CN210460176U - Protector for construction - Google Patents

Protector for construction Download PDF

Info

Publication number
CN210460176U
CN210460176U CN201921245041.1U CN201921245041U CN210460176U CN 210460176 U CN210460176 U CN 210460176U CN 201921245041 U CN201921245041 U CN 201921245041U CN 210460176 U CN210460176 U CN 210460176U
Authority
CN
China
Prior art keywords
fixed
main base
building construction
vertically arranged
protector
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921245041.1U
Other languages
Chinese (zh)
Inventor
陈仙娇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921245041.1U priority Critical patent/CN210460176U/en
Application granted granted Critical
Publication of CN210460176U publication Critical patent/CN210460176U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a protector for construction, including the main base, the both ends of main base all have the support side post of vertical setting through bolted connection, two the spacing post groove of vertical setting is all seted up at the top of supporting the side post, two the spacing post of vertical setting has been cup jointed in the circumference inner wall slip of spacing post groove, two there is the fixed ejector pin of same level setting through bolted connection between the top of spacing post, the slip king-rod of vertical setting is installed to the bottom of fixed ejector pin. The utility model discloses in, the gim peg piece is all installed at the bottom both ends of main base, and gim peg piece and main base become the vertically state, and extends to both sides, and the gim peg piece is fixed through gim peg hole and ground, improves the distance of fixed point for whole protector's fixed stability more, when whole protector risees, also can provide stronger ground power of grabbing, make this protector's use longer-term and safety more.

Description

Protector for construction
Technical Field
The utility model relates to a construction technical field especially relates to a protector for construction.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place. The method comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like.
In the in-process of construction, because high altitude construction possess dangerous occurence of failure such as object fall, consequently need erect the protection rail and keep apart danger area on ground, present construction site often uses monoblock various steel tile iron sheet and cooperation iron pipe to weld the support, the bottom is only fixed through two inflation screws, the land fertility of grabbing of whole bottom is insecure, and bottom stress point interval is little, make the difference of the stability ten minutes of whole protection rail, do not have the stability of long-term use.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a protective device for building construction.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a protector for construction, includes the main base, there is the support side post of vertical setting, two at the both ends of main base all through bolted connection the spacing post groove of vertical setting, two are all seted up at the top of support side post the spacing post of vertical setting is slided to cup joint the spacing post of vertical setting, two through bolted connection has the fixed ejector pin of same level setting between the top of spacing post, the slip king-rod of vertical setting is installed to the bottom of fixed ejector pin, two top position between the support side post has the connecting rod of level setting through bolted connection, the fixed orifices of vertical setting is seted up at the top of connecting rod, and the fixed orifices cup joints with the slip king-rod mutually.
Preferably, the fixing bolt pieces horizontally arranged are arranged at two ends of the bottom of the main base, and two fixing bolt holes are formed in the tops of the two fixing bolt pieces.
Preferably, two the equal screw thread of one end that supports the side post and be located spacing post groove has cup jointed spacing bolt.
Preferably, the bottom of one side of each of the two limiting columns is provided with a limiting bolt hole, and the limiting bolt holes are connected with limiting bolts.
Preferably, a vertically arranged fixed rail is connected between the top of the main base and the bottom of the connecting rod through a bolt.
Preferably, the bottom of the sliding middle rod is provided with a horizontally arranged limiting wafer.
Preferably, the two supporting side columns are provided with a fixing frame on one side close to each other, a vertically arranged scissor type support is hinged between the two fixing frames, and the top of the scissor type support is hinged with the top of the fixed ejector rod in a sliding manner.
The utility model has the advantages that:
1. this protector for construction, the gim peg piece is all installed at protector's main base's bottom both ends, and gim peg piece and main base become the vertically state, and to the both sides extension, the gim peg piece is fixed through gim peg hole and ground, improve the distance of fixed point, make whole protector's fixed stability more, when whole protector risees, also can provide stronger ground power of grabbing, make this protector's use longer-term and safety more.
2. This protector for construction installs the slip king-rod in the bottom of protector's fixed ejector pin, and the slip king-rod cup joints with the fixed orifices of connecting rod mutually, can make the slip king-rod lapse when the protector joint, imbeds between connecting rod and the main base for when this protector has better wall ability, also have folding nature of being convenient for to accomodate.
3. This protector for construction installs the formula support of cutting through the mount between protector's main base and fixed ejector pin, can unload the fixed ejector pin at top and the strength of slip king-rod to main base when protector risees on, prevent that the power at whole top from bearing at the top that supports the side post, also make whole device more stable.
Drawings
Fig. 1 is a schematic view of the overall structure of a protective device for building construction according to the present invention;
fig. 2 is a schematic diagram of a structure of a limit bolt hole of the protective device for building construction provided by the utility model;
fig. 3 is the utility model provides a protection device for construction's formula of cutting support structure sketch map.
In the figure: the device comprises a fixing bolt hole 1, a fixing bolt piece 2, a supporting side column 3, a limiting bolt 4, a limiting column 5, a fixing ejector rod 6, a sliding middle rod 7, a connecting rod 8, a limiting wafer 9, a main base 10, a limiting bolt hole 11, a limiting column groove 12, a fixing hole 13, a shear type support 14 and a fixing railing 15.
Detailed Description
The technical solution of the present patent will be described in further detail with reference to the following embodiments.
Reference will now be made in detail to embodiments of the present patent, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are exemplary only for the purpose of explaining the present patent and are not to be construed as limiting the present patent.
In the description of this patent, it is to be understood that the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in the orientations and positional relationships indicated in the drawings for the convenience of describing the patent and for the simplicity of description, and are not intended to indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and are not to be considered limiting of the patent.
In the description of this patent, it is noted that unless otherwise specifically stated or limited, the terms "mounted," "connected," and "disposed" are to be construed broadly and can include, for example, fixedly connected, disposed, detachably connected, disposed, or integrally connected and disposed. The specific meaning of the above terms in this patent may be understood by those of ordinary skill in the art as appropriate.
Example 1
Referring to fig. 1-2, a protector for construction, including main base 10, the both ends of main base 10 all have the support side post 3 of vertical setting through bolted connection, the spacing post groove 12 of vertical setting is all seted up at the top of two support side posts 3, the spacing post 5 of vertical setting has been cup jointed in the circumference inner wall slip of two spacing post grooves 12, there is fixed ejector pin 6 of same level setting through bolted connection between the top of two spacing posts 5, the slip king-rod 7 of vertical setting is installed to the bottom of fixed ejector pin 6, the top position between two support side posts 3 has the connecting rod 8 of level setting through bolted connection, the fixed orifices 13 of vertical setting is seted up at the top of connecting rod 8, and fixed orifices 13 cup joints mutually with slip king-rod 7.
The utility model discloses in, the gim peg piece 2 that the level set up is all installed at the bottom both ends of main base 10, and two gim peg holes 1 have all been seted up at two gim peg piece 2's top, two one end equal screw threads that support 3 side posts and be located spacing post groove 12 have cup jointed spacing bolt 4, spacing keyhole 11 has all been seted up to one side bottom of two spacing posts 5, and spacing keyhole 11 is connected with spacing bolt 4, there is the fixed railing 15 of vertical setting through bolted connection between the top of main base 10 and the bottom of connecting rod 8, the spacing disk 9 that the level set up is installed to the bottom of pole 7 in the slip.
Example 2
Referring to fig. 1-3, a protection device for building construction, wherein fixed frames are installed on one side, close to a supporting side column 3, of the supporting side column, a vertically arranged scissor type support 14 is hinged between the two fixed frames, the top of the scissor type support 14 is hinged with the top of a fixed ejector rod 6 in a sliding mode, the force of the fixed ejector rod 6 and the force of a sliding middle rod 7 on the top can be unloaded onto a main base 10 when the protection device is lifted, the force of the whole top is prevented from being borne on the top of the supporting side column 3, and the whole device is further stable.
The working principle is as follows: when the protective device for building construction is used, an operator inserts the top and the bottom of the protective device to ensure that the whole protective device has smaller volume and is conveyed to a protected section, when the operator takes off the protective device, the fixed bolt piece 2 at the bottom of the main base 10 is fixed at the position of the ground through the fixed bolt hole 1 and is fixed stably, the operator loosens the limit bolt 4 through a screwdriver, stretches the fixed ejector rod 6 at the top and the sliding middle rod 7 upwards to ensure that the position of the top is lifted, and is connected with the limit bolt hole 11 through the tightening of the limit bolt 4 to ensure that the whole protective device is fixed stably, the sliding middle rod 7 and the fixed railing 15 can ensure the middle filling, so that the whole rigidity is stronger, and the lifting of the shear type support 14 can provide certain tension to ensure that the whole lifted protective device is fixed more stably, the pressure of the raised top position on the top of the support jamb 3 is reduced making the guard more stable.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. A protective device for building construction comprises a main base (10) and is characterized in that, the two ends of the main base (10) are connected with vertically arranged supporting side columns (3) through bolts, the tops of the two supporting side columns (3) are respectively provided with a vertically arranged limiting column groove (12), the circumferential inner walls of the two limiting column grooves (12) are sleeved with a vertically arranged limiting column (5) in a sliding manner, a fixing ejector rod (6) which is horizontally arranged is connected between the tops of the two limiting columns (5) through bolts, the bottom of the fixed ejector rod (6) is provided with a vertically arranged sliding middle rod (7), the top position between the two supporting side columns (3) is connected with a horizontally arranged connecting rod (8) through a bolt, the top of the connecting rod (8) is provided with a vertically arranged fixing hole (13), and the fixing hole (13) is sleeved with the sliding middle rod (7).
2. The protection device for building construction according to claim 1, characterized in that the horizontally arranged fixing bolt pieces (2) are installed at both ends of the bottom of the main base (10), and two fixing bolt holes (1) are opened at the tops of the two fixing bolt pieces (2).
3. The protection device for building construction according to claim 1, characterized in that the limit bolt (4) is sleeved on the end of the two support side columns (3) located in the limit column groove (12) in a threaded manner.
4. The protection device for building construction according to claim 3, characterized in that the bottom of one side of each of the two limit posts (5) is provided with a limit bolt hole (11), and the limit bolt holes (11) are connected with the limit bolts (4).
5. The protection device for building construction according to claim 1, characterized in that a vertically arranged fixed rail (15) is connected between the top of the main base (10) and the bottom of the connecting rod (8) through a bolt.
6. A protective device for building construction according to claim 1, characterized in that the bottom of the sliding middle rod (7) is provided with a horizontally arranged limiting disc (9).
7. The protection device for building construction according to claim 1, characterized in that a fixed frame is installed on one side of each of the two supporting side columns (3) close to each other, a vertically arranged scissor-type bracket (14) is hinged between the two fixed frames, and the top of the scissor-type bracket (14) is slidably hinged with the top of the fixed ejector rod (6).
CN201921245041.1U 2019-08-02 2019-08-02 Protector for construction Expired - Fee Related CN210460176U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921245041.1U CN210460176U (en) 2019-08-02 2019-08-02 Protector for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921245041.1U CN210460176U (en) 2019-08-02 2019-08-02 Protector for construction

Publications (1)

Publication Number Publication Date
CN210460176U true CN210460176U (en) 2020-05-05

Family

ID=70449400

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921245041.1U Expired - Fee Related CN210460176U (en) 2019-08-02 2019-08-02 Protector for construction

Country Status (1)

Country Link
CN (1) CN210460176U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012571A (en) * 2020-09-11 2020-12-01 赵邦娥 Collapsible anti building rail of falling of preventing wind based on spring buckle

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012571A (en) * 2020-09-11 2020-12-01 赵邦娥 Collapsible anti building rail of falling of preventing wind based on spring buckle

Similar Documents

Publication Publication Date Title
CN103526949A (en) Lifting and slipping device for wall-attached vertical structure and construction method thereof
CN210460176U (en) Protector for construction
CN105003090A (en) Temporary support frame for mounting assembly type steel structure
CN210369825U (en) But carrying frame is built in height-adjusting formula room
CN210342602U (en) Scaffold frame convenient to adjust for building engineering
CN111350337A (en) Bearing frame for building construction
CN204876631U (en) Assembled steel structure installation uses interim support frame
CN204754159U (en) Outer wall body is encorbelmented board and is built template and set up support
CN107988915B (en) Self-elevating water platform for bridge construction
CN204662501U (en) A kind of pass in and out immersed tube vertical occasional passage
CN212897455U (en) Prevent portable scaffold frame that topples
CN212249300U (en) Construction faces limit protective structure
CN213015777U (en) Movable protective fence for building construction
CN211548680U (en) Scaffold for building construction
CN209891688U (en) High building quick-building safe construction foot rest
CN217734758U (en) Anti-overturning scaffold with strong stability
CN211473323U (en) Operating platform for elevator well
CN213927558U (en) A assembled platform of unloading safely for construction
CN218842867U (en) Movable bridge arch rib support frame
CN215926657U (en) Construction engineering site operation platform
CN213597433U (en) Insulating fast-assembling scaffold frame
CN205063307U (en) Dedicated uninstallation device of inserted lift scaffold
CN220059030U (en) Top support frame device
CN218406331U (en) Anti-tilting scaffold
CN215854775U (en) Anti-climbing device for tower crane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200505

Termination date: 20210802

CF01 Termination of patent right due to non-payment of annual fee