Mud pollution discharge device for water conservancy construction Download PDF

Info

Publication number
CN214005793U
CN214005793U CN202023177147.8U CN202023177147U CN214005793U CN 214005793 U CN214005793 U CN 214005793U CN 202023177147 U CN202023177147 U CN 202023177147U CN 214005793 U CN214005793 U CN 214005793U
Authority
CN
China
Prior art keywords
mud
pipe
wall
mud pipe
sludge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023177147.8U
Other languages
Chinese (zh)
Inventor
崔宝振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202023177147.8U priority Critical patent/CN214005793U/en
Application granted granted Critical
Publication of CN214005793U publication Critical patent/CN214005793U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a water conservancy construction is with blowdown mud device, including mud extraction structure, mud pipe and inlet tube, the bottom of mud extraction structure one side has the mud pipe through bolt fixed mounting, one side of mud pipe outer wall has first manual butterfly valve through bolt fixed mounting, one side of mud pipe outer wall bottom has seted up the mud pipe mouth, one side at mud pipe outer wall top has seted up the inlet opening, the mud pipe outer wall is around one side of mud pipe mouth has the mud pipe through bolt fixed mounting, the mud pipe outer wall is close to one side of mud pipe is through bolt fixed mounting second manual butterfly valve; the utility model discloses make things convenient for the clearance of mud pipe jam mud, this blowdown mud device simple structure, it is convenient to maintain, and long service life occupies the place for a short time, for the user has practiced thrift the cost, has promoted blowdown mud efficiency.

Description

Mud pollution discharge device for water conservancy construction
Technical Field
The utility model relates to a hydraulic engineering technical field specifically is a blowdown mud device for water conservancy construction.
Background
Hydraulic engineering is a general term for various engineering constructions constructed for controlling, utilizing and protecting surface and underground water resources and environments, and is a construction constructed for eliminating water damage and developing and utilizing water resources; dividing the service objects into flood control engineering, farmland hydraulic engineering, hydroelectric power engineering, channel and harbor engineering, water supply and drainage engineering, environmental hydraulic engineering, coastal reclamation engineering and the like according to the service objects; the hydraulic engineering which can serve multiple targets such as flood control, water supply, irrigation, power generation and the like at the same time is called comprehensive utilization hydraulic engineering; hydraulic engineering needs to build various types of hydraulic buildings such as dams, dikes, spillways, water gates, water inlets, channels, transition troughs, rafts, fishways and the like so as to achieve the aims.
Sludge discharge in hydraulic engineering is particularly important, and a sludge discharge device is required to discharge sludge at the bottom of water, but the existing sewage discharge device adopts direct sewage discharge, and the sludge cannot be discharged clearly due to the fact that water pretreatment sludge is easy to harden, so that blockage is caused by long-term use; the maintenance and cleaning of the equipment are very troublesome, the maintenance cost is high, and the efficiency is low.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a blowdown mud device for water conservancy construction to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a blowdown mud device for water conservancy construction, includes mud extraction structure, play mud pipe, mud pipe and inlet tube, there is a mud pipe bottom of mud extraction structure one side through bolt fixed mounting, there is first manual butterfly valve mud pipe one side of going out mud pipe outer wall through bolt fixed mounting, the mud mouth has been seted up to one side of going out mud pipe outer wall bottom, the inlet opening has been seted up to one side of going out mud pipe outer wall top, it centers on mud pipe outer wall there is a mud pipe one side of leading the mouth through bolt fixed mounting, mud pipe outer wall is close to there is the manual butterfly valve of second one side of mud pipe through bolt fixed mounting, it centers on mud pipe outer wall there is the inlet tube one side of inlet opening through bolt fixed mounting, the inlet tube outer wall is close to there is the manual butterfly valve of third one side of mud pipe through bolt fixed mounting.
Wherein, mud extraction structure includes blow off pipe, driving motor, pivot and helical blade, there is driving motor at the center department at blow off pipe top through bolt fixed mounting, the driving motor output has through bolt fixed mounting the pivot of blow off pipe, the pivot outer wall is located the even fixed mounting of bolt has helical blade in the inside one end of blow off pipe, the mud discharging mouth has been seted up at the top of blow off pipe outer wall one side.
The sludge outlet pipe is fixedly arranged at the top of one side of the outer wall of the sewage discharge pipe in a surrounding mode through bolts.
The center of the top of the sewage discharge pipe is inlaid with a shaft sleeve matched with the rotating shaft, the rotating shaft penetrates through the shaft sleeve, and the rotating shaft is rotatably connected with the shaft sleeve.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses a mud extraction structure provides submarine mud, then the mud discharging port carries mud in the play mud pipe, discharge mud through a mud pipe, when a mud pipe appears blockking up, close first manual butterfly valve, then open second manual butterfly valve and third manual butterfly valve simultaneously, and with inlet tube and external water piping connection, then pour into the clear water into a mud pipe through the inlet tube, then wash the mud of the intraductal jam of mud of play through the clear water, then discharge mud after will washing through the mud pipe, thereby made things convenient for the clearance that a mud pipe blockked up mud, this blowdown mud device simple structure, convenient maintenance, long service life, occupy the place for a short time, for the user has practiced thrift the cost, blowdown mud efficiency has been promoted.
Drawings
FIG. 1 is a schematic view of the structure of the present invention;
FIG. 2 is a schematic view of the sludge extraction structure in a front view cross section;
fig. 3 is a schematic view of the main section structure of the mud discharging pipe of the present invention.
In the figure: 10. a sludge extraction structure; 11. a blowdown cylinder; 12. a drive motor; 13. a rotating shaft; 14. a helical blade; 15. a sludge discharge port; 16. a shaft sleeve; 20. a mud outlet pipe; 21. a first manual butterfly valve; 22. a mud guide port; 23. a water inlet hole; 30. a mud guide pipe; 31. a second manual butterfly valve; 40. a water inlet pipe; 41. and a third manual butterfly valve.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: a sludge discharge device for water conservancy construction comprises a sludge extraction structure 10, a sludge outlet pipe 20, a sludge guide pipe 30 and a water inlet pipe 40.
Wherein, there is a mud pipe 20 bottom of mud extraction structure 10 one side through bolt fixed mounting, there is first manual butterfly valve 21 one side of mud pipe 20 outer wall through bolt fixed mounting, lead mud mouth 22 has been seted up to one side of mud pipe 20 outer wall bottom, inlet opening 23 has been seted up to one side at mud pipe 20 outer wall top, there is a mud pipe 30 around leading one side of mud mouth 22 to go out mud pipe 20 outer wall, there is a second manual butterfly valve 31 one side that the mud pipe 30 outer wall is close to mud pipe 20 through bolt fixed mounting, there is inlet tube 40 outer wall one side that goes out mud pipe 20 outer wall around inlet opening 23 through bolt fixed mounting, there is a third manual butterfly valve 41 one side that inlet tube 40 outer wall is close to mud pipe 20 through bolt fixed mounting.
Wherein, draw structure 10 through mud and propose submarine mud, then carry mud through mud discharging port 15 in mud pipe 20, discharge mud through mud pipe 20, when mud pipe 20 appears blockking up, close first manual butterfly valve 21, then open second manual butterfly valve 31 and third manual butterfly valve 41 simultaneously, and with inlet tube 40 and external water piping connection, then pour into the clear water into mud pipe 20 through inlet tube 40 in, then wash the mud of blockking up in mud pipe 20 through the clear water, then discharge the mud after will washing through leading mud pipe 30, thereby made things convenient for the clearance that mud pipe 20 blockked up mud.
Wherein, mud extraction structure 10 includes blow off pipe 11, driving motor 12, pivot 13 and helical blade 14, and there is driving motor 12 at the center department at blow off pipe 11 top through bolt fixed mounting, and there is pivot 13 that runs through blow off pipe 11 at driving motor 12 output through bolt fixed mounting, and there is helical blade 14 in the one end that pivot 13 outer wall is located blow off pipe 11 inside through the even fixed mounting of bolt, and mud discharging port 15 has been seted up at the top of blow off pipe 11 outer wall one side.
Wherein, the sludge outlet pipe 20 is fixedly arranged at the top of one side of the outer wall of the sewage discharge pipe 11 around the sludge discharge port 15 through bolts.
When sludge treatment needs to be continuously discharged from the water bottom, the bottom of the sewage discharge cylinder 11 is placed at the water bottom, then the driving motor 12 is started, then the driving motor 12 drives the helical blade 14 to rotate through the rotating shaft 13, the water bottom sludge is lifted out through the rotating helical blade 14, the lifted sludge is conveyed into the sludge discharge pipe 20 through the sludge discharge port 15, and the sludge is discharged through the sludge discharge pipe 20.
Wherein, the axle sleeve 16 that has the cooperation pivot 13 is inlayed in the center department at blow off pipe 11 top, and pivot 13 runs through axle sleeve 16, and pivot 13 rotates with axle sleeve 16 to be connected, through axle sleeve 16 and the cooperation of pivot 13, has made things convenient for the rotation of pivot 13.
The working principle is as follows: when in use, the bottom of the sewage discharging cylinder 11 is firstly placed at the water bottom, then the driving motor 12 is opened, then the driving motor 12 drives the helical blade 14 to rotate through the rotating shaft 13, the underwater sludge is lifted through the rotating helical blade 14, then the lifted sludge is conveyed into the sludge discharging pipe 20 through the sludge discharging port 15, the sludge is discharged through the sludge discharging pipe 20, when the sludge discharging pipe 20 is blocked, the first manual butterfly valve 21 is closed, then the second manual butterfly valve 31 and the third manual butterfly valve 41 are simultaneously opened, the water inlet pipe 40 is connected with an external water pipe, then clear water is injected into the sludge discharging pipe 20 through the water inlet pipe 40, then the sludge blocked in the sludge discharging pipe 20 is washed through the clear water, and then the washed sludge is discharged through the sludge guiding pipe 30, thereby facilitating the cleaning of the sludge blocked by the sludge discharging pipe 20, and the sewage discharging device has simple structure and convenient maintenance, the working life is long, the occupied area is small, the cost is saved for users, and the sludge discharge efficiency is improved.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a blowdown mud device for water conservancy construction, includes that mud draws structure (10), play mud pipe (20), leads mud pipe (30) and inlet tube (40), its characterized in that: a sludge outlet pipe (20) is fixedly arranged at the bottom of one side of the sludge extraction structure (10) through a bolt, a first manual butterfly valve (21) is fixedly arranged on one side of the outer wall of the mud outlet pipe (20) through a bolt, a mud guide opening (22) is arranged on one side of the bottom of the outer wall of the mud outlet pipe (20), a water inlet hole (23) is arranged on one side of the top of the outer wall of the mud outlet pipe (20), a mud guide pipe (30) is fixedly arranged on one side of the outer wall of the mud outlet pipe (20) surrounding the mud guide opening (22) through bolts, a second manual butterfly valve (31) is fixedly arranged on one side of the outer wall of the mud guide pipe (30) close to the mud outlet pipe (20) through bolts, a water inlet pipe (40) is fixedly arranged on one side of the outer wall of the mud outlet pipe (20) surrounding the water inlet hole (23) through a bolt, and a third manual butterfly valve (41) is fixedly installed on one side, close to the mud outlet pipe (20), of the outer wall of the water inlet pipe (40) through bolts.
2. The mud drainage device for water conservancy construction according to claim 1, characterized in that: sludge extraction structure (10) are including blow off pipe (11), driving motor (12), pivot (13) and helical blade (14), there are driving motor (12) at the center department at blow off pipe (11) top through bolt fixed mounting, driving motor (12) output has through bolt fixed mounting pivot (13) of blow off pipe (11), pivot (13) outer wall is located there are helical blade (14) in the inside one end of blow off pipe (11) through the even fixed mounting of bolt, mud discharging mouth (15) have been seted up at the top of blow off pipe (11) outer wall one side.
3. The mud drainage device for water conservancy construction according to claim 2, characterized in that: the sludge outlet pipe (20) surrounds the sludge discharge port (15) through a bolt and is fixedly arranged at the top of one side of the outer wall of the sewage discharge pipe (11).
4. A mud drainage device for water conservancy construction according to claim 3, characterized in that: the center department at blow off pipe (11) top inlays and has the cooperation shaft sleeve (16) of pivot (13), pivot (13) run through shaft sleeve (16), just pivot (13) with shaft sleeve (16) rotate and are connected.
CN202023177147.8U 2020-12-25 2020-12-25 Mud pollution discharge device for water conservancy construction Active CN214005793U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023177147.8U CN214005793U (en) 2020-12-25 2020-12-25 Mud pollution discharge device for water conservancy construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023177147.8U CN214005793U (en) 2020-12-25 2020-12-25 Mud pollution discharge device for water conservancy construction

Publications (1)

Publication Number Publication Date
CN214005793U true CN214005793U (en) 2021-08-20

Family

ID=77290554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023177147.8U Active CN214005793U (en) 2020-12-25 2020-12-25 Mud pollution discharge device for water conservancy construction

Country Status (1)

Country Link
CN (1) CN214005793U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114871202A (en) * 2022-05-10 2022-08-09 刘阳 High-efficient environmental protection decontamination equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114871202A (en) * 2022-05-10 2022-08-09 刘阳 High-efficient environmental protection decontamination equipment

Similar Documents

Publication Publication Date Title
CN214005793U (en) Mud pollution discharge device for water conservancy construction
CN214219797U (en) Drainage device for river course construction
CN207079082U (en) A kind of up flow type aeration structure for being used to improve water quality of river
CN116446348B (en) Water conservancy hydropower station water blocking dam with sediment separation function
CN109868856A (en) The box feed ditch sand discharge apparatus of small reservoir
CN213014130U (en) Be applied to composite set of drainage pump station forebay desilting
CN209873729U (en) Device for underwater sand flushing and silt prevention of gate
CN109183739A (en) It is a kind of can the anti-silting rotary tide-block sluice of dredging
CN215630591U (en) Dredging device for water conservancy pipeline
CN220598354U (en) Guide wall of overflow dam
CN112161839A (en) Sewage sampling device based on new generation information technology
CN214883461U (en) Bottom shaft driving steel dam for water environment treatment
CN218346105U (en) Sluice for hydraulic engineering
CN216297239U (en) Water sluicegate screw rod belt cleaning device
CN219581284U (en) Pipeline cleaning device for hydraulic engineering
CN219621728U (en) Water conservancy and hydropower gate with dredging function
CN109235605A (en) It is a kind of to be responsible for the automatic device for removing pipeline deposit suitable for multichannel
CN220352750U (en) River sluice is used to water conservancy
CN212612350U (en) Ecological flow facility for releasing by utilizing temporary construction branch tunnel of built hydropower station
CN212153313U (en) Water sluicegate hoisting device
CN216892775U (en) Energy-efficient drainage pumping station for hydraulic engineering
CN211849302U (en) Reservoir drainage hole lock chamber structure
CN214783605U (en) A breakwater culvert component that is used for nuclear power compensation water intaking amount, conveniently leads dirty
CN209128936U (en) A kind of water conservancy water storage loop structure
CN214116546U (en) Garbage collection device for hydraulic engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant