼支座26。As shown in Figure 2, the
所述地下室第二道结构梁板22中心部分端部施工缝处预留主筋17,便于与后期施工的周边区域的第二道结构梁板的结构主筋进行连接。The
所述地下室第二道结构梁板22的施工缝距坡底预留大于等于1m的施工操作空间。A construction operation space greater than or equal to 1m is reserved between the construction joints of the second
上述描述仅是对本发明较佳实施例的描述,并非对本发明范围的任何限定,本发明领域的普通技术人员根据上述揭示内容做的任何变更、修饰,均属于权利要求范围。The above description is only a description of the preferred embodiments of the present invention, and does not limit the scope of the present invention. Any changes and modifications made by those of ordinary skill in the field of the present invention based on the above disclosures shall fall within the scope of the claims.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310189215.1A CN116289979A (en) | 2023-03-02 | 2023-03-02 | Construction Method of Deep Foundation Pit Supporting Underground Simultaneous Construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310189215.1A CN116289979A (en) | 2023-03-02 | 2023-03-02 | Construction Method of Deep Foundation Pit Supporting Underground Simultaneous Construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116289979A true CN116289979A (en) | 2023-06-23 |
Family
ID=86800713
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310189215.1A Pending CN116289979A (en) | 2023-03-02 | 2023-03-02 | Construction Method of Deep Foundation Pit Supporting Underground Simultaneous Construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116289979A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117248539A (en) * | 2023-11-17 | 2023-12-19 | 上海建工一建集团有限公司 | Co-construction reverse excavation supporting structure for subway cross soft soil oversized foundation pit and construction method |
| CN118880897A (en) * | 2024-09-30 | 2024-11-01 | 上海建工四建集团有限公司 | A method for controlling micro-deformation of foundation pit in soft soil area |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08269969A (en) * | 1995-03-30 | 1996-10-15 | Toudentsuu:Kk | Sheathing device |
| CN108203994A (en) * | 2018-03-14 | 2018-06-26 | 中建四局第建筑工程有限公司 | Along the method for subinverse construction technology on a kind of basement |
| CN109778866A (en) * | 2018-12-20 | 2019-05-21 | 上海建工集团股份有限公司 | Combination supporting system and its construction method for foundation pit central island basin excavation |
| CN112922028A (en) * | 2021-02-02 | 2021-06-08 | 中铁四局集团有限公司 | Construction method suitable for oversized circular subway station |
-
2023
- 2023-03-02 CN CN202310189215.1A patent/CN116289979A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08269969A (en) * | 1995-03-30 | 1996-10-15 | Toudentsuu:Kk | Sheathing device |
| CN108203994A (en) * | 2018-03-14 | 2018-06-26 | 中建四局第建筑工程有限公司 | Along the method for subinverse construction technology on a kind of basement |
| CN109778866A (en) * | 2018-12-20 | 2019-05-21 | 上海建工集团股份有限公司 | Combination supporting system and its construction method for foundation pit central island basin excavation |
| CN112922028A (en) * | 2021-02-02 | 2021-06-08 | 中铁四局集团有限公司 | Construction method suitable for oversized circular subway station |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117248539A (en) * | 2023-11-17 | 2023-12-19 | 上海建工一建集团有限公司 | Co-construction reverse excavation supporting structure for subway cross soft soil oversized foundation pit and construction method |
| CN117248539B (en) * | 2023-11-17 | 2024-02-06 | 上海建工一建集团有限公司 | Co-construction reverse excavation supporting structure for subway cross soft soil oversized foundation pit and construction method |
| CN118880897A (en) * | 2024-09-30 | 2024-11-01 | 上海建工四建集团有限公司 | A method for controlling micro-deformation of foundation pit in soft soil area |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102747736B (en) | A combined tool-type internal support replacement method | |
| CN112962663B (en) | Construction Method of Narrow Outer Protection Space for Deep Foundation | |
| CN105926963A (en) | Vertical supporting method of underground top-down storey addition of existing high-rise building | |
| CN101418577B (en) | Construction Method of Covering and Excavating Underground Space Pavement in Soft Soil Area | |
| KR101011805B1 (en) | Method of constructing underground structures crossing the pile foundation and underground structures constructed using the same | |
| CN116289979A (en) | Construction Method of Deep Foundation Pit Supporting Underground Simultaneous Construction | |
| CN108978680B (en) | Mucky soil elevator foundation pit supporting construction device and method | |
| CN116180757A (en) | A deep foundation pit support system | |
| CN210737607U (en) | A hang braced system for reverse construction method beam slab construction | |
| CN219732023U (en) | A kind of enclosure pile and steel diagonal brace enclosure structure | |
| CN219586774U (en) | Prefabricated retaining wall suitable for crown beam top | |
| CN116464060A (en) | A construction method for accelerating high-span area structures at high-span areas of basement floors | |
| CN118360949A (en) | A large-area deep foundation pit support system and construction method | |
| CN116988506A (en) | Structure integrated tower crane foundation structure and construction method thereof | |
| CN113266038B (en) | Construction method for excavating underground building in foundation pit | |
| CN111827705A (en) | Method for expanding well barrel-shaped underground garage in existing underground garage | |
| CN115822252A (en) | Construction method and supporting structure of limited space ultrahigh batter post | |
| CN116497835A (en) | Construction method of a combined steel sheet pile support system | |
| CN115369916A (en) | A kind of underground building construction method | |
| CN114508113A (en) | Construction method of waist-supported anti-sliding pile structure | |
| CN201172825Y (en) | A Beam-column Joint Used in Foundation Pit Engineering of Upside-Down Method | |
| CN108442406B (en) | Semi-reverse construction method foundation pit inner supporting structure and construction method thereof | |
| CN218090882U (en) | An underground structure that does not need to be replaced during the construction period | |
| CN115492126B (en) | Foundation pit supporting structure and method for combining steel sheet piles and vertical shafts | |
| CN215629919U (en) | Use RJP stake to consolidate foundation ditch and compromise structure of biography power area |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |
