CN216617582U - Shaft maintenance construction platform - Google Patents

Shaft maintenance construction platform Download PDF

Info

Publication number
CN216617582U
CN216617582U CN202122479577.3U CN202122479577U CN216617582U CN 216617582 U CN216617582 U CN 216617582U CN 202122479577 U CN202122479577 U CN 202122479577U CN 216617582 U CN216617582 U CN 216617582U
Authority
CN
China
Prior art keywords
support
platform
cage
sleeve
maintenance construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122479577.3U
Other languages
Chinese (zh)
Inventor
张康
李�杰
单卫东
张�浩
尹晓平
张喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN202122479577.3U priority Critical patent/CN216617582U/en
Application granted granted Critical
Publication of CN216617582U publication Critical patent/CN216617582U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a shaft maintenance construction platform which comprises a platform support and a platform plate detachably arranged above the platform support, wherein the platform support comprises at least two movable supports, each movable support comprises a support column, the upper end of each support column is vertically connected with a sleeve, a support rod penetrates through the sleeve, two ends of each support rod are respectively provided with a baffle, the support columns are uniformly arranged on one side of the top of a cage side by side, the support rods extend towards the outer side of the cage, threaded holes are uniformly formed in the upper side surfaces, extending out of the sleeves, of the support rods, the platform plate is flatly laid above the support rods, through holes corresponding to the threaded holes are formed in the platform plate, and the platform plate is arranged above the support rods through bolts in the through holes. The utility model can be arranged at the top of the cage, the supporting rod extends out when in use, and the supporting rod is recycled when not in use, so that the utility model does not need to be erected every time and is convenient to use.

Description

Shaft maintenance construction platform
Technical Field
The utility model relates to the technical field of mine construction, in particular to a shaft maintenance construction platform.
Background
Vertical wells in mines in China are developed and divided into main wells and auxiliary wells, wherein the main wells mainly lift ores, and the auxiliary wells mainly lift and lower personnel, materials, equipment and waste rocks. The steel structure facility in the auxiliary shaft has the condition of corrosion and damage after being used for a long time, in order to ensure the use safety of the auxiliary shaft, the auxiliary shaft is required to be maintained regularly, an air supply pipeline, a water drainage pipeline and a water supply pipeline are arranged in the auxiliary shaft, the pipelines are all fixed on a cage way beam bracket, the structure is complex, great trouble is caused to shaft maintenance or facility replacement, and the maintenance or facility replacement requires long time. At present, maintenance is generally adopted, a temporary platform is built on the upper portion of a cage for operation, the temporary platform is detached after maintenance is finished, maintenance time is long, normal use of the cage is affected, normal underground work is affected, the platform needs to be built and detached again during each maintenance, and working efficiency is low.
SUMMERY OF THE UTILITY MODEL
In view of the above problems, an object of the present invention is to provide a shaft maintenance construction platform, which is installed on the top of a cage, and has a movable support extending out when in use, and a movable support retracting when not in use, and is not required to be set up each time, and is convenient to use, and the cage can be used at any time when in other situations during maintenance.
The utility model provides a shaft maintenance construction platform, which comprises a platform support and a platform plate detachably arranged above the platform support, wherein the platform support comprises at least two movable supports, each movable support comprises a support column, the upper end of each support column is vertically connected with a sleeve, a support rod penetrates through the sleeve, two ends of each support rod are respectively provided with a baffle, the area of each baffle is larger than that of the end part of each support rod, and the length of each support rod is larger than 3 times of that of each sleeve; the supporting columns are uniformly arranged on one side of the top of the cage side by side, the supporting rods extend out of the cage, and threaded holes are uniformly formed in the upper side faces, extending out of the sleeve, of the supporting rods; the platform board is spread the top of bracing piece be provided with on the platform board with the corresponding through-hole of screw hole, the platform board passes through bolt in the through-hole is installed the top of bracing piece.
The sleeve is a steel pipe with a rectangular longitudinal section, and the support column is a cylindrical steel pipe.
Reinforcing ribs are uniformly arranged at the joints of the supporting columns and the sleeves.
Reinforcing ribs are uniformly arranged at the joints of the supporting columns and the top of the cage.
The platform plate is a steel plate or a wood plate.
The support rod is a channel steel or a steel pipe.
The bracing piece orientation the one end in the outside of cage is connected with the guardrail, the guardrail includes rectangular frame, rectangular frame's width with the width of bracing piece is the same, rectangular frame's broadside passes through the bolt and installs the up side tip of bracing piece.
The bracing piece to stretch out the inboard of cage the bracing piece stretches out sheathed tube side of going up just closes on sheathed tube position is provided with the screw hole be provided with spacing bolt in the screw hole.
The bracing piece to stretch out the inboard of cage the bracing piece stretches out sheathed tube horizontal side just closes on sheathed tube position is provided with the through-hole be provided with bolt and nut combination on the through-hole.
From the above description, it can be seen that the shaft maintenance construction platform provided by the present invention is characterized in that a plurality of movable supports which can be extended and retracted relative to the top edge are installed on the top of the cage, after the support rods of the movable supports are extended, the platform plate is laid on the upper portion of the movable supports, a worker stands on the platform plate to perform shaft maintenance, after the maintenance is completed, the platform plate is detached, and the support rods are retracted to the position above the top of the cage. Need not to build and demolish when maintaining at every turn, have other circumstances to use cage or personnel when from top to bottom during the maintenance, can easily pull down the landing slab, the bracing piece is retrieved to the cage top, ensures cage normal operating. The problem of normal operation of the cage in the shaft maintenance period is effectively solved, so that the safety of maintenance personnel is greatly improved, and the auxiliary shaft can be better and comprehensively maintained. The utility model has the advantages of simple structure, convenient use, safety, reliability, improvement of working efficiency and lower cost.
Drawings
Other objects and results of the present invention will become more apparent and more readily appreciated as the same becomes better understood by reference to the following description and appended claims, taken in conjunction with the accompanying drawings.
In the drawings:
FIG. 1 is a schematic illustration of a wellbore maintenance construction platform according to an embodiment of the present invention;
FIG. 2 is a top view of a wellbore maintenance construction platform according to an embodiment of the present invention;
FIG. 3 is a schematic diagram of a retracted configuration of a mobile stent according to an embodiment of the present invention;
wherein, 1-platform support, 2-platform plate, 3-movable support, 4-support column, 5-sleeve, 6-support rod, 7-baffle, 8-bolt, 9-reinforcing rib, 10-guardrail, 11-limit bolt, 12-cage.
The same reference numbers in all figures indicate similar or corresponding features or functions.
Detailed Description
Specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
FIG. 1 is a schematic illustration of a wellbore maintenance construction platform according to an embodiment of the present invention; FIG. 2 is a top view of a wellbore maintenance construction platform according to an embodiment of the present invention; FIG. 3 is a schematic diagram of a retracted configuration of a mobile stent according to an embodiment of the present invention;
as shown in fig. 1, 2 and 3, the shaft maintenance construction platform provided by this embodiment may be used for shaft maintenance and repair, and may also be used as a repair platform installed on the upper portion of other cages.
This embodiment includes platform support 1 and can dismantle the landing slab 2 of setting in platform support 1 top, and platform support 1 includes two at least movable support 3, and movable support 3 evenly sets up side by side at a side edge at cage 12 top, and movable support 3 can stretch out and retrieve for the top edge. When the movable support 3 extends out, the platform plate 2 is laid on the part extending out of the top of the cage for workers to stand. The number of the movable supports 3 is determined according to the construction specific situation.
The movable support 3 comprises a support column 4, a sleeve 5 is vertically connected to the upper end of the support column 4, the support column 4 can be a cylindrical steel pipe, the sleeve 5 can be a steel pipe with a rectangular longitudinal section, and the middle of the wider side face of the sleeve 5 is welded with the upper port of the support column 4. In order to firmly weld the sleeve 5 and the support pillar 4, reinforcing ribs 9 are uniformly arranged at the connecting circumference of the support pillar 4 and the sleeve 5.
In order to facilitate the movable support 3 to extend out of the top of the cage, a support rod 6 is arranged in the sleeve 5 in a penetrating mode, the support rod 6 can be made of channel steel or steel pipes, and the support rod 6 is matched with the inside of the sleeve 5. In order to prevent the support column 4 from sliding out of the sleeve 5, baffles 7 are arranged at two ends of the support rod 6, and the area of each baffle 7 is larger than that of the end part of the support rod 6. When the support column 4 extends out of the top of the cage in the sleeve 5 or the support column 4 is recovered from the sleeve 5 to the inner side of the top of the cage, the baffle 7 plays a limiting role.
The support column 4 welds the position that is close to the edge in one side at cage 12 top side by side evenly, and for support column 4 welding is firm, the circumference department is connected evenly to support column 4 and cage 12's top is provided with the strengthening rib. The sleeve 5 should be inside the rim, preferably not protruding from the rim. The length of the support rod 6 is determined according to the specific construction situation, and in order to ensure the bearing of the support rod 6, the length of the support rod 6 is x, wherein x is more than 3 times of the length of the sleeve and less than 5 times of the length of the sleeve. The height of the supporting column 4 can be determined according to the condition of the top of the cage, and the movement of the supporting rod is not influenced.
The platform plate 2 is used for standing construction of workers. When the shaft needs to be maintained, the supporting rod 6 of each movable support 3 extends out of the cage, and the upper side surface of the part, extending out of the sleeve 5, of the supporting rod 6 is evenly provided with an internal thread hole along the axis direction. The landing slab 2 tiles in all 6 tops of bracing piece, is provided with the through-hole corresponding with every screw hole on landing slab 2, and the bolt 8 that landing slab 2 passes through in the through-hole is installed in 6 tops of bracing piece. The support bars 6 support workers on the deck plate 2 and the deck plate. The platform plate can be a patterned steel plate or a wood plate.
In order to further increase the safety, a guardrail 10 is connected to one end of the support bar 6 facing the outside of the cage, the guardrail 10 comprises a rectangular frame, the width of the rectangular frame is the same as that of the support bar 6, and the width side of the rectangular frame is mounted at the upper side end of the support bar 6 through bolts. Protective ropes can be connected between the guardrails on the adjacent support rods 6 to prevent workers from falling from the platform.
After the shaft is maintained, the support rod 6 is recovered to the top of the cage. In order to prevent the support rod 6 from sliding outwards in the running process of the cage and colliding with the cage guide beam or the wind and water pipeline. If support column 4 is the channel-section steel, retrieve the back completely to the cage inboard at bracing piece 6, stretch out the side of going up of sleeve pipe part and close to sheathed tube position and be provided with the internal thread hole, twist limit bolt 11 in the internal thread hole. The sleeve 5 is limited between the baffle 7 and the limit bolt 11, and the support rod 6 cannot move.
If the support column 4 is a steel pipe, the support rod 6 can extend out of the horizontal side face of the sleeve 5 part after being completely recovered towards the inner side of the cage, a through hole is formed in the position close to the sleeve 5, and bolt and nut combinations are arranged at two ends of the through hole. The sleeve 5 is constrained between the stop 7 and the bolt and nut combination and the support bar 6 does not move.
At the well casing wall that needs to maintain, this pit shaft maintenance construction platform all needs to be installed to cage top edge that closes on, and the support column of attention every construction platform can not contradict each other after retrieving during the installation.
The use process comprises the following steps:
when beginning the pit shaft maintenance, personnel get into cage top canopy below, at this moment every support column of this construction platform is retrieved in cage top, and the cage is slowly transferred to operating position, dismantles spacing bolt, and every support column stretches out the cage top, and the mounting platform board, constructor can carry out the operation under the condition of effective protection.
When the cage needs to be moved to the next working point, personnel enter the lower part of the rain shelter, the platform plates are disassembled, each supporting column is recovered, the limiting bolts are arranged, and the cage is prevented from colliding with the cage guide beam or the wind-water pipeline during operation.
When personnel need to rise the well in the pit, can easily withdraw every support column at any time, can use the cage to carry out personnel's transport immediately.
The construction platform is fast and reliable, the problem that normal operation of the cage is hindered when a shaft is maintained is effectively solved, the extendable and retractable construction platform guarantees the operation range of shaft maintenance, and construction is safe and reliable.
A wellbore servicing construction platform according to the present invention is described above by way of example with reference to the accompanying drawings. However, it will be appreciated by those skilled in the art that various modifications may be made to the wellbore servicing construction platform set forth above without departing from the teachings of the present invention. Accordingly, the scope of the utility model should be determined from the content of the appended claims.

Claims (9)

1. A shaft maintenance construction platform is characterized by comprising a platform support and a platform plate which is detachably arranged above the platform support, wherein,
the platform support comprises at least two movable supports, each movable support comprises a support column, a sleeve is vertically connected to the upper end of each support column, a support rod penetrates through the sleeve, baffles are arranged at the two ends of each support rod, the area of each baffle is larger than that of the end of each support rod, and the length of each support rod is larger than 3 times of that of each sleeve;
the supporting columns are uniformly arranged on one side of the top of the cage side by side, the supporting rods extend out of the cage, and threaded holes are uniformly formed in the upper side faces, extending out of the sleeve, of the supporting rods;
the platform board is spread the top of bracing piece be provided with on the platform board with the corresponding through-hole of screw hole, the platform board passes through bolt in the through-hole is installed the top of bracing piece.
2. The wellbore maintenance construction platform of claim 1, wherein the casing is a steel tube having a rectangular longitudinal cross-section and the support column is a cylindrical steel tube.
3. The wellbore maintenance construction platform of claim 1, wherein reinforcing ribs are uniformly disposed at the junction of the support columns and the casing.
4. The wellbore maintenance construction platform of claim 1, wherein reinforcing bars are uniformly disposed at the junction of the support columns and the top of the cage.
5. The wellbore maintenance construction platform of claim 1, wherein the platform plate is a steel or wood plate.
6. The wellbore maintenance construction platform of claim 1, wherein the support rods are channel steel or steel pipe.
7. The wellbore maintenance construction platform of claim 1, wherein a guardrail is connected to an end of the support bar facing an outside of the cage, the guardrail comprises a rectangular frame having a width equal to that of the support bar, and a wide side of the rectangular frame is mounted at an upper end of the support bar by bolts.
8. The wellbore maintenance construction platform of claim 1, wherein the support bar extends inwardly of the cage, a threaded hole is provided in the support bar adjacent the sleeve at a position where the support bar extends above the upper side of the sleeve, and a stop bolt is disposed in the threaded hole.
9. The wellbore maintenance construction platform of claim 1, wherein the support rods extend inwardly of the cage, through holes are provided in the support rods extending out of the horizontal sides of the casing adjacent the casing, and bolt and nut assemblies are provided in the through holes.
CN202122479577.3U 2021-10-14 2021-10-14 Shaft maintenance construction platform Active CN216617582U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122479577.3U CN216617582U (en) 2021-10-14 2021-10-14 Shaft maintenance construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122479577.3U CN216617582U (en) 2021-10-14 2021-10-14 Shaft maintenance construction platform

Publications (1)

Publication Number Publication Date
CN216617582U true CN216617582U (en) 2022-05-27

Family

ID=81694448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122479577.3U Active CN216617582U (en) 2021-10-14 2021-10-14 Shaft maintenance construction platform

Country Status (1)

Country Link
CN (1) CN216617582U (en)

Similar Documents

Publication Publication Date Title
CN105672678A (en) Method for mounting overall steel protective shed cantilever frame
CN107217836A (en) A kind of construction hanging basket suspension arrangement for steel construction shelter bridge
CN203173644U (en) Multifunctional lifting shaft working platform system
CN207296479U (en) Steel structure stairway in elevator
WO2020098394A1 (en) Gob-side entry confined concrete supporting construction device and mechanized construction method
CN202945798U (en) Overhanging type scaffold corner device
CN216617582U (en) Shaft maintenance construction platform
KR200415037Y1 (en) Gang Form Level Adjusting Apparatus for Guide Climbing System
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN104164889A (en) Demountable tower crane foundation
CN216690350U (en) Concrete circular silo slip form construction equipment
CN205935727U (en) Elevartor shaft automatic crawl robot and safety protection stage mechanism
CN210563531U (en) Steel structure support for building protection
CN110206331B (en) Trolley type elevator shaft mouth and well protection device and construction method
CN210239201U (en) Cart type elevator wellhead and hoistway protection device
CN210561720U (en) Pier stud maintenance repair operation platform
CN104594631B (en) The construction technology of sliding form apparatus traction operation platform construction granulation tower spraying layer
CN108775016B (en) Concrete support horizontal movement adjustable hanging basket
CN207063488U (en) A kind of construction hanging basket suspension arrangement for steel construction shelter bridge
CN211665580U (en) Pier shaft template attached type operation platform
JP4839052B2 (en) Rotating dismantling method of storage tank
CN218621853U (en) High mound reinforcing bar installation truss structure
CN219587256U (en) Adjustable horizontal entrance to a cave rail guard
CN221546481U (en) Curtain wall protection construction system when tower crane cannot be used
CN218324028U (en) Be used for pipeline welding protection portal assembled to hang corridor protector on road

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant