CN212534206U - Cast-in-place formula piping lane erects wall construction platform truck - Google Patents

Cast-in-place formula piping lane erects wall construction platform truck Download PDF

Info

Publication number
CN212534206U
CN212534206U CN202020073610.5U CN202020073610U CN212534206U CN 212534206 U CN212534206 U CN 212534206U CN 202020073610 U CN202020073610 U CN 202020073610U CN 212534206 U CN212534206 U CN 212534206U
Authority
CN
China
Prior art keywords
platform truck
cast
piping lane
multiunit
type slide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020073610.5U
Other languages
Chinese (zh)
Inventor
刘学深
张兆奎
白代柱
徐腾
何晴
李元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tai'an Changye Machinery Equipment Co ltd
Original Assignee
Tai'an Changye Machinery Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tai'an Changye Machinery Equipment Co ltd filed Critical Tai'an Changye Machinery Equipment Co ltd
Priority to CN202020073610.5U priority Critical patent/CN212534206U/en
Application granted granted Critical
Publication of CN212534206U publication Critical patent/CN212534206U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a cast-in-place formula piping lane erects wall construction platform truck, including platform truck body and multiunit vertical wall template, the platform truck body comprises multiunit platform truck portal, and top crossbeam lower part activity block has multiunit U type slide, and there is the hanging wheel on two inside walls of U type slide opening upper end all through round pin axle movable mounting, and U type slide passes through hanging wheel and top crossbeam lower part sliding connection, and the chain fall is all installed to U type slide lower part both sides, vertical wall template passes through the chain fall suspension type and installs under the top crossbeam, vertical support frame lower end fixed mounting walks shape wheel. The utility model discloses simple structure, convenient operation can very conveniently control the position of erecting the wall template through removing the hanging wheel, can conveniently adjust the size of piping lane structure, through walking shape wheel mobile trolley portal, can make things convenient for the construction of pouring of one section piping lane next to the efficiency of construction has been improved.

Description

Cast-in-place formula piping lane erects wall construction platform truck
Technical Field
The utility model relates to a piping lane construction technical field, more specifically say, in particular to cast-in-place formula piping lane erects wall construction platform truck.
Background
The utility tunnel is a facility for implementing unified planning, design, construction and maintenance, and is a civic public facility built under the city for laying municipal public pipelines. General utility tunnel sets up along basic road is supporting, and utility tunnel locates the below of basic road and parallels with basic road promptly, and this utility tunnel is used for holding underground pipeline, solves underground pipeline's the problem of laying.
Utility tunnel generally adopts the rectangle structure, its work progress is for excavating out the piping lane tunnel earlier, then construction department piping lane structure in the piping lane tunnel, the piping lane structure is concrete structure, current conventional way forms for adopting the prefabricated component concatenation, perhaps cast in situ concrete forms, when adopting the prefabricated component construction, need hoist and mount and transport to operation such as construction position concatenation again, loaded down with trivial details is under construction, adopt cast in situ concrete construction, need formwork pouring and tear open form again and transport to next construction area and carry out operations such as formwork pouring again, the work load of construction is big, the efficiency of construction is low, and adjustment piping lane structure size that can not be convenient.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a cast-in-place formula piping lane erects wall construction trolley to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: a cast-in-place type pipe gallery vertical wall construction trolley comprises a trolley body and a plurality of groups of vertical wall templates, wherein the trolley body is composed of a plurality of groups of trolley door frames, the plurality of groups of trolley door frames are fixedly connected through a support, each trolley door frame is composed of a top cross beam and two vertical supporting frames, the two vertical supporting frames are fixedly arranged at two ends of the lower portion of the top cross beam, the top cross beam is of an I-shaped steel structure, a plurality of groups of U-shaped sliding plates are movably clamped at the lower portion of the top cross beam, hanging wheels are movably arranged at the upper ends of two inner side walls of an opening of each U-shaped sliding plate through pin shafts, the U-shaped sliding plates are slidably connected with the lower portions of the top cross beams through the hanging wheels, inverted chains are arranged at two sides of the lower portions of the U-shaped sliding plates, the vertical wall templates are arranged below the top cross beams through inverted chain suspension types, walking wheels are fixedly arranged at the lower ends, the lower end of the inner side surface of the vertical wall template is movably hinged with a second positive and negative lead screw, and the other end of the second positive and negative lead screw is fixedly installed on the bottom surface of the pipe gallery.
Preferably, an operating platform is arranged on the top cross beam, is of a steel plate structure and is tiled on the multiple groups of trolley gantries.
Preferably, the inclined struts are fixedly mounted on the two side surfaces of the vertical strut frame, and the other ends of the inclined struts are fixedly mounted on the lower surface of the top cross beam at an angle of 45 degrees.
Preferably, the vertical wall formworks are fixedly connected through inner tie rods.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model discloses simple structure, convenient operation can very conveniently control the position of erecting the wall template through removing the hanging wheel, can conveniently adjust the size of piping lane structure, through dismantling first positive and negative lead screw, the positive and negative lead screw of second and inner pull rod, then accomplish the form removal work of erecting the wall template, place various article after the form removal on operation platform, then through walking shape wheel removal platform truck portal, can make things convenient for the construction of pouring of next section piping lane to the efficiency of construction has been improved.
Drawings
Fig. 1 is a schematic structural view of a cast-in-place pipe gallery vertical wall construction trolley of the utility model;
figure 2 is the utility model relates to a cast-in-place formula piping lane erects side view of wall construction platform truck.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 and fig. 2, the present invention provides a technical solution: a cast-in-place type pipe gallery vertical wall construction trolley comprises a trolley body and a plurality of groups of vertical wall templates 1, wherein the trolley body is composed of a plurality of groups of trolley door frames which are fixedly connected through a support 9, each trolley door frame is composed of a top cross beam 3 and two vertical support frames 10, the two vertical support frames 10 are fixedly arranged at two ends of the lower part of the top cross beam 3, the top cross beam 3 is of an I-shaped steel structure, a plurality of groups of U-shaped sliding plates 12 are movably clamped at the lower part of the top cross beam 3, hanging wheels 4 are movably arranged at the upper ends of two inner side walls of an opening of each U-shaped sliding plate 12 through pin shafts, the U-shaped sliding plates 12 are slidably connected with the lower part of the top cross beam 3 through the hanging wheels 4, inverted chains 2 are respectively arranged at two sides of the lower part of each U-shaped sliding plate 12, the vertical wall templates 1 are arranged below the top cross beam 3 through the inverted chains 2 in a, the other end of the first positive and negative screw rod 6 is movably hinged on the vertical wall template 1 corresponding to the position, the lower end of the inner side surface of the vertical wall template 1 is movably hinged with a second positive and negative screw rod 13, and the other end of the second positive and negative screw rod 13 is fixedly installed on the bottom surface of the pipe gallery to play a role in supporting the vertical wall template 1.
In this embodiment, be provided with operation platform 8 on the top crossbeam 3, operation platform 8 is the steel sheet structure, and its tiling is on the multiunit platform truck portal for place construction material.
In this embodiment, the equal fixed mounting in vertical braces 10 both sides surface has bracing 11, and the 11 other ends of bracing are 45 jiaos fixed mounting at a crossbeam 3 lower surface to trolley portal overall structure's stability and intensity have been improved.
In this embodiment, the vertical wall formworks 1 are fixedly connected through the inner tie bars 5.
The working principle is as follows: can very conveniently control the position of erecting wall template 1 through removing hanging wheel 4 to conveniently adjust the size of piping lane structure, through dismantling first positive and negative lead screw 6, the positive and negative lead screw 13 of second and inner pull rod 5, then accomplish the work of demolishing of erecting wall template 1, place various article after the form removal on operation platform 8, then through walking shape wheel 7 removal platform truck portal, can make things convenient for the construction of pouring of next section piping lane.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a cast-in-place formula piping lane erects wall construction platform truck, includes platform truck body and multiunit and erects the wall template, and the platform truck body comprises multiunit platform truck portal, through support fixed connection between the multiunit platform truck portal, and the platform truck portal comprises top beam and two perpendicular struts, its characterized in that: two erect strut fixed mounting at top crossbeam lower part both ends, the top crossbeam is the I-steel structure, and top crossbeam lower part activity block has multiunit U type slide, and there is the hanging wheel all through round pin axle movable mounting on two inside wall upper ends of U type slide opening, and U type slide passes through hanging wheel and top crossbeam lower part sliding connection, and the chain fall is all installed to U type slide lower part both sides, erect the wall template and pass through chain fall suspension type and install under the top crossbeam, erect a lower extreme fixed mounting of strut frame and walk the shape wheel, erect and prop the equal activity hinge of frame both sides surface and install first positive and negative lead screw, the equal activity hinge of first positive and negative lead screw other end is installed on the erect wall template that corresponds the position, and the activity hinge of the inboard surface lower extreme of erecting wall template installs the positive and negative lead screw of second, and the.
2. The cast-in-place pipe gallery vertical wall construction trolley according to claim 1, characterized in that: the top beam is provided with an operating platform which is of a steel plate structure and is tiled on the plurality of groups of trolley gantries.
3. The cast-in-place pipe gallery vertical wall construction trolley according to claim 1, characterized in that: the inclined struts are fixedly mounted on the two side surfaces of the vertical strut frame, and the other ends of the inclined struts are fixedly mounted on the lower surface of the top cross beam at an angle of 45 degrees.
4. The cast-in-place pipe gallery vertical wall construction trolley according to claim 1, characterized in that: the vertical wall formworks are fixedly connected through inner pull rods.
CN202020073610.5U 2020-01-14 2020-01-14 Cast-in-place formula piping lane erects wall construction platform truck Active CN212534206U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020073610.5U CN212534206U (en) 2020-01-14 2020-01-14 Cast-in-place formula piping lane erects wall construction platform truck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020073610.5U CN212534206U (en) 2020-01-14 2020-01-14 Cast-in-place formula piping lane erects wall construction platform truck

Publications (1)

Publication Number Publication Date
CN212534206U true CN212534206U (en) 2021-02-12

Family

ID=74525749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020073610.5U Active CN212534206U (en) 2020-01-14 2020-01-14 Cast-in-place formula piping lane erects wall construction platform truck

Country Status (1)

Country Link
CN (1) CN212534206U (en)

Similar Documents

Publication Publication Date Title
CN108330842A (en) A kind of Bridge Erector and construction method of large span steel reinforced concrete combination beam erection construction
CN203768814U (en) High-pier minor-radius curve cast-in-situ box girder novel moving die carrier
CN208087078U (en) A kind of boom hoisting of large span steel reinforced concrete combination beam Bridge Erector
CN104533460A (en) Construction method for concrete pouring of support-changing type formwork trolley and underground channel
CN106593469A (en) Trolley for construction of inverted arch
CN103526697B (en) Self-propelled movable formwork for construction of double-rectangle water conservancy aqueduct
CN104131515A (en) Method for constructing cast-in-place box beam by means of movable formwork
CN210216163U (en) Self-supporting cantilever formwork support system
CN208533370U (en) A kind of Bridge Erector of large span steel reinforced concrete combination beam erection construction
CN208563380U (en) A kind of self-propelled pipe gallery plate device
CN212177157U (en) Simple trolley template for gallery
CN212534206U (en) Cast-in-place formula piping lane erects wall construction platform truck
CN109162737A (en) A kind of self-styled reinforcing steel bar-binding bench vehicle
CN212052371U (en) Hanging basket device for variable width concrete box girder suspension casting construction
CN214883071U (en) Porous cast-in-situ box culvert bottom plate template system
CN210856979U (en) Culvert roof platform truck
CN201343704Y (en) Movable scaffolding system for casting T-shaped beam bridge flange slabs in situ
CN212335790U (en) Large cantilever bent cap construction trolley
CN218147885U (en) Movable rainwater box culvert outer template mounting and dismounting trolley
CN114294023A (en) Preliminary bracing trolley with formwork
CN208717748U (en) A kind of large span steel reinforced concrete combination beam Bridge Erector support leg device
CN211420881U (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam
CN109677946B (en) Handling device for slope
CN209369829U (en) A kind of self-styled reinforcing steel bar-binding bench vehicle
CN113152309A (en) Self-supporting synchronous hanging bracket system for corrugated steel web construction and construction method