CN108775016B - Concrete support horizontal movement adjustable hanging basket - Google Patents
Concrete support horizontal movement adjustable hanging basket Download PDFInfo
- Publication number
- CN108775016B CN108775016B CN201810756895.XA CN201810756895A CN108775016B CN 108775016 B CN108775016 B CN 108775016B CN 201810756895 A CN201810756895 A CN 201810756895A CN 108775016 B CN108775016 B CN 108775016B
- Authority
- CN
- China
- Prior art keywords
- adjusting
- adjustment
- fixedly connected
- crossbar
- pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 28
- 230000003014 reinforcing effect Effects 0.000 claims description 9
- 230000001681 protective effect Effects 0.000 claims description 4
- 230000002787 reinforcement Effects 0.000 claims description 4
- 238000005096 rolling process Methods 0.000 claims 1
- 229910000831 Steel Inorganic materials 0.000 abstract description 8
- 239000010959 steel Substances 0.000 abstract description 8
- 238000000465 moulding Methods 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000004064 recycling Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/001—Safety or protective measures against falling down relating to scaffoldings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Movable Scaffolding (AREA)
- Ladders (AREA)
Abstract
Description
技术领域Technical field
本发明涉及建筑领域中的外挂篮领域,具体涉及一种混凝土支撑水平移动可调式挂篮。The invention relates to the field of external hanging baskets in the field of construction, and in particular to a horizontally movable and adjustable hanging basket supported by concrete.
背景技术Background technique
目前我国的轨道交通工程、地下管廊、超高层深基坑等迅猛发展,支撑广泛应用于基坑围护结构中,其中,钢筋混凝土支撑的应用颇为广泛。由于该围护结构体系在基坑土方开挖后悬挂于围护桩及围檩之间,底部及周边无着力点,在支撑立面作业时无可倚靠的体系,采用此混凝土支撑水平移动可调式挂篮体系可解决上述问题。At present, my country's rail transit projects, underground pipe corridors, super high-rise deep foundation pits, etc. are developing rapidly. Supports are widely used in foundation pit enclosure structures. Among them, reinforced concrete supports are widely used. Since the retaining structure system is suspended between the retaining piles and the purlins after the excavation of the foundation pit, there are no points of force at the bottom and periphery, and there is no system to rely on when supporting the facade. Using this concrete support can move horizontally The adjustable hanging basket system can solve the above problems.
根据不同设计要求,对混凝土支撑截面提供了不同尺寸,本挂篮体系通过本身可调节式固定螺栓从而满足不同尺寸的要求,达到能够在不同截面的混凝土支撑中通过滚轮的滑动进行水平移动的要求,极大的简便了作业时的各道工序,且在很大程度上保障了作业的安全。According to different design requirements, different sizes of concrete support sections are provided. This hanging basket system meets the requirements of different sizes through its own adjustable fixing bolts, and can achieve horizontal movement through the sliding of rollers in concrete supports of different sections. , which greatly simplifies the various processes during operation and ensures the safety of the operation to a large extent.
发明内容Contents of the invention
本发明的目的在于提供一种混凝土支撑水平移动可调式挂篮,在混凝土支撑体系中采用活动式脚手架搭设作业平台,解决了施工时移动较为困难、对脚手架基底承载力要求高,且安全隐患较大的问题,实现了挂篮的混凝土支撑立面作业时的通用性。The object of the present invention is to provide a horizontally movable adjustable hanging basket with concrete support. In the concrete support system, movable scaffolding is used to erect a working platform, which solves the problem of difficulty in moving during construction, high requirements on the bearing capacity of the scaffold base, and high safety hazards. Big problem, achieving versatility when working on the concrete support facade of the hanging basket.
本发明解决其技术问题所采用的技术方案如下:The technical solutions adopted by the present invention to solve the technical problems are as follows:
一种混凝土支撑水平移动可调式挂篮,包括有多个并置排列的移动框架,多个移动框架固定连接为一体,所述移动框架包括上调节横杆、下调节横杆、调节立杆一、调节立杆二、调节立杆三,上调节横杆、下调节横杆左端分别开有多个调节孔,调节立杆一、调节立杆二、调节立杆三下端分别开有多个调节孔,调节立杆一上端与上调节横杆左端的调节孔通过螺栓固定连接,调节立杆二上端与上调节横杆固定连接,调节立杆三上端与上调节横杆右端固定连接;调节立杆一下端的调节孔与下调节横杆左端的调节孔通过螺栓固定连接,调节立杆二下端的调节孔与下调节横杆通过螺栓固定连接,调节立杆三下端的调节孔与下调节横杆右端通过螺栓固定连接,调节立杆一、调节立杆二上分别安装有可沿混凝土两侧立面水平滚动的滑轮,上调节横杆上安装有可沿混凝土支撑顶面水平滚动的滑轮;所述多个移动框架的调节立杆二与调节立杆三之间区域为挂篮操作区,相邻的两个移动框架的下调节横杆之间固定连接有底板加强杆,底板加强杆上铺设有挂篮底板。A concrete-supported horizontally movable adjustable hanging basket includes a plurality of movable frames arranged side by side, and the plurality of movable frames are fixedly connected as one body. The mobile frame includes an upper adjusting cross bar, a lower adjusting cross bar, and an adjusting vertical bar. , Adjusting vertical pole two, adjusting vertical pole three, there are multiple adjustment holes at the left ends of the upper and lower adjusting horizontal bars respectively, and there are multiple adjustment holes at the lower ends of adjusting vertical pole one, adjusting vertical pole two and adjusting vertical pole three. hole, the upper end of the adjusting vertical pole is fixedly connected to the adjusting hole at the left end of the upper adjusting crossbar through bolts, the upper end of the second adjusting vertical rod is fixedly connected to the upper adjusting horizontal bar, the upper end of the third adjusting vertical rod is fixedly connected to the right end of the upper adjusting horizontal bar; The adjustment hole at the lower end of the pole is fixedly connected with the adjustment hole at the left end of the lower adjustment crossbar through bolts. The adjustment hole at the second lower end of the adjustment pole is fixedly connected with the lower adjustment crossbar through bolts. The adjustment hole at the third lower end of the adjustment upright pole is connected with the lower adjustment crossbar. The right end is fixedly connected by bolts. The first and second adjusting vertical poles are respectively equipped with pulleys that can roll horizontally along the concrete facades on both sides, and the upper adjusting cross bar is equipped with pulleys that can roll horizontally along the top surface of the concrete support; so The area between the two adjustment poles and the three adjustment poles of the plurality of mobile frames is the hanging basket operation area. The lower adjustment cross bars of the two adjacent mobile frames are fixedly connected with bottom plate reinforcing rods, which are laid on the bottom plate reinforcing rods. There is a hanging basket base.
所述的上调节横杆与调节立杆一之间固定连接有斜撑杆,斜撑杆上端与上调节横杆左端通过螺栓固定连接,斜撑杆下端固定连接有调节套管,调节套管滑动套装于调节立杆一外,调节套管侧壁上开设有多个宽度调节孔,调节立杆一侧壁上开有锁紧孔,调节套管侧壁的宽度调节孔与调节立杆一侧壁的锁紧孔通过调节螺栓相固定连接。There is a diagonal brace fixedly connected between the upper adjusting crossbar and the adjusting vertical bar. The upper end of the diagonal brace and the left end of the upper adjusting crossbar are fixedly connected by bolts. The lower end of the diagonal brace is fixedly connected with an adjusting sleeve. The adjusting sleeve The sliding sleeve is installed outside the adjusting pole. There are multiple width adjustment holes on the side wall of the adjusting sleeve. There are locking holes on one side of the adjusting pole. The width adjustment holes on the side wall of the adjusting sleeve are on the same side as the adjusting pole. The locking holes on the side walls are fixedly connected by adjusting bolts.
所述的调节立杆二与调节立杆三之间固定连接有挂篮加强横杆,挂篮加强横杆上设有铺设有防护网。A hanging basket reinforcing cross bar is fixedly connected between the two adjusting upright poles and the adjusting upright pole three, and a protective net is laid on the hanging basket reinforcing cross bar.
所述挂篮操作区的上调节横杆连接有爬梯。The upper adjustment crossbar of the hanging basket operating area is connected to a ladder.
所述的相邻两个移动框架之间通过连接杆固定连接,连接杆上安装有可沿混凝土两侧立面水平滚动的滑轮。The two adjacent mobile frames are fixedly connected through connecting rods, and pulleys that can roll horizontally along the concrete facades on both sides are installed on the connecting rods.
本发明的上调节横杆、下调节横杆左端的调节孔与调节立杆一通过螺栓固定连接,调节立杆一、调节立杆二、调节立杆三下端的调节孔与下调节横杆通过螺栓固定连接,实现了移动框架的长度、宽度可调节的功能,以适应于不同截面尺寸的混凝土支撑面安装要求,同时利用斜撑杆加强移动框架整体强度,并利用滚轮带动移动框架实现水平移动,移动框架右侧为挂篮操作区,挂篮操作区底面设有底板加强杆、挂篮底板,挂篮操作区侧面设有挂篮加强横杆、防护网,防止操作工具的意外跌落和人员的意外坠落。施工人员上下挂篮时通过爬梯。The adjustment holes at the left ends of the upper and lower adjustment crossbars of the present invention are fixedly connected to the adjustment vertical pole 1 through bolts, and the adjustment holes at the lower ends of the adjustment vertical pole 1, the adjustment vertical pole 2, and the adjustment vertical pole 3 are connected to the lower adjustment crossbar. The bolted connection realizes the adjustable length and width of the mobile frame to adapt to the installation requirements of concrete support surfaces of different cross-section sizes. At the same time, diagonal braces are used to strengthen the overall strength of the mobile frame, and rollers are used to drive the mobile frame to achieve horizontal movement. , the right side of the mobile frame is the hanging basket operating area. The bottom of the hanging basket operating area is equipped with a bottom reinforcement bar and a hanging basket bottom plate. The side of the hanging basket operating area is equipped with a hanging basket reinforced cross bar and a protective net to prevent accidental falls of operating tools and personnel. accidental fall. Construction workers use ladders when going up and down the hanging basket.
本发明解决了混凝土支撑面作业难度大,危险系数高的技术难题,且操作方便,安全可靠。通过在移动框架上的可调节固定螺栓,实现不同截面尺寸的混凝土支撑面可操作性,通过在支撑挂篮周边增加密封性措施,保障操作人员的安全和便利性。The invention solves the technical problems that the concrete support surface operation is difficult and the risk factor is high, and is easy to operate, safe and reliable. Through the adjustable fixing bolts on the movable frame, the operability of the concrete support surface of different cross-sectional sizes is achieved. By adding sealing measures around the support basket, the safety and convenience of the operator are ensured.
附图说明Description of drawings
下面结合附图对本发明实施例作进一步说明。The embodiments of the present invention will be further described below with reference to the accompanying drawings.
图1是本发明的结构示意图。Figure 1 is a schematic structural diagram of the present invention.
图2是本发明的俯视图。Figure 2 is a top view of the present invention.
图3是滚轮的结构示意图。Figure 3 is a schematic structural diagram of the roller.
图4是挂篮操作区的侧视图。Figure 4 is a side view of the hanging basket operating area.
具体实施方式Detailed ways
参见附图,一种混凝土支撑水平移动可调式挂篮,包括有多个并置排列的移动框架1,多个移动框架1固定连接为一体,移动框架1包括上调节横杆2、下调节横杆3、调节立杆一4、调节立杆二5、调节立杆三6,上调节横杆1、下调节横杆2左端分别开有多个调节孔7,调节立杆一4、调节立杆二5、调节立杆三6下端分别开有多个调节孔8,调节立杆一4上端与上调节横杆2左端的调节孔7通过螺栓固定连接,调节立杆二5上端与上调节横杆2固定连接,调节立杆三6上端与上调节横杆2右端固定连接;调节立杆一4下端的调节孔8与下调节横杆3左端的调节孔7通过螺栓固定连接,调节立杆二5下端的调节孔8与下调节横杆3通过螺栓固定连接,调节立杆三6下端的调节孔8与下调节横杆3右端通过螺栓固定连接,调节立杆一4、调节立杆二5上分别安装有可沿混凝土9两侧立面水平滚动的滑轮10,上调节横杆2上安装有可沿混凝土9支撑顶面水平滚动的滑轮10;多个移动框架1的调节立杆二5与调节立杆三6之间区域为挂篮操作区11,相邻的两个移动框架1的下调节横杆3之间固定连接有底板加强杆12,底板加强杆12上铺设有挂篮底板13;上调节横杆2与调节立杆一4之间固定连接有斜撑杆14,斜撑杆14上端与上调节横杆2左端通过螺栓固定连接,斜撑杆14下端固定连接有调节套管15,调节套管15滑动套装于调节立杆一4外,调节套管15侧壁上开设有多个宽度调节孔20,调节立杆一4侧壁上开有锁紧孔,调节套管15侧壁的宽度调节孔20与调节立杆一4侧壁的锁紧孔通过调节螺栓16相固定连接;调节立杆二5与调节立杆三6之间固定连接有挂篮加强横杆17,挂篮加强横杆17上设有铺设有防护网18;挂篮操作区11的上调节横杆2连接有爬梯19;相邻两个移动框架1之间通过连接杆21固定连接,连接杆21上安装有可沿混凝土9两侧立面水平滚动的滑轮10。Referring to the drawings, a concrete-supported horizontally movable adjustable hanging basket includes a plurality of movable frames 1 arranged side by side. The plurality of movable frames 1 are fixedly connected into one body. The movable frame 1 includes an upper adjusting cross bar 2 and a lower adjusting cross bar. Rod 3, Adjusting Vertical Rod 1, 4, Adjusting Vertical Rod 2, 5, Adjusting Vertical Rod 3, 6. There are multiple adjustment holes 7 on the left ends of the upper adjusting horizontal bar 1 and lower adjusting horizontal bar 2. Adjusting vertical rod 1, 4, adjusting vertical rods There are a plurality of adjustment holes 8 at the lower ends of rod two 5 and adjustment pole three 6 respectively. The upper end of adjustment rod one 4 is connected with the adjustment hole 7 at the left end of upper adjustment crossbar 2 through bolts. The upper end of adjustment rod two 5 is connected with the upper adjustment hole 7 The horizontal bar 2 is fixedly connected, and the upper end of the adjusting vertical bar 36 is fixedly connected to the right end of the upper adjusting horizontal bar 2; the adjusting hole 8 at the lower end of the adjusting vertical bar 14 is fixedly connected with the adjusting hole 7 at the left end of the lower adjusting horizontal bar 3 through bolts, and the adjusting vertical bar 2 is fixedly connected. The adjustment hole 8 at the lower end of rod two 5 is fixedly connected with the lower adjustment crossbar 3 through bolts. The adjustment hole 8 at the lower end of adjustment rod three 6 is fixedly connected with the right end of the lower adjustment crossbar 3 by bolts. Adjustment rod one 4, adjustment rod Pulleys 10 that can roll horizontally along both sides of the concrete 9 are installed on the second 5 respectively, and pulleys 10 that can roll horizontally along the top surface of the concrete 9 are installed on the upper adjustment crossbar 2; multiple adjustment poles of the mobile frame 1 The area between the second 5 and the adjusting pole 3 6 is the hanging basket operating area 11. The lower adjusting cross bars 3 of the two adjacent mobile frames 1 are fixedly connected with a bottom plate reinforcing rod 12, and a hanging basket is laid on the bottom plate reinforcing rod 12. Basket bottom plate 13; an inclined brace 14 is fixedly connected between the upper adjusting crossbar 2 and the adjusting vertical bar 14. The upper end of the inclined brace 14 and the left end of the upper adjusting crossbar 2 are fixedly connected by bolts. The lower end of the inclined brace 14 is fixedly connected with The adjusting sleeve 15 is slidably mounted outside the adjusting pole 14. A plurality of width adjustment holes 20 are provided on the side wall of the adjusting sleeve 15, and locking holes are provided on the side wall of the adjusting pole 14. The width adjustment hole 20 on the side wall of the casing 15 and the locking hole on the side wall of the adjustment pole 14 are fixedly connected through the adjustment bolt 16; the adjustment pole 25 and the adjustment pole 36 are fixedly connected with a hanging basket to strengthen the horizontal direction. Rod 17, the hanging basket reinforced cross bar 17 is provided with a protective net 18; the upper adjusting cross bar 2 of the hanging basket operating area 11 is connected to a ladder 19; two adjacent mobile frames 1 are fixedly connected by a connecting rod 21. Pulleys 10 that can roll horizontally along both sides of the concrete 9 are installed on the connecting rod 21 .
上调节横杆2、下调节横杆3、调节立杆一4、调节立杆二5、调节立杆三6均采用50*50mm方钢,并分别在杆件开M16螺栓孔对穿,移动框架安装成型加上滑轮尺寸后孔距要求分别为600mm、800mm、900mm、1000mm、1200mm(可根据不同截面要求进行加工),用于杆件之间连接固定的螺栓采用M16*80mm螺栓,斜撑杆采用50*50mm方钢,调节套管为55*55mm,调节螺栓采用M16*80mm进行固定,滑轮采用6寸的橡胶滑轮组,挂篮底板为木质胶合模板;操作挂篮上下可调节尺寸,所有杆件连接均采用焊接(除立面底部可调节处外),挂篮底部铺设建筑用木质胶合模板,周边采用3.6*40*40mm钢丝网16,钢制爬梯10采用直径14mm圆钢制作而成。The upper adjusting crossbar 2, the lower adjusting crossbar 3, the adjusting vertical rod 1, 4, the adjusting vertical rod 2 5, and the adjusting vertical rod 3 6 are all made of 50*50mm square steel, and M16 bolt holes are opened in the rods to pass through them. After the frame is installed and formed and the pulley size is added, the hole spacing requirements are 600mm, 800mm, 900mm, 1000mm, 1200mm (can be processed according to different cross-section requirements). The bolts used to connect and fix the rods are M16*80mm bolts and diagonal braces. The rod is made of 50*50mm square steel, the adjusting sleeve is 55*55mm, the adjusting bolt is fixed with M16*80mm, the pulleys are made of 6-inch rubber pulleys, and the bottom plate of the hanging basket is a wooden glued template; the size of the hanging basket can be adjusted up and down by operating it, and all The rod connections are all welded (except for the adjustable bottom part of the facade). The bottom of the hanging basket is laid with a wooden glue template for construction. The surrounding area is made of 3.6*40*40mm steel wire mesh16. The steel ladder 10 is made of round steel with a diameter of 14mm. .
根据混凝土支撑的外截面尺寸先安装与混凝土接触面的钢制框架,拧紧连接固定螺栓13和套管固定螺栓12,安装好滚轮。拼装操作挂篮,焊接挂篮加强横杆5和挂篮底部加强杆9,铺设底部胶板8、周围钢丝网16,安装完成后即可吊装至混凝土支撑面进行作业,当该道混凝土支撑施工完毕后,可按上述方法向上安装以循环使用。According to the external cross-sectional size of the concrete support, first install the steel frame on the contact surface with the concrete, tighten the connecting fixing bolts 13 and the casing fixing bolts 12, and install the rollers. Assemble the hanging basket, weld the hanging basket reinforcement crossbar 5 and the hanging basket bottom reinforcement bar 9, lay the bottom rubber plate 8 and the surrounding steel wire mesh 16. After the installation is completed, it can be hoisted to the concrete support surface for operation. When the concrete support is constructed After completion, it can be installed upward according to the above method for recycling.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810756895.XA CN108775016B (en) | 2018-07-11 | 2018-07-11 | Concrete support horizontal movement adjustable hanging basket |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810756895.XA CN108775016B (en) | 2018-07-11 | 2018-07-11 | Concrete support horizontal movement adjustable hanging basket |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108775016A CN108775016A (en) | 2018-11-09 |
| CN108775016B true CN108775016B (en) | 2024-02-23 |
Family
ID=64031133
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810756895.XA Active CN108775016B (en) | 2018-07-11 | 2018-07-11 | Concrete support horizontal movement adjustable hanging basket |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108775016B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109750601B (en) * | 2019-01-16 | 2020-08-07 | 四川同风源建设工程有限公司 | Highway bridge avris construction work platform |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR200326093Y1 (en) * | 2003-05-07 | 2003-09-13 | 최규헌 | Railing of concrete sheeting for building |
| CN203247021U (en) * | 2013-05-03 | 2013-10-23 | 中国葛洲坝集团股份有限公司 | Crossbeam hanging basket device for bridge type crane |
| CN203361597U (en) * | 2013-07-09 | 2013-12-25 | 中建安装工程有限公司 | Vertical ladder hanging platform |
| CN203452012U (en) * | 2013-09-09 | 2014-02-26 | 中建八局第三建设有限公司 | Mobile hanging basket for guard bar outer side construction |
| CN203462738U (en) * | 2013-08-02 | 2014-03-05 | 天津二十冶建设有限公司 | Movable safety hanging basket |
| CN205976416U (en) * | 2016-07-19 | 2017-02-22 | 中建钢构有限公司 | Steel beam hanging basket device |
| CN206091259U (en) * | 2016-09-30 | 2017-04-12 | 中建八局第一建设有限公司 | Adjustable steel configuration operation hanging flower basket |
| CN106677512A (en) * | 2016-12-12 | 2017-05-17 | 中建钢构有限公司 | Adjustable sliding-rail type suspension girder operating platform for high-rise building |
-
2018
- 2018-07-11 CN CN201810756895.XA patent/CN108775016B/en active Active
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR200326093Y1 (en) * | 2003-05-07 | 2003-09-13 | 최규헌 | Railing of concrete sheeting for building |
| CN203247021U (en) * | 2013-05-03 | 2013-10-23 | 中国葛洲坝集团股份有限公司 | Crossbeam hanging basket device for bridge type crane |
| CN203361597U (en) * | 2013-07-09 | 2013-12-25 | 中建安装工程有限公司 | Vertical ladder hanging platform |
| CN203462738U (en) * | 2013-08-02 | 2014-03-05 | 天津二十冶建设有限公司 | Movable safety hanging basket |
| CN203452012U (en) * | 2013-09-09 | 2014-02-26 | 中建八局第三建设有限公司 | Mobile hanging basket for guard bar outer side construction |
| CN205976416U (en) * | 2016-07-19 | 2017-02-22 | 中建钢构有限公司 | Steel beam hanging basket device |
| CN206091259U (en) * | 2016-09-30 | 2017-04-12 | 中建八局第一建设有限公司 | Adjustable steel configuration operation hanging flower basket |
| CN106677512A (en) * | 2016-12-12 | 2017-05-17 | 中建钢构有限公司 | Adjustable sliding-rail type suspension girder operating platform for high-rise building |
Also Published As
| Publication number | Publication date |
|---|---|
| CN108775016A (en) | 2018-11-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN207048306U (en) | Sliding formwork flexibility platform | |
| CN102877637B (en) | Method for implementing operating platform in bottom wall construction of cantilever beam | |
| CN111395730B (en) | A curtain wall construction system and method suitable for high-rise buildings with special-shaped giant columns | |
| CN103806645B (en) | Light intelligent hydraulic climbing formwork device with good wind-resistant and fireproof performances | |
| CN109356167B (en) | Deep foundation pit support demolition system and construction method | |
| CN110259088B (en) | Method for erecting external protection scaffold of building with twisted vertical face | |
| CN206581577U (en) | Using housing construction builder's jack | |
| CN108775016B (en) | Concrete support horizontal movement adjustable hanging basket | |
| CN117248714A (en) | Interclimbing steel column horizontal beam-slab construction platform and construction method | |
| CN210316599U (en) | A curtain wall annular track for roof frame beams | |
| CN111705677A (en) | A smooth frame that rises for high pier stud turns over mould construction | |
| CN106639303B (en) | Elevator dedicated hydraulic creeping formwork frame body | |
| CN109944164A (en) | Self-elevating hollow thin-walled pier roller formwork system and construction method thereof | |
| CN207749818U (en) | A kind of suspension type hanging basket for anti-lift-slb construction | |
| CN204386135U (en) | Portable Hanging Basket | |
| CN209384619U (en) | Hanging basket device capable of safely walking on foundation pit reinforced concrete | |
| CN103359625A (en) | Automatic construction equipment for building hoisting and platform elevating of new rural construction | |
| CN208517943U (en) | A kind of concrete supporting horizontal movable adjustable hanging basket | |
| CN216921297U (en) | A fixed support structure for a hanging basket | |
| CN209989801U (en) | Diaphragm Wall | |
| CN213297074U (en) | A convenient outer wall cantilever operation frame | |
| CN112502475B (en) | Supporting bearing capacity conversion device and using method thereof | |
| CN104278628A (en) | Light hanging basket applicable to bridge detection and maintenance operations | |
| CN110965803B (en) | Underground diaphragm wall dismantling construction device and construction method thereof | |
| CN210563531U (en) | Steel structure support for building protection |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB02 | Change of applicant information | ||
| CB02 | Change of applicant information |
Address after: 230001 no.329 Wuhu Road, Hefei City, Anhui Province Applicant after: Anhui Construction Engineering Third Construction Group Co.,Ltd. Address before: 230001 no.329 Wuhu Road, Hefei City, Anhui Province Applicant before: ANHUI SANJIAN ENGINEERING Co.,Ltd. |
|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20241208 Address after: No. 40, Wangjiang West Road, Shushan District, Hefei, Anhui 230000 Patentee after: Anhui Sanjian Engineering Technology Co.,Ltd. Country or region after: China Address before: 230001 no.329 Wuhu Road, Hefei City, Anhui Province Patentee before: Anhui Construction Engineering Third Construction Group Co.,Ltd. Country or region before: China |