CN216616908U - Unloading device for preventing material damage for building construction - Google Patents

Unloading device for preventing material damage for building construction Download PDF

Info

Publication number
CN216616908U
CN216616908U CN202123170645.4U CN202123170645U CN216616908U CN 216616908 U CN216616908 U CN 216616908U CN 202123170645 U CN202123170645 U CN 202123170645U CN 216616908 U CN216616908 U CN 216616908U
Authority
CN
China
Prior art keywords
sets
groups
mounting
base
building construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123170645.4U
Other languages
Chinese (zh)
Inventor
杨瑞波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tangshan Caofeidian Zhenkai Technology Co ltd
Original Assignee
Tangshan Caofeidian Zhenkai Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tangshan Caofeidian Zhenkai Technology Co ltd filed Critical Tangshan Caofeidian Zhenkai Technology Co ltd
Priority to CN202123170645.4U priority Critical patent/CN216616908U/en
Application granted granted Critical
Publication of CN216616908U publication Critical patent/CN216616908U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to the technical field of unloading of building construction materials, in particular to an unloading device for preventing materials from being damaged in building construction, which can enhance the unloading safety of the building materials and avoid influencing the construction progress; the on-line screen storage device comprises a base, a mounting bracket, the blowing board, the apparatus further comprises a rotating shaft, two sets of cylinders, including a motor, a controller, and a cover plate, the base bottom is equipped with four groups of pillars, mounting bracket fixed mounting is on the base top, the blowing board is rotated through the pivot and is installed on the mounting bracket, two sets of cylinders are fixed mounting respectively in the base bottom, the output of two sets of cylinders is equipped with a set of cylinder pole respectively, the blowing board bottom slides and is equipped with two sets of slides, two sets of cylinder pole tops are articulated with two sets of slides respectively, blowing board bottom is equipped with the mounting panel, the motor is installed on the mounting panel, the output of motor is equipped with the lead screw, the lead screw rotates and passes the mounting panel, solenoid and lead screw threaded connection, blowing board bottom is equipped with the spout, the cooperation slidable mounting that the extension board passes through the spout is in the blowing board bottom.

Description

Unloading device for preventing material damage for building construction
Technical Field
The utility model relates to the technical field of unloading of building construction materials, in particular to an unloading device for preventing materials from being damaged in building construction.
Background
The building material is a variety of materials used in construction works, and is in a wide variety, such as metal materials, natural stone, burned products, plastics, coating asphalt concrete, polymer concrete, and the like. Therefore, during the construction, the construction materials are frequently loaded and unloaded and transported or transported.
At present, on a building site, a transfer vehicle is generally used for transferring building materials, when the building materials are transferred to a destination, the building materials need to be unloaded, however, when the existing transfer vehicle is used for unloading, the building materials directly fall on the ground, and when the height of the existing transfer vehicle is higher, the building materials are easily damaged, and the construction progress is influenced.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problems, the utility model provides an unloading device for preventing materials from being damaged in building construction, which can enhance the unloading safety of building materials and avoid influencing the construction progress.
The utility model relates to an unloading device for preventing materials from being damaged in building construction, which comprises a base, a mounting frame, a material discharging plate and a rotating shaft, two sets of cylinders, including a motor, a controller, and a cover plate, the screwed pipe and extension board, the base bottom is equipped with four groups of pillars, mounting bracket fixed mounting is on the base top, the blowing board is installed on the mounting bracket through the pivot rotation, two sets of cylinders are fixed mounting respectively in the base bottom, the output of two sets of cylinders is equipped with a set of cylinder pole respectively, blowing board bottom slides and is equipped with two sets of slides, two sets of cylinder pole tops are articulated with two sets of slides respectively, blowing board bottom is equipped with the mounting panel, the motor is installed on the mounting panel, the output of motor is equipped with the lead screw, the lead screw rotates and passes the mounting panel, screwed pipe and lead screw threaded connection, blowing board bottom is equipped with the spout, the cooperation slidable mounting that the extension board passes through the spout is in blowing board bottom, the extension board bottom is equipped with the connecting plate, screwed pipe right-hand member fixed mounting is at the connecting plate left end.
The unloading device for preventing materials from being damaged for building construction further comprises two groups of baffle plates, and the two groups of baffle plates are fixedly arranged at the top ends of the material discharging plates respectively.
The utility model relates to a material damage prevention unloading device for building construction, which further comprises four groups of shock absorption seats, wherein the four groups of shock absorption seats are respectively arranged at the bottom ends of four groups of supporting columns.
The utility model relates to a material damage prevention unloading device for building construction, which further comprises four groups of universal wheels, wherein the four groups of universal wheels are respectively arranged at the bottom ends of four groups of shock absorption seats.
The unloading device for preventing materials from being damaged for building construction further comprises a hand push rod and an anti-skidding handle sleeve, wherein the hand push rod is fixedly installed at the left end of the base, and the anti-skidding handle sleeve is fixedly sleeved on the hand push rod.
The unloading device for preventing materials from being damaged for building construction further comprises two sets of sliding sleeves, and the two sets of sliding sleeves are fixedly installed in the front and rear sets of through holes of the installation frame respectively.
The utility model relates to an unloading device for preventing materials from being damaged in building construction, which further comprises four groups of cross beams, wherein the four groups of cross beams are respectively and fixedly arranged between two adjacent groups of pillars.
The unloading device for preventing materials from being damaged for building construction further comprises two groups of reinforcing ribs, wherein the two groups of reinforcing ribs are fixedly arranged between the front end and the rear end of the mounting frame and the top end of the base respectively.
Compared with the prior art, the utility model has the beneficial effects that: at first building material places on the blowing board, when needs are unloaded, start two sets of cylinders, drive two sets of cylinder pole rebound, under the cooperation of two sets of slides, drive blowing board left end rebound, make the blowing board slope, make building material slowly to the below of right side slip, slowly drop subaerial, can prevent building material damage, when building material height is higher, so the starter motor simultaneously, the transmission drives the lead screw and rotates, it moves to drive the screwed pipe right, drive connecting plate and extension board simultaneously and slide right, extend the blowing board, can make building material slowly fall to the ground, strengthen the security that building material fell to the ground, avoid influencing the construction progress, construction cost is reduced.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic cross-sectional view of FIG. 1;
FIG. 3 is a schematic left side view of the base and cylinder connection;
FIG. 4 is a schematic top view of the base;
in the drawings, the reference numbers: 1. a base; 2. a pillar; 3. a mounting frame; 4. a material placing plate; 5. a rotating shaft; 6. a cylinder; 7. a cylinder rod; 8. a slide base; 9. a motor; 10. a lead screw; 11. a solenoid; 12. a chute; 13. an extension plate; 14. a connecting plate; 15. a baffle plate; 16. a shock absorbing seat; 17. a universal wheel; 18. a handspike; 19. an anti-slip handle sleeve; 20. a sliding sleeve; 21. a cross beam; 22. and (5) reinforcing ribs.
Detailed Description
The following detailed description of embodiments of the present invention is provided in connection with the accompanying drawings and examples. The following examples are intended to illustrate the utility model but are not intended to limit the scope of the utility model.
As shown in fig. 1 to 4, the unloading device for preventing material damage in building construction of the utility model comprises a base 1, a mounting frame 3, a material placing plate 4, a rotating shaft 5, two sets of cylinders 6, a motor 9, a screw tube 11 and an extension plate 13, wherein four sets of struts 2 are arranged at the bottom end of the base 1, the mounting frame 3 is fixedly arranged at the top end of the base 1, the material placing plate 4 is rotatably arranged on the mounting frame 3 through the rotating shaft 5, the two sets of cylinders 6 are respectively fixedly arranged at the bottom end of the base 1, the output ends of the two sets of cylinders 6 are respectively provided with a set of cylinder rods 7, the bottom end of the material placing plate 4 is slidably provided with two sets of slide seats 8, the top ends of the two sets of cylinder rods 7 are respectively hinged with the two sets of slide seats 8, the bottom end of the material placing plate 4 is provided with a mounting plate, the motor 9 is arranged on the mounting plate, the output end of the motor 9 is provided with a screw rod 10, the screw rod 10 rotates to pass through the mounting plate, the screw tube 11 is in threaded connection with the screw rod 10, the bottom end of the material placing plate 4 is provided with a chute 12, an extension plate 13 is slidably mounted at the bottom end of the material placing plate 4 through the matching of a chute 12, a connecting plate 14 is arranged at the bottom end of the extension plate 13, and the right end of a solenoid 11 is fixedly mounted at the left end of the connecting plate 14; at first building material places on blowing board 4, when needs are unloaded, start two sets of cylinders 6, drive two sets of cylinder pole 7 rebound, under the cooperation of two sets of slides 8, drive blowing board 4 left end rebound, make blowing board 4 slope, make building material slowly slide to the right below, slowly drop subaerial, can prevent building material damage, when building material height is higher, so simultaneously starter motor 9, the transmission drives lead screw 10 and rotates, drive screwed pipe 11 and remove to the right, drive connecting plate 14 and extension plate 13 simultaneously and slide to the right, extend blowing board 4, can make building material slowly fall to the ground, strengthen the security that building material fell to the ground, avoid influencing the construction progress, construction cost is reduced.
The unloading device for preventing materials from being damaged for building construction further comprises two groups of baffles 15, wherein the two groups of baffles 15 are respectively and fixedly arranged at the top ends of the material discharging plates 4; through setting up baffle 15, can play the effect of protection to the building material on blowing board 4 top, prevent that building material from rolling down.
The unloading device for preventing materials from being damaged for building construction further comprises four groups of shock absorption seats 16, wherein the four groups of shock absorption seats 16 are respectively arranged at the bottom ends of the four groups of pillars 2; through setting up the cushion socket 16, can slow down vibrations, strengthen the stability of whole device.
The unloading device for preventing materials from being damaged for building construction further comprises four groups of universal wheels 17, wherein the four groups of universal wheels 17 are respectively arranged at the bottom ends of four groups of shock absorption seats 16; through setting up universal wheel 17, the removal of the whole device of being convenient for improves the flexibility.
The unloading device for preventing materials from being damaged for building construction further comprises a hand push rod 18 and an anti-skidding handle sleeve 19, wherein the hand push rod 18 is fixedly arranged at the left end of the base 1, and the anti-skidding handle sleeve 19 is fixedly sleeved on the hand push rod 18; the staff of being convenient for promotes the overall device and removes, improves the practicality.
The unloading device for preventing materials from being damaged for building construction further comprises two groups of sliding sleeves 20, wherein the two groups of sliding sleeves 20 are fixedly arranged in the front and rear groups of through holes of the mounting rack 3 respectively; by providing the sliding sleeve 20, the sliding smoothness of the rotating shaft 5 can be enhanced.
The unloading device for preventing materials from being damaged for building construction further comprises four groups of cross beams 21, wherein the four groups of cross beams 21 are respectively and fixedly arranged between two adjacent groups of pillars 2; by providing the cross member 21, the connection between the four groups of pillars 2 can be strengthened, thereby improving the stability of the entire apparatus.
The unloading device for preventing materials from being damaged for building construction further comprises two groups of reinforcing ribs 22, wherein the two groups of reinforcing ribs 22 are fixedly arranged between the front end and the rear end of the mounting rack 3 and the top end of the base 1 respectively; through setting up strengthening rib 22, can strengthen the connection of mounting bracket 3 and base 1, improve stability.
The utility model relates to a material damage prevention unloading device for building construction, which is characterized in that when in work, building materials are firstly placed on an unloading plate 4, when unloading is needed, two groups of cylinders 6 are started to drive two groups of cylinder rods 7 to move upwards, the left end of the unloading plate 4 is driven to move upwards under the cooperation of two groups of sliding seats 8, the unloading plate 4 is inclined, the building materials slowly slide towards the lower right and slowly fall on the ground, so that the building materials can be prevented from being damaged, when the building materials are higher in height, a motor 9 is simultaneously started to drive a lead screw 10 to rotate in a transmission manner, a screw pipe 11 is driven to move towards the right, a connecting plate 14 and an extending plate 13 are simultaneously driven to slide towards the right, the unloading plate 4 is extended, the building materials can slowly fall on the ground, a baffle plate 15 can play a role in protecting the building materials at the top end of the unloading plate 4, the building materials are prevented from rolling down, and a damping seat 16 can slow down vibration, the stability of the whole device is enhanced, if the worker needs to push the whole device to move, the worker holds the hand push rod 18 to push the base 1, and the universal wheel 17 is driven to rotate.
According to the unloading device for preventing materials from being damaged for building construction, the installation mode, the connection mode or the arrangement mode are common mechanical modes, and the unloading device can be implemented as long as the beneficial effects are achieved; the air cylinder 6 and the motor 9 of the unloading device for preventing materials from being damaged for building construction are purchased from the market, and technicians in the industry only need to install and operate the unloading device according to the attached operating instructions.
The above description is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, several modifications and variations can be made without departing from the technical principle of the present invention, and these modifications and variations should also be regarded as the protection scope of the present invention.

Claims (8)

1. A material damage prevention unloading device for building construction is characterized by comprising a base (1), a mounting frame (3), a material placing plate (4), a rotating shaft (5), two groups of cylinders (6), a motor (9), a solenoid (11) and an extension plate (13), wherein four groups of struts (2) are arranged at the bottom end of the base (1), the mounting frame (3) is fixedly arranged at the top end of the base (1), the material placing plate (4) is rotatably arranged on the mounting frame (3) through the rotating shaft (5), the two groups of cylinders (6) are respectively and fixedly arranged at the bottom end of the base (1), the output ends of the two groups of cylinders (6) are respectively provided with a group of cylinder rods (7), the bottom end of the material placing plate (4) is provided with two groups of sliding seats (8) in a sliding manner, the top ends of the two groups of cylinder rods (7) are respectively hinged with the two groups of sliding seats (8), the bottom end of the material placing plate (4) is provided with a mounting plate, the motor (9) is arranged on the mounting plate, the output of motor (9) is equipped with lead screw (10), and lead screw (10) rotate and pass the mounting panel, solenoid (11) and lead screw (10) threaded connection, and blowing board (4) bottom is equipped with spout (12), and extension board (13) are through the cooperation slidable mounting of spout (12) in blowing board (4) bottom, and extension board (13) bottom is equipped with connecting plate (14), and solenoid (11) right-hand member fixed mounting is in connecting plate (14) left end.
2. A discharge apparatus for preventing damage to materials in building construction as claimed in claim 1, further comprising two sets of baffles (15), wherein the two sets of baffles (15) are fixedly installed at the top ends of the discharge plates (4), respectively.
3. A material damage prevention discharge apparatus for construction use according to claim 2, further comprising four sets of shock absorbing seats (16), the four sets of shock absorbing seats (16) being installed at the lower ends of the four sets of columns (2), respectively.
4. A discharge apparatus for preventing damage of materials in construction work, as claimed in claim 3, further comprising four sets of universal wheels (17), wherein the four sets of universal wheels (17) are respectively installed at the bottom ends of the four sets of shock-absorbing seats (16).
5. An unloading device for preventing material damage in building construction as claimed in claim 4, further comprising a hand push rod (18) and an anti-slip handle sleeve (19), wherein the hand push rod (18) is fixedly installed at the left end of the base (1), and the anti-slip handle sleeve (19) is fixedly sleeved on the hand push rod (18).
6. An unloading device for preventing material damage in building construction according to claim 5, further comprising two sets of sliding sleeves (20), wherein the two sets of sliding sleeves (20) are respectively and fixedly installed in the front and rear sets of through holes of the mounting rack (3).
7. A discharge apparatus for preventing damage of materials in building construction according to claim 6, further comprising four sets of beams (21), wherein the four sets of beams (21) are fixedly installed between the adjacent two sets of columns (2), respectively.
8. An unloading apparatus for preventing material damage in building construction as claimed in claim 7, further comprising two sets of reinforcing ribs (22), the two sets of reinforcing ribs (22) being fixedly installed between the front and rear ends of the mounting frame (3) and the top end of the base (1), respectively.
CN202123170645.4U 2021-12-16 2021-12-16 Unloading device for preventing material damage for building construction Active CN216616908U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123170645.4U CN216616908U (en) 2021-12-16 2021-12-16 Unloading device for preventing material damage for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123170645.4U CN216616908U (en) 2021-12-16 2021-12-16 Unloading device for preventing material damage for building construction

Publications (1)

Publication Number Publication Date
CN216616908U true CN216616908U (en) 2022-05-27

Family

ID=81703041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123170645.4U Active CN216616908U (en) 2021-12-16 2021-12-16 Unloading device for preventing material damage for building construction

Country Status (1)

Country Link
CN (1) CN216616908U (en)

Similar Documents

Publication Publication Date Title
CN106225555B (en) Multiple degrees of freedom filling device
CN110080557A (en) A kind of wall dismounting device
CN205980935U (en) Missile loading device
CN108248647B (en) A building site handcart for grit mud transportation
CN208915977U (en) A kind of vertical rotary formula tire storage device
CN216616908U (en) Unloading device for preventing material damage for building construction
CN111350358A (en) Multifunctional cement plate erecting machine with good safety protection
CN217972190U (en) Super high-rise building material conveyer
CN206662912U (en) A kind of highway removes spike devices
CN215622161U (en) Air brick handling device for building engineering
CN212890515U (en) Dry-mixed mortar discharge apparatus
CN112550705B (en) Highway patrol unmanned aerial vehicle that breaks rules and regulations
CN111809833B (en) Building rubbish discharging equipment in construction
CN210563449U (en) Concrete excess material collecting and rapid utilizing device
CN217778678U (en) Auxiliary construction device for discharging building materials
CN213892595U (en) LCD and OLED screen body tray cleaning machine transport module
CN221605855U (en) Building material selling and transferring device
CN219077260U (en) Toughened glass protection handling device
CN213473158U (en) Material transportation device for building construction
CN219769968U (en) Coal dumper device with shock-absorbing protection function
CN217320465U (en) Material transfer device is used in construction of steel landing stage
CA3018479A1 (en) Tire caddy
CN111217077B (en) Multifunctional deflection chute
CN219007899U (en) Anti-tilting transport vehicle for building materials
CN211945304U (en) Automatic conveyer of transport board

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant