CN214195373U - Elevator mouth threshold stone structure convenient to change construction - Google Patents

Elevator mouth threshold stone structure convenient to change construction Download PDF

Info

Publication number
CN214195373U
CN214195373U CN202022317701.1U CN202022317701U CN214195373U CN 214195373 U CN214195373 U CN 214195373U CN 202022317701 U CN202022317701 U CN 202022317701U CN 214195373 U CN214195373 U CN 214195373U
Authority
CN
China
Prior art keywords
elevator
threshold stone
layer
adjustable bearing
bearing layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022317701.1U
Other languages
Chinese (zh)
Inventor
李俊
林靓靓
芦超
杨浩锋
吉乔伟
李源
陶如钧
朱爽
杜传良
林晓渝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202022317701.1U priority Critical patent/CN214195373U/en
Application granted granted Critical
Publication of CN214195373U publication Critical patent/CN214195373U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Elevator Door Apparatuses (AREA)

Abstract

The utility model provides an elevator mouth threshold stone structure convenient to change construction, including building ground main screed-coat, lift-cabin door sill and ceramic tile shop pad district, the highly uniform of district and lift-cabin door sill is spread to the ground brick in the building, its characterized in that: an adjustable bearing layer is laid on a main leveling layer of the building ground between the floor tile paving and pasting area and the elevator door sill, a threshold stone is laid on the top of the adjustable bearing layer, and the height of the threshold stone after being laid on the top of the adjustable bearing layer is consistent with or close to the height of the elevator door sill or the floor tile paving and pasting area; the traditional cement mortar bonding layer paved on the threshold stone is changed into the graded sand adjustable bearing layer, so that the construction process is simplified, the construction and maintenance time is greatly shortened, the use interference of maintenance construction on elevator facilities is reduced, and the problems of difficulty in maintenance and repair of the threshold stone at an elevator entrance caused by difficulty in replacement construction of the threshold stone, high replacement labor cost and great influence on use of corresponding building facilities such as an elevator due to limited operation space are solved.

Description

Elevator mouth threshold stone structure convenient to change construction
Technical Field
The utility model relates to a building decoration technical field, concretely relates to elevator mouth threshold stone structure convenient to change construction.
Background
The method for decorating by arranging the doorsill stones between the elevator sill and the tile paving area in the building is a common decoration method in the building decoration engineering, and has two functions: 1. filling pits between the elevator door sill and the tile paving area in the building; 2. decorate the building interior together with elevator mouth door pocket, skirting line. The decoration mode for arranging the threshold stone is almost the current practice in the building decoration industry at the present stage.
Traditional elevator mouth threshold stone structure begins to set gradually main screed-coat, threshold stone and spreads and paste cement mortar tie coat, threshold stone from the interior unfinished ground elevation of room, totally three layer construction. Under traditional threshold stone structure condition, common main construction flow is: firstly, performing main leveling layer construction; secondly, placing the threshold stone coated with cement mortar at the bottom at a preset installation position, and enabling the surface of the threshold stone to be horizontal in a manual pressing or rubber hammer knocking mode, wherein the top elevation of the threshold stone is consistent with the top elevation of the elevator door sill; and thirdly, jointing and cleaning after the cement mortar bonding layer is hardened. The threshold stone constructed by the structure is broken by the impact of a heavy object, and is inconvenient to construct when needing to be replaced.
The doorsill stone constructed in the traditional structure form has the following defects in later use and maintenance: first, in the replacement process, the construction operation is inconvenient. When the existing threshold stone structure is adopted, electric and pneumatic breaking and dismantling equipment or manual chiseling and removing are needed to be used for replacement. In the dismantling process, the damaged threshold stone is within 2mm from the elevator door, the elevator sill, the elevator exit door pocket and the adjacent floor tiles, the operation space is limited, the mechanical operation is likely to damage peripheral materials, the loss is further enlarged, and the dismantling difficulty is high. Meanwhile, when a new threshold stone coated with cement mortar at the bottom is installed back into the original groove again, the gap between the original groove and the periphery is extremely small and is only 1-2mm, the installation space is not enough, the process time for fixing the threshold stone in the original installation groove is long when the position of the threshold stone is adjusted repeatedly, and due to the fluidity of the cement mortar, the mortar at the bottom of the threshold stone can continuously fall off in the installation process, so that a floor tile area, an elevator car and the like can be stained, and the construction operation is inconvenient.
Second, maintenance can be carried out for a long time with adverse effects on the building facilities, adjacent elevator facilities, and normal use of the building. When in maintenance, the original broken threshold stone and the lower bonding layer are chiseled for a longer time; meanwhile, the time of the process of waiting for the lower bonding mortar to be completely hardened after the threshold stone is paved is long, so that the corresponding elevator needs to be stopped for a long time, and the influence on the normal use of the elevator and the building is long.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an elevator mouth threshold stone structure convenient to change construction, the utility model discloses lay traditional threshold stone and paste cement mortar tie coat and change into the supporting layer with adjustable the sand is joined in marriage to the grade, simplified the construction flow, shorten construction and maintenance time greatly, it is long to the use interference of elevator facility to have reduced the maintenance construction, solve because of the limited threshold stone of messenger's operating space change construction difficulty, change the cost of labor higher, use the influence great and lead to the problem of maintaining the difficulty to elevator mouth threshold stone to corresponding building facilities such as elevator.
Therefore, the utility model adopts the following technical scheme:
the utility model provides an elevator mouth threshold stone structure convenient to change construction which characterized in that: the building floor comprises a building floor main leveling layer, an elevator door sill and a floor tile paving region, wherein the height of the floor tile paving region in the building is consistent with that of the elevator door sill, an adjustable bearing layer is paved on the building floor main leveling layer between the floor tile paving region and the elevator door sill, threshold stones are paved on the top of the adjustable bearing layer, and the height of the threshold stones paved on the top of the adjustable bearing layer is consistent with or close to that of the elevator door sill or the floor tile paving region.
Further: the material of the adjustable bearing layer is graded sand.
Further: the threshold stone and the adjustable bearing layer can be separated from each other.
Further: the graded sand of the adjustable bearing layer can be increased and decreased, and the effect of secondary leveling threshold stone height marking is achieved.
Further: the whole layer surface of the adjustable supporting layer is kept in a non-bonding state.
Further: the height of the elevator door sill or floor tile paving area is higher than that of the main leveling layer of the building ground.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. the utility model simplifies the construction operation flow of replacing the damaged threshold stone of the elevator port, and avoids the steps of breaking and dismantling ground machinery, mixing cement mortar, waiting for the drying of the cement mortar and the like; the graded sand adjustable bearing layer and the main leveling layer as well as the graded sand adjustable bearing layer and the threshold stone are in natural contact and are fixed by non-adhesive, so that the replacement, maintenance and construction of the threshold stone are facilitated; meanwhile, the graded sand adjustable bearing layer is convenient for adjusting the height and the flatness of the threshold stone while providing bearing support for the threshold stone, so that the top surface of the threshold stone is consistent with the top surface of the elevator sill in height, and the integral attractiveness of architectural decoration is improved while the construction is convenient;
2. further, the utility model discloses compare with traditional threshold stone structure, the bearing layer structure construction flow is simplified, the engineering time shortens with adjustable the sand is joined in marriage to the grade. On the construction flow, after the main leveling layer of the building ground is finished and the positions for paving the threshold stones are cleaned, firstly, the elevation of the pavement layer of the ground threshold stones is marked, then, the elevation of the adjustable layer pavement of the graded sand is marked downwards along the mark, the adjustable bearing layer of the graded sand is sprayed and rolled to the designed pavement elevation, then, the threshold stones are lifted by two large sucking discs and put into the preset installation position, and the rubber hammer is used for slightly pressing and adjusting the elevation of the top surface of the threshold stones to be consistent with the elevation of the top surface of the elevator sill so as to be directly used. The system eliminates a series of time-consuming and labor-consuming links such as mixing mortar and waiting for hardening of cement mortar in the traditional structure, realizes convenient and quick construction, simplifies the construction flow, shortens the construction time, and greatly improves the working efficiency of pavement.
3. Further, the utility model discloses compare with traditional threshold stone structure, the bearing layer is convenient for the threshold stone change construction with adjustable sand is joined in marriage to the grade. When the traditional structure is used for replacing the threshold stone, old threshold stones and a cement mortar bonding layer at the bottom are required to be chiseled, then mortar is mixed again, the threshold stones are paved and pasted until the cement mortar is completely hardened, and the elevator cannot be used in the period. The contact surfaces of the graded sand adjustable bearing layer structure layer, the main leveling layer and the doorsill stone do not use adhesives or bonding materials, when damaged doorsill stones are maintained and replaced, the large sucking discs are used for adsorbing old doorsill stones to lift and take out the old doorsill stones, then the large sucking discs are used for adsorbing new doorsill stones to lift and place the new doorsill stones in the original doorsill stone installation areas, and the construction time is extremely short; the elevator sill stone maintenance device has the advantages that the use interference of maintenance construction to elevator facilities is long, and the problems that the elevator cannot be used in the period of replacing the sill stone, and the elevator is difficult to maintain and maintain due to the fact that the elevator cannot be used by the traditional structure and corresponding building facilities such as the elevator are greatly influenced are solved.
4. Further, the utility model discloses compare with traditional threshold stone structure, the easy accurate adjustment threshold stone of bearing layer structure with adjustable sand is joined in marriage to the level is unanimous with elevator sill top altitude difference, ensures threshold stone and elevator sill elevation, eliminates the altitude difference, improves pleasing to the eye degree and use comfort.
Drawings
Fig. 1 is a schematic plan view of the present invention;
fig. 2 is a cross-sectional view of fig. 1A-a.
The labels in the figures are: 1-threshold stone; 2-adjustable supporting layer; 3, paving a floor tile pasting area; 4-elevator door sill; 5-building a ground main leveling layer.
Detailed Description
The following description is made with reference to the accompanying drawings and examples, but not to be construed as limiting the invention.
As shown in fig. 1-2, the utility model provides a pair of elevator mouth threshold stone structure convenient to change construction, including building ground main screed-coat 5, lift-cabin door sill 4 and ceramic tile shop tile district 3, the highly uniform of district 3 and lift-cabin door sill 4 is spread to the ceramic tile, lay adjustable supporting layer 2 on the building ground main screed-coat 5 between district 3 and the lift-cabin door sill 4 is spread to the ceramic tile, and threshold stone 1 is laid at adjustable supporting layer 2 top, and height and lift-cabin door sill 4 or the highly uniform of floor tile shop district 3 or be close unanimous behind the supporting layer 2 top of adjustable are laid to threshold stone 1. The adjustable bearing layer 2 has the functions of adjusting the elevation and the flatness of the threshold stone 1, bearing the threshold stone 1 and quickly constructing. After the adjustable bearing layer 2 is tiled and compacted, the top elevation is consistent with the bottom elevation of the threshold stone 1.
The material of the adjustable bearing layer 2 is graded sand, and no additional materials such as cement, lime, glue and the like are added.
The threshold stone 1 and the adjustable bearing layer 2 can be separated from each other without being bonded by an adhesive.
The graded sand of the adjustable bearing layer 2 can be increased and decreased, and the elevation of the doorsill stone 1 for secondary leveling is realized.
The whole layer surface of the adjustable bearing layer 2 is kept in a non-bonding state, and the adjustable bearing layer 2 is in non-bonding natural contact with the threshold stone 1 and the building ground main leveling layer 5.
The height of the elevator door sill 4 or the floor tile paving area 3 is higher than that of the main leveling layer 5 of the building ground.
The utility model discloses a construction flow:
after the main leveling layer 5 of the building ground is finished and cleaned, firstly marking the elevation of the ground pavement layer, then gradually marking the elevation of the adjustable bearing layer 2 downwards along the mark, spraying water to roll the adjustable bearing layer 2 to the designed laying elevation, then lifting the doorsill stone 1 by using two large suckers and placing the doorsill stone 1 into a preset mounting position, slightly pressing and adjusting the elevation of the top surface of the doorsill stone 1 to be consistent with the elevation of the top surface of the elevator door sill 4 by using a rubber hammer, and then directly using the doorsill stone;
when maintenance is carried out, if the doorsill stone 1 needs to be replaced, the large-scale sucking disc can be used for adsorbing the old doorsill stone 1 to lift up and take out the old doorsill stone 1, then the large-scale sucking disc is used for adsorbing the new doorsill stone 1 to lift up and place the new doorsill stone 1 in the installation area of the original doorsill stone 1;
when maintaining, if find that new threshold stone 1 is inconsistent with elevator sill elevation and need the adjustment, adsorb on threshold stone 1 with large-scale sucking disc and promote and take out threshold stone 1, increase and decrease bottom gradation sand adjustable supporting layer 2 thickness, then strickle off, suppress to required elevation, and put back threshold stone 1, and slightly suppress the adjustment threshold stone 1 top surface elevation and the unanimous and can directly use of elevator sill top surface elevation with the rubber hammer.
The above embodiments are merely preferred technical solutions of the present invention, and it should be understood by those skilled in the art that modifications or substitutions of technical solutions or parameters in the embodiments can be made without departing from the principles and essential conditions of the present invention, and all the modifications or substitutions should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides an elevator mouth threshold stone structure convenient to change construction, spreads the district of subsides including building ground main screed-coat, lift-cabin door sill and ceramic tile, and the highly uniform of district and lift-cabin door sill is spread to the brick in the building, its characterized in that: an adjustable bearing layer is laid on the building ground main leveling layer between the floor tile paving region and the elevator door sill, threshold stones are laid on the top of the adjustable bearing layer, and the height of the threshold stones laid on the top of the adjustable bearing layer is consistent or close to consistent with the height of the elevator door sill or the floor tile paving region.
2. The elevator sill stone structure convenient for replacement construction according to claim 1, characterized in that: the material of the adjustable bearing layer is graded sand.
3. The elevator sill stone structure convenient for replacement construction according to claim 1, characterized in that: the threshold stone and the adjustable bearing layer can be separated from each other.
4. The elevator sill stone structure convenient for replacement construction according to claim 2, characterized in that: the graded sand of the adjustable bearing layer can be increased and decreased, and the effect of secondary leveling threshold stone height marking is achieved.
5. The elevator sill stone structure convenient for replacement construction according to claim 1, characterized in that: the whole layer surface of the adjustable supporting layer is kept in a non-bonding state.
6. The elevator sill stone structure convenient for replacement construction according to claim 1, characterized in that: the height of the elevator door sill or floor tile paving area is higher than that of the main leveling layer of the building ground.
CN202022317701.1U 2020-10-16 2020-10-16 Elevator mouth threshold stone structure convenient to change construction Active CN214195373U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022317701.1U CN214195373U (en) 2020-10-16 2020-10-16 Elevator mouth threshold stone structure convenient to change construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022317701.1U CN214195373U (en) 2020-10-16 2020-10-16 Elevator mouth threshold stone structure convenient to change construction

Publications (1)

Publication Number Publication Date
CN214195373U true CN214195373U (en) 2021-09-14

Family

ID=77643107

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022317701.1U Active CN214195373U (en) 2020-10-16 2020-10-16 Elevator mouth threshold stone structure convenient to change construction

Country Status (1)

Country Link
CN (1) CN214195373U (en)

Similar Documents

Publication Publication Date Title
CN106884536A (en) A kind of construction method of compound terrace
CN107152145A (en) A kind of stone material flooring construction method
CN101457581A (en) Construction method for auto-flowing floor
CN111042479B (en) Construction method for laying building ground decoration floor tiles
CN111734085A (en) Floating integral terrace and construction method thereof
CN214195373U (en) Elevator mouth threshold stone structure convenient to change construction
CN202898944U (en) Ultra-large type side-pavement assembling plate block
CN102535807B (en) Modular wall tile pre-bonding structure and construction method thereof
CN216921186U (en) Ground structure of golden millstone
CN111255191A (en) Semi-pre-pasted ceramic tile and paving method thereof
CN112030665A (en) Construction method of vibration-compacted large-pore permeable concrete pavement
CN211949245U (en) Roof stone flashing structure
CN212836509U (en) Floating integral terrace
CN214169786U (en) Terrazzo floor used in shopping center
CN208533945U (en) A kind of flexible assembly floor tile
CN111472524B (en) Anti-hollowing floor construction method capable of achieving precise leveling
CN211256561U (en) Anti-fracture pavement floor tile
CN114876155A (en) Construction process for polishing ground by using non-ignition fine stone concrete
CN210684782U (en) Prefabricated adjustable ring
CN107327117A (en) The preparation method on flat-die color concrete ground
CN214616077U (en) Prevent to strike and destroy and be convenient for construction maintenance's elevator mouth threshold stone structure
CN110499784B (en) Synchronous lifting construction process for manhole cover
CN112324279A (en) Prevent to strike and destroy and be convenient for construction maintenance's elevator mouth threshold stone structure
CN110965745A (en) Paving method of floor tiles and wall tiles
CN110318522A (en) A kind of quick paving structure of compound ceramic tile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant