CN103290929A - Assembled steel beam splicing node - Google Patents

Assembled steel beam splicing node Download PDF

Info

Publication number
CN103290929A
CN103290929A CN2012100636145A CN201210063614A CN103290929A CN 103290929 A CN103290929 A CN 103290929A CN 2012100636145 A CN2012100636145 A CN 2012100636145A CN 201210063614 A CN201210063614 A CN 201210063614A CN 103290929 A CN103290929 A CN 103290929A
Authority
CN
China
Prior art keywords
splicing
node
place
girder steel
scab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100636145A
Other languages
Chinese (zh)
Inventor
郁有升
胡海涛
李建峰
王燕
井彦青
孙婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao University of Technology
Qingdao Tengyuan Design Institute Co Ltd
Original Assignee
Qingdao University of Technology
Qingdao Tengyuan Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao University of Technology, Qingdao Tengyuan Design Institute Co Ltd filed Critical Qingdao University of Technology
Priority to CN2012100636145A priority Critical patent/CN103290929A/en
Publication of CN103290929A publication Critical patent/CN103290929A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention relates to an assembled splicing node of constructional steel structural beams. The splicing node of the beams is characterized in that splicing plates are intersectionally arranged on upper and lower flanges at splicing beam sections on the two sides, and the splicing plates on the two sides of are connected with the beams by welding in a processing plant in advance. The securely welded splicing plates on the two sides serve as lug plates to allow the mounting beam sections to be in place quickly during on-site splicing and assembly. After the beam sections are in place, the splicing plates are connected with upper and lower flanges of the beam on the other side, and web plates on the two sides are spliced. The splicing node is spliced by the bolts at a mounting site. The splicing node is reasonable in structure, free from welding, high in construction efficiency and good in safety, transmits a force clearly, and is in place quickly during on-site mounting, the mounting efficiency can be improved, and the fire risk caused by the welding can be avoided. In addition, the node is assembled by the bolts at the construction site, and great convenience is brought to the site where the welding is inconvenient due to severe construction site conditions.

Description

A kind of assembling girder steel splicing node
Technical field
The present invention relates to a kind of connecting method of construction steel structure beam, be specifically related to a kind of assembling splicing node.
Background technology
Steel work has the intensity height, from heavy and light, series of advantages such as anti-seismic performance is good, speed of application is fast, ground cost saving, floor space is little, industrialization degree is high, good looking appearance.Compare the characteristics with environmental protection and reusable edible with concrete structure, be the environmental type product of generally acknowledging, the policy that meets sustainable development, developed country extensively adopts steel work in building construction, in the U.S., Japan, the steel work steel using amount has accounted for more than 30% of output of steel, and along with the enhancing of Chinese economic development and comprehensive strength, steel building will develop rapidly.And in steel work, steel structure node influences great for structure power transmission, construction difficulty or ease, construction costs.
Wherein, the splicing node of beam splicing form traditionally mainly contains three kinds: 1. going up the bottom flange is that full penetration weld connects, and web connects with high-strength bolt; 2. going up the bottom flange all is connected with high-strength bolt with web; 3. the edge of a wing and web are the full penetration weldering and are connected.For first kind and the third connected mode, the bottom flange is that full penetration connects on the beam, needs in the construction welding again is installed earlier, and construction speed is longer, because work high above the ground, weldquality is difficult to guarantee.For second kind of connecting method, the full bolt connecting mode that the edge of a wing and web all are connected with high-strength bolt, to the requirement on machining accuracy of member and node than higher, simultaneously because the high-strength bolt unit price is more expensive, so cost is also high.In addition, when these three kinds traditional splicing nodes splice at the scene, owing to be that install in the high-altitude, for convenience in place also needs to weld the ear plate in addition in the top flange of beam, after finishing, also to excise node construction time-consuming taking a lot of work.
Summary of the invention
The present invention is directed in the existing steel structure girder splicing exists installation in position need borrow auxiliary part, the field operation engineering quantity is big, cycle is long, and installation quality is difficult to deficiencies such as guarantee, and a kind of on-the-spot do not have welding, flexible, the safe and reliable quick-assembling node of splicing are provided.
Technical scheme of the present invention is: a kind of assembling splicing node of girder steel, the girder steel section that comprises both sides, scab and supporting bolt, the upper and lower edge of a wing scab interlaced arrangement of beam is in the outside, the upper and lower edge of a wing of the beam section of both sides, and in processing factory, finish welding with the beam section in advance, and splicing at the scene in the installation process, upper and lower edge of a wing scab serves as plate in place, after member was in place, the upper and lower edge of a wing of beam and web were all realized the splicing of node with bolt;
Preferably, earlier the bottom flange scab of beam section in place is connected with the bottom flange of this Duan Liang by the weld seam connection, and has welded in processing factory and to have finished;
Preferably, the top flange scab of back beam section in place is connected with the top flange of this Duan Liang by weld seam connection, and has welded in processing factory and to have finished;
Preferably, the web of two sections girder steels is held bolt hole successfully in processing factory;
Preferably, the overhanging side of bottom flange scab of beam section in place is held bolt hole successfully in processing factory earlier;
Preferably, the overhanging side of top flange scab of back beam section in place is held bolt hole successfully in processing factory;
Preferably, the top flange of beam section in place is held bolt hole successfully in processing factory earlier;
Preferably, the bottom flange of back beam section in place is held bolt hole successfully in processing factory;
Preferably, the scab of the last bottom flange of the splicing node of girder steel is made usefulness in place in splicing is installed;
The invention has the beneficial effects as follows: the present invention is rational in infrastructure, power transmission is clear and definite, do not have welding, efficiency of construction height in the field-mounted process, and safety is good.This invention is by the reasonable Arrangement of bottom flange scab on the beam, interaction arrangement is in two sides splicing beam section respectively, and in processing factory, finish with the welding of beam section in advance, splice in the installation process at the scene, convenient in place, need not weld, both improve installation effectiveness, avoid welding to bring the risk that causes fire again; Welding has been avoided in this invention at the construction field (site), and adopts the bolt Fast Installation, and the building site that this is inconvenient to weld for the job site inclement condition brings great convenience; Simultaneously, owing to the convenience of node concatenation, will advance the standardized process of steel structure system.
Description of drawings
Accompanying drawing 1 is the installation process schematic diagram of the specific embodiment of the invention;
Accompanying drawing 2 is the structural representation of the specific embodiment of the invention.
The specific embodiment
Shown in Fig. 1 to 2, a kind of girder steel assembling splicing node comprises (23) two sections beams of girder steel (22) and girder steel, and girder steel (22) is elder generation's beam in place, and girder steel (23) is back beam in place.Wherein, girder steel (22) comprises top flange (1), the bolt hole of holding successfully in advance on the top flange (1) (2), web (3), the bolt hole of holding successfully in advance on the web (3) (4), bottom flange (5), the scab (6) of bottom flange (3), the bolt hole of holding successfully in advance on the scab (6) of bottom flange (3) (7), the weld seam (8) that the scab of bottom flange (3) is connected with bottom flange (3); Girder steel (23) comprises top flange (9), the scab (10) of top flange (9), the bolt hole of holding successfully in advance on the scab (10) of top flange (9) (11), the weld seam (12) that the scab (10) of top flange (9) is connected with top flange (9), web (13), the bolt hole of holding successfully in advance on the web (13) (14), bottom flange (15), the bolt hole of holding successfully in advance on the bottom flange (15) (16), the installation direction of girder steel (23) is (21).After treating girder steel (23) installation in position, at the web (3) of girder steel (22) and the side attached node plate (17) of the web (13) of girder steel (23), fixing with bolt (18), girder steel (22) top flange (1) is fixing with bolt (19) with the scab (10) of the top flange of girder steel (23), and the scab (6) of girder steel (22) lower flange of girder edge (5) is fixing with bolt (20) with the bottom flange (15) of girder steel (23).

Claims (9)

1. the assembling of a girder steel splices node, the girder steel section that comprises both sides, scab and supporting bolt, the upper and lower edge of a wing scab interlaced arrangement of beam is in the outside, the upper and lower edge of a wing of the beam section of both sides, and in processing factory, finish welding with the beam section in advance, and splicing at the scene in the installation process, upper and lower edge of a wing scab serves as plate in place, after member was in place, the upper and lower edge of a wing of beam and web were all realized the splicing of node with bolt.
2. assembling girder steel according to claim 1 splicing node, it is characterized in that: the bottom flange scab of beam section in place is connected with the bottom flange of this Duan Liang by the weld seam connection earlier, and has welded in processing factory and to have finished.
3. assembling girder steel according to claim 1 splicing node, it is characterized in that: the top flange scab of back beam section in place is connected with the top flange of this Duan Liang by the weld seam connection, and has welded in processing factory and to have finished.
4. assembling girder steel according to claim 1 splices node, and it is characterized in that: the web of two sections girder steels is held bolt hole successfully in processing factory.
5. assembling girder steel according to claim 2 splices node, it is characterized in that: the overhanging side of top flange scab of beam section in place is held bolt hole successfully in adding processing factory earlier.
6. assembling girder steel according to claim 3 splices node, it is characterized in that: the overhanging side of bottom flange scab of back beam section in place is held bolt hole successfully in adding processing factory.
7. assembling girder steel according to claim 1 splices node, it is characterized in that: the top flange of beam section in place is held bolt hole successfully in processing factory earlier.
8. assembling girder steel according to claim 1 splices node, it is characterized in that: the bottom flange of back beam section in place is held bolt hole successfully in processing factory.
9. assembling girder steel according to claim 1 splices node, it is characterized in that: the scab of the last bottom flange of the splicing node of girder steel plays usefulness in place in splicing is installed.
CN2012100636145A 2012-03-02 2012-03-02 Assembled steel beam splicing node Pending CN103290929A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100636145A CN103290929A (en) 2012-03-02 2012-03-02 Assembled steel beam splicing node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100636145A CN103290929A (en) 2012-03-02 2012-03-02 Assembled steel beam splicing node

Publications (1)

Publication Number Publication Date
CN103290929A true CN103290929A (en) 2013-09-11

Family

ID=49092415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100636145A Pending CN103290929A (en) 2012-03-02 2012-03-02 Assembled steel beam splicing node

Country Status (1)

Country Link
CN (1) CN103290929A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669571A (en) * 2013-12-19 2014-03-26 上海都市绿色工程有限公司 Wall beam fixing structure for greenhouse
CN104088370A (en) * 2014-05-29 2014-10-08 中建钢构有限公司 High-strength bolt friction-type connecting structure and connection node performance optimizing method thereof
CN104863269A (en) * 2015-05-29 2015-08-26 重庆大学 Primary and secondary beam rigid connection joint for wave web steel structure
CN106670676A (en) * 2016-12-29 2017-05-17 中铁大桥勘测设计院集团有限公司 Steel bridge three-dimensional intersectional welding seam structure and construction method thereof
CN106702831A (en) * 2017-01-24 2017-05-24 北京交通大学 Straddling type monorail traffic full-steel structural system based on assembly type technology
CN108193832A (en) * 2017-12-29 2018-06-22 上海建工集团股份有限公司 A kind of i-shape steel beam assembled connecting node and its construction method
CN110258794A (en) * 2019-05-15 2019-09-20 深圳市建筑设计研究总院有限公司 The full bolt connection node and its construction method of girder steel
CN112376691A (en) * 2020-10-30 2021-02-19 中冶(上海)钢结构科技有限公司 Construction method for H-shaped steel beam bolt joint
CN112854449A (en) * 2021-01-08 2021-05-28 盛尔建设集团有限公司 Steel construction assembled building component
CN110258794B (en) * 2019-05-15 2024-07-12 深圳市建筑设计研究总院有限公司 Full-bolt connection node of steel beam and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1144002A (en) * 1997-07-25 1999-02-16 Nkk Corp Brace joining structure
CN2841792Y (en) * 2005-10-06 2006-11-29 中国矿业大学 Steel frame structure cantilever beam connection node
JP2007205035A (en) * 2006-02-01 2007-08-16 Watahan Technos Kk Tool for assembling splice plate for connecting upper flange of h-shape steel frame, and assembling method using the same
CN201151954Y (en) * 2007-11-27 2008-11-19 贵阳铝镁设计研究院 Steel column and concrete column connection structure
CN202644736U (en) * 2012-03-02 2013-01-02 青岛理工大学 Fabricated-type steel beam splicing joint

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1144002A (en) * 1997-07-25 1999-02-16 Nkk Corp Brace joining structure
CN2841792Y (en) * 2005-10-06 2006-11-29 中国矿业大学 Steel frame structure cantilever beam connection node
JP2007205035A (en) * 2006-02-01 2007-08-16 Watahan Technos Kk Tool for assembling splice plate for connecting upper flange of h-shape steel frame, and assembling method using the same
CN201151954Y (en) * 2007-11-27 2008-11-19 贵阳铝镁设计研究院 Steel column and concrete column connection structure
CN202644736U (en) * 2012-03-02 2013-01-02 青岛理工大学 Fabricated-type steel beam splicing joint

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669571A (en) * 2013-12-19 2014-03-26 上海都市绿色工程有限公司 Wall beam fixing structure for greenhouse
CN103669571B (en) * 2013-12-19 2016-02-17 上海都市绿色工程有限公司 A kind of greenhouse wall beam fixed structure
CN104088370A (en) * 2014-05-29 2014-10-08 中建钢构有限公司 High-strength bolt friction-type connecting structure and connection node performance optimizing method thereof
CN104863269A (en) * 2015-05-29 2015-08-26 重庆大学 Primary and secondary beam rigid connection joint for wave web steel structure
CN106670676A (en) * 2016-12-29 2017-05-17 中铁大桥勘测设计院集团有限公司 Steel bridge three-dimensional intersectional welding seam structure and construction method thereof
CN106670676B (en) * 2016-12-29 2019-01-29 中铁大桥勘测设计院集团有限公司 A kind of steel bridge crossings on different level welding line structure and its construction method
CN106702831A (en) * 2017-01-24 2017-05-24 北京交通大学 Straddling type monorail traffic full-steel structural system based on assembly type technology
CN108193832A (en) * 2017-12-29 2018-06-22 上海建工集团股份有限公司 A kind of i-shape steel beam assembled connecting node and its construction method
CN110258794A (en) * 2019-05-15 2019-09-20 深圳市建筑设计研究总院有限公司 The full bolt connection node and its construction method of girder steel
CN110258794B (en) * 2019-05-15 2024-07-12 深圳市建筑设计研究总院有限公司 Full-bolt connection node of steel beam and construction method thereof
CN112376691A (en) * 2020-10-30 2021-02-19 中冶(上海)钢结构科技有限公司 Construction method for H-shaped steel beam bolt joint
CN112854449A (en) * 2021-01-08 2021-05-28 盛尔建设集团有限公司 Steel construction assembled building component

Similar Documents

Publication Publication Date Title
CN103290929A (en) Assembled steel beam splicing node
CN202644735U (en) Assembly type rigid node of steel-structure beam column
CN103334490B (en) One how high-rise assembling type steel structure frame supported system
CN103290928A (en) Steel structure beam column assembly type rigid joint
CN102979176B (en) Industrialized multi-story high-rise assembled steel structure system
CN201972269U (en) Prefabricated reinforcing steel bar concrete shear wall
CN103334488B (en) Assembled steel structure deformed column framework support system
CN102995756B (en) Concrete-filled rectangular steel tube column-box girder full-bolt connection node and construction method
CN103015536A (en) Beam-column joint connecting device for multi-story/high-rise assembly type steel structure system
CN205444492U (en) H type cantilever girder steel post geometric cross section mosaic structure
CN202730970U (en) Assembly type beam column node
CN103276799B (en) A kind of industrialization assembling post through beam steel flanged beam steel structure frame eccentrical braces
CN202644736U (en) Fabricated-type steel beam splicing joint
CN102493553A (en) Member for connection node of reinforced beam and steel beam and construction method thereof
CN203808237U (en) Tall building structure system with prefabricated assembled type buckling-restrained steel plate shear walls
CN103290922B (en) A kind of industrialization assembling post through beam steel flanged beam steel structure frame system
CN205421562U (en) H type cantilever girder steel post mosaic structure
CN203701386U (en) Steel-structure floor slab group
CN103122658B (en) Industrial fabricated multi-story steel frame structure and construction method thereof
CN203420477U (en) Steel structure set-up platform for concrete pouring
CN202882117U (en) Precast-concrete prefabricated frame structure
CN215253433U (en) Beam-beam rigid connection node connecting device
CN202194250U (en) Bolting-welding mixed joint for on-site butting of steel girders and flanges
CN204662804U (en) A kind of assembled steel structure stair
CN202347665U (en) Connection node constructional member of reinforced concrete beam and steel beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130911