CN212506244U - Fixing pile for building - Google Patents

Fixing pile for building Download PDF

Info

Publication number
CN212506244U
CN212506244U CN202020281355.3U CN202020281355U CN212506244U CN 212506244 U CN212506244 U CN 212506244U CN 202020281355 U CN202020281355 U CN 202020281355U CN 212506244 U CN212506244 U CN 212506244U
Authority
CN
China
Prior art keywords
spud pile
connecting rod
fixed surface
pile
installs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020281355.3U
Other languages
Chinese (zh)
Inventor
王海芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongda Fujian Engineering Construction Group Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020281355.3U priority Critical patent/CN212506244U/en
Application granted granted Critical
Publication of CN212506244U publication Critical patent/CN212506244U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a spud pile for building relates to architectural equipment technical field, including the spud pile, the fixed surface of spud pile installs spiral flabellum, the last fixed surface of spud pile installs the locating piece, the last skin weld of locating piece has the spliced pole, the ring channel has been seted up to the surface of spliced pole, the surface of ring channel is provided with the position sleeve, the fixed surface of position sleeve installs the connecting rod. This spud pile for building, cooperation setting through regulating block and threaded rod, the in-process that uses can make whole device level through adjusting the regulating block, thereby played the effect that prevents the spud pile slope, reached the purpose that reduces intensity of labour, cooperation setting through mounting hole and locking card, the in-process that uses can make the locking card enter into earth through the rotation of rotation axis, thereby played the effect that increases the spud pile fastness, the purpose that improves the security has been reached.

Description

Fixing pile for building
Technical Field
The utility model relates to a construction equipment technical field specifically is a spud pile for building.
Background
The pile foundation is a foundation form with high bearing capacity, wide application range and long history. With the improvement of production level and the development of scientific technology, the type, process, design theory, calculation method and application range of the pile foundation are greatly developed, and the method is widely applied to projects such as high-rise buildings, ports, bridges and the like. The pile is a force transmission component which transmits all or part of the load of the building to the foundation soil and has certain rigidity and bending resistance, and the cross section size of the pile is far smaller than the length of the pile.
Among the prior art, there are a lot of spud piles all adopt the mode of artifical installation, though can accomplish the installation of spud pile, nevertheless can appear the spud pile slope at the in-process of installation, often need demolish reinstallation, cause work efficiency's decline, the fixed effect of spud pile is insecure moreover, causes certain potential safety hazard for the building.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a spud pile for building has solved the problem of proposing among the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a spud pile for building, includes the spud pile, the outer fixed surface of spud pile installs spiral fan blade, the last fixed surface of spud pile installs the locating piece, the last skin weld of locating piece has the spliced pole, the ring channel has been seted up to the surface of spliced pole, the surface of ring channel is provided with the position sleeve, the outer fixed surface of position sleeve installs the connecting rod, the one end fixed mounting of connecting rod has longitudinal tie rod, the both ends of longitudinal tie rod all are through bolt and transverse connection pole threaded connection, the upper surface at longitudinal tie rod and transverse connection pole middle part all is provided with the spirit level, the lower fixed surface of longitudinal tie rod installs the push rod, the one end of push rod is pegged graft in the inside of location.
Optionally, a sliding groove is formed in the positioning box, a moving plate matched with the sliding groove is clamped in the sliding groove, a push rod is fixedly mounted on the upper surface of the moving plate, a damping spring is arranged on the lower surface of the moving plate, one end of the damping spring is arranged on the inner bottom wall of the positioning box, a threaded rod is fixedly mounted on the lower surface of the positioning box, an adjusting block is connected to the outer surface of the threaded rod in a threaded manner, and one end of the adjusting block is inserted into the positioning base.
Optionally, the positioning sleeve includes a first positioning sleeve and a second positioning sleeve, and the first positioning sleeve is in threaded connection with the second positioning sleeve through a fixing bolt.
Optionally, a rotating shaft is inserted into the fixing pile, a mounting nut is fixedly mounted on the upper surface of the connecting column, and one end of the rotating shaft penetrates through the mounting nut and is fixedly connected with the rotating nut.
Optionally, the outer surface fixed mounting of rotation axis has the connecting block, the one end fixed mounting of connecting block has the locking card, the quantity of locking card is three.
Optionally, the outer surface of the fixed pile is provided with mounting holes, and the mounting holes are formed in the outer surface of the fixed pile at different heights and angles.
(III) advantageous effects
The utility model provides a spud pile for building possesses following beneficial effect:
1. this spud pile for building through the setting of spirit level, makes this spud pile for building possess and can observe whether horizontally effect of the device, sets up through the cooperation of regulating block and threaded rod, can make whole device level through adjusting the regulating block at the in-process that uses to play the effect that prevents the spud pile slope, reached the purpose that reduces intensity of labour.
2. This spud pile for building through swivel nut's setting, makes this spud pile for building possess and to have made the effect of rotation axis rotation, sets up through the cooperation of mounting hole and locking card, can make the locking card enter into earth through the rotation of rotation axis at the in-process that uses to play the effect that increases the spud pile fastness, reached the purpose that improves the security.
Drawings
FIG. 1 is a schematic view of the structure of the present invention;
FIG. 2 is a schematic top view of the connecting rod of the present invention;
fig. 3 is a schematic view of the three-dimensional structure of the fixing pile of the present invention;
fig. 4 is a schematic view of the top-view cross-sectional structure of the rotating shaft according to the present invention.
In the figure: 1. fixing the pile; 2. a helical fan blade; 3. positioning blocks; 4. connecting columns; 5. an annular groove; 6. a positioning sleeve; 601. a first positioning sleeve; 602. a second positioning sleeve; 603. fixing the bolt; 7. a connecting rod; 8. a longitudinal connecting rod; 9. a transverse connecting rod; 10. a level gauge; 11. a push rod; 12. positioning the box body; 13. a chute; 14. moving the plate; 15. a damping spring; 16. a threaded rod; 17. an adjusting block; 18. positioning a base; 19. a rotating shaft; 20. mounting a nut; 21. rotating the nut; 22. connecting blocks; 23. locking the card; 24. and (7) installing holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 4, the present invention provides a technical solution: a fixing pile for building comprises a fixing pile 1, a rotating shaft 19 is inserted into the fixing pile 1, a mounting nut 20 is fixedly mounted on the upper surface of a connecting column 4, one end of the rotating shaft 19 penetrates through the mounting nut 20 and is fixedly connected with a rotating nut 21, a connecting block 22 is fixedly mounted on the outer surface of the rotating shaft 19, a locking clamping piece 23 is fixedly mounted at one end of the connecting block 22, the number of the locking clamping pieces 23 is three, the fixing pile for building has the effect of enabling the rotating shaft 19 to rotate through the arrangement of the rotating nut 21, the locking clamping pieces 23 can enter soil through the rotation of the rotating shaft 19 in the using process through the matching arrangement of a mounting hole 24 and the locking clamping pieces 23, so that the firmness of the fixing pile 1 is increased, the purpose of improving safety is achieved, and spiral fan blades 2 are fixedly mounted on the outer surface of the fixing pile 1, the positioning block 3 is fixedly arranged on the upper surface of the fixing pile 1, the connecting column 4 is welded on the upper surface of the positioning block 3, the annular groove 5 is formed in the outer surface of the connecting column 4, the positioning sleeve 6 is arranged on the outer surface of the annular groove 5, the positioning sleeve 6 comprises a first positioning sleeve 601 and a second positioning sleeve 602, the first positioning sleeve 601 is in threaded connection with the second positioning sleeve 602 through a fixing bolt 603, the connecting rod 7 is fixedly arranged on the outer surface of the positioning sleeve 6, a longitudinal connecting rod 8 is fixedly arranged at one end of the connecting rod 7, both ends of the longitudinal connecting rod 8 are in threaded connection with a transverse connecting rod 9 through bolts, level gauges 10 are arranged on the upper surfaces of the middle parts of the longitudinal connecting rod 8 and the transverse connecting rod 9, the fixing pile for the building has the effect of observing whether the device is horizontal or not through the arrangement of the level gauges 10, the whole device can be leveled through the matching arrangement of the adjusting block, thereby the effect of preventing the slope of spud pile 1 has been played, the purpose that reduces intensity of labour has been reached, the lower fixed surface of longitudinal tie rod 8 installs push rod 11, the one end of push rod 11 is pegged graft in the inside of location box 12, spout 13 has been seted up to the inside of location box 12, the inside joint of spout 13 has rather than matching suitable movable plate 14, the last fixed surface of movable plate 14 installs push rod 11, the lower surface of movable plate 14 is provided with damping spring 15, damping spring 15's one end sets up on the interior diapire of location box 12, the lower fixed surface of location box 12 installs threaded rod 16, the surface threaded connection of threaded rod 16 has regulating block 17, the one end of regulating block 17 is pegged graft in the inside of location base 18, mounting hole 24 has been seted up to the surface of spud pile 1, mounting hole 24 sets up the different height and the angle.
When the device is used, the positioning sleeve 6 is firstly installed inside the annular groove 5, the device can rotate inside the positioning sleeve 6, then the ground is shoveled, the positioning base 18 is placed on the ground, the level gauge 10 is observed, the whole device is in the horizontal position by adjusting the adjusting block 17, then the mounting nut 20 is screwed by a machine, at the moment, the fixing pile 1 can move downwards under the action of the spiral fan blades 2, the moving plate 14 also moves downwards, the damping spring 15 is compressed, the damping effect can be achieved, when the positioning block 3 is contacted with the ground, the mounting nut 20 stops being screwed, at the moment, the rotating shaft 19 rotates by screwing the rotating nut 21, the locking clamping piece 23 is driven to rotate, and finally the locking clamping piece 23 enters the soil, so that the stability of the fixing pile 1 is improved.
The utility model discloses a theory of operation and beneficial effect: this spud pile for building through the setting of spirit level 10, makes this spud pile for building possess and can observe whether horizontally effect of the device, sets up through the cooperation of regulating block 17 and threaded rod 16, can make whole device level through adjusting block 17 in the in-process of using to play the effect that prevents spud pile 1 slope, reached the purpose that reduces intensity of labour. Through swivel nut 21's setting, make this spud pile for building possess and to have made the rotatory effect of rotation axis 19, through the cooperation setting of mounting hole 24 and locking card 23, can make locking card 23 enter into earth through rotation axis 19's rotation at the in-process of using to play the effect that increases spud pile 1 fastness, reached the purpose that improves the security.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. A spud pile for building, includes spud pile (1), its characterized in that: the outer fixed surface of the fixing pile (1) is provided with a spiral fan blade (2), the upper fixed surface of the fixing pile (1) is provided with a positioning block (3), the upper surface of the positioning block (3) is welded with a connecting column (4), the outer surface of the connecting column (4) is provided with an annular groove (5), the outer surface of the annular groove (5) is provided with a positioning sleeve (6), the outer fixed surface of the positioning sleeve (6) is provided with a connecting rod (7), one end of the connecting rod (7) is fixedly provided with a longitudinal connecting rod (8), the two ends of the longitudinal connecting rod (8) are both in threaded connection with a transverse connecting rod (9) through bolts, the upper surfaces of the middle parts of the longitudinal connecting rod (8) and the transverse connecting rod (9) are both provided with a level meter (10), and the lower surface of the, one end of the push rod (11) is inserted in the positioning box body (12).
2. A constructional spud pile according to claim 1, characterised in that: the inside of location box (12) has seted up spout (13), its joint in the inside of spout (13) has with match suitable movable plate (14), the last fixed surface of movable plate (14) installs push rod (11), the lower surface of movable plate (14) is provided with damping spring (15), damping spring (15) one end sets up on the interior diapire of location box (12), the lower fixed surface of location box (12) installs threaded rod (16), the surface threaded connection of threaded rod (16) has regulating block (17), the one end of regulating block (17) is pegged graft in the inside of location base (18).
3. A constructional spud pile according to claim 1, characterised in that: the locating sleeve (6) comprises a first locating sleeve (601) and a second locating sleeve (602), and the first locating sleeve (601) is in threaded connection with the second locating sleeve (602) through a fixing bolt (603).
4. A constructional spud pile according to claim 1, characterised in that: a rotating shaft (19) is inserted into the fixing pile (1), a mounting nut (20) is fixedly mounted on the upper surface of the connecting column (4), and one end of the rotating shaft (19) penetrates through the mounting nut (20) and is fixedly connected with a rotating nut (21).
5. A constructional spud pile according to claim 4, characterised in that: the outer fixed surface of rotation axis (19) installs connecting block (22), the one end fixed mounting of connecting block (22) has locking card (23), the quantity of locking card (23) is three.
6. A constructional spud pile according to claim 1, characterised in that: mounting hole (24) have been seted up to the surface of spud pile (1), mounting hole (24) set up the not co-altitude and the angle department at spud pile (1) surface.
CN202020281355.3U 2020-03-09 2020-03-09 Fixing pile for building Expired - Fee Related CN212506244U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020281355.3U CN212506244U (en) 2020-03-09 2020-03-09 Fixing pile for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020281355.3U CN212506244U (en) 2020-03-09 2020-03-09 Fixing pile for building

Publications (1)

Publication Number Publication Date
CN212506244U true CN212506244U (en) 2021-02-09

Family

ID=74440252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020281355.3U Expired - Fee Related CN212506244U (en) 2020-03-09 2020-03-09 Fixing pile for building

Country Status (1)

Country Link
CN (1) CN212506244U (en)

Similar Documents

Publication Publication Date Title
US9605404B2 (en) High strain dynamic load testing procedure
US9458593B2 (en) Deep pile foundation construction methodology for existing and new buildings
CN109440762B (en) Construction method of filling pile for drainage pump station
CN211257012U (en) Foundation pit supporting structure
CN108842798B (en) Static pressure sinking construction method of prefabricated pouring type open caisson
CN102021908A (en) Mechanical connection structure and construction method for splicing precast square piles
CN108093979B (en) Method for installing and constructing photovoltaic power generation body of light-agricultural combined greenhouse
CN212506244U (en) Fixing pile for building
WO2015147674A1 (en) Method for installing overhead transmission line supports in permafrost soils
CN110593301A (en) Prefabricated foundation assembly and assembling method thereof
CN212865950U (en) Connecting piece for foundation pit support
CN212896435U (en) Combined prefabricated bearing platform pile foundation
CN113846714B (en) Method for repairing and reinforcing raft foundation
CN205934925U (en) Pile pressing machine
CN106400832A (en) Environment-friendly assembling type post-grouting steel cylinder pile foundation and construction method thereof
CN111636696A (en) Accurate adjustment support of concrete built-in fitting
CN110847175A (en) Foundation pile cuts off guide bracket
CN115125952B (en) Device for installing spiral anchor foundation of transmission line iron tower and construction method
CN111101984A (en) Tunnel supporting mechanism
CN104895066A (en) Construction method for overlength jet grouting stiffness core combined pile
CN114991202B (en) Quick anchoring and attaching construction method for van foundation
CN212984674U (en) Accurate adjustment support of concrete built-in fitting
CN220598428U (en) Spiral ground pile installation device
CN104695427A (en) Construction method of bionic power tower
CN213329086U (en) Pile foundation structure for building engineering that stability is strong

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210508

Address after: 362200 room 703, building 3, shuangshuiwan phase I, Shuanglong Road, Xiyuan street, Jinjiang City, Quanzhou City, Fujian Province

Patentee after: Zhongda (Fujian) Engineering Construction Group Co.,Ltd.

Address before: Shandong Yongsheng Construction Group Co., Ltd., Guangming Road, Jihe street, Sishui County, Jining City, Shandong Province

Patentee before: Wang Haifang

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210209

CF01 Termination of patent right due to non-payment of annual fee