CN216041201U - Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards - Google Patents

Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards Download PDF

Info

Publication number
CN216041201U
CN216041201U CN202122146580.3U CN202122146580U CN216041201U CN 216041201 U CN216041201 U CN 216041201U CN 202122146580 U CN202122146580 U CN 202122146580U CN 216041201 U CN216041201 U CN 216041201U
Authority
CN
China
Prior art keywords
pile
piles
foundation pit
double
diagonal bracing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122146580.3U
Other languages
Chinese (zh)
Inventor
周玉石
谢晓东
谢益飞
张群
周磊
刘泽海
张亚风
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Teyu Technology Co ltd
Original Assignee
Shanghai Chengdi Rock Soil Design Co ltd
Shanghai Chengdixiangjiang Data Technology Co ltd
Chengdi Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Chengdi Rock Soil Design Co ltd, Shanghai Chengdixiangjiang Data Technology Co ltd, Chengdi Construction Group Co ltd filed Critical Shanghai Chengdi Rock Soil Design Co ltd
Priority to CN202122146580.3U priority Critical patent/CN216041201U/en
Application granted granted Critical
Publication of CN216041201U publication Critical patent/CN216041201U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model relates to a supporting-first-excavation double-layer inclined supporting foundation pit supporting system which comprises a vertical waterproof curtain and an inclined supporting structure, wherein the vertical waterproof curtain comprises a row of cement soil mixing piles, H-shaped sheet piles are inserted in the row of cement soil mixing piles, the H-shaped sheet piles are precast piles, the inclined supporting structure comprises an upper inclined pile and a lower inclined pile, the inclined piles are precast piles, and the inclined piles and the vertical waterproof curtain are connected through ring beams. The utility model greatly shortens the construction period, reduces the construction cost, has simple structure and large excavation space, and is particularly suitable for the deep foundation pit support of a two-storey basement.

Description

Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards
Technical Field
The utility model belongs to the technical field of foundation pit engineering, and particularly relates to a support-first-excavation double-layer inclined support foundation pit support system.
Background
The existing support type of the foundation pit of the two-layer basement is mainly composed of row piles and two supports, the horizontal support can be generally in the form of a reinforced concrete inner support or a steel support (a steel pipe support, an H-shaped steel support, a prestressed fish-belly sill inner support and the like), the lower part of the support is provided with stand columns which are different in support, the number of the stand columns is large or small, so that the construction operation surface of the foundation pit is narrow, the excavation of earthwork in the pit is difficult, the total construction period is seriously influenced, and the removal of the horizontal support is also a factor influencing the construction progress after the underground structure is constructed to a support replacement position; in addition, the horizontal support and the upright post pile have higher manufacturing cost. In summary, no economical, safe, energy-saving, environment-friendly and fast-construction enclosure mode exists in the foundation pit of the two-layer basement, and the utility model provides a possibility based on the aim.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a support-and-excavation double-layer inclined support foundation pit support system according to the defects of the prior art, the support-and-excavation double-layer inclined support foundation pit support system has the advantages of economy, safety, energy conservation, environmental protection, quick construction and the like, and the construction space in a foundation pit cannot be reduced, so that the construction period of the foundation pit is shortened while the construction cost is saved.
The utility model is realized by the following technical modes:
1. the utility model provides an earlier prop later and dig double-deck diagonal bracing foundation ditch enclosure system, enclosure system include vertical stagnant water curtain and slant supporting construction, vertical stagnant water curtain include one row of cement mixing pile, its interpolation H type sheet pile, H type sheet pile be the precast pile, slant supporting construction be upper and lower twice batter pile, the batter pile be the precast pile, adopt the collar tie beam to be connected between batter pile and the vertical stagnant water curtain.
2. The pile top of the batter pile is arranged in the ring beam.
3. The oblique angle of the oblique pile can be adjusted within 15-50 degrees.
4. The upper and lower layers of inclined piles are arranged in a staggered mode, and the distance between the upper and lower layers of inclined piles is 3-7 m.
5. The inclined pile is pressed in through an inclined pile pressing machine.
6. The construction method of the enclosure system comprises the following steps:
1) leveling a construction site, and releasing a real sample according to a construction drawing;
2) constructing a row of vertical cement-soil mixing piles and internally-inserted H-shaped plate piles;
3) obliquely pressing two oblique piles in the pile by using an oblique pile pressing machine;
4) excavating earth to a construction operation surface of the ring beam, and pouring the ring beam between the top of the upper layer of the inclined piles and the vertical waterproof curtain to enable the inclined piles and the vertical waterproof curtain to form a whole;
5) after the ring beam concrete reaches the design strength, excavating earthwork layer by layer to the next layer of inclined pile ring beam construction operation surface;
6) repeating the step 4), excavating earthwork in layers to the bottom of the foundation pit, and pouring a reinforcement cushion layer;
7) then constructing a ground warehouse structure (to +/-0.000);
8) constructing an outer wall of an underground structure for waterproofing, backfilling a gap between the outer wall and a containment to an inclined strut position, firstly cutting inclined piles between the outer wall and a waterproof curtain, and then cutting inclined piles in an underground chamber;
9) and after the oblique piles are cut off, continuously backfilling the earth to the ground.
Compared with the prior art, the utility model provides a construction method of a recyclable foundation pit support system with support before excavation, which has the following advantages:
1. the upper layer support of the foundation pit does not have any support and anchor cable, the excavation space is large, the excavation speed of the foundation pit is high, and a larger construction space is provided for other underground construction operations;
2. the H-shaped sheet pile and the inclined pile belong to prefabricated components, so that the strength is high, the mass production and the standardized production are realized, and the cost is low;
3. simple structure, the efficiency of construction is high.
Drawings
FIG. 1 is a schematic view of a double-layer inclined support foundation pit support system formed by firstly supporting and then excavating
1-ring beam 2-inclined pile 3-cement soil mixing pile 4-H type sheet pile 5-reinforcing bar cushion layer
Detailed Description
The utility model is described in detail with reference to the figures and the specific embodiments. The embodiments are implemented on the premise of the technical scheme of the utility model, and detailed implementation modes and specific operation processes are given below. The present invention is intended to be protected by the structural forms of the present invention itself, but the scope of the present invention is not limited to the following examples.
Examples
As shown in fig. 1, a prop earlier and dig double-deck diagonal bracing foundation ditch enclosure system afterwards, enclosure system include vertical waterproof curtain and slant supporting construction, vertical waterproof curtain include one row of cement mixing pile 3, its interpolation H template pile 4, slant supporting construction be upper and lower twice batter pile 2, the batter pile be the precast pile, adopt collar tie 1 to be connected between batter pile and the vertical waterproof curtain.
The utility model relates to a construction method for a support-first and excavation-later double-layer inclined support foundation pit support system, which comprises the following steps:
1) leveling a construction site, and releasing a real sample according to a construction drawing;
2) constructing a row of vertical cement mixing piles 3 and an inserted H-shaped plate pile 4;
3) obliquely pressing two oblique piles 2 into the pile by using an oblique pile press;
4) excavating earth to the construction operation surface of the ring beam 1, pouring the ring beam 1 between the top of the upper layer of inclined piles 2 and the vertical waterproof curtain, and enabling the inclined piles 2 and the vertical waterproof curtain to form a whole;
5) after the concrete of the ring beam 1 reaches the design strength, excavating earthwork layer by layer to the next layer of inclined piles 2 and constructing the operation surface of the ring beam 1;
6) repeating the step 4), excavating earthwork in layers to the bottom of the foundation pit, and pouring a reinforcement cushion layer 5;
7) then constructing a ground warehouse structure (to +/-0.000);
8) constructing an outer wall of an underground structure for waterproofing, backfilling a gap between the outer wall and a containment to an inclined strut position, firstly cutting an inclined pile 2 between the outer wall and a waterproof curtain, and then cutting an inclined pile 2 in an underground chamber;
9) and after the inclined piles 2 are cut off, earth is continuously backfilled to the ground.

Claims (5)

1. The utility model provides an earlier prop later and dig double-deck diagonal bracing foundation ditch enclosure system, enclosure system include vertical stagnant water curtain and slant supporting construction, vertical stagnant water curtain include one row of cement mixing pile, its interpolation H type sheet pile, H type sheet pile be the precast pile, slant supporting construction be upper and lower twice batter pile, the batter pile be the precast pile, adopt the collar tie beam to be connected between batter pile and the vertical stagnant water curtain.
2. The system of claim 1, wherein the batter pile is supported and then dug within a collar beam.
3. The foundation pit support system with the double-layer diagonal bracing structure, according to claim 1, wherein the diagonal angle of the diagonal piles can be adjusted within 15-50 °.
4. The foundation pit support system with the double-layer diagonal bracing structure, according to claim 1, is characterized in that the upper and lower inclined piles are arranged in a staggered manner, and the distance between the upper and lower inclined piles is 3-7 m.
5. The system of claim 1, wherein the slanted pile is pressed into the foundation pit by an oblique pile press.
CN202122146580.3U 2021-09-07 2021-09-07 Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards Active CN216041201U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122146580.3U CN216041201U (en) 2021-09-07 2021-09-07 Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122146580.3U CN216041201U (en) 2021-09-07 2021-09-07 Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards

Publications (1)

Publication Number Publication Date
CN216041201U true CN216041201U (en) 2022-03-15

Family

ID=80597504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122146580.3U Active CN216041201U (en) 2021-09-07 2021-09-07 Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards

Country Status (1)

Country Link
CN (1) CN216041201U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115262573A (en) * 2022-07-13 2022-11-01 上海勘察设计研究院(集团)有限公司 Combined type multilayer vertical self-stabilizing enclosure structure and construction method
CN115262572A (en) * 2022-07-13 2022-11-01 上海勘察设计研究院(集团)有限公司 Multi-channel multi-layer self-stabilizing foundation pit supporting device and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115262573A (en) * 2022-07-13 2022-11-01 上海勘察设计研究院(集团)有限公司 Combined type multilayer vertical self-stabilizing enclosure structure and construction method
CN115262572A (en) * 2022-07-13 2022-11-01 上海勘察设计研究院(集团)有限公司 Multi-channel multi-layer self-stabilizing foundation pit supporting device and construction method

Similar Documents

Publication Publication Date Title
CN212641473U (en) Foundation pit supporting structure adjacent to existing building
CN216041201U (en) Earlier prop and dig double-deck diagonal bracing foundation ditch enclosure system afterwards
CN110004919B (en) Foundation pit enclosure construction method used in pipeline influence range
CN110777806B (en) Multi-connecting-rod plane frame permanent supporting structure and construction process thereof
CN109024662A (en) Method of the anchor pile underpinning without basement building underground space increasing layer
CN111851567A (en) Wind power foundation newly built or expanded on soft foundation shallow covering layer and construction method thereof
CN111236241A (en) Weak water-rich stratum subway foundation pit reinforcing excavation method based on half-cover excavation method
CN113550322A (en) Enclosure system next to deep and shallow foundation pit and construction method
CN105064711A (en) Method for constructing underground garage between residential buildings
CN116289979A (en) Deep foundation pit supporting construction method for underground forward and reverse synchronous construction
CN216713040U (en) Full-prefabricated pier type portal inclined support pile structure system
CN213709548U (en) Advanced structure system for positive and negative zero beam plates in deep foundation pit building seat area
CN212052780U (en) Oblique supporting type deep foundation pit supporting structure
CN114250784A (en) Foundation pit enclosure system combining piles with inclined piles in support-first and excavation-later construction method
CN111851541A (en) Circular secant pile-single-wall steel combined cofferdam and construction method
CN111733830B (en) Super high-rise building foundation pit bearing and enclosing system
CN113931228B (en) Material platform construction method for basement construction
CN217298886U (en) Transmission line engineering slip casting rock anchor foundation structure
CN220580007U (en) Inclined strut supporting structure of steel lattice column of subway deep foundation pit
CN218757521U (en) PC construction method pile and inclined strut combined supporting structure
CN109137944B (en) Construction method of water-stop wall in deep-water bottom-sealing-free steel cofferdam
CN201896321U (en) Construction device for underground substation by topdown construction method
CN218667560U (en) Precast concrete square pile and steel lattice combined diagonal bracing
CN211006702U (en) Inclined strut underground structure is thrown in soft soil foundation double-deck
CN217734046U (en) Supporting pile and supporting plate combined supporting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231106

Address after: Room J815, 3rd Floor, No. 5358 Huyi Road, Jiading District, Shanghai, June 2018

Patentee after: Zhongji Engineering (Shanghai) Geotechnical Co.,Ltd.

Address before: 201806 room j404, 3 / F, No. 5358, Huyi Road, Jiading District, Shanghai

Patentee before: Chengdi Construction Group Co.,Ltd.

Patentee before: Shanghai chengdixiangjiang Data Technology Co.,Ltd.

Patentee before: SHANGHAI CHENGDI ROCK-SOIL DESIGN Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240201

Address after: 201306 2nd Floor, No. 979 Yunhan Road, Lingang New Area, Jiading District, Shanghai

Patentee after: Shanghai Teyu Technology Co.,Ltd.

Country or region after: China

Address before: Room J815, 3rd Floor, No. 5358 Huyi Road, Jiading District, Shanghai, June 2018

Patentee before: Zhongji Engineering (Shanghai) Geotechnical Co.,Ltd.

Country or region before: China