CN214940398U - Assembled precast concrete overhaul (inspection) well - Google Patents

Assembled precast concrete overhaul (inspection) well Download PDF

Info

Publication number
CN214940398U
CN214940398U CN202120633400.1U CN202120633400U CN214940398U CN 214940398 U CN214940398 U CN 214940398U CN 202120633400 U CN202120633400 U CN 202120633400U CN 214940398 U CN214940398 U CN 214940398U
Authority
CN
China
Prior art keywords
well
shaft
closing
cover cylinder
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120633400.1U
Other languages
Chinese (zh)
Inventor
田万明
罗明
张贤
白跃东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Tianfu Yuanda Construction Industrialization Co ltd
Xinjiang Tianfu Group Co ltd
Original Assignee
Xinjiang Tianfu Yuanda Construction Industrialization Co ltd
Xinjiang Tianfu Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Tianfu Yuanda Construction Industrialization Co ltd, Xinjiang Tianfu Group Co ltd filed Critical Xinjiang Tianfu Yuanda Construction Industrialization Co ltd
Priority to CN202120633400.1U priority Critical patent/CN214940398U/en
Application granted granted Critical
Publication of CN214940398U publication Critical patent/CN214940398U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model relates to an assembly type precast concrete overhaul (inspection) well, which comprises a well base, a shaft adjusting ring, a well closing-up cover cylinder and a well top well ring well cover which are connected in sequence, wherein the shaft is formed by assembling at least two shaft adjusting rings with the same or different heights, and the well bottom seat, the shaft adjusting ring, the well closing-up cover cylinder and the well top well ring well cover are mutually independent prefabricated components, hoisting holes and in-well crawling ladder embedded iron pieces are arranged on the shaft bottom seat, the shaft adjusting ring and the shaft closing-up cover cylinder, the shaft bottom seat is radially provided with a through hole A, and the shaft can be radially provided with a through hole B as required; the well maintenance (inspection) well with the proper height can be flexibly assembled according to the field requirement, the errors of the well maintenance (inspection) well and the designed elevation are reduced, and the well base, the shaft adjusting ring and the well closing-up cover cylinder are provided with the hoisting holes, so that the hoisting at the construction field is facilitated, the installation efficiency can be improved, and the labor intensity of workers can be reduced.

Description

Assembled precast concrete overhaul (inspection) well
Technical Field
The utility model relates to an overhaul (look into) well, concretely relates to assembled precast concrete overhauls (looks into) well.
Background
The manhole is set up for the convenience of installation, inspection and maintenance of various pipelines (channels) of power supply, heat supply, gas supply pipe, water supply, drainage, pollution discharge, communication network, cable TV, street lamp line, etc. of the underground infrastructure of city. It is usually installed at the junction of pipeline, turning, pipe diameter or slope changing position and at regular intervals on straight pipe section, and is an essential accessory structure for regular inspection and maintenance of pipeline.
The overhaul (inspection) well room in urban construction is mostly formed by traditional construction site brick laying or concrete cast-in-place, the operation procedures are complicated, the construction period is long, the potential safety hazard is many, the quality assurance degree is poor, the environment pollution such as dust and noise is large, and the overhaul (inspection) well room cannot be recycled.
At present, prefabricated reinforced concrete combined inspection chambers are also used, for example: patent document CN201593195U discloses an assembled water meter gate valve well, which mainly comprises a well cover, a trapezoidal wall, a circular wall and a bottom plate, wherein the bottom plate, the circular wall and the trapezoidal wall of the water meter gate valve well are respectively prefabricated and molded by reinforced concrete and connected through an L-shaped occlusion port, and the middle part of the circular wall is provided with symmetrical through-hole. Although the water meter gate valve well can be assembled, the production efficiency is improved, and the quality is relatively stable.
However, the circular wall of the scheme is integrally prefabricated, so that the height of the gate valve well cannot be flexibly adjusted according to actual requirements, and the problem that the height of the assembled gate valve well has a large error with the height of a designed elevation or the actual height of a site often occurs; and the well lid, the trapezoidal wall and the circular wall are not provided with hoisting holes, and the assembly operation can be carried out only by lifting of workers on a construction site, so that the problems of high installation labor intensity and unsafety exist. And the scheme is not divided into a round well, a rectangular well and a light well, a heavy well according to the use environment and the use.
SUMMERY OF THE UTILITY MODEL
To the technical problem that above-mentioned exists, the utility model provides an assembled precast concrete overhauls (looks into) well.
The utility model adopts the technical proposal that:
the utility model provides an assembled precast concrete overhauls (looks into) well, contains well base, pit shaft, well binding off lid section of thick bamboo and well top walling crib well lid that connect gradually at least, the pit shaft is assembled by two the same or not pit shaft regulating rings of co-altitude and is constituted, and well base, pit shaft regulating ring, well binding off lid section of thick bamboo and well top walling crib well lid are mutually independent prefabricated component, all are equipped with hole for hoist and mount and well cat ladder embedded iron spare on well base, pit shaft regulating ring, well binding off lid section of thick bamboo, and the well base radially is equipped with tube passing hole A, radially can establish tube passing hole B on the pit shaft.
Further, above-mentioned assembled precast concrete overhauls (looks up) well, well base, pit shaft regulating ring and well binding off lid section of thick bamboo can be circular or rectangle, can divide into light-duty and heavy two kinds again, and well binding off lid section of thick bamboo upper portion binding off wherein, can directly install finished product well top walling crib well lid in its upper portion.
Furthermore, the fabricated precast concrete inspection well is characterized in that lightening holes are formed in the well base, the shaft adjusting ring and the well closing cover cylinder.
Further, in the fabricated precast concrete inspection (checking) well, the joint of the well base and the shaft adjusting ring and the joint of the shaft adjusting ring and the well closing-up cover barrel are provided with concave-convex tongue-and-groove structures which are mutually embedded, so that the well base, the shaft adjusting ring and the well closing-up cover barrel are sequentially spliced.
The utility model discloses beneficial effect after implementing is:
1. the shaft is formed by assembling shaft adjusting rings with the same or different heights, so that a maintenance (inspection) well with a proper height can be flexibly assembled according to the field requirement, and the error between the maintenance (inspection) well and the designed elevation (the precision can reach cm) is reduced;
2. hoisting holes are formed in the well base, the shaft adjusting ring and the well closing-up cover cylinder, so that hoisting in a construction site is facilitated, and therefore the installation efficiency can be improved and the labor intensity of workers can be reduced;
3. the repair (inspection) well can be assembled and molded in different places for reuse after being disassembled part by part when not needed, and can be recycled for multiple times, so that the repair (inspection) well can be permanently fixed for use and recycled for use;
4. the overhaul (inspection) well is divided into a round well and a rectangular well, and is also divided into a light well and a heavy well, the light well is used on landscapes, greenbelts and sidewalks, the heavy well is used on a vehicle road, and the overhaul (inspection) well is suitable and reasonably used according to local conditions, so that the overhaul (inspection) well saves and does not waste;
5. this scheme overhauls (looks up) well and compares traditional masonry well and cast-in-place well and has: the system has the advantages of high safety, high quality assurance, environmental protection, circular economy, high durability, high flexibility, high precision, simplicity, rapidness, time saving, high efficiency, cost saving, economy and the like.
Drawings
FIG. 1 is a view of the assembly structure of the assembly type precast concrete inspection well of the present invention;
FIG. 2 is an exploded view of the prefabricated concrete inspection well of the present invention;
fig. 3 is an assembly structure diagram of embodiment 3 of the present invention;
fig. 4 is an exploded view of embodiment 3 of the present invention.
Reference numerals in the drawings of the specification include: the well comprises a well base 1, a pipe penetrating hole A10, a shaft adjusting ring 2, a well closing cover barrel 3, a hoisting hole 4, a groove 5, a flange 6, a well top well ring well cover 7, a ladder stand embedded iron piece 8 and a pipe penetrating hole B9.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, embodiments of the present invention will be described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1 was carried out: with reference to FIGS. 1 and 2
The scheme provides an assembled precast concrete overhaul (inspection) well, which at least comprises a well bottom seat 1, a well shaft, a well closing-up cover cylinder 3 and a well top well ring well cover 7 which are connected in sequence, wherein the well shaft is formed by assembling at least two well shaft adjusting rings 2 with the same or different heights, the figure specifically shows that the well shaft is formed by assembling 4 well shaft adjusting rings 2 with different heights, the well bottom seat 1, the well shaft adjusting rings 2 and the well closing-up cover cylinder 3 can be round or rectangular, the figure specifically shows that the shape is round, the upper part of the well closing-up cover cylinder 3 is closed up, the upper part can be directly provided with a finished well ring well cover, the well bottom seat 1, the well shaft adjusting rings 2 and the well closing-up cover cylinder 3 are mutually independent precast components, hoisting holes 4 are respectively arranged on the well bottom seat 1, the shaft adjusting ring 2 and the well closing-up cover barrel 3, a through hole A10 is radially arranged on the well bottom seat 1, and a through hole B10 can be radially arranged on the shaft as required.
The assembly process of the assembly type precast concrete overhaul (inspection) well comprises the following steps:
1. and excavating a pit and leveling the bottom of the pit.
2. And (3) hoisting the well base 1, stably hoisting the well base 1 to the bottom of the pit to be leveled, and then penetrating a pipeline through the pipe penetrating hole A10.
3. The method comprises the steps of setting slurry waterproof mortar or paving an annular rubber mat (not shown) at the upper opening of a well base 1, hoisting a shaft adjusting ring 2 through a hoisting hole 4, connecting the shaft adjusting ring 2 and the well base 1 through the slurry waterproof mortar or paving the annular rubber mat, hoisting different shaft adjusting rings 2 to assemble a shaft according to the actual need of well maintenance (inspection), and setting the slurry waterproof mortar or paving the annular rubber mat at the joint of the adjacent shaft adjusting rings 2 for connection.
4. A hoisting well closing-in cover cylinder or a well closing-in cover cylinder 3 is arranged at the upper opening of the shaft, waterproof mortar is placed at the joint of the well closing-in cover cylinder or the well closing-in cover cylinder 3 and the shaft or an annular rubber mat is laid for connection,
5. and finally, mounting a finished well ring well cover 7 on the well closing-up cover cylinder 3, and finally, uniformly backfilling soil along the periphery of the well to backfill the well pit.
This scheme overhauls (looks up) well and compares traditional masonry well and cast-in-place well and have following advantage:
1. the safety is good: the well components of the prefabricated concrete overhaul (inspection) well are prefabricated in advance on a PC production line of a factory, and the well pit excavation, the assembly completion, the backfilling and the leveling in the same day can be realized on a construction site. The potential safety hazard brought by long-time exposure of the pit due to the fact that excavation of the pit in the same day, construction completion in the same day and backfill leveling in the same day cannot be achieved due to the fact that the traditional masonry well and the cast-in-place well are limited by complex and tedious construction procedures is solved.
2. The quality assurance degree is high: the assembled precast concrete inspection well is produced in PC production line with standardized steel forming mold, numerically controlled automatic steel bar producing line, numerically controlled automatic indoor concrete mixing station, numerically controlled automatic concrete distributor, HF vibration table, numerically controlled automatic constant temperature and humidity maintaining kiln, numerically controlled automatic conveying and hoisting system and other production units, and has high quality, high concrete part and member forming quality. The traditional masonry well and the cast-in-place well are caused by a plurality of adverse factors and different quality of workers on a construction site: the mortar plumpness of masonry mortar of masonry wells generally does not reach the standard (generally can only reach 60-80%, and the vertical joint is worse and is generally about 60%), dry bricks are put into the wells and plastered, the plastering on the inner side and the outer side of the well wall can be applied and processed in a living way (generally existing common quality problems of thickness, thinness, penetration and leakage), and the quality is poor.
3. Green and environment-friendly: meets the requirement of one section for four sections and one section for environmental protection in national green buildings. Compared with the defects of more manpower, more material consumption, long time consumption and more occupied area of the traditional masonry well and a cast-in-place well, the characteristics of less manpower, short time, small occupied area, high efficiency and quickness in the assembled precast concrete overhaul (inspection) well realize energy conservation, land conservation, material conservation, water conservation and environmental protection. All parts of the prefabricated concrete well are produced in factories and are assembled and molded on a construction site. The problems of dust pollution, noise pollution and environmental pollution which can not be avoided by the traditional masonry well and the cast-in-place well are solved.
4. And (3) recycling economy: the method meets the policy requirement of circular economy vigorously advocated by the nation, can be recycled in one piece and has the characteristic of recycling. All parts of the prefabricated concrete inspection well are standardized universal parts produced in factories and are assembled and molded on a construction site. When not needed, the parts can be detached one by one, and then the parts can be assembled and molded in different places for reuse, and can be recycled for multiple times. And once the traditional masonry well and the cast-in-place well are removed, the traditional masonry well and the cast-in-place well become a pile of construction waste.
5. The durability is good: the service life of the fabricated precast concrete inspection well can be as long as that of the single building engineering, and is longer than that of the fabricated precast concrete inspection well. The service life is more than 70 years and 2 times higher than that of the traditional masonry well.
6. Can adjust the height wantonly, the flexibility is good, the precision is high: the assembled precast concrete inspection well is a standardized universal component, the shaft adjusting ring 2 has specifications of different heights of 600 mm, 500 mm, 300 mm, 250 mm and 200mm, can be assembled into drainage wells or inspection wells with different depths according to actual needs on site, and has good adjustability and flexibility. The adjusting precision can reach 10mm level.
7. The on-site assembly is simple and quick, and is time-saving and efficient: 3 workers on the construction site can assemble 1 complete set of prefabricated concrete inspection (checking) well in about 30-40 minutes, 8-12 sets of wells can be installed in 1 day, and the number of the prefabricated concrete wells is 0.3 day/set. The masonry well is combined with 3 workers/set of well (2 workers can complete the construction of cushion, masonry, plastering and the like of 1 masonry well in 1.5 days). The cast-in-place well closes 2 worker day/set of well (2 workers can complete the construction of a bottom plate cushion layer, reinforcement manufacturing, binding and installation, template manufacturing and erecting, concrete pouring, form removal and the like of 1 cast-in-place well in 2 days). The work efficiency of the fabricated precast concrete inspection (checking) well is 10 times higher than that of a masonry well and 6.7 times higher than that of a cast-in-place well. The construction period can be greatly shortened by 6-10 times, the project progress is accelerated by 6-10 times, and therefore the economic benefit is improved.
Example 2: with reference to FIGS. 1 and 2
Compared with the embodiment 1, the difference is that lightening holes (not shown) are arranged on the well bottom seat 1, the shaft adjusting ring 2 and the well closing-up cover barrel 3, the lightening holes can lighten the mass of each part and the labor intensity of workers, the use amount of raw materials is saved while the quality of the whole overhaul (inspection) well is not influenced, and the manufacturing cost of the overhaul (inspection) well is reduced.
Example 3: with reference to FIGS. 3 and 4
Compared with the embodiment 2, the difference is that the connection part of the well bottom seat 1 and the shaft 2 and the connection part between the shaft 2 and the well closing-up cover cylinder 3 are provided with concave-convex tongue-and-groove structures which are mutually embedded or the connection mode of each part adopts two connection parts of slurry sitting connection and annular rubber mat connection, so that the well bottom seat 1, the shaft 2 and the well closing-up cover cylinder 3 are sequentially spliced; the attached drawing of the concave-convex tongue-and-groove structure specifically illustrates the structure of the flange 6 matched with the groove 5; the concave-convex tongue-and-groove structure improves the side pressure bearing capacity of the assembled precast concrete combined type overhaul (inspection) well, and connection dislocation can be avoided after installation and backfilling.
The above description is only an example of the present invention, and the detailed structure and characteristics of the embodiments are not described herein. It should be noted that, for those skilled in the art, without departing from the structure of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent. The scope of the claims of the present application shall be determined by the contents of the claims, and the description of the embodiments and the like in the specification shall be used to explain the contents of the claims.

Claims (4)

1. The utility model provides an assembled precast concrete overhauls (looks into) well, contains well base (1), pit shaft, well binding off cover section of thick bamboo (3) and well top walling crib well lid (7) that connect gradually at least, its characterized in that: the shaft is assembled by two shaft regulating rings (2) of the same height or different heights at least and is formed, and well base (1), shaft regulating ring (2), a well closing-up cover cylinder (3) and a well top well ring well lid (7) are prefabricated parts which are mutually independent, hoisting holes (4) and well ladder embedded iron pieces (8) are arranged on the well base (1), the shaft regulating ring (2) and the well closing-up cover cylinder (3), a pipe penetrating hole A (10) is radially arranged on the well base (1), and a pipe penetrating hole B (9) can be radially arranged on the shaft.
2. The fabricated precast concrete manhole of claim 1, wherein: the well base (1), the shaft adjusting ring (2) and the well closing-up cover cylinder (3) can be circular or rectangular, and can be light and heavy, the upper part of the well closing-up cover cylinder (3) is closed up, and a finished well top well ring well cover (7) can be directly installed on the upper part of the well closing-up cover cylinder.
3. The fabricated precast concrete manhole of claim 2, wherein: and lightening holes are formed in the well base (1), the shaft adjusting ring (2) and the well closing-up cover barrel (3).
4. An assembly type precast concrete manhole according to any one of claims 1 to 3, wherein: the well base (1) and the shaft adjusting ring (2) are connected, and the shaft adjusting ring (2) and the well closing-up cover cylinder (3) are connected, and concave-convex tongue-and-groove structures which are mutually embedded are arranged at the positions of the well base (1) and the shaft adjusting ring (2) and the well closing-up cover cylinder (3), so that the well base (1), the shaft adjusting ring (2) and the well closing-up cover cylinder (3) are sequentially spliced.
CN202120633400.1U 2021-03-29 2021-03-29 Assembled precast concrete overhaul (inspection) well Active CN214940398U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120633400.1U CN214940398U (en) 2021-03-29 2021-03-29 Assembled precast concrete overhaul (inspection) well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120633400.1U CN214940398U (en) 2021-03-29 2021-03-29 Assembled precast concrete overhaul (inspection) well

Publications (1)

Publication Number Publication Date
CN214940398U true CN214940398U (en) 2021-11-30

Family

ID=79038316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120633400.1U Active CN214940398U (en) 2021-03-29 2021-03-29 Assembled precast concrete overhaul (inspection) well

Country Status (1)

Country Link
CN (1) CN214940398U (en)

Similar Documents

Publication Publication Date Title
CN210031914U (en) Assembled inspection shaft
CN210887523U (en) Precast concrete assembled rainwater well
CN103806470B (en) Mounting method produced by steel concrete manhole
CN112227502A (en) Drainage inspection well construction method
CN210797642U (en) Assembled reinforced concrete inspection shaft of assembling fast
CN214940398U (en) Assembled precast concrete overhaul (inspection) well
CN209854577U (en) Assembled thin-wall box-shaped channel
KR101965801B1 (en) Assembly manhole apparatus for connecting hume pipe and constructing method thereof
CN216949733U (en) Novel reinforced concrete structure inverted cone and molding device
CN112431289A (en) Municipal sewage well wall prefabrication and assembly process and concrete well wall component
CN205576973U (en) Circular inspection shaft of prefabricated formula
CN111335445B (en) Construction method of concrete catch basin by using steel pipe as inner mold
CN111335442B (en) Large integral inspection well and preparation method thereof
CN112726784A (en) Fully-prefabricated PC sewer inspection well component assembly type structure and construction method
CN205205863U (en) Prefabricated inspection shaft
KR20070076560A (en) Sectional manhole
KR960003303Y1 (en) Fabricated manhole structure
CN217399865U (en) Assembled precast concrete inspection shaft
CN110644593A (en) Embedded anti-settling prefabricated overhaul well and construction method thereof
CN216892739U (en) Assembled drainage inspection shaft
CN218990255U (en) Prefabricated composite node suitable for small-size utility tunnel quick construction
CN221072929U (en) Non-excavation assembly caisson type inspection well for rural sewage pipe network
CN218148510U (en) Prefabricated inspection shaft of trisection formula complete Assembly
KR102018992B1 (en) Assembly manhole structure using using waste plastic
CN202543972U (en) Liftable multi-ring manhole cover

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant