CN211256688U - Steel trestle integral type construction platform and steel-pipe pile positioning system - Google Patents

Steel trestle integral type construction platform and steel-pipe pile positioning system Download PDF

Info

Publication number
CN211256688U
CN211256688U CN201921813651.7U CN201921813651U CN211256688U CN 211256688 U CN211256688 U CN 211256688U CN 201921813651 U CN201921813651 U CN 201921813651U CN 211256688 U CN211256688 U CN 211256688U
Authority
CN
China
Prior art keywords
anchoring
rod
fixed
rods
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921813651.7U
Other languages
Chinese (zh)
Inventor
刘盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Wuzhou Highway Engineering Co ltd
Original Assignee
Dalian Wuzhou Highway Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Wuzhou Highway Engineering Co ltd filed Critical Dalian Wuzhou Highway Engineering Co ltd
Priority to CN201921813651.7U priority Critical patent/CN211256688U/en
Application granted granted Critical
Publication of CN211256688U publication Critical patent/CN211256688U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a steel trestle integrated construction platform and steel pipe pile positioning system, which comprises an anchoring rod, an anchoring pull rod, a diagonal draw bar, a fixed rod, a fixed cross rod, an anchoring vertical rod and a construction platform which is erected on the fixed rod in the later period; an anchoring pull rod is arranged between the anchoring rods, and the anchoring rods are fixed with the erected bailey group; an anchoring pull rod is arranged between the anchoring upright rods, and the anchoring upright rods and the anchoring rods are vertically arranged and fixed into a whole; an inclined pull rod is arranged between the anchoring vertical rod and the anchoring rod; the lower end of the anchoring vertical rod is vertical to the fixed rod and is fixed into a whole; a fixed cross rod is arranged between the fixed rods, and an inclined pull rod is arranged between the anchoring vertical rod and the fixed rods; the fixed rods and the fixed cross rods are fixed with the steel pipe piles. The utility model discloses in the work progress, can play good prevent collapsing, prevent the effect of falling to can stop the emergence of incident.

Description

Steel trestle integral type construction platform and steel-pipe pile positioning system
Technical Field
The utility model relates to a bridge construction field specifically is a system of putting up construction platform, carrying out accurate location to the steel-pipe pile to steel trestle steel-pipe pile.
Background
In bridge building construction, in cross-sea and cross-river bridge engineering, a construction trestle and a construction platform must be built for construction convenience, so that the steel trestle is widely applied. Only a safe and stable construction platform and a positioning system are erected on water, the personal safety of constructors and the accuracy of steel pipe pile construction can be guaranteed. The construction of the project is ensured to be carried out orderly, so that the economic benefit of a construction unit is maximized.
The steel pipe piles of the fixed trestle on the common construction site are fixed by ropes and are constructed by adopting a hoisting platform. The steel pipe pile is hoisted to be in place through the crane, the steel pipe pile is obliquely pulled and fixed on a fixing point through the rope, the flexible connection is achieved, the rope only has tension, the stability is poor, the influence of site factors is great, the steel pipe pile collapses in the installation process, an operation platform of an operator is unstable, the danger is high, the early protection is equal to zero, and the serious potential safety hazard exists.
SUMMERY OF THE UTILITY MODEL
In order to overcome the not enough of technical and security that the aforesaid appears, the utility model discloses a steel trestle integral type construction platform and steel-pipe pile positioning system to set up artifical construction platform on this system. The problem of the steel-pipe pile collapse accident and the personnel safety caused by the fact that operating personnel do not have stable operating platforms during the construction process is thoroughly solved, and the good protection effect is achieved.
The technical scheme of the utility model is that:
the integrated construction platform of the steel trestle and the positioning system of the steel pipe pile comprise an anchoring rod, an anchoring pull rod, a diagonal draw bar, a fixed rod, a fixed cross rod, an anchoring upright rod and a construction platform which is erected on the fixed rod at the later stage;
an anchoring pull rod is arranged between the anchoring rods, and the anchoring rods are fixed with the erected bailey group; an anchoring pull rod is arranged between the anchoring upright rods, and the anchoring upright rods and the anchoring rods are vertically arranged and fixed into a whole; an inclined pull rod is arranged between the anchoring vertical rod and the anchoring rod; the lower end of the anchoring vertical rod is vertical to the fixed rod and is fixed into a whole; a fixed cross rod is arranged between the fixed rods, and an inclined pull rod is arranged between the anchoring vertical rod and the fixed rods;
the fixed rods and the fixed cross rods are fixed with the steel pipe piles.
The anchoring vertical rod, the anchoring rod and the fixing rod are all provided with through holes, and the anchor rod penetrates through the through holes to fix the anchoring vertical rod and the anchoring vertical rod and the fixing rod into a whole.
The anchoring rod is fixed with the erected Bailey group through a bolt.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses in the work progress, can play good prevent collapsing, prevent the effect of falling to can stop the emergence of incident.
2. The utility model discloses the main supporting component of structure all adopts triangle-shaped steel part to connect, and is safe firm, at the difficult emergence of bad weather self scatter.
3. The utility model discloses simple structure, the installation of being convenient for can be according to the construction needs forward removal in proper order, labour saving and time saving.
Drawings
Fig. 1 is an axonometric view of the present invention.
Fig. 2 is a transverse sectional view of fig. 1.
Fig. 3 is a top view of fig. 1.
In the figure, 1, an anchoring rod, 2, an anchoring pull rod, 3, an anchoring point, 4, a diagonal pull rod, 5, a fixing rod, 6, a fixing cross rod, 7 and an anchoring vertical rod.
Detailed Description
As shown in fig. 1-3, the utility model comprises an anchoring rod 1, an anchoring pull rod 2, a diagonal pull rod 4, a fixed rod 5, a fixed cross rod 6, an anchoring upright rod 7 and a construction platform erected on the fixed rod 5 in the later period;
an anchoring pull rod 2 is arranged between the anchoring rods 1, and the anchoring rods 1 are fixed with the erected Bailey group; the anchoring pull rod 2 is arranged between the anchoring upright stanchions 7, and the anchoring upright stanchions 7 and the anchoring rods 1 are vertically arranged and fixed into a whole; an inclined pull rod 4 is arranged between the anchoring vertical rod 7 and the anchoring rod 1; the lower end of the anchoring upright rod 7 is vertical to the fixed rod 5 and is fixed into a whole; a fixed cross rod 6 is arranged between the fixed rods 5, and an inclined pull rod 4 is arranged between the anchoring upright rod 7 and the fixed rods 5;
the fixed rods 6 and the fixed cross rods 5 are fixed with the steel pipe piles.
The anchoring upright stanchion 7, the anchoring rod 1 and the fixing rod 5 are all provided with through holes, and the anchor rod penetrates through the through holes to fix the anchoring upright stanchion 7 and the anchoring rod 1, the anchoring upright stanchion 7 and the fixing rod 5 into a whole.
The anchoring rod 1 is fixed with the erected Bailey group through a bolt.
After the system is normally installed, a construction platform is erected on the fixed rod 6, so that a good anti-falling effect is achieved on operating personnel in the platform, and greater personal injury is prevented; and then, the steel pipe piles are effectively fixed by utilizing the positions of the fixed rods 6 and the fixed cross rods 5, so that collapse accidents are prevented. After the construction range of the construction platform is finished, the protection system can be integrally hoisted to the next construction section by using a crane for installation and use.

Claims (3)

1. Steel trestle integral type construction platform and steel-pipe pile positioning system, its characterized in that: the device comprises an anchoring rod, an anchoring pull rod, a diagonal draw bar, a fixed rod, a fixed cross bar, an anchoring upright rod and a construction platform erected on the fixed rod at the later stage; an anchoring pull rod is arranged between the anchoring rods, and the anchoring rods are fixed with the erected bailey group; an anchoring pull rod is arranged between the anchoring upright rods, and the anchoring upright rods and the anchoring rods are vertically arranged and fixed into a whole; an inclined pull rod is arranged between the anchoring vertical rod and the anchoring rod; the lower end of the anchoring vertical rod is vertical to the fixed rod and is fixed into a whole; a fixed cross rod is arranged between the fixed rods, and an inclined pull rod is arranged between the anchoring vertical rod and the fixed rods; the fixed rods and the fixed cross rods are fixed with the steel pipe piles.
2. The steel trestle integrated construction platform and steel pipe pile positioning system of claim 1, which is characterized in that: the anchoring vertical rod, the anchoring rod and the fixing rod are all provided with through holes, and the anchor rod penetrates through the through holes to fix the anchoring vertical rod and the anchoring vertical rod and the fixing rod into a whole.
3. The steel trestle integrated construction platform and steel pipe pile positioning system of claim 1, which is characterized in that: the anchoring rod is fixed with the erected Bailey group through a bolt.
CN201921813651.7U 2019-10-28 2019-10-28 Steel trestle integral type construction platform and steel-pipe pile positioning system Active CN211256688U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921813651.7U CN211256688U (en) 2019-10-28 2019-10-28 Steel trestle integral type construction platform and steel-pipe pile positioning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921813651.7U CN211256688U (en) 2019-10-28 2019-10-28 Steel trestle integral type construction platform and steel-pipe pile positioning system

Publications (1)

Publication Number Publication Date
CN211256688U true CN211256688U (en) 2020-08-14

Family

ID=71985936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921813651.7U Active CN211256688U (en) 2019-10-28 2019-10-28 Steel trestle integral type construction platform and steel-pipe pile positioning system

Country Status (1)

Country Link
CN (1) CN211256688U (en)

Similar Documents

Publication Publication Date Title
CN204098463U (en) Builder's jack
CN108643544B (en) High-altitude overhanging construction platform support system and construction method
CN107227814B (en) A kind of large cantilever concrete structure section construction method
CN103993735A (en) Support system of roof inclined beam and slab cantilever structure and construction method of support system
CN211622528U (en) Basket type outer vertical surface scaffold inclined-pulling type I-steel cantilever beam
CN113550578A (en) High-altitude overhanging structure formwork support and upper protection system construction method
CN109973112B (en) Super-large-dip-angle narrow-space tunnel anchor cable saddle gantry system and installation method thereof
CN106013774A (en) Slip-form flexible platform device suitable for assigning
CN202945798U (en) Overhanging type scaffold corner device
CN211256688U (en) Steel trestle integral type construction platform and steel-pipe pile positioning system
CN210178366U (en) Scattered cable saddle portal system of narrow space tunnel anchor of super large inclination
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN208618838U (en) A kind of safety device
CN216616802U (en) Three-layer hydraulic self-lifting construction platform for vertical shaft
CN207620384U (en) Jack device for discharging
CN216809608U (en) Wet seam template piece supporting device
CN213268820U (en) Pull rod type I-steel cantilever beam
CN205976725U (en) A face limit safety barrier for standardizing construction
CN209011132U (en) A kind of fixed foundation pit berm structure of assembled two point
CN207143751U (en) Splice pier top block Support bracket in upstriker section
CN201762664U (en) Bracket for mounting guardrail templates in bridge building
CN215212258U (en) Safe and reliable elevator shaft protection operation platform convenient to layer-by-layer turnover use
CN217998886U (en) Narrow space climbing platform
CN206091253U (en) Be suitable for irregular space's simple and easy steel bracket platform
CN110172965B (en) Sectional construction device and construction method for underground continuous wall reinforcing steel bars