CN211736290U - A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform - Google Patents

A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform Download PDF

Info

Publication number
CN211736290U
CN211736290U CN201921945590.XU CN201921945590U CN211736290U CN 211736290 U CN211736290 U CN 211736290U CN 201921945590 U CN201921945590 U CN 201921945590U CN 211736290 U CN211736290 U CN 211736290U
Authority
CN
China
Prior art keywords
cantilevered
section
overhanging
steel
steel beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921945590.XU
Other languages
Chinese (zh)
Inventor
吴志球
孙明
高艾春
黄星
陈慧
张载荣
王利胜
张静
陈正涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaian Construction Engineering Quality Inspection Center Co ltd
Original Assignee
Huaian Construction Engineering Quality Inspection Center Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaian Construction Engineering Quality Inspection Center Co ltd filed Critical Huaian Construction Engineering Quality Inspection Center Co ltd
Priority to CN201921945590.XU priority Critical patent/CN211736290U/en
Application granted granted Critical
Publication of CN211736290U publication Critical patent/CN211736290U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

本实用新型公开一种壳截面大跨度挑檐高空搭设模架作业平台,包括若干根位于待施工挑檐下一层的悬挑钢梁,悬挑钢梁的其中一段伸出结构梁板,若干根悬挑钢梁的伸出段组成悬挑支撑,挑檐支模架搭设在该悬挑支撑上;每个所述悬挑钢梁与结构梁板锚固位置的上方均设置有一立柱,立柱垂直于所述悬挑钢梁,且立柱的底部固定在所述悬挑钢梁上,立柱的顶部连接有至少一道钢丝拉索,所述钢丝拉索的另一端拉结在悬挑钢梁伸出段上;每个所述悬挑钢梁伸出段的底部还固定有一支撑钢杆,支撑钢杆的另一端固定在悬挑层下一层的结构梁板上。本实用新型不依赖上层结构梁板,仍然可以保证悬挑的安全,缩短工期,节约施工成本。

Figure 201921945590

The utility model discloses a high-altitude building formwork working platform with a large-span overhanging eaves of a shell section, which comprises a plurality of cantilevered steel beams located on a layer below the overhanging eaves to be constructed, a section of the cantilevered steel beams protruding from a structural beam plate, a plurality of cantilevered steel beams The protruding section of the cantilevered steel beam constitutes a cantilever support, and the overhanging formwork is erected on the cantilever support; a column is provided above each of the cantilevered steel beams and the anchoring position of the structural beam plate, and the column is vertical On the cantilevered steel beam, the bottom of the column is fixed on the cantilevered steel beam, the top of the column is connected with at least one steel wire cable, and the other end of the steel cable is tied to the cantilevered steel beam. A supporting steel rod is also fixed at the bottom of each extending section of the cantilevered steel beam, and the other end of the supporting steel rod is fixed on the structural beam plate on the lower layer of the cantilevered layer. The utility model does not rely on the beams and slabs of the superstructure, and can still ensure the safety of the cantilever, shorten the construction period and save the construction cost.

Figure 201921945590

Description

一种壳截面大跨度挑檐高空搭设模架作业平台A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform

技术领域technical field

本实用新型涉及建筑施工技术领域,具体是涉及一种大跨度挑檐的支模架搭设平台。The utility model relates to the technical field of building construction, in particular to a large-span overhanging formwork erecting platform.

背景技术Background technique

近年来随着我过经济的快速发展,城市化进程的加快。我们面临做日益膨胀的城市人口的压力,为了缓解城市空间的拥挤,立体化的城市空间发展目前已经成为建筑行业的主流,越来越多的高层和超高层建筑在城市中耸立起来。In recent years, with the rapid economic development, the urbanization process has accelerated. We are facing the pressure of growing urban population. In order to alleviate the crowding of urban space, three-dimensional urban space development has become the mainstream of the construction industry, and more and more high-rise and super high-rise buildings are erected in cities.

对于高层和超高层建筑,采用传统脚手架从地面开始一层层向上搭设施工平台,会严重影响施工效率,并且从经济效益和施工安全角度来看,这种施工方式也存在较大的不足。For high-rise and super-high-rise buildings, using traditional scaffolding to build construction platforms from the ground up layer by layer will seriously affect the construction efficiency, and from the perspective of economic benefits and construction safety, this construction method also has major shortcomings.

为了解决这一问题,目前在高层建筑施工中出现了一种悬挑式脚手架,从施工完成的结构中伸出悬挑梁,从悬挑梁开始向上搭设脚手架。但这种悬挑方式,完全由悬挑梁受力,悬挑梁再将荷载传递到结构梁板上,因此对于悬挑梁、结构梁板,一级两者的结合部分要求都非常高,很多施工现场都不能确保受力的稳定,因此产生了极大的安全隐患。在CN104389419A公开的益中悬挑支模平台安装结构及施工方法中也同样提出了类似的问题,在该专利文献中,其采用上拉下撑的方式,在悬挑梁的下部采用支撑斜杆进行支撑,上部采用拉索拉结,拉索的另一端拉结在上层的结构梁板中,从而保证整个悬挑梁受力稳定。In order to solve this problem, a kind of cantilever scaffolding has appeared in the construction of high-rise buildings. Cantilever beams are extended from the completed structure, and scaffolding is erected upwards from the cantilever beams. However, this cantilever method is completely stressed by the cantilever beam, and the cantilever beam then transfers the load to the structural beam plate. Therefore, for the cantilever beam and the structural beam plate, the requirements for the combination of the two are very high, and many construction The stability of the force cannot be ensured at the scene, so there is a great potential safety hazard. Similar problems are also raised in the installation structure and construction method of Yizhong cantilevered formwork platform disclosed in CN104389419A. In this patent document, the method of pulling up and supporting down is adopted, and supporting inclined rods are used at the lower part of the cantilever beam. For support, the upper part is tied with a cable, and the other end of the cable is tied in the structural beam plate of the upper layer, so as to ensure the stability of the entire cantilever beam.

但对于上层未施工完成或在顶层的挑檐施工时,由于没有上层结构梁板的存在,仍然会导致上述问题的存在,因此有必然对上述结构和施工方式进一步改进。而且高层挑檐为了保证防水效果和受力状况稳定,主体部分必须要一次整体浇筑,这也决定了悬挑脚手架无法以屋面层的结构梁板作为拉结支撑。However, for the unfinished construction of the upper layer or the construction of the overhanging eaves on the top floor, the above problems will still occur due to the absence of the superstructure beams and slabs. Therefore, it is necessary to further improve the above structure and construction method. In addition, in order to ensure the waterproof effect and stable stress condition of high-rise overhangs, the main part must be poured as a whole, which also determines that the cantilevered scaffolding cannot be supported by the structural beams of the roof layer.

发明内容SUMMARY OF THE INVENTION

发明目的:本实用新型目的在于针对现有技术的不足,提供一种为壳截面大跨度挑檐施工作为稳定支撑的高空搭设模架作业平台。Purpose of the invention: The purpose of this utility model is to aim at the deficiencies of the prior art, and to provide a high-altitude formwork operation platform for the construction of large-span overhanging eaves of shell section as a stable support.

技术方案:本实用新型所述壳截面大跨度挑檐高空搭设模架作业平台,包括若干根位于待施工挑檐下一层的悬挑钢梁,所述悬挑钢梁锚固在待施工挑檐下一层的结构梁板上,该层作为悬挑层,悬挑钢梁的其中一段伸出结构梁板,若干根悬挑钢梁的伸出段组成悬挑支撑,挑檐支模架搭设在该悬挑支撑上;Technical scheme: the shell section large-span overhanging eaves high-altitude erecting formwork work platform of the utility model includes a number of cantilevered steel beams located on the first floor of the overhanging eaves to be constructed, and the cantilevered steel beams are anchored on the overhanging eaves to be constructed. On the structural beam plate of the next layer, this layer is used as a cantilever layer. One section of the cantilevered steel beam extends out of the structural beam plate, and the projecting sections of several cantilevered steel beams form a cantilever support. on the overhanging support;

每个所述悬挑钢梁与结构梁板锚固位置的上方均设置有一立柱,立柱垂直于所述悬挑钢梁,且立柱的底部固定在所述悬挑钢梁上,立柱的顶部连接有至少一道钢丝拉索,所述钢丝拉索的另一端拉结在悬挑钢梁伸出段上;A column is provided above each of the cantilevered steel beams and the anchoring positions of the structural beam plates, the column is perpendicular to the cantilevered steel beam, the bottom of the column is fixed on the cantilevered steel beam, and the top of the column is connected with a At least one steel wire cable, the other end of the steel wire cable is tied on the projecting section of the cantilevered steel beam;

每个所述悬挑钢梁伸出段的底部还固定有一斜向的支撑钢杆,支撑钢杆的另一端固定在悬挑层下一层的结构边梁上。An oblique supporting steel rod is also fixed at the bottom of each overhanging section of the cantilevered steel beam, and the other end of the supporting steel rod is fixed on the structural edge beam on the lower layer of the cantilevered layer.

本实用新型进一步优选地技术方案为,所述悬挑钢梁的另一段作为固定段,锚固在悬挑层的楼面上。A further preferred technical solution of the present invention is that the other section of the cantilevered steel beam is used as a fixed section and is anchored on the floor of the cantilevered floor.

作为优选地,所述立柱的顶部两侧各连接有至少一道钢丝拉索,钢丝拉索的另一端分别拉结在悬挑钢梁的伸出段和固定段上。拉结体系与悬挑钢梁形成稳定的三角支撑结构,提升结构的稳定性。Preferably, at least one steel wire cable is connected to both sides of the top of the column, and the other ends of the steel wire cable are respectively tied to the projecting section and the fixed section of the cantilevered steel beam. The tie system and the cantilevered steel beam form a stable triangular support structure to improve the stability of the structure.

优选地,所述立柱与悬挑钢梁的伸出段之间通过两道钢丝拉索拉结,两道钢丝拉索分别连接在悬挑钢梁伸出段的端部和中部。Preferably, the upright column and the outgoing section of the cantilevered steel beam are tied by two wire cables, and the two wire cables are respectively connected to the ends and the middle of the outgoing section of the cantilevered steel beam.

优选地,每道所述钢丝拉索上均设置有一紧绳螺栓,调节所述钢丝拉索的松紧。Preferably, each wire cable is provided with a tight rope bolt to adjust the tightness of the wire cable.

优选地,所述悬挑钢梁伸出段的底部贴紧悬挑层边梁处设置有一个定位耳板,该定位耳板中间开有圆孔。Preferably, a positioning lug is provided at the bottom of the projecting section of the cantilevered steel beam close to the side beam of the cantilevered layer, and a circular hole is opened in the middle of the positioning lug.

优选地,在所述悬挑钢梁伸出段的端部下方设置有一个耳板,且中间开有圆孔,该耳板与所述定位耳板上悬挂防坠网。定位耳板不仅仅可以定位悬挑钢梁与结构梁板的锚固位置,并且兼用于悬挂防坠网。Preferably, a lug plate is provided below the end of the overhanging section of the cantilevered steel beam, and a circular hole is opened in the middle, and the lug plate and the positioning lug plate are hung with an anti-falling net. The positioning lug plate can not only locate the anchoring position of the cantilevered steel beam and the structural beam plate, but also be used for suspending the anti-falling net.

优选地,所述悬挑支撑上还搭设有防护脚手架,防护脚手架搭设在悬挑钢梁伸出段的端部,防护脚手架的顶部高度高于待施工挑檐。Preferably, the cantilever support is also provided with protective scaffolding, the protective scaffolding is erected on the end of the overhanging section of the cantilevered steel beam, and the top height of the protective scaffolding is higher than the eaves to be constructed.

优选地,每个悬挑钢梁均通过水平连杆与相邻的悬挑钢梁连接。Preferably, each cantilevered steel beam is connected with the adjacent cantilevered steel beam through a horizontal connecting rod.

优选地,每个所述立柱均通过水平连杆与相邻的立柱连接。Preferably, each of the uprights is connected with the adjacent uprights through horizontal links.

有益效果:本实用新型中在悬挑钢梁与结构梁板锚固位置的上方设置一立柱,以立柱作为悬挑钢梁上拉系统的连接点,不依赖上层结构梁板,在上层施工未完成,或者施工大跨度挑檐等无法将拉结体系与上层结构梁板连接时,仍然可以保证悬挑的安全,缩短工期,节约施工成本。Beneficial effect: In this utility model, a column is arranged above the anchoring position of the cantilevered steel beam and the structural beam plate, and the column is used as the connection point of the pull-up system of the cantilevered steel beam. , or when the construction of large-span overhangs cannot connect the tie system with the superstructure beams and slabs, the safety of the cantilever can still be guaranteed, the construction period is shortened, and the construction cost is saved.

附图说明Description of drawings

图1为本实用新型的作业平台的结构示意图;Fig. 1 is the structural representation of the working platform of the present utility model;

图中,1-悬挑钢梁、2-支模架、3-防护脚手架、4-立柱、5-钢丝拉索、6-支撑钢杆、7-定位耳板、8-防坠网。In the figure, 1- cantilevered steel beam, 2- formwork frame, 3- protective scaffolding, 4- column, 5- steel wire cable, 6- supporting steel rod, 7- positioning lug plate, 8- anti-fall net.

具体实施方式Detailed ways

下面通过附图对本实用新型技术方案进行详细说明,但是本实用新型的保护范围不局限于所述实施例。The technical solutions of the present invention will be described in detail below with reference to the accompanying drawings, but the protection scope of the present invention is not limited to the embodiments.

实施例:一种壳截面大跨度挑檐高空搭设模架作业平台,包括若干根位于待施工挑檐下一层的悬挑钢梁1,悬挑钢梁1锚固在待施工挑檐下一层的结构梁板上,该层作为悬挑层,悬挑钢梁1的其中一段伸出结构梁板作为伸出段,另一段作为固定段,锚固在悬挑层的楼面上。每个悬挑钢梁1的伸出段均通过水平连杆与相邻的悬挑钢梁1连接。若干根悬挑钢梁1的伸出段组成悬挑支撑,挑檐支模架2和防护脚手架3搭设在该悬挑支撑上,防护脚手架3搭设在悬挑钢梁1伸出段的端部,防护脚手架3的顶部高度高于待施工挑檐。Embodiment: a shell section large-span overhanging eaves high-altitude erecting formwork operation platform, including several cantilevered steel beams 1 located on the first floor under the overhanging eaves to be constructed, and the cantilevered steel beams 1 are anchored on the first floor under the overhanging eaves to be constructed One section of the cantilevered steel beam 1 protrudes from the structural beam slab as a protruding section, and the other section serves as a fixed section, which is anchored on the floor of the cantilevered layer. The protruding section of each cantilevered steel beam 1 is connected with the adjacent cantilevered steel beam 1 through horizontal connecting rods. The outriggers of several cantilevered steel beams 1 form an overhanging support, the overhanging formwork 2 and the protective scaffolding 3 are erected on the overhanging support, and the protective scaffolding 3 is erected at the end of the outstretched section of the overhanging steel beam 1. , the top height of the protective scaffold 3 is higher than the eaves to be constructed.

每个悬挑钢梁1与结构梁板锚固位置的上方均设置有一立柱4,立柱4垂直于悬挑钢梁1,且立柱4的底部固定在悬挑钢梁1上。立柱4的顶部连接有三道钢丝拉索5,一道钢丝拉索5拉结在悬挑钢梁1的固定段上,另两道钢丝拉索5分别拉结在悬挑钢梁1伸出段的中部和端部。每道钢丝拉索5上均设置有一紧绳螺栓,调节钢丝拉索5的松紧。每个立柱4均通过水平连杆与相邻的立柱4连接。Above each cantilevered steel beam 1 and the anchoring position of the structural beam plate is provided a column 4 , the column 4 is perpendicular to the cantilevered steel beam 1 , and the bottom of the column 4 is fixed on the cantilevered steel beam 1 . The top of the column 4 is connected with three steel wire cables 5, one steel wire cable 5 is tied on the fixed section of the cantilevered steel beam 1, and the other two steel wire cables 5 are respectively tied at the outgoing section of the cantilevered steel beam 1. middle and ends. Each wire rope 5 is provided with a rope tightening bolt to adjust the tightness of the wire rope 5 . Each column 4 is connected with the adjacent column 4 through a horizontal link.

每个悬挑钢梁1伸出段的底部还固定有一斜向的支撑钢杆6,支撑钢杆6的另一端固定在悬挑层下一层的结构边梁上。An oblique supporting steel rod 6 is also fixed at the bottom of the protruding section of each cantilevered steel beam 1, and the other end of the supporting steel rod 6 is fixed on the structural edge beam on the lower layer of the cantilevered layer.

悬挑钢梁1伸出段的底部设置有两个定位耳板7,其中一个定位耳板7位于悬挑钢梁1伸出段的端部,另一个定位耳板7位于悬挑钢梁1与结构梁板锚固位置的外侧。定位耳板7上悬挂防坠网8。The bottom of the projecting section of the cantilevered steel beam 1 is provided with two positioning lugs 7, one of which is located at the end of the projecting section of the cantilevered steel beam 1, and the other positioning lug 7 is located at the end of the projecting section of the cantilevered steel beam 1. Outside of the anchorage location to the structural beam slab. An anti-falling net 8 is hung on the positioning lug plate 7 .

如上所述,尽管参照特定的优选实施例已经表示和表述了本实用新型,但其不得解释为对本实用新型自身的限制。在不脱离所附权利要求定义的本实用新型的精神和范围前提下,可对其在形式上和细节上作出各种变化。As mentioned above, although the present invention has been shown and described with reference to specific preferred embodiments, this should not be construed as limiting the invention itself. Various changes in form and details may be made therein without departing from the spirit and scope of the present invention as defined by the appended claims.

Claims (10)

1.一种壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,包括若干根位于待施工挑檐下一层的悬挑钢梁,所述悬挑钢梁锚固在待施工挑檐下一层的结构梁板上,该层作为悬挑层,悬挑钢梁的其中一段伸出结构梁板,若干根悬挑钢梁的伸出段组成悬挑支撑,挑檐支模架搭设在该悬挑支撑上;1. a shell section large-span overhanging eaves high-altitude erecting formwork operation platform, is characterized in that, comprises several cantilevered steel beams positioned at the next floor of the overhanging eaves to be constructed, and the cantilevered steel beams are anchored at the overhanging eaves to be constructed. On the structural beam plate of the next layer, this layer is used as a cantilever layer. One section of the cantilevered steel beam extends out of the structural beam plate, and the projecting sections of several cantilevered steel beams form a cantilever support. on the overhanging support; 每个所述悬挑钢梁与结构梁板锚固位置的上方均设置有一立柱,立柱垂直于所述悬挑钢梁,且立柱的底部固定在所述悬挑钢梁上,立柱的顶部连接有至少一道钢丝拉索,所述钢丝拉索的另一端拉结在悬挑钢梁伸出段上;A column is provided above each of the cantilevered steel beams and the anchoring positions of the structural beam plates, the column is perpendicular to the cantilevered steel beam, the bottom of the column is fixed on the cantilevered steel beam, and the top of the column is connected with a At least one steel wire cable, the other end of the steel wire cable is tied on the projecting section of the cantilevered steel beam; 每个所述悬挑钢梁伸出段的底部还固定有一斜向的支撑钢杆,支撑钢杆的另一端固定在悬挑层下一层的结构边梁上。An oblique supporting steel rod is also fixed at the bottom of each overhanging section of the cantilevered steel beam, and the other end of the supporting steel rod is fixed on the structural edge beam on the lower layer of the cantilevered layer. 2.根据权利要求1所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,所述悬挑钢梁的另一段作为固定段,锚固在悬挑层的楼面上。2 . The large-span overhanging eaves high-altitude building formwork work platform according to claim 1 , wherein the other section of the cantilevered steel beam is used as a fixed section and is anchored on the floor of the cantilevered floor. 3 . 3.根据权利要求2所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,所述立柱的顶部两侧各连接有至少一道钢丝拉索,钢丝拉索的另一端分别拉结在悬挑钢梁的伸出段和固定段上。3. The shell section large-span overhanging eaves high-altitude erecting formwork working platform according to claim 2 is characterized in that, at least one wire cable is connected to each of the top two sides of the column, and the other end of the wire cable is respectively pulled Knot on the projecting section and the fixed section of the cantilevered steel beam. 4.根据权利要求3所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,所述立柱与悬挑钢梁的伸出段之间通过两道钢丝拉索拉结,两道钢丝拉索分别连接在悬挑钢梁伸出段的端部和中部。4. The shell section large-span overhanging eaves high-altitude erecting formwork work platform according to claim 3, is characterized in that, between the said upright column and the projecting section of the cantilevered steel beam, two steel wire cables are connected, and the two The steel wire cables are respectively connected to the ends and the middle of the projecting section of the cantilevered steel beams. 5.根据权利要求1~4任意一项所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,每道所述钢丝拉索上均设置有一紧绳螺栓,调节所述钢丝拉索的松紧。5. The large-span overhanging eaves high-altitude construction work platform for shell section according to any one of claims 1 to 4, is characterized in that, each described wire cable is provided with a tightening rope bolt to adjust the wire The tension of the cable. 6.根据权利要求1所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,所述悬挑钢梁伸出段的底部贴紧悬挑层边梁处设置有一个定位耳板,该定位耳板中间开有圆孔。6. The shell section large-span overhanging eaves high-altitude erecting formwork work platform according to claim 1 is characterized in that, a positioning lug is provided at the bottom of the overhanging section of the cantilevered steel beam close to the cantilevered layer side beam A circular hole is opened in the middle of the positioning lug. 7.根据权利要求6所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,在所述悬挑钢梁伸出段的端部下方设置有一个耳板,且中间开有圆孔,该耳板与所述定位耳板上悬挂防坠网。7. The shell section large-span overhanging eaves high-altitude erecting formwork working platform according to claim 6 is characterized in that, a lug plate is provided below the end of the overhanging section of the cantilevered steel beam, and there is an opening in the middle. A round hole, the lug plate and the positioning lug plate are hung with an anti-falling net. 8.根据权利要求1所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,所述悬挑支撑上还搭设有防护脚手架,防护脚手架搭设在悬挑钢梁伸出段的端部,防护脚手架的顶部高度高于待施工挑檐。8. The shell section large-span overhanging eaves high-altitude erecting formwork work platform according to claim 1, is characterized in that, on the described overhanging support, also erects protective scaffolding, and the protective scaffolding is erected on the overhanging section of the overhanging steel beam. At the end, the top height of the protective scaffolding is higher than the eaves to be constructed. 9.根据权利要求1所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,每个悬挑钢梁均通过水平连杆与相邻的悬挑钢梁连接。9 . The large-span overhanging eaves high-altitude building formwork work platform according to claim 1 , wherein each cantilevered steel beam is connected to an adjacent cantilevered steel beam through a horizontal connecting rod. 10 . 10.根据权利要求1所述的壳截面大跨度挑檐高空搭设模架作业平台,其特征在于,每个所述立柱均通过水平连杆与相邻的立柱连接。10 . The large-span overhanging eaves high-altitude construction formwork work platform according to claim 1 , wherein each of the uprights is connected to the adjacent uprights by horizontal connecting rods. 11 .
CN201921945590.XU 2019-11-12 2019-11-12 A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform Expired - Fee Related CN211736290U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921945590.XU CN211736290U (en) 2019-11-12 2019-11-12 A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921945590.XU CN211736290U (en) 2019-11-12 2019-11-12 A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform

Publications (1)

Publication Number Publication Date
CN211736290U true CN211736290U (en) 2020-10-23

Family

ID=72873388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921945590.XU Expired - Fee Related CN211736290U (en) 2019-11-12 2019-11-12 A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform

Country Status (1)

Country Link
CN (1) CN211736290U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323395A (en) * 2021-06-11 2021-08-31 中铁十二局集团建筑安装工程有限公司 Winter construction method of steel structure thick-coating type non-expansion fireproof coating
CN113482303A (en) * 2021-07-23 2021-10-08 江苏晟益建筑安装工程有限公司 High-rise building cornice construction supporting device
CN115627922A (en) * 2022-11-04 2023-01-20 中国建筑第四工程局有限公司 A cable-stayed post-anchored self-stabilizing cantilever plate installation platform
CN115961770A (en) * 2023-01-11 2023-04-14 中国电建市政建设集团有限公司 Floor type external scaffold erecting structure and method for penetrating cornices

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323395A (en) * 2021-06-11 2021-08-31 中铁十二局集团建筑安装工程有限公司 Winter construction method of steel structure thick-coating type non-expansion fireproof coating
CN113482303A (en) * 2021-07-23 2021-10-08 江苏晟益建筑安装工程有限公司 High-rise building cornice construction supporting device
CN115627922A (en) * 2022-11-04 2023-01-20 中国建筑第四工程局有限公司 A cable-stayed post-anchored self-stabilizing cantilever plate installation platform
CN115961770A (en) * 2023-01-11 2023-04-14 中国电建市政建设集团有限公司 Floor type external scaffold erecting structure and method for penetrating cornices

Similar Documents

Publication Publication Date Title
CN211736290U (en) A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform
CN208430687U (en) Self-anchored type suspended-cable structure support construction and system
CN106760529B (en) Roof steel truss sliding assembly construction platform and installation method
CN107100187B (en) Tower crane steel girder erection structure and installation method
CN101775896B (en) Rigid hanging scaffolding for installation of steel roof equipment piping
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN105298100A (en) Construction method of cantilever construction platform with ultrahigh cast-in-place flaring structure in cylindrical building
CN105442839A (en) Erecting method of cantilever structure formwork bent
CN111779248A (en) High-support formwork system and its construction method
CN107227814B (en) Sectional construction method for large cantilever concrete structure
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN103236656B (en) Column suspension type crossing structure and operating method thereof
CN112832368A (en) Quick construction process for cantilever beam at ultrahigh position
WO2023240812A1 (en) Overall construction platform structure and method for adding core tube wall body in air
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN206319597U (en) A kind of cantilever steel girder erecting device
CN213836318U (en) Bridge floor wet joint hangs mould structure
CN213204915U (en) Overweight overhanging suspended component supporting system of super high-rise residential conversion layer
CN105442840B (en) A kind of building method of supporting frame for overhanging mold plate
CN211228141U (en) A New Type of T-beam Diaphragm Construction Platform Cross Bracing
CN211622801U (en) Shallow round bin assembled bin top cover
CN112854702A (en) Large-span silo roof construction platform and erection method
CN202081639U (en) Steel truss tool type supporting structure for concrete framework industrial building templates
CN111456399A (en) A large-span cantilever support system for a corridor between high-rise units and its construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201023

CF01 Termination of patent right due to non-payment of annual fee