CN214765692U - Treatment facility for construction waste - Google Patents

Treatment facility for construction waste Download PDF

Info

Publication number
CN214765692U
CN214765692U CN202121309887.4U CN202121309887U CN214765692U CN 214765692 U CN214765692 U CN 214765692U CN 202121309887 U CN202121309887 U CN 202121309887U CN 214765692 U CN214765692 U CN 214765692U
Authority
CN
China
Prior art keywords
treatment box
construction waste
motor
treatment
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121309887.4U
Other languages
Chinese (zh)
Inventor
陈国礼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Kaicheng Exploration And Mapping Technology Co ltd
Original Assignee
Guangdong Kaicheng Exploration And Mapping Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Kaicheng Exploration And Mapping Technology Co ltd filed Critical Guangdong Kaicheng Exploration And Mapping Technology Co ltd
Priority to CN202121309887.4U priority Critical patent/CN214765692U/en
Application granted granted Critical
Publication of CN214765692U publication Critical patent/CN214765692U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a treatment facility for construction waste, including backup pad, mount and processing case, the mount table is installed at the top of backup pad, the mount is installed at the top of mount table, the internally mounted of mount has the motor, the output of motor is connected with the rotation axis, the gear is installed in the outside of rotation axis, the processing case is installed at the top of backup pad, and the processing case is located one side of mount table, install the limiting plate on the inner wall of processing case, the filter is installed at the top of limiting plate, and the both sides of filter are installed on the inner wall of processing case, one side of processing case is installed the mounting bracket through the bolt, the feed inlet is installed to the opposite side of processing case; the utility model discloses an install the shower nozzle again in one side of water pipe, shower nozzle spun water can be with smashing building rubbish and producing the bottom that the dust brought into the processing case under the effect of water, can not cause the pollution to outside air.

Description

Treatment facility for construction waste
Technical Field
This reality is novel relates to building technical field, specifically is a treatment facility for construction waste.
Background
In recent years, the high buildings in various cities in China are erected like cobweb, house reconstruction and city construction development are carried out, so that the high buildings are more and more fiercely, more and more waste cement mortar brought by house removal are paid attention to by many people, the waste cement mortar is firstly required to be applied to treatment equipment, and the waste cement mortar is crushed.
The existing construction waste treatment equipment has certain defects: 1. traditional construction waste treatment facility can not remove dust to treatment facility's inside, can produce a large amount of dusts when handling construction waste at every turn, can cause the pollution to the air that can not play, and the user of service inhales and can cause harm in the health. 2. Traditional construction waste treatment facility single structure can appear that construction waste smashes inhomogeneous quality too low, influences the use of later construction waste.
Therefore, a novel construction waste treatment device is developed and has a certain use value.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a treatment facility for construction waste to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a treatment device for construction waste comprises a supporting plate, a fixing frame and a treatment box, wherein a mounting table is mounted at the top of the supporting plate, the fixing frame is mounted at the top of the mounting table, a motor is mounted inside the fixing frame, the output end of the motor is connected with a rotating shaft, a gear is mounted on the outer side of the rotating shaft, the treatment box is mounted at the top of the supporting plate and is located on one side of the mounting table, a limiting plate is mounted on the inner wall of the treatment box, a filter plate is mounted at the top of the limiting plate, two sides of the filter plate are mounted on the inner wall of the treatment box, the mounting frame is mounted on one side of the treatment box through bolts, and a feed inlet is mounted on the other side of the treatment box;
the utility model discloses a shower nozzle, including processing case, water inlet, shower nozzle, observation window, control panel and control panel, the outlet is installed to one side of handling the case, and the water inlet is installed to the opposite side of handling the case, installs the water pipe on the inner wall of handling the case, and the shower nozzle is installed to one side of water pipe, and the front of handling the case is installed and is observed the window, and the front of handling the case is installed control panel, and control panel is located the below of handling the case
The internally mounted of mounting bracket has the motor, and the axis of rotation is installed to the output of motor, and crushing pole is installed to the one end of axis of rotation, and the axis of rotation runs through the inner wall of handling the case, and the outside welding of crushing pole has crushing tooth.
Preferably, the bottom of backup pad has the connecting block through bolted mounting, and the support column is installed to the bottom of connecting block, and the base is installed to the bottom of support column.
Preferably, the outside of gear is installed the conveyer belt, and the installation pole is installed to the outside one side of gear, and the dead lever is installed through the connecting piece in one side of installation pole.
Preferably, a closing cover is installed on one side of the feed inlet, and a handle is installed on one side of the closing cover.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses an install the water pipe on the inner wall of handling the case, the shower nozzle is installed again to one side of water pipe, through make water enter into the inside of water pipe from the water inlet from handling the water inlet of case one side, again from the inside of water pipe enter into the shower nozzle in by the shower nozzle blowout, when handling the case at the during operation, because inside is the crushing of examining rubbish, so can produce a large amount of dusts, shower nozzle spun water can produce the bottom that the dust brought into the processing case under the effect of water with smashing building rubbish, make the dust can not waft aloft, can not lead to the fact the pollution to the air of outside, also can not produce harm to staff's healthy.
2. The utility model discloses an install the filter on the inner wall of handling the case, when building rubbish smashes in the case, the filter can be lived with needs kibbling building rubbish support, smash building rubbish by reducing mechanism, when building rubbish is smashed by reducing mechanism and is accomplished, the filter can filter the conveyer belt with the building rubbish of smashing the completion, can stay on the filter and continue smashing not smashing the completion, can make the kibbling more thoroughly more even of building rubbish like this, great increase smashes the quality of back material, make things convenient for the reutilization of rubbish.
Drawings
Fig. 1 is a cross-sectional view of the present invention;
FIG. 2 is a front view of the present invention;
fig. 3 is a top view of the present invention;
fig. 4 is a schematic structural view of the conveying device of the present invention;
in the figure: 1. a support plate; 101. connecting blocks; 102. a support pillar; 103. a base; 2. a fixed mount; 201. an installation table; 202. a motor; 203. a rotating shaft; 3. a gear; 301. a conveyor belt; 302. mounting a rod; 303. fixing the rod; 4. a treatment tank; 401. a water outlet; 402. a water inlet; 403. a limiting plate; 404. a filter plate; 405. a water pipe; 406. a spray head; 407. an observation window; 408. a control panel; 5. a mounting frame; 501. a motor; 502. a rotating shaft; 503. crushing the stems; 504. crushing teeth; 6. a feed inlet; 601. a closure cap; 602. a handle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
The first embodiment is as follows:
referring to fig. 1 to 4, a construction waste treatment device includes a support plate 1, a fixing frame 2 and a treatment tank 4, and is characterized in that: the mounting table 201 is mounted at the top of the supporting plate 1, the fixing frame 2 is mounted at the top of the mounting table 201, the motor 202 is mounted inside the fixing frame 2, the output end of the motor 202 is connected with the rotating shaft 203, the gear 3 is mounted on the outer side of the rotating shaft 203, the processing box 4 is mounted at the top of the supporting plate 1, the processing box 4 is located on one side of the mounting table 201, the limiting plate 403 is mounted on the inner wall of the processing box 4, the filter plate 404 is mounted at the top of the limiting plate 403, two sides of the filter plate 404 are mounted on the inner wall of the processing box 4, the mounting frame 5 is mounted on one side of the processing box 4 through bolts, and the feeding port 6 is mounted on the other side of the processing box 4;
a water outlet 401 is arranged on one side of the treatment box 4, a water inlet 402 is arranged on the other side of the treatment box 4, a water pipe 405 is arranged on the inner wall of the treatment box 4, a spray head 406 is arranged on one side of the water pipe 405, an observation window 407 is arranged on the front surface of the treatment box 4, a control panel 408 is arranged on the front surface of the treatment box 4, and the control panel 408 is positioned below the treatment box 4;
the internally mounted of mounting bracket 5 has motor 501, and axis of rotation 502 is installed to motor 501's output, and crushing pole 503 is installed to the one end of axis of rotation 502, and axis of rotation 502 runs through the inner wall of handling case 4, and crushing tooth 504 has been welded to the outside welding of crushing pole 503.
Example two:
referring to fig. 1 to 4, the present invention provides another embodiment: a treatment device for construction waste comprises a supporting plate 1, a fixing frame 2 and a treatment box 4, wherein a mounting table 201 is mounted at the top of the supporting plate 1, the fixing frame 2 is mounted at the top of the mounting table 201, a motor 202 is mounted inside the fixing frame 2, the output end of the motor 202 is connected with a rotating shaft 203, the supporting plate 1 is used for supporting the whole treatment device, so that the construction waste treatment device is in a mounting position, the mounting table 201 can provide a mounting position for the fixing frame 2 and the fixing frame 2, the motor 202 can convert electric energy into kinetic energy after being electrified and provide power for a transmission device and also provide a mounting position for the rotating shaft 203, a gear 3 is mounted on the outer side of the rotating shaft 203, the rotating shaft 203 can provide rotating power for the gear 3, the gear 3 is mounted on the outer side of the rotating shaft 203, the treatment box 4 is mounted at the top of the supporting plate 1, and the treatment box 4 is positioned on one side of the mounting table 201, the inner wall of the treatment box 4 is provided with a limiting plate 403, the top of the limiting plate 403 is provided with a filter plate 404, two sides of the filter plate 404 are arranged on the inner wall of the treatment box 4, the gear 3 provides a mounting position for the conveyor belt 301, the conveyor belt 301 is matched through the gear 3, the treatment box 4 can provide a treatment space for crushing the construction waste and can also provide a mounting position for other devices, the limiting plate 403 can be used for limiting the treated construction waste, the treated construction waste can reach the conveyor belt 301 from the inner side of the limiting plate 403, when the construction waste is crushed in the treatment box 4, the filter plate 404 can support the construction waste needing to be crushed, the crushing device can crush the construction waste, when the construction waste is crushed by the crushing device, the filter plate 404 can filter the crushed construction waste onto the conveyor belt 301, not smashing the completion and staying on filter 404 and continuing to smash, can make the kibbling more thoroughly of building rubbish more even like this, great increase the quality after smashing, the mounting bracket 5 is installed through the bolt in one side of handling case 4, handle the opposite side of case 4 and install feed inlet 6, mounting bracket 5 is used for fixing inside motor 501, make motor 501 can more stable operation, can not produce and rock, feed inlet 6 makes and is used for providing the space that gets into in handling case 4 for the building rubbish gets into.
Further, connecting block 101 is installed through the bolt in the bottom of backup pad 1, and support column 102 is installed to the bottom of connecting block 101, and base 103 is installed to the bottom of support column 102, and connecting block 101 can increase area of contact and make support column 102 can be more stable install in the bottom of backup pad 1, and support column 102 can be used for supporting treatment facility's weight, and base 103 is used for making that processing apparatus can place more stable.
Further, conveyer belt 301 is installed to the outside of gear 3, installation pole 302 is installed to the outer one side of gear 3, dead lever 303 is installed through the connecting piece in one side of installation pole 302, conveyer belt 301 can transport the construction waste that has handled in 4 treatment casees out of 4 treatment casees, make and to carry out crushing rubbish in 4 treatment casees always, installation pole 302 is used for supporting conveyer, make conveyer operation that can be more stable, dead lever 303 is used for fixing conveyer, can make conveyer more stable firm.
Further, a water outlet 401 is installed at one side of the treatment tank 4, a water inlet 402 is installed at the other side of the treatment tank 4, a water pipe 405 is installed on the inner wall of the treatment tank 4, a spray head 406 is installed at one side of the water pipe 405, an observation window 407 is installed at the front side of the treatment tank 4, a control panel 408 is installed at the front side of the treatment tank 4, the control panel 408 is located below the treatment tank 4, the water outlet 401 can be used for discharging water inside the treatment tank 4 to provide a space for discharging water, water can enter the water pipe 405 through the water inlet 402 to provide a space for water to enter, the water pipe 405 is used for storing water and also has a drainage function, so that water can enter the spray head 406, water sprayed from the spray head 406 can bring dust generated by crushing construction waste into the bottom of the treatment tank 4 under the effect of water, so that the dust cannot float in the air and cause pollution to the outside, the health of workers is not harmed, the observation window 407 can observe the crushing condition inside the treatment box 4, the user can conveniently watch the crushing condition, and the control panel 408 is used for controlling the operation and the closing of the treatment device.
Further, the internally mounted of mounting bracket 5 has motor 501, axis of rotation 502 is installed to motor 501's output, crushing pole 503 is installed to axis of rotation 502's one end, and axis of rotation 502 runs through the inner wall of handling case 4, the outside welding of crushing pole 503 has crushing tooth 504, motor 501 can be with electric energy conversion kinetic energy after the circular telegram, provide power for reducing mechanism's operation, also provide power for axis of rotation 502, axis of rotation 502 can drive crushing pole 503 through rotating and rotate, also provide the mounted position for crushing pole 503, crushing pole 503 can drive the crushing pole 503 outside through rotating and smash tooth 504 and rotate, provide power for the rotation of crushing tooth 504, crushing tooth 504 can smash building rubbish through rotating.
Further, a closing cover 601 is installed on one side of the feeding hole 6, a handle 602 is installed on one side of the closing cover 601, the closing cover 601 can block the construction waste inside the treatment box 4 when being closed, the crushed construction waste is prevented from being crushed and ejected out, damage to the body can be caused, and the handle 602 is used for opening or closing the closing cover 601, so that the user is more convenient and fast.
The working principle is as follows: whether the treatment equipment has the problem of influencing use or not is checked before the treatment equipment is used, the treatment equipment for the construction waste is moved to a place needing to be used, the treatment equipment is placed more stably by using the base 103, shaking is avoided, then the treatment equipment is opened and operated by using the control panel 408, the construction waste is placed into the treatment tank 4 from the feed inlet 6, the construction waste is crushed by the crushing teeth 504 outside the crushing rod 503, the construction waste can be filtered by the filter plate 404 after crushing is completed, the construction waste can fall into the conveyor belt 301 under the action of the limiting plate 403 after filtering is completed, and the construction waste after treatment is conveyed out of the treatment tank 4 by the conveyor belt 301.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein, and any reference signs in the claims are not intended to be construed as limiting the claim concerned.

Claims (4)

1. The utility model provides a treatment facility is used to construction waste, includes backup pad (1), mount (2) and processing case (4), its characterized in that: the top of the supporting plate (1) is provided with an installation platform (201), the top of the installation platform (201) is provided with a fixed frame (2), a motor (202) is arranged in the fixed frame (2), the output end of the motor (202) is connected with a rotating shaft (203), a gear (3) is arranged on the outer side of the rotating shaft (203), a treatment box (4) is arranged on the top of the supporting plate (1), and the treatment box (4) is positioned at one side of the mounting table (201), a limiting plate (403) is arranged on the inner wall of the treatment box (4), a filter plate (404) is arranged at the top of the limiting plate (403), two sides of the filter plate (404) are arranged on the inner wall of the treatment box (4), one side of the treatment box (4) is provided with a mounting frame (5) through a bolt, and the other side of the treatment box (4) is provided with a feeding hole (6);
a water outlet (401) is installed on one side of the treatment box (4), a water inlet (402) is installed on the other side of the treatment box (4), a water pipe (405) is installed on the inner wall of the treatment box (4), a spray head (406) is installed on one side of the water pipe (405), an observation window (407) is installed on the front surface of the treatment box (4), a control panel (408) is installed on the front surface of the treatment box (4), and the control panel (408) is located below the treatment box (4);
the internally mounted of mounting bracket (5) has motor (501), and axis of rotation (502) are installed to the output of motor (501), and crushing pole (503) are installed to the one end of axis of rotation (502), and axis of rotation (502) run through the inner wall of handling case (4), and the outside welding of crushing pole (503) has crushing tooth (504).
2. The processing apparatus for construction waste according to claim 1, characterized in that: connecting block (101) are installed through the bolt in the bottom of backup pad (1), and support column (102) are installed to the bottom of connecting block (101), and base (103) are installed to the bottom of support column (102).
3. The processing apparatus for construction waste according to claim 1, characterized in that: conveyer belt (301) are installed in the outside of gear (3), and installation pole (302) are installed to gear (3) outer one side, and dead lever (303) are installed through the connecting piece in one side of installation pole (302).
4. The processing apparatus for construction waste according to claim 1, characterized in that: a sealing cover (601) is installed on one side of the feeding hole (6), and a handle (602) is installed on one side of the sealing cover (601).
CN202121309887.4U 2021-06-11 2021-06-11 Treatment facility for construction waste Expired - Fee Related CN214765692U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121309887.4U CN214765692U (en) 2021-06-11 2021-06-11 Treatment facility for construction waste

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121309887.4U CN214765692U (en) 2021-06-11 2021-06-11 Treatment facility for construction waste

Publications (1)

Publication Number Publication Date
CN214765692U true CN214765692U (en) 2021-11-19

Family

ID=78712272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121309887.4U Expired - Fee Related CN214765692U (en) 2021-06-11 2021-06-11 Treatment facility for construction waste

Country Status (1)

Country Link
CN (1) CN214765692U (en)

Similar Documents

Publication Publication Date Title
CN212284235U (en) Building rubbish reducing mechanism with dust removal function
CN109225551B (en) Waste recycling and crushing device
CN107744867A (en) A kind of solid waste reducing mechanism of anti-dust
CN111589566A (en) Broken recovery unit of portable building rubbish
CN210815435U (en) Novel dustless rubbing crusher
CN214765692U (en) Treatment facility for construction waste
CN207385570U (en) A kind of disintegrating apparatus for treatment of urban garbage
CN110394222A (en) A kind of environment-friendly type building refuse treatment plant
CN213377190U (en) Building rubbish crushing apparatus for building engineering
CN215312705U (en) Waste recovery device for building engineering
CN212237461U (en) Garbage disposal equipment for construction to dust is handled
CN214439431U (en) Novel construction site refuse treatment device
CN213000466U (en) Garbage collecting and releasing device for constructional engineering
CN212549748U (en) Garbage collection device for building
CN211329510U (en) Stone crushing device for building engineering
CN210252415U (en) Waste material shredding device for building engineering
CN207174583U (en) One kind is gone out cigarette dustbin
CN210473351U (en) Dust collecting equipment is used in rock wool panel production
CN210613913U (en) Inorganic heavy matter crushing and filtering device for remaining garbage
CN216419642U (en) High-efficient broken processing apparatus of construction waste material
CN211838399U (en) Novel crawler-type mobile crusher
CN217221666U (en) Municipal works's building rubbish reducing mechanism with adjustable
CN215964065U (en) Building engineering retrieves and uses environmental protection waste material processing apparatus
CN220238680U (en) Building rubbish reducing mechanism for construction
CN220004201U (en) Recovery device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211119