CN216851234U - Ground anchor type cable high-hanging device - Google Patents

Ground anchor type cable high-hanging device Download PDF

Info

Publication number
CN216851234U
CN216851234U CN202123133671.XU CN202123133671U CN216851234U CN 216851234 U CN216851234 U CN 216851234U CN 202123133671 U CN202123133671 U CN 202123133671U CN 216851234 U CN216851234 U CN 216851234U
Authority
CN
China
Prior art keywords
cable
support
rod
connecting rod
vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123133671.XU
Other languages
Chinese (zh)
Inventor
李征宇
张自安
朱峻齐
李文祥
陆通
孔宪勇
刘钊
王鑫
李佳俊
王坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Construction Engineering Co Ltd
Original Assignee
Wuhan Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Construction Engineering Co Ltd filed Critical Wuhan Construction Engineering Co Ltd
Priority to CN202123133671.XU priority Critical patent/CN216851234U/en
Application granted granted Critical
Publication of CN216851234U publication Critical patent/CN216851234U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses a high device of hanging of earth anchor formula cable, including support body, vertical holding power pole, one side of support body is provided with climbs the horizontal pole, and the support body upper end is provided with the cable support, and a plurality of insulating vase pass through the connecting rod to be fixed on the I shape support of cable support, and the cable erects through insulating vase. The lower end of the frame body is provided with a plurality of sets of fixing assemblies which comprise longitudinal holding rods and transverse connecting rods, the longitudinal holding rods are drilled into the soil body through a drilling spanner, the transverse connecting rods and the upper ends of the longitudinal holding rods are fixed together through cross fasteners, the frame body can be fixed, and the reliable and firm ground anchor type cable high-hanging device is formed. The device simple structure, the installation is dismantled conveniently, but reuse, the earth anchor sets up the position and can changes in a flexible way, erects that the cable is firm reliable, provides safe and reliable's condition of erectting to earth excavation stage cable very much.

Description

Ground anchor type cable high-hanging device
Technical Field
The utility model relates to a construction site cable erection protection technical field, concretely relates to device is hung to ground anchor formula cable height.
Background
In the project early planning stage of a building project, a temporary power utilization organization design is compiled, and a detailed guidance scheme is provided for the arrangement and the trend of cables. However, the site construction situation is complex, the construction situations of the excavation stage and the structure construction stage are different, the situation that the cable is excavated and broken or crushed by a vehicle and the like often occurs, the site production progress is directly influenced, and even some safety accidents occur.
In construction sites, cables are usually laid directly in trenches, or laid on the ground, covered with wooden covers, etc., and some cables are erected on walls, etc. However, in some construction stages, the cable is easily broken, for example, in an earth excavation stage, the power supply cable leading to the tower crane is generally directly thrown on the ground, and the cable is easily buried in the earth in the excavation stage and is easily broken when excavated again. Of course, measures can be taken on site, such as erecting the cable by arranging a steel pipe tripod, if the root of the tripod is not poured with concrete, the stability and the safety can not be ensured, and the later-stage dismantling of the poured concrete is troublesome.
Disclosure of Invention
In order to solve the problem that above-mentioned prior art exists, the utility model provides a device is hung to earth anchor formula cable height, the device simple structure, the installation is dismantled conveniently, but reuse, the earth anchor sets up the position and can change in a flexible way, erects the firm reliable of cable, provides safe and reliable's condition of erectting to the earth excavation stage cable very much.
Realize the utility model discloses the technical scheme that above-mentioned purpose adopted does:
the utility model provides a ground anchor type cable height hangs device, comprising a frame body, cable support and fixed subassembly, cable support installs at the support body top, the last suspension of cable support has a plurality of insulating porcelain insulator, detachable installs the fixed subassembly of many sets of ground anchor types around the support body lower part, fixed subassembly includes vertical holding power pole and transverse connecting rod, vertical holding power pole lower extreme buries underground deeply, transverse connecting rod one end fixed mounting is in the lower part of support body, the other end and the position fastening connection of vertical holding power pole more than ground.
The support body includes many montants and the horizontal pole of welding between the montant, and the support body can be a truss, is provided with on one side of the truss and climbs the horizontal pole, makes things convenient for the workman to climb and hangs the cable.
The cable support comprises an I-shaped support and a plurality of insulating porcelain bottles, the insulating porcelain bottles penetrate through the connecting rod along the central axis, the connecting rod is parallel to the support rod in the middle of the I-shaped support, and two ends of the connecting rod are fixed on the fixing plates extending upwards from two ends of the support rod respectively, so that the insulating porcelain bottles can be suspended above the support rod, and cables can slide on the insulating porcelain bottles and be erected.
The lower end of the longitudinal holding rod is spiral, and the top end of the longitudinal holding rod is square.
The utility model discloses a support body, including support body, horizontal connecting rod, cross fastener, through-hole I, through-hole II, through-hole I and through-hole II, horizontal connecting rod one end is detained detachable through the U type and is installed on the montant of support body, and the other end passes through cross fastener and vertical holding power pole fastening connection, the U type is detained have with the straight portion of montant contact of support body to fix on the montant is close to the height on ground through straight portion, the U type is detained the perpendicular ear of both sides and has been seted up through-hole I, the one end of horizontal connecting rod is equipped with and can insert the U type and detain middle connecting portion, through-hole II has been seted up to this connecting portion, the connecting portion of horizontal connecting rod inserts the U type and detains the back, through-hole I aligns with through-hole II, the screw rod passes through-hole I and through-hole II back, it is rotatory that the horizontal connecting rod uses montant (21) of support body as the pivot.
Compared with the prior art, the beneficial effects and advantages of the utility model reside in that:
the device simple structure, the installation is dismantled conveniently, but reuse, but the ground anchor formula of vertical holding force pole sets up the position and can change in a flexible way, erects the cable firm reliable, provides safe and reliable's condition of erectting to the earth excavation stage cable very much.
Drawings
Fig. 1 is a schematic structural diagram of a ground anchor type cable high-hanging device.
Fig. 2 is an assembly schematic diagram of the cable support and the porcelain insulator.
FIG. 3 is an assembly view of the U-shaped fastener and the transverse link.
Fig. 4 is an assembly schematic of the transverse link.
FIG. 5 is a schematic view of a longitudinal support bar.
Fig. 6 is a schematic view of a drilling wrench.
The device comprises a frame body 1, a vertical rod 21, a transverse rod 22, a transverse rod 2, a cable support 3, an I-shaped support 31, a pair of support rods 32, a through rod 4, an insulating porcelain bottle 5, a U-shaped buckle 6, a transverse connecting rod 7, a cross fastener 8, a longitudinal holding rod 9, a screw rod 10, a nut 11 and a drilling wrench 12.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
The structure of the ground anchor type cable hanging device provided by this embodiment is as shown in fig. 1, and includes a frame body 1, a cable support 3, and a fixing assembly.
As shown in fig. 1 and 2, a cable support 3 is installed on the upper portion of the frame body 1, the cable support 3 includes an i-shaped support 31 and a plurality of porcelain insulators 5, the porcelain insulators 5 penetrate through the connecting rod 4 along the central axis, the connecting rod 4 is parallel to the support rod 32 in the middle of the i-shaped support 31, and two ends of the support rod are respectively fixed on the fixing plates extending upwards from two ends of the support rod 32, so that the porcelain insulators 5 can be suspended above the support rod 32, and a cable can slide on the porcelain insulators 5 and be erected.
As shown in fig. 1 and 3, a plurality of sets of fixing components are uniformly distributed on the lower portion of the frame body 1, each set of fixing component comprises a transverse connecting rod 7 and a longitudinal supporting rod 9, one end of each transverse connecting rod 7 is detachably mounted on a vertical rod of the frame body 1 through a U-shaped buckle 4, and the other end of each transverse connecting rod is fixedly connected with the longitudinal supporting rod 9 through a cross-shaped buckle 8. As shown in fig. 3 and 4, the U-shaped buckle 6 has a vertical bar contact straight portion with the support body 1, and fix on the height that the vertical bar of the support body 1 is close to the ground through straight portion, the vertical ears at both sides of the U-shaped buckle 6 have opened through-hole one, the one end of the transverse connecting rod 7 is equipped with a connecting portion that can be inserted into the middle of the U-shaped buckle 6, through-hole two has been opened to this connecting portion, the connecting portion of the transverse connecting rod 7 inserts the U-shaped buckle 6 back, through-hole one aligns with through-hole two, after the screw rod 10 passed through-hole one and through-hole two, the transverse connecting rod 7 can use the vertical bar of the support body 1 as a rotating shaft, in the circumferential direction of the support body 1. As shown in fig. 5 and 6, the lower end of the longitudinal holding rod 9 is spiral, the top end is square and can match with the trepan of the wrench 12, and the longitudinal holding rod 9 can be drilled into the soil for stabilization by drilling the wrench 12.
Support body 1 comprises many montants 21 and the horizontal pole 22 of setting between the montant, and in order to make support body 1 more firm, support body 1 can be a truss, is provided with on one side of the truss and climbs horizontal pole 2, makes things convenient for the workman to climb and hangs the cable.
The fabrication and installation of the device is further described below:
the manufacturing of this device: the support body 1 is formed by welding 50mm square steel and 30mm small square steel, wherein the vertical rod is 50mm square steel, the transverse rod is 30mm small square steel, the transverse climbing rod 2 is also 30mm square steel, the horizontal plane projection outer edge size is 400mm x 400mm rectangle, the height is 2.5m, and the height can be different according to different engineering conditions. The cable support 3 is made of 50mm square steel, steel sheets with the thickness of 10mm are arranged on two sides of the middle support rod, and the insulating porcelain bottle 5 is butterfly-shaped and has the model ED-1. And welding two ends of the connecting rod 4 penetrated with a plurality of insulating porcelain bottles 5 on the steel sheet of the cable support 3. And the assembly parts of the cable support 3 and the insulating porcelain bottle 5 are welded at the upper end of the frame body 1. The U-shaped buckle 6 and the transverse connecting rod 7 are manufactured and processed in a factory. The clear interval in the middle of the U-shaped buckle 6 is 52mm, the diameter of a through hole on the vertical lugs at two sides of the U-shaped buckle is 22mm, and the U-shaped buckles 6 are welded at the positions, close to the ground, of the vertical rods of the frame body 1. The thickness of the connecting part of the transverse connecting rod 7 inserted into the U-shaped buckle 6 is 50mm, the diameter of the through hole II on the transverse connecting rod is 22mm, and the transverse connecting rod 7 is a common steel pipe with the outer diameter of 48 mm. The screw 10 is selected to be M20, and the nut 11 is the corresponding matching model. The middle rod piece of the longitudinal supporting rod 9 is solid round steel, the section size is 48mm, a spiral piece with the thickness of 10mm is welded on the periphery of the lower end of the middle rod piece, and the cross section of the uppermost end of the middle rod piece is a square with the thickness of 40mm multiplied by 40 mm. The transverse links 7 and the longitudinal support bars 9 can be connected by means of conventional cross fasteners 8. The drilling wrench 12 is also custom made with a central trepan size of 40mm x 40 mm.
When the device is installed and used, the position is selected and leveled according to the trend of cable planning, the rack body with the upper end welded with the cable support and the insulating porcelain bottle assembly part is placed at the selected position, and the longitudinal holding rod 9 is drilled into the soil at a plurality of positions on the periphery of the rack body through the drilling wrench 12. A plurality of transverse connecting rods 7 are inserted into the U-shaped buckle 6, and a screw rod 10 and a nut 11 are installed. The cross-shaped fastener 8 is fastened by rotating the transverse link 7 and approaching the longitudinal support rod 9 drilled into the soil. And finishing the placing and fixing work of the device. And finally, a worker erects a cable on the insulating porcelain bottle 5 through the climbing cross rod 2, and in order to ensure safety, the worker needs to wear a safety belt which can be hung on the climbing cross rod 2.

Claims (5)

1. The utility model provides a high device of hanging of ground anchor formula cable, comprising a frame body (1), cable support (3) and fixed subassembly, a serial communication port, install at support body (1) top cable support (3), it has a plurality of insulating vase (5) to hang on cable support (3), detachable installs the fixed subassembly of many sets of ground anchor formulas around support body (1) lower part, fixed subassembly is including vertical power pole (9) and horizontal connecting rod (7), vertical power pole (9) lower extreme buries underground deeply, horizontal connecting rod (7) one end fixed mounting is in the lower part of support body (1), the other end and vertical power pole (9) position fastening connection more than ground.
2. An earth-anchored cable high-hanging device as claimed in claim 1, wherein the frame body (1) comprises a plurality of vertical rods (21) and cross rods (22) welded between the vertical rods (21), the frame body (1) can be a truss, and a climbing rod (2) is arranged on one side of the truss to facilitate workers to climb up and hang cables.
3. An earth-anchored cable high-hanging device as claimed in claim 1, wherein the cable support (3) comprises an i-shaped bracket (31) and a plurality of porcelain insulators (5), the porcelain insulators (5) penetrate through the connecting rod (4) along the central axis, the connecting rod (4) is parallel to the support rod (32) in the middle of the i-shaped bracket (31), and two ends of the connecting rod are respectively fixed on fixing plates extending upwards from two ends of the support rod (32), so that the porcelain insulators (5) can be hung above the support rod (32), and the cable can be slid and erected on the porcelain insulators (5).
4. An earth-anchored cable overhead suspension device according to claim 1, wherein the longitudinal support bar (9) is helical at its lower end and square at its top end.
5. An earth-anchored cable overhead suspension device as defined in claim 1 or claim 2, one end of the transverse connecting rod (7) is detachably arranged on a vertical rod (21) of the frame body (1) through a U-shaped buckle (6), the other end is fixedly connected with a longitudinal supporting rod (9) through a cross fastener (8), the U-shaped buckle (6) is provided with a straight part which is contacted with the vertical rod (21) of the frame body (1), and is fixed on the vertical rod (21) at the height close to the ground through the straight part, the vertical lugs at the two sides of the U-shaped buckle (6) are provided with a through hole I, one end of the transverse connecting rod (7) is provided with a connecting part which can be inserted into the middle of the U-shaped buckle (6), the connecting part is provided with a second through hole, after the connecting part of the transverse connecting rod (7) is inserted into the U-shaped buckle (6), the screw rod (10) penetrates through the first through hole and the second through hole which are aligned up and down, and the transverse connecting rod (7) rotates by taking the vertical rod (21) of the frame body (1) as a rotating shaft.
CN202123133671.XU 2021-12-14 2021-12-14 Ground anchor type cable high-hanging device Active CN216851234U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123133671.XU CN216851234U (en) 2021-12-14 2021-12-14 Ground anchor type cable high-hanging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123133671.XU CN216851234U (en) 2021-12-14 2021-12-14 Ground anchor type cable high-hanging device

Publications (1)

Publication Number Publication Date
CN216851234U true CN216851234U (en) 2022-06-28

Family

ID=82108028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123133671.XU Active CN216851234U (en) 2021-12-14 2021-12-14 Ground anchor type cable high-hanging device

Country Status (1)

Country Link
CN (1) CN216851234U (en)

Similar Documents

Publication Publication Date Title
CN103470093B (en) Concrete chimney dismantling method
CN204435979U (en) A kind of protection device for installing of electric power facility
CN113323365B (en) Elevator shaft protection platform and construction method
CN207392772U (en) A kind of no cable wind rope steel column straightening system
JP5351382B2 (en) Method for assembling shaft scaffolding and method for removing shaft scaffolding
JP3181041U (en) Mounting member for scaffolding for bridge
CN216851234U (en) Ground anchor type cable high-hanging device
CN203867274U (en) Installing equipment for double cross arms
CN205145443U (en) Transformer upper portion construction safety belt hanging device
JP2012002030A (en) Temporary scaffold for slope face and installation method of the same
CN111527302B (en) Method for building a tower, tower segment, supply structure and tower
CN109019371B (en) Turnover supporting device and tower crane climbing method
CN105311771A (en) Safety belt suspending device for upper construction of transformer
JP6223874B2 (en) Lifting device and method of attaching and removing pole using the same
KR102281205B1 (en) Extension arm and construction method of transmission tower
JP2019108701A (en) Fence for safety measures of reinforced soil wall construction
CN107217912A (en) It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction
CN210460176U (en) Protector for construction
CN111764623A (en) Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method
JP6108512B1 (en) Suspension scaffold and installation method
CN206873970U (en) A kind of adjustable BIPV project constructions roofing edge protection device
CN220504477U (en) Easily install and wide scaffold frame of encorbelmenting of application scope
CN218205631U (en) Oblique roofing hanging flower basket erects frame
CN216516801U (en) Lifting device for assembly of assembly type building
CN214368976U (en) Monitoring rod

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant