CN215594136U - Novel basement outer wall post-cast strip construction device - Google Patents

Novel basement outer wall post-cast strip construction device Download PDF

Info

Publication number
CN215594136U
CN215594136U CN202121716922.4U CN202121716922U CN215594136U CN 215594136 U CN215594136 U CN 215594136U CN 202121716922 U CN202121716922 U CN 202121716922U CN 215594136 U CN215594136 U CN 215594136U
Authority
CN
China
Prior art keywords
cast strip
post
wall
steel
steel sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121716922.4U
Other languages
Chinese (zh)
Inventor
黄伟鹏
邵博文
慕雄
杨春
任超
辛勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202121716922.4U priority Critical patent/CN215594136U/en
Application granted granted Critical
Publication of CN215594136U publication Critical patent/CN215594136U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses a novel basement outer wall post-cast strip construction device which comprises a structure main body, wherein the structure main body comprises a plurality of vertically arranged steel bars, the steel bars form a wall inner structure through steel bar drag hooks, two water stop steel plates are symmetrically arranged inside the wall inner structure, steel plate templates are fixedly arranged on the outer walls of the front side and the rear side of each water stop steel plate, wood templates are arranged on the front side and the rear side of the wall inner structure, concrete is poured in the wood templates, the wood templates are fixedly arranged on the steel bars through a plurality of split bolts, the two ends of the split bolts are horizontally connected with steel pipes in a penetrating mode, and a plurality of battens are uniformly arranged on the outer walls of the wood templates at equal intervals. The post-cast strip supporting device can quickly and effectively support the inner structures of the walls on two sides of the post-cast strip, improves the waterproof quality of the post-cast strip, avoids the situation that the post-cast strip is leaked, and avoids the situations that the slurry leakage and the vibration are not easy to be dense.

Description

Novel basement outer wall post-cast strip construction device
Technical Field
The utility model relates to the field of building construction, in particular to a novel basement outer wall post-cast strip construction device.
Background
The post-cast strip for construction is divided into a post-cast settlement strip, a post-cast shrinkage strip and a post-cast temperature strip, and is respectively used for solving the problems of differential settlement between a high-rise main building and a low-rise skirt house, the difference of the shrinkage deformation of reinforced concrete and the small temperature stress. The post-cast strip generally has the functions of various deformation joints, and one function is considered as the main function and other functions are considered as the auxiliary functions during design. The post-cast strip for construction is a whole building, and comprises reserved seams (the seams are wide and are called as strips) in foundation and structure construction, after the main body structure is completed, the post-cast strip concrete is filled, the seams do not exist, the differential settlement of a high-rise main building and a low-residential skirt house is solved in the whole structure construction, and the purpose of not setting a permanent deformation seam is achieved.
For a long time, the construction of the inner structure of the outer wall of the basement has the phenomenon of time limit for construction periods of different degrees due to the existence of a plurality of restriction factors such as construction organization and the like. Particularly, when the wall body formwork at the post-cast strip is erected, the situation that the lateral common wood formwork of the post-cast strip cannot be smoothly erected due to the blocking of the steel bars in the wall is frequently encountered. Construction team often compels to adopt steel wire net piece or other flexible material to replace the plank sheathing and carries out simple shutoff, form the hourglass thick liquid phenomenon often in steel sheet net department after concrete placement vibrates, finally lead to template and steel sheet net demolish the back, the concrete surface of post-cast strip department is uneven, the both sides concrete is closely knit or even appears the dog hole, and then lead to the construction unit later stage to put into a large amount of manpower and materials and carry out the secondary and repair, even follow-up operation period causes the outer wall seepage from hereon in closely knit region, the serious thing influences the phenomenon of structural entity intensity even. The labor cost and the construction period delay are high, and the construction unit can feel the misstatement. How can just accomplish basement outer wall post-cast strip department template fast, effectual and prop up and establish, guarantee the concrete quality after the form removal simultaneously, avoid later stage seepage or repair, be the construction difficult problem that needs to solve at present urgently.
Disclosure of Invention
The utility model aims to provide a novel basement outer wall post-cast strip construction device which can quickly and effectively complete the erection of templates at two sides of a post-cast strip, avoid the phenomena of difficult vibration and compaction, slurry leakage, dog holes and the like which have extremely poor apparent quality during the concrete construction at the post-cast strip, ensure the waterproof quality at the post-cast strip and save a great deal of cost such as repair and the like.
The utility model is realized by the following steps:
a novel basement exterior wall post-cast strip construction device comprises a structure main body;
the utility model discloses a wall inner structure, including the structure main part, the wall inner structure is formed to the reinforcing bar through the reinforcing bar drag hook, the inside symmetry of wall inner structure is equipped with two stagnant water steel sheets, just all fixed steel sheet templates that are equipped with on the outer wall of both sides around the stagnant water steel sheet, the side all is equipped with the plank sheathing around the wall inner structure, concrete is pour in the plank sheathing, the plank sheathing all through a plurality of tie bolt fixed mounting on the reinforcing bar, just the tie bolt both ends are the equal level through connection have the steel pipe, impartial distance is equipped with a plurality of flitches on the plank sheathing outer wall.
The end part of the steel plate template is connected with the outer wall of the water stop steel plate in a welding mode.
The steel sheet template is kept away from the equal equidistance of stagnant water steel sheet one end is equipped with a plurality of mounting groove, all run through on the steel sheet template outer wall and be equipped with a plurality of gas pocket.
And the outer walls of the steel plate templates are subjected to galvanizing anti-corrosion treatment.
The front side of the water stop steel plate is the upstream surface.
According to the utility model, the main structure body is composed of the steel bars, the steel bar drag hooks, the wooden templates, the battens, the split bolts and the steel pipes, the supporting of the inner structures of the walls at two sides of the post-cast strip can be quickly and effectively completed, the waterproof quality of the post-cast strip is improved through the arrangement of the water stop steel plates and the steel plate templates, the condition that the post-cast strip is leaked is avoided, and the conditions that slurry leakage and vibration are not easy to be dense are avoided.
Drawings
FIG. 1 is a schematic view of the overall structure of the novel basement exterior wall post-cast strip construction device of the utility model;
FIG. 2 is a schematic view of a connection structure of a steel plate formwork and a water stop steel plate of the novel basement exterior wall post-cast strip construction device;
FIG. 3 is a schematic structural diagram of a steel plate formwork of the novel basement exterior wall post-cast strip construction device;
fig. 4 is a schematic structural body pouring structure diagram of the novel basement exterior wall post-cast strip construction device.
In the figure, 1, a structural body; 2. a steel pipe; 3. a wood template; 4. oppositely pulling the bolts; 5. a steel plate template; 6. reinforcing steel bars; 7. wood block; 8. a water stop steel plate; 9. a steel bar draw hook; 10. mounting grooves; 11. air holes; 12. and (3) concrete.
Detailed Description
The utility model is further described with reference to the following figures and specific examples.
Referring to fig. 1 to 4, a novel basement exterior wall post-cast strip construction device comprises a structure body 1;
the structure body 1 includes the reinforcing bar 6 of a plurality of perpendicular settings, wall inner structure is constituteed through reinforcing bar drag hook 9 to reinforcing bar 6, the inside symmetry of wall inner structure is equipped with two stagnant water steel sheet 8, just all fixedly on the both sides outer wall around stagnant water steel sheet 8 and be equipped with steel sheet template 5, the side all is equipped with plank sheathing 3 around the wall inner structure, concrete 12 is pour in the plank sheathing 3, plank sheathing 3 all through a plurality of stay bolt 4 fixed mounting to on the reinforcing bar 6, just there is steel pipe 2 to the equal level through connection in 4 both ends of stay bolt, impartial distance is equipped with a plurality of flitches 7 on the 3 outer walls of plank sheathing. In this embodiment, constitute main structure 1 through reinforcing bar 6, reinforcing bar drag hook 9, plank sheathing 3, flitch 7, split bolt 4 and steel pipe 2, can realize quick, effectual completion post-cast strip department both sides wall inner structure prop up and establish, through stagnant water steel sheet 8 and steel sheet template 5's setting, improve the waterproof quality of post-cast strip department, avoid post-cast strip department to take place the condition of seepage, and avoid appearing leaking thick liquid, the difficult closely knit condition of vibrating.
As shown in fig. 2, the end portions of the steel plate formworks 5 are all connected with the outer wall of the water stop steel plate 8 in a welding mode. In this embodiment, the stagnant water steel sheet 8 is installed on the wall inner structure through welded connection's mode, and stagnant water steel sheet 8 is welded fastening with 8mm diameter reinforcing bar 6 when the welding, and steel sheet template 5 hookup location department should full weld, guarantees steel sheet template 5's installation fixed.
As shown in fig. 3, steel sheet template 5 keeps away from 8 one ends of stagnant water steel sheet equal equidistance are equipped with a plurality of mounting groove 10, all run through on the 5 outer walls of steel sheet template and be equipped with a plurality of gas pocket 11. In this embodiment, receive blockking of reinforcing bar 6 when the installation for steel sheet template 5, arrange the interval according to the horizontal muscle of reinforcing bar 6, cut out mounting groove 10 in 5 both sides of steel sheet template, the incision diameter is 10mm, slightly be greater than the horizontal muscle diameter of reinforcing bar 6 (generally 8mm), gas pocket 11 diameter is 6mm, horizontal interval is 10mm, vertical interval 100mm, can vibrate closely when making gas pocket 11 be convenient for concrete 12 pour, and avoid carrying out concrete 12 chisel hair work, it is inseparable to do benefit to seam crossing connection.
And the outer walls of the steel plate templates 5 are subjected to galvanizing anti-corrosion treatment. In the present embodiment, the galvanization is a surface treatment technique for plating a layer of zinc on the surface of a metal, an alloy or other materials to perform an aesthetic effect, rust prevention or the like, and the method mainly used is the hot galvanizing.
As shown in fig. 1, the front side of the water stop steel plate 8 is the upstream side. In the present embodiment, the concave surface of the water stop steel plate 8 faces the upstream surface, and pressure water penetration can be prevented.
When the post-cast strip is in operation, a plurality of steel bars 6 and steel bar drag hooks 9 are connected into a wall inner steel bar 6 structure in a binding mode according to the actual construction requirement of the post-cast strip, the steel bars 6 need to be horizontally and vertically bound during binding, longitudinal steel bars 6 in the post-cast strip are not bound, then a steel plate template 5 is welded on the outer wall of a water stop steel plate 8, the water stop steel plate 8 is installed on the wall inner steel bars 6 in a welding mode, the water stop steel plate 8 is welded and fixed through short steel bars 6 with the diameter of 8mm during welding, then a wood template 3 and a batten 7 are installed on the front side and the rear side of the wall surface steel bars 6 through matching of split bolts 4 and steel pipes 2, finally concrete 12 is poured in the wood template 3, and the pouring construction of the post-cast strip is completed.
The present invention is not limited to the above embodiments, and any modifications, equivalent replacements, improvements, etc. within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. A novel basement outer wall post-cast strip construction device comprises a structure main body (1);
the method is characterized in that: the utility model discloses a wall structure, including the perpendicular reinforcing bar (6) that sets up of a plurality of, wall inner structure is constituteed through reinforcing bar drag hook (9) in main structure (1), the inside symmetry of wall inner structure is equipped with two stagnant water steel sheet (8), just all fixed steel sheet template (5) that are equipped with on both sides outer wall around stagnant water steel sheet (8), the side all is equipped with plank sheathing (3) around the wall inner structure, concreting (12) in plank sheathing (3), plank sheathing (3) all through a plurality of stay bolt (4) fixed mounting to stay bolt (4) fixed mounting on reinforcing bar (6), just there are steel pipe (2) to the equal level through connection in stay bolt (4) both ends, impartial distance is equipped with a plurality of flitch (7) on plank sheathing (3) outer wall.
2. The novel basement exterior wall post-cast strip construction device of claim 1, characterized in that: the end parts of the steel plate templates (5) are all connected with the outer wall of the water stop steel plate (8) in a welding mode.
3. The novel basement exterior wall post-cast strip construction device of claim 1, characterized in that: keep away from steel sheet template (5) stagnant water steel sheet (8) one end equal equidistance is equipped with a plurality of mounting groove (10), all run through on steel sheet template (5) outer wall and be equipped with a plurality of gas pocket (11).
4. The novel basement exterior wall post-cast strip construction device of claim 1, characterized in that: the outer walls of the steel plate templates (5) are subjected to galvanizing anti-corrosion treatment.
5. The novel basement exterior wall post-cast strip construction device of claim 1, characterized in that: the front side of the water stop steel plate (8) is the upstream surface.
CN202121716922.4U 2021-07-27 2021-07-27 Novel basement outer wall post-cast strip construction device Active CN215594136U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121716922.4U CN215594136U (en) 2021-07-27 2021-07-27 Novel basement outer wall post-cast strip construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121716922.4U CN215594136U (en) 2021-07-27 2021-07-27 Novel basement outer wall post-cast strip construction device

Publications (1)

Publication Number Publication Date
CN215594136U true CN215594136U (en) 2022-01-21

Family

ID=79879276

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121716922.4U Active CN215594136U (en) 2021-07-27 2021-07-27 Novel basement outer wall post-cast strip construction device

Country Status (1)

Country Link
CN (1) CN215594136U (en)

Similar Documents

Publication Publication Date Title
CN107327050B (en) Disassembly-free basement exterior wall flanging unilateral formwork supporting device and construction method
CN105569224A (en) Concrete-filled steel tube edge restraint overlapping integrated shear wall and preparing and installation methods thereof
CN108999212A (en) The template construction method of underground concrete pool wall antiseep
CN206467667U (en) Suspended net shotcrete building enclosure between a kind of stake of use expansion type fixation reinforced mesh
CN104989149B (en) A kind of Civil building basement just before a battle converting system and construction method
CN215594136U (en) Novel basement outer wall post-cast strip construction device
CN211228607U (en) Integrally formed construction structure of outer wall and bottom plate of cast-in-place concrete structure of structure
CN209538214U (en) A kind of late poured band structure of outer wall of basement
CN210563363U (en) Pouring template without tie bar hole
CN209456992U (en) Low damage unilateral formwork supporting structure under campshed support system
CN110374214A (en) Finished product post-cast strip
CN213979911U (en) Basement outer wall post-cast strip template structure
CN215857879U (en) Post-cast strip for bottom plate of underground chamber
CN206220132U (en) A kind of base plate and exterior wall junction construction typified form support
CN212223971U (en) Post-cast strip side-fixing inner-supporting steel plate combined template
CN211368733U (en) Prefabricated assembled concrete pipe props structure
CN215596606U (en) Fixing structure of through-wall pipeline
CN210529717U (en) Foundation pit side wall protection structure
CN211898422U (en) Prefabricated high-strength waist beam with narrow fertilizer groove of foundation pit
CN110258650A (en) A kind of basement shear wall late poured band structure and its construction method
CN110593918A (en) Freezing method based tunnel connection channel pump house construction method
CN210395449U (en) Protective structure convenient for backfilling post-cast strip in advance
CN107304566B (en) A kind of detachable soil nailing wall board structure
CN211773751U (en) Template structure of slide-resistant pile dado
CN220183845U (en) Hanging die mounting structure at chamfer of rainwater box culvert

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant