CN212670179U - Concrete that permeates water fast flat curbstone - Google Patents

Concrete that permeates water fast flat curbstone Download PDF

Info

Publication number
CN212670179U
CN212670179U CN202020874503.2U CN202020874503U CN212670179U CN 212670179 U CN212670179 U CN 212670179U CN 202020874503 U CN202020874503 U CN 202020874503U CN 212670179 U CN212670179 U CN 212670179U
Authority
CN
China
Prior art keywords
flat
kerbstone
curbstone
drainage
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020874503.2U
Other languages
Chinese (zh)
Inventor
张伟军
李剑
华勇勇
缪泽远
唐丽芳
王文超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSCEC Kexin Design Group Co., Ltd
Original Assignee
Zhejiang Kexin Engineering Design Consultation Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Kexin Engineering Design Consultation Co ltd filed Critical Zhejiang Kexin Engineering Design Consultation Co ltd
Priority to CN202020874503.2U priority Critical patent/CN212670179U/en
Application granted granted Critical
Publication of CN212670179U publication Critical patent/CN212670179U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model relates to a concrete tie kerbstone permeates water fast solves the concrete tie kerbstone that permeates water that has now that the infiltration area utilization is lower, and the infiltration rate is not enough can lead to surface gathered water, and a large amount of rainwater passes through the inlet for stom water and emits into the problem of municipal pipe network. The concrete flat curbstone permeates water includes the flat stone, and the middle part upper surface of flat stone sets up the kerbstone, and flat stone and kerbstone adopt the concrete material integrated into one piece that permeates water, and the drainage groove has been seted up to the flat stone upper surface of kerbstone lateral side, and longitudinal extension is followed to the drainage groove, the horizontal pre-buried drainage tube that is provided with the inside and outside both sides of intercommunication kerbstone in bottom of kerbstone, the bottom surface of flat stone is equipped with the earial drainage passageway of going up the concavity. The utility model discloses a concrete flat curbstone permeates water, through horizontal pre-buried drainage tube and the vertical drainage groove structure in the outside, the flat stone infiltration area of the inside and outside both sides of make full use of curbstone improves effective infiltration area, infiltration with higher speed, more keep somewhere the rainwater infiltration in gravel and the soil of road below.

Description

Concrete that permeates water fast flat curbstone
Technical Field
The utility model belongs to the town road field relates to a sponge urban road infiltration structure, in particular to concrete tie kerbstone that permeates water fast.
Background
The sponge city is a new generation of urban rainfall flood management concept, which means that the city has good elasticity in the aspects of adapting to environmental changes, coping with natural disasters caused by rainwater and the like, and can be called as a water elasticity city. The sponge city adopts a method combining natural approach and artificial measures, and the supporting facilities can realize water absorption, water storage, water seepage and water purification in rainy days, and release and utilize the stored water when needed. With the advance of urbanization, the natural ecology of cities faces a serious imbalance. The urban pavement is hardened and paved by waterproof materials everywhere, so that the original natural ecological background and hydrological characteristics are changed, and therefore, natural permeation is enhanced and put in the first place. The method has the advantages that surface runoff can be avoided, the phenomenon that the hardened impervious pavement is converged into a municipal pipe network is reduced, meanwhile, underground water is conserved, the deficiency of the underground water is supplemented, the water quality can be purified through soil, and the urban microclimate is improved. The method for permeating the rainwater is various, and mainly changes various road surfaces and ground permeable paving materials to enable urban road surfaces to naturally permeate, adjusts the vertical direction of a green land, and reserves the rainwater from the source and then permeates.
In order to meet the rainwater infiltration requirement and improve the whole water permeability of the road, the flat curbstone made of pervious concrete is also used for improving the water permeability of the side of the road. Pervious concrete has a large number (15% to 35%) of interconnected voids. Like conventional concrete, it is made of a mixture of cement, coarse aggregate and water, however, it contains little or no sand, which results in a porous open-cell structure through which water can easily pass. When pervious concrete is used in municipal structures, it can rapidly absorb rain water at rates of 3 to 5 gallons per square foot of surface area, which exceeds the flow rates required to prevent runoff in most rainfall events. Rain water may be stored in a coarse gravel layer below the road surface or may penetrate into the soil below. The pervious concrete curbstones help prevent most of the polluting runoff that normally occurs on impervious pavements, since the pavement itself acts as a reserved area. However, the pervious concrete flat curbstone blocks rainwater on one side close to the road, the permeation area is only utilized on the side close to the road, the water seepage area is limited, after the pervious concrete flat curbstone is used for a long time, the permeability can be reduced, and when the precipitation is large, the permeation speed of the pervious concrete flat curbstone is insufficient, so that local water accumulation on the road surface can be caused, and the water accumulation on the road surface is drained into a municipal pipe network through a rainwater inlet, so that the soil water seepage rate is reduced.
Disclosure of Invention
The utility model aims to solve the current concrete tie kerbstone that permeates water infiltration area utilization ratio that permeates water is lower, and the infiltration rate is not enough can lead to surface ponding, and a large amount of rainwater passes through the problem that the inlet for stom water discharged municipal pipe network, provides a concrete tie kerbstone permeates water that permeates water fast, and make full use of permeates water in the concrete tie kerbstone, the synchronous infiltration of outer both sides, increases the infiltration area, improves infiltration efficiency, keeps more rainwater seepage in coarse sand gravel layer and the soil of road surface below.
The utility model provides a technical scheme that its technical problem adopted is: the utility model provides a concrete that permeates water flat curbstone that permeates water fast, includes the flat stone with road surface parallel and level, and the middle part of flat stone makes progress the arch and is provided with longitudinal extension's curbstone, and flat stone and curbstone adopt the concrete material integrated into one piece that permeates water, its characterized in that: use as the inboard towards road one side, the road one side of being the outside dorsad, the drainage groove has been seted up to the flat stone upper surface of kerbstone lateral side, and longitudinal extension is followed in the drainage groove, the bottom of kerbstone is transversely pre-buried and is provided with the drainage tube of the inside and outside both sides of intercommunication kerbstone, the bottom surface of flat stone is equipped with the earial drainage passageway. In this scheme, the concrete prefab that permeates water that kerbstone and flat stone were pour as an organic whole, bury the inside and outside of drainage tube intercommunication kerbstone in advance among the prefabricated forming process, when being used for impervious road surface, the curb department is assembled to the rainwater, partial rainwater passes through the drainage groove in the drainage tube inflow kerbstone outside, the drainage groove is with the vertical drainage of rainwater, make the rainwater along the synchronous infiltration of drainage groove in vertical circulation, make full use of the flat stone infiltration area of the inside and outside both sides of kerbstone, improve effective infiltration area, infiltration with higher speed, keep more with the rainwater infiltration in gravel and the soil of road below, reduce the rainwater proportion of discharging through the inlet for a river. And simultaneously, the rainwater retention on the road surface is reduced as much as possible by improving the permeation efficiency. The drainage tube of surface about not directly burying intercommunication flat stone underground is because soil local water storage ability is limited, directly arranges in line can lead to local water yield saturation rapidly about through the drainage tube, leads to soil part to receive a large amount of water impact, leads to the soil property to dilute, causes soil erosion and water loss, consequently adopts along the fore-and-aft even infiltration of road, more is favorable to holistic sponge city retaining.
Preferably, the drainage tube is arranged downwards from inside to outside in an inclined manner, the lower wall of the inner end of the drainage tube is flush with the upper surface of the flat stone, and the upper wall of the outer end of the drainage tube is not higher than the notch plane of the drainage groove. The outer end of the drainage tube is embedded with the bottom of the intersection, so that the notch can be conveniently paved with other pavement structures.
Preferably, the notch plane of the drainage groove is flush with the upper surface of the flat stone.
Preferably, a horizontal step surface for erecting an access board is arranged between the top end of the inner side groove wall of the drainage groove and the outer side wall of the kerbstone. When the lateral side of the drainage groove is required to be provided with facilities such as sidewalks, the erection plate can be erected on the horizontal step surface and then constructed above the erection plate, and the structure of the drainage groove can be effectively reserved.
Preferably, the drainage groove is a trapezoidal groove with a large upper part and a small lower part. The trapezoidal groove is convenient for prefabricating and demoulding.
Preferably, the drain channel is an upwardly concave arcuate channel. The arch-shaped groove has good structural strength and can effectively maintain the supporting strength.
Preferably, the end faces of the flat stone and the curbstone are flush, the flat stone and the curbstone form an integrally formed flat curbstone, the length of the flat curbstone is 0.5-2m, and 1-2 drainage tubes are pre-buried in each flat curbstone.
Preferably, the flat curbstones abut against and are spliced on the lateral end faces of the road, and rainwater openings are formed between the adjacent flat curbstones every 20-30 meters.
Preferably, the drainage groove and the drainage channel are both connected with the rainwater port in an open mode. After the flat curbstone is installed, the drainage grooves and the drainage channels are connected in series in sequence and are communicated to the rainwater inlet. When the precipitation is large, the drainage groove and the drainage channel can be used as auxiliary drainage pipelines to drain rainwater into the rainwater port.
The utility model discloses a concrete flat curbstone permeates water, through horizontal pre-buried drainage tube and the vertical drainage groove structure in the outside, the flat stone infiltration area of the inside and outside both sides of make full use of curbstone improves effective infiltration area, and infiltration with higher speed, more keep somewhere the rainwater infiltration in gravel and the soil of road below, reduce through inlet for stom water exhaust rainwater proportion, also reduce road surface rainwater to be detained through improving infiltration efficiency as far as possible simultaneously.
Drawings
The present invention will be further explained with reference to the accompanying drawings.
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic view of the structure of the drainage tube of the present invention.
In the figure: 1. the drainage device comprises a flat stone, 2, a curbstone, 3, a drainage tube, 4, a drainage groove, 5, a horizontal step surface, 6 and a drainage channel.
Detailed Description
The present invention will be further described with reference to the following specific embodiments and accompanying drawings.
Example (b): a rapid water penetration pervious concrete flat kerbstone is shown in figures 1 and 2. The pervious concrete curbstone in the embodiment is used for the road side of the impervious road. The pervious concrete flat curbstone comprises a flat stone 1 which is flush with the road surface, wherein the middle part of the flat stone 1 is upwards convexly provided with a longitudinally extending curbstone 2, and the flat stone and the curbstone are integrally formed by adopting a pervious concrete material. In this example, the width of the flat stone is 40cm, the length thereof is 80cm, the height thereof is 20cm, and the height thereof is 17cm and the width thereof is 16 cm. The kerbstone is centrally disposed on the upper surface of the flat stone.
As shown in fig. 2, the side facing the road is the inner side, the side facing away from the road is the outer side, and the flat stone upper surface at the outer side of the kerbstone 2 is provided with a drainage groove 4 which extends along the longitudinal direction and is a trapezoidal groove with a large upper part and a small lower part. The bottom of the kerbstone is transversely pre-buried and provided with a drainage tube 3 communicated with the inner side and the outer side of the kerbstone, the drainage tube 3 is obliquely and downwards arranged from inside to outside, the lower wall of the inner end of the drainage tube 3 is flush with the upper surface of the flat stone 1, and the upper wall of the outer end of the drainage tube is not higher than the notch plane of the drainage groove 4. The notch plane of the drainage groove is flush with the upper surface of the flat stone. A horizontal step surface 5 for erecting an attachment strap is arranged between the top end of the inner side wall of the drainage groove and the outer side wall of the kerbstone. The bottom surface of the flat stone is provided with an upward concave drainage channel 6 which is in a semicircular arch shape with the diameter of 20 cm.
In the actual construction process, the flat curbstones abut against the end faces of the side of the road and are longitudinally spliced along the road direction, and rainwater openings are formed between the adjacent flat curbstones at intervals of 20-30 meters. The drainage groove and the drainage channel are both connected with the rainwater port in an open manner at the rainwater port.
During precipitation, the rainwater on the impervious road surface assembles curb stone department on roadside, and the rainwater flows in the drainage groove in the curb stone outside through the drainage tube, and the drainage groove is with the vertical drainage of rainwater, makes the rainwater along the drainage groove in the synchronous infiltration of vertical circulation, and the flat stone infiltration area of the inside and outside both sides of make full use of curb improves effective infiltration area, and infiltration with higher speed keeps somewhere more with the rainwater infiltration in gravel and the soil of road below, reduces the rainwater proportion of discharging through the inlet for stom water. And simultaneously, the rainwater retention on the road surface is reduced as much as possible by improving the permeation efficiency. When the precipitation is large, the drainage groove and the drainage channel can be used as auxiliary drainage pipelines to drain rainwater into the rainwater port.

Claims (9)

1. The utility model provides a concrete that permeates water flat curbstone that permeates water fast, includes the flat stone with road surface parallel and level, and the middle part of flat stone makes progress the arch and is provided with longitudinal extension's curbstone, and flat stone and curbstone adopt the concrete material integrated into one piece that permeates water, its characterized in that: use as the inboard towards road one side, the road one side of being the outside dorsad, the drainage groove has been seted up to the flat stone upper surface of kerbstone lateral side, and longitudinal extension is followed in the drainage groove, the bottom of kerbstone is transversely pre-buried and is provided with the drainage tube of the inside and outside both sides of intercommunication kerbstone, the bottom surface of flat stone is equipped with the earial drainage passageway.
2. The rapid water-permeable concrete flat kerbstone of claim 1, wherein: the drainage tube is arranged downwards from inside to outside in an inclined mode, the lower wall of the inner end of the drainage tube is flush with the upper surface of the flat stone, and the upper wall of the outer end of the drainage tube is not higher than the notch plane of the drainage groove.
3. The rapid water-permeable concrete flat kerbstone of claim 1, wherein: the notch plane of the drainage groove is flush with the upper surface of the flat stone.
4. The rapid water permeable concrete curbstone of claim 1, 2 or 3, wherein: and a horizontal step surface for erecting a lapping plate is arranged between the top end of the inner side groove wall of the drainage groove and the outer side wall of the kerbstone.
5. The rapid water permeable concrete curbstone of claim 1, 2 or 3, wherein: the drainage groove is a trapezoidal groove with a large upper part and a small lower part.
6. The rapid water permeable concrete curbstone of claim 1, 2 or 3, wherein: the drainage channel is an arch-shaped groove which is concave upwards.
7. The rapid water permeable concrete curbstone of claim 1, 2 or 3, wherein: the end faces of the flat stones and the curbstones are parallel and level, the flat stones and the curbstones form the integrally formed flat curbstones, the length of the flat curbstones is 0.5-2m, and 1-2 drainage tubes are pre-buried in each flat curbstone.
8. The rapid water-permeable concrete curbstone of claim 7, wherein: the flat curbstones are abutted and spliced on the side end faces of the road, and rainwater openings are formed between the adjacent flat curbstones at intervals of 20-30 meters.
9. The rapid water-permeable concrete flat kerbstone of claim 8, wherein: and the drainage groove and the drainage channel are both connected with the rainwater port in an open manner.
CN202020874503.2U 2020-05-22 2020-05-22 Concrete that permeates water fast flat curbstone Active CN212670179U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020874503.2U CN212670179U (en) 2020-05-22 2020-05-22 Concrete that permeates water fast flat curbstone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020874503.2U CN212670179U (en) 2020-05-22 2020-05-22 Concrete that permeates water fast flat curbstone

Publications (1)

Publication Number Publication Date
CN212670179U true CN212670179U (en) 2021-03-09

Family

ID=74811979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020874503.2U Active CN212670179U (en) 2020-05-22 2020-05-22 Concrete that permeates water fast flat curbstone

Country Status (1)

Country Link
CN (1) CN212670179U (en)

Similar Documents

Publication Publication Date Title
CN205420946U (en) Novel ecology that prevents surface gathered water road structure of permeating water
CN106638918A (en) Construction method for sponge city rainwater collection system
KR100500957B1 (en) Road side ditch having seepage paving-material and construction method of the same
CN106351309A (en) Urban road rainwater detention and seepage system applicable to North
CN109338839B (en) Urban seepage storage system for recycling construction waste
CN107794822B (en) Permeable pavement based on sponge city idea
CN207228292U (en) One kind omits water system in printing slowly after first catchmenting
CN210507029U (en) Road drainage structure
CN105421647B (en) A kind of step building block of Collection utilization rainwater
CN104594155A (en) Permeable pavement laying method
CN215329163U (en) Structure of combined sponge city system for sidewalk and green belt
CN216474335U (en) A foundation structure for installing night light ceramic tile that permeates water
CN212670179U (en) Concrete that permeates water fast flat curbstone
CN214656073U (en) Natural permeable quarrying paving structure for sponge city
CN213740396U (en) Natural permeable quarrying paving structure for sponge city
CN108411728A (en) Surface drainage
CN212895755U (en) Urban road sidewalk drainage device
CN205529776U (en) Infiltration structure of waterproof road in road surface
CN208250846U (en) Surface drainage
CN217052889U (en) Structure of combined sponge city system for sidewalk and green belt
CN217579586U (en) A formula greenbelt structure that sinks for town road
CN206360052U (en) Heat-extraction system is received in a kind of sponge type rain penetration
CN217324803U (en) Town road paves road surface structure that permeates water
CN217711049U (en) Prefabricated infiltration ditch that permeates water suitable for sponge city pavement
CN218580392U (en) Urban road rainwater rapid infiltration structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 310000 floor 7, building 4, No. 1418-66, Moganshan Road, Hangzhou, Zhejiang

Patentee after: CSCEC Kexin Design Group Co., Ltd

Address before: Room 602, building 15-2, No. 1418-6, Moganshan Road, Hangzhou, Zhejiang Province

Patentee before: Zhejiang Kexin Engineering Design Consulting Co., Ltd