CN215287890U - Be applicable to rubbish power plant boiler maintenance platform - Google Patents
Be applicable to rubbish power plant boiler maintenance platform Download PDFInfo
- Publication number
- CN215287890U CN215287890U CN202120234916.9U CN202120234916U CN215287890U CN 215287890 U CN215287890 U CN 215287890U CN 202120234916 U CN202120234916 U CN 202120234916U CN 215287890 U CN215287890 U CN 215287890U
- Authority
- CN
- China
- Prior art keywords
- pedal
- boiler
- triangular
- triangular beam
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000012423 maintenance Methods 0.000 title abstract description 13
- 230000001737 promoting effect Effects 0.000 claims description 2
- 238000004804 winding Methods 0.000 claims 1
- 230000000694 effects Effects 0.000 abstract description 2
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- 238000007689 inspection Methods 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000001816 cooling Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model relates to the technical field of boiler maintenance, and discloses a boiler maintenance platform suitable for a garbage power plant, which comprises a bearing beam, wherein an assembly module pedal is arranged at the top of the bearing beam, a triangular beam is movably arranged at one end of the bearing beam through a bolt, an extension pedal is arranged at the top of the triangular beam, extension guardrails are arranged at two sides of the triangular beam, an L-shaped connecting beam is arranged at the bottom of the triangular beam, a connecting fastener is arranged at one end of the L-shaped connecting beam, fixed blocks are symmetrically arranged at one side of the top of the assembly module pedal, the lifting platform is quickly assembled and maintained, the time consumption is reduced compared with that of a scaffold, the assembly can be completed in one tenth of time, the assembly time is fast, the time of other maintenance workers can be shortened, the production efficiency is accelerated, and the maintenance platform adopts a two-side folding mode, the front arch and the rear arch of the garbage boiler are effectively avoided, so that the effect of avoiding touching a water-cooled wall is achieved.
Description
Technical Field
The utility model relates to a boiler overhauls technical field, specifically is a boiler overhauls platform suitable for rubbish power plant.
Background
The boiler is widely developed at the moment, therefore, the boiler plays an important role in the history of economic development in China, is important heat energy supply equipment in national economy, and simultaneously boiler maintenance becomes necessary work content because the volume of the boiler is large, the operations of daily instrument inspection, maintenance, replacement and the like need to be completed on a maintenance platform, most of the existing maintenance platforms adopt scaffolds, the safety is poor, and the working efficiency is low.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a be applicable to rubbish power plant boiler maintenance platform to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a boiler overhaul platform suitable for a garbage power plant comprises a bearing beam, wherein an assembly module pedal is installed at the top of the bearing beam, a triangular beam is movably installed at one end of the bearing beam through a bolt, an extension pedal is arranged at the top of the triangular beam, extension guardrails are installed on two sides of the triangular beam, an L-shaped connecting beam is arranged at the bottom of the triangular beam, a connecting fastener is arranged at one end of the L-shaped connecting beam, fixed blocks are symmetrically installed on one side of the top of the assembly module pedal, a supporting piece is fixedly connected to the top of the fixed blocks, mounting pieces are arranged at the top of the supporting piece, a connecting piece is connected between the two mounting pieces, a supporting block is arranged at the top of the connecting piece, lifting frames are symmetrically arranged at the top of the assembly module pedal, a lifting motor is fixedly installed inside the lifting frames, and a steel wire rope is wound at the output shaft end of the lifting motor, the top of the assembling module pedal is provided with a main body guardrail.
Preferably, the through-hole has been seted up to the inside of installed part, the bolt embedding is inside the through-hole, one side of fixed block seted up with connect fastener assorted draw-in groove, the triangular beam of being convenient for is folding.
Preferably, the installation pendant is installed at the both ends of main part guardrail, main part guardrail and spandrel girder pass through fixing bolt fixed mounting, and through the bolt fastening, the operating personnel dismouting of being convenient for.
Preferably, the extension pedal and the assembly module pedal are in the same plane, so that the extension pedal at the top of the triangular beam after being inverted and the assembly module pedal can be connected with each other at a high fitting degree.
Preferably, the top of spandrel girder is fixed with the backup pad, the equipment module footboard is assembled at the top of backup pad, erects through the backup pad and supports the equipment module footboard.
Compared with the prior art, the utility model provides a be applicable to rubbish power plant boiler and overhaul platform possesses following beneficial effect:
this be applicable to rubbish power plant boiler overhauls platform, overhaul lift platform through fast assembly, the time spent reduces than the scaffold frame, it just can assemble the completion to need one tenth of time, the equipment time just means the work kind of other overhauls just can shorten the time soon, consequently whole maintenance time will reduce, production efficiency has been accelerated, secondly this kind overhauls the platform and adopts the two-sided folding mode, effectual preceding arch and the back arch of avoiding rubbish boiler, thereby reached and exempted from the effect of water-cooling wall.
Drawings
Fig. 1 is an expanded schematic view of a triangular beam of the present invention;
FIG. 2 is a schematic view of the triangular beam of the present invention;
fig. 3 is the connection diagram of the present invention.
In the figure: 1. a spandrel girder; 2. assembling a module pedal; 3. a mounting member; 4. a support member; 5. A support block; 6. a connecting member; 7. a triangular beam; 8. extending the guard bar; 9. lifting the frame; 10. A main body guardrail; 11. a wire rope; 12. a support plate; 13. a fixed block; 14. mounting a hanging piece; 15. a bolt; 16. connecting fasteners; 17. an L-shaped connecting beam; 18. an extension pedal; 19. a hoisting motor; 20. and (5) fixing the bolt.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Please refer to fig. 1-3, which is a boiler overhaul platform suitable for a garbage power plant, and includes a load-bearing beam 1, an assembly module pedal 2 installed on the top of the load-bearing beam 1, a triangular beam 7 movably installed on one end of the load-bearing beam 1 through a bolt 15, an extension pedal 18 installed on the top of the triangular beam 7, extension guardrails 8 installed on two sides of the triangular beam 7, an L-shaped connecting beam 17 installed on the bottom of the triangular beam 7, a connecting fastener 16 installed on one end of the L-shaped connecting beam 17, fixing blocks 13 symmetrically installed on one side of the top of the assembly module pedal 2, a supporting member 4 fixedly connected to the top of the fixing block 13, a mounting member 3 installed on the top of the supporting member 4, a connecting member 6 connected between the two mounting members 3, a supporting block 5 installed on the top of the connecting member 6, a lifting frame 9 symmetrically installed on the top of the assembly module pedal 2, and a lifting motor 19 fixedly installed inside the lifting frame 9, the output shaft end of the lifting motor 19 is wound with a steel wire rope 11, and the top of the assembled module pedal 2 is provided with a main body guardrail 10.
The through-hole has been seted up to the inside of installed part 3, the bolt 15 embedding is inside the through-hole, one side of fixed block 13 seted up with be connected 16 assorted draw-in grooves of fastener, triangular beam 7 of being convenient for is folding, installation pendant 14 is installed at the both ends of main part guardrail 10, main part guardrail 10 passes through fixing bolt 20 fixed mounting with spandrel girder 1, through the bolt fastening, the operating personnel dismouting of being convenient for, extension footboard 18 is at the coplanar with equipment module footboard 2, the extension footboard 18 and the linking that equipment module footboard 2 can the high degree of agreeing with at top after making triangular beam 7 reverse, the top fixed mounting of spandrel girder 1 has backup pad 12, equipment module footboard 2 assembles the top in backup pad 12, erect support assembly module footboard 2 through backup pad 12.
The working principle is as follows: before using, the user need install the inspection to the device, whether each part erection joint of inspection is reasonable, can reach the user demand, the inspection is accomplished and can be used, at first need fix the 11 tops of wire rope at the boiler top that needs overhaul, then 19 fixed mounting of hoisting motor in promoting frame 9, then start hoisting motor 19, when this testing platform promoted the maintenance position, reverse both ends with triangular beam 7, make connecting fastener 16 with the inside draw-in groove block of fixed block 13 can, then will extend guardrail 8 and extension footboard 18 splice the equipment and can overhaul the operation.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. The utility model provides a be applicable to rubbish power plant boiler overhauls platform, includes spandrel girder (1), its characterized in that: the assembling module pedal (2) is installed at the top of the bearing beam (1), one end of the bearing beam (1) is movably provided with a triangular beam (7) through a bolt (15), an extending pedal (18) is arranged at the top of the triangular beam (7), extending guardrails (8) are installed on two sides of the triangular beam (7), an L-shaped connecting beam (17) is arranged at the bottom of the triangular beam (7), a connecting fastener (16) is arranged at one end of the L-shaped connecting beam (17), fixing blocks (13) are symmetrically installed on one side of the top of the assembling module pedal (2), a supporting piece (4) is fixedly connected with the top of each fixing block (13), an installing piece (3) is arranged at the top of each supporting piece (4), a connecting piece (6) is connected between the two installing pieces (3), and a supporting block (5) is arranged at the top of each connecting piece (6), the top symmetry of equipment module footboard (2) is provided with promotes frame (9), the inside fixed mounting of promoting frame (9) has hoisting motor (19), the output shaft end winding of hoisting motor (19) has wire rope (11), the top of equipment module footboard (2) is provided with main part guardrail (10).
2. The boiler overhaul platform for a refuse powered plant of claim 1, further comprising: the through-hole has been seted up to the inside of installed part (3), bolt (15) embedding is inside the through-hole, one side of fixed block (13) is seted up with connecting fastener (16) assorted draw-in groove.
3. The boiler overhaul platform for a refuse powered plant of claim 1, further comprising: the mounting hanging pieces (14) are installed at two ends of the main body guardrail (10), and the main body guardrail (10) and the bearing beam (1) are fixedly installed through the fixing bolts (20).
4. The boiler overhaul platform for a refuse powered plant of claim 1, further comprising: the extension pedal (18) and the assembly module pedal (2) are in the same plane.
5. The boiler overhaul platform for a refuse powered plant of claim 4, wherein: the top fixed mounting of spandrel girder (1) has backup pad (12), equipment module footboard (2) is assembled at the top of backup pad (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120234916.9U CN215287890U (en) | 2021-01-28 | 2021-01-28 | Be applicable to rubbish power plant boiler maintenance platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120234916.9U CN215287890U (en) | 2021-01-28 | 2021-01-28 | Be applicable to rubbish power plant boiler maintenance platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215287890U true CN215287890U (en) | 2021-12-24 |
Family
ID=79530557
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120234916.9U Expired - Fee Related CN215287890U (en) | 2021-01-28 | 2021-01-28 | Be applicable to rubbish power plant boiler maintenance platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215287890U (en) |
-
2021
- 2021-01-28 CN CN202120234916.9U patent/CN215287890U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103290929A (en) | Assembled steel beam splicing node | |
CN215287890U (en) | Be applicable to rubbish power plant boiler maintenance platform | |
CN202170649U (en) | Temporary support steel frame for steel structure | |
CN205645441U (en) | Make things convenient for transformer maintenance's installation crane span structure | |
CN112323643A (en) | Beam transporting vehicle and method for carrying bridge girder erection machine | |
CN201694749U (en) | Solar automatic power supply system for gantry crane | |
CN204299803U (en) | A kind of wind power generating set assembling shipping platform | |
CN201695661U (en) | Component for arranging external suspending bracket of window | |
CN205051627U (en) | Photovoltaic support mounting structure | |
CN215280757U (en) | Photovoltaic module dismouting device | |
CN202544399U (en) | Supporting frame for overhang floor slab with steel structure | |
CN210393502U (en) | Bridge deck crane for mounting steel box girder for bridge | |
CN201971520U (en) | Connection structure of a small-well elevator car wall | |
CN212553671U (en) | Special tool for installing main shaft flange connecting bolt of water turbine | |
CN220394293U (en) | Detachable operating platform for catwalk portal frame | |
CN110593407A (en) | I-shaped aluminum connection structure of aluminum alloy room | |
CN219548782U (en) | Integral type bridge concrete anticollision wall safety maintenance cat ladder | |
CN220359063U (en) | Mounting structure for solar photovoltaic panel | |
CN217299895U (en) | Large eccentric stress lifting frame device serving as support frame | |
CN214989517U (en) | Elevator guide rail connecting and fixing structure | |
CN213951943U (en) | Steel case roof beam edge of a wing overhauls operation platform | |
CN215479220U (en) | High-efficient instrument of installation generator export PT | |
CN215519146U (en) | Assembled outer wall connected node | |
CN217230049U (en) | Electric power overhauls uses equipment machine of lifting | |
CN218912402U (en) | Vertical hydraulic generator export lead wire overhauls platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211224 |