CN210373951U - Building site project management board house that gives sound insulation and ventilates - Google Patents

Building site project management board house that gives sound insulation and ventilates Download PDF

Info

Publication number
CN210373951U
CN210373951U CN201921275096.7U CN201921275096U CN210373951U CN 210373951 U CN210373951 U CN 210373951U CN 201921275096 U CN201921275096 U CN 201921275096U CN 210373951 U CN210373951 U CN 210373951U
Authority
CN
China
Prior art keywords
air inlet
air
air outlet
pipeline
project management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921275096.7U
Other languages
Chinese (zh)
Inventor
李忻忻
徐向锋
张东立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jiaotong University
Original Assignee
Shandong Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jiaotong University filed Critical Shandong Jiaotong University
Priority to CN201921275096.7U priority Critical patent/CN210373951U/en
Application granted granted Critical
Publication of CN210373951U publication Critical patent/CN210373951U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a building site project management board house with sound insulation and ventilation, which is provided with an air inlet pipeline and an air outlet pipeline; the air outlet of the air inlet pipeline is arranged on the upper portion of the board room, the air inlet of the air outlet pipeline is located on the lower portion of the board room, an air inlet device is arranged on the air inlet of the air inlet pipeline, an air outlet device is arranged on the air outlet of the air outlet pipeline, the air inlet device and the air outlet device are composed of a rotating shaft, a vertical cylinder, a horizontal cylinder and a wind direction rudder, the outer port of the horizontal cylinder on the air inlet device and the wind direction rudder are respectively located on two sides of the rotating shaft, and the outer port of the horizontal cylinder on the air outlet device and the wind direction rudder. The utility model discloses a building site project management board house has realized the exchange and the circulation of the inside air of board house, has solved the problem that current board house external noise also got into thereupon when opening door and window exchange air, has also avoided flying upward of the subaerial dust of board house simultaneously, and beneficial effect is showing, is suitable for application and popularization.

Description

Building site project management board house that gives sound insulation and ventilates
Technical Field
The utility model relates to a building site board house, more specifically the saying so especially relates to a building site project management board house that gives sound insulation and ventilates.
Background
For project which takes longer time, a simple board house is usually built for engineering personnel to work and rest; for example, a certain number of board houses are constructed on the construction site for technicians and supervisors to work. Receive the influence of the parallel operation of all kinds of construction of building site, the building site environment is comparatively more abominable relatively, and noise, raise dust pollution are comparatively serious, and the board house is built again in the very near place apart from the construction area, and this just leads to the noise in the board house great relatively, if adopt the ventilation mode of opening the door, opening the window, the noise of construction operation can pass to indoor, influences staff's normal work in the board house. If the doors and the windows are closed, the ventilation in the board house is not facilitated, and the physical and psychological health of workers can be influenced if the workers are in a non-ventilated workplace for a long time.
Moreover, the area of building site place all belongs to unhardened ground, and the dust on its earth's surface are more relatively, and personnel frequently get into and out the board house and can bring the dust on ground into indoorly, lead to indoor dust more, are unfavorable for keeping clean indoor environment.
Therefore, in order to improve the working environment in the board house, by additionally installing an air conditioner, the temperature can be adjusted by the air conditioner in cold winter and hot summer, but the indoor air environment cannot be improved. Especially in spring and summer with proper temperature, if the door and window is opened, the noise will be affected by the construction operation noise, and if the door and window is closed, the indoor air environment will not be improved.
Disclosure of Invention
The utility model discloses an overcome above-mentioned technical problem's shortcoming, provide a building site project management board house that gives sound insulation and ventilates.
The utility model discloses a building site project management board house that gives sound insulation and ventilates, the board house is built on the ground, is provided with the intake stack and goes out the tuber pipe way on the board house; the method is characterized in that: the air outlet of the air inlet pipeline is arranged at the upper part of the board room, the air inlet of the air outlet pipeline is positioned at the lower part of the board room, the air inlet of the air inlet pipeline is provided with an air inlet device, the air outlet of the air outlet pipeline is provided with an air outlet device, the air inlet of the air inlet device always faces the incoming air direction, and the air outlet of the air outlet device always faces back to the incoming air direction;
the air inlet device consists of a rotating shaft, a vertical cylinder, a horizontal cylinder and an air vane, wherein the vertical cylinder is communicated with the horizontal cylinder, the upper end opening of the air inlet pipeline faces, the vertical cylinder is inserted into the upper end opening of the air inlet pipeline, a lower bearing and an upper bearing are arranged in an inner cavity at the upper part of the vertical cylinder, the rotating shaft is rotatably arranged on the lower bearing and the upper bearing in the vertical direction, and the inner wall of the vertical cylinder is fixed on the rotating shaft through a plurality of second connecting rods; the wind rudder is fixed on the vertical cylinder or the horizontal cylinder through a third connecting rod, and the outer port of the horizontal cylinder and the wind rudder are respectively positioned at two sides of the rotating shaft.
The utility model discloses a building site project management board house that gives sound insulation and ventilate, the air-out device except that the setting position of wind direction rudder all the other structures with hot blast blowpipe apparatus's homogeneous phase is the same, and the outer port of wind direction rudder and horizontal cylinder on the air-out device lies in same one side of pivot.
The utility model discloses a building site project management board house that gives sound insulation and ventilate, be connected with the horn mouth that expands outward on the outer port of horizontal cylinder.
The utility model discloses a building site project management board house that gives sound insulation and ventilate, be provided with removable filtration cotton on the air outlet of intake stack.
The utility model discloses a building site project management board house that gives sound insulation and ventilate, all be provided with the hand switch valve on the air outlet of intake stack and the air intake of air-out pipeline.
The utility model has the advantages that: the utility model discloses a building site project management board house, through setting up with the communicating intake stack in board house upper portion, with the communicating air-out pipeline in board house lower part, and set up the hot blast blowpipe apparatus towards the incoming wind direction all the time on the intake stack, set up the air-out device of the incoming wind direction all the time dorsad on the air-out pipeline, and thus, when the intake stack, the back is opened to the air-out pipeline, outside air insufflates the upper portion of board house through the intake stack, flow through the air-out pipeline of bottom again after the circulation from top to bottom in the board house, the exchange and the circulation of the inside air of board house have been realized, the problem that current board house external noise also got into thereupon when opening door and window exchange air has been solved, the board house is simultaneously also avoided flying upward of subaerial dust, beneficial effect is showing.
Furthermore, the air inlet device and the air outlet device are composed of a rotating shaft, a vertical cylinder, a horizontal cylinder and an air rudder, and the air rudder of the air inlet device and the outer port of the horizontal cylinder are arranged on two sides of the rotating shaft, so that the outer port of the horizontal cylinder always faces the incoming air direction, and external air can enter the board room through an air inlet pipeline; the outer port of the horizontal cylinder is always back to the incoming wind direction through arranging the wind rudder of the wind outlet device and the outer port of the horizontal cylinder on the same side of the rotating shaft, so that the air in the board room is discharged through the wind outlet pipeline, and the exchange of the air in the board room is realized.
Drawings
Fig. 1 is a schematic structural view of a construction site project management board room of the present invention;
fig. 2 is a partial cross-sectional view of the position of the middle air intake device of the present invention.
In the figure: 1 board house, 2 foundations, 3 air inlet pipes, 4 air outlet pipes, 5 air inlet devices, 6 air outlet devices, 7 filter cotton, 8 vertical cylinders, 9 horizontal cylinders, 10 horn mouths, 11 lower bearings, 12 upper bearings, 13 first connecting rods, 14 rotating shafts, 15 second connecting rods, 16 wind direction rudders and 17 third connecting rods.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings and examples.
As shown in fig. 1, a schematic structural diagram of a construction site project management board room of the present invention is given, a board room 1 is built on a foundation 2, an air inlet pipeline 3 and an air outlet pipeline 4 are arranged on the board room 1, and an air outlet of the air inlet pipeline 3 is arranged at an upper portion of the board room 1 and is used for introducing external air into the board room 1; the air inlet of the air outlet pipeline 4 is positioned at the lower part of the board room 1 and is used for pumping out the air inside the board room 1. The upper end of the air inlet pipeline 3 is provided with an air inlet device 5, the upper end of the air outlet pipeline 3 is provided with an air outlet device 6, an air inlet of the air inlet device 5 faces the incoming air direction all the time, and an air outlet of the air outlet device 6 faces the incoming air direction all the time.
Because the air inlet device 5 always faces to the incoming air direction, the automatic blowing of the external air into the air inlet pipeline 3 and then into the board room 1 is realized. Because the air outlet device 6 always faces back to the incoming air direction, the air in the board room 1 is extracted through the air outlet pipeline 4. Thus, under the combined action of the air inlet device 5 and the air outlet device 6, outside air is blown in through the upper part of the board room 1 and then flows out through the lower part of the board room 1, so that air exchange inside the board room 1 is realized when a door and a window are not opened, and the entrance of outside engineering operation noise is avoided; meanwhile, as the air in the board room 1 flows from top to bottom, the floating and flying of dust on the ground of the board room are avoided, and the air in the board room is ensured to be in a good state all the time.
When the outside temperature is too low or too high, in order to avoid the entering of the outside air, the air outlet of the air inlet pipeline 3 and the air inlet of the air outlet pipeline 4 are both provided with manual valves, and when air exchange is not needed, the air inlet pipeline 3 and the air outlet pipeline 4 are both closed through the manual valves. The air outlet of the air inlet pipe 3 is provided with replaceable filter cotton 7 to prevent external dust from entering.
As shown in fig. 2, the utility model discloses the local cross-sectional view at well hot blast blowpipe apparatus place position is given, shown hot blast blowpipe apparatus 5 comprises pivot 14, vertical section of thick bamboo 8, horizontal cylinder 9, horn mouth 10, lower bearing 11, upper bearing 12 and wind rudder 16, and vertical section of thick bamboo 8 is linked together and becomes 90 degrees contained angles with horizontal cylinder 9, and the outer end of horizontal cylinder 9 is connected with the horn mouth 10 that expands outward. The upper part of the air inlet pipeline 3 is vertically arranged, and the vertical cylinder 8 is inserted at the upper end of the air inlet pipeline 3. The upper bearing 12 and the lower bearing 11 are located at the central position of the upper part of the air inlet pipeline 3, the bearing seats of the upper bearing 12 and the lower bearing 11 are fixed on the inner wall of the air inlet pipeline 3 through the first connecting rod 13, and the rotating shaft 14 is arranged on the upper bearing 11 and the lower bearing 12, so that the rotating shaft 14 and the upper end of the air inlet pipeline 3 are coaxially arranged.
The upper end of the rotating shaft 14 is fixedly connected with the inner wall of the vertical cylinder 8 through a plurality of second connecting rods 15 so as to ensure that the horizontal cylinder 9 and the vertical cylinder 8 rotate together with the rotating shaft 14. Wind rudder 16 is through third connecting rod 17 and horizontal cylinder 9 fixed connection, wind rudder 16 adopts vertical flat board, wind rudder 16 and bellmouth 10 are located the both sides of pivot 14 respectively, like this, under the effect of external wind force, wind rudder 16 can be in leeward all the time and ascending, this also makes bellmouth 10 be in the upwind direction, be towards the incoming wind direction promptly, like this, external air can get into through bellmouth 10, and then blows in board room 1 through intake stack 3.
Except that the position of the wind direction rudder 16 of the air outlet device 6 is different from that of the air inlet device 5, the rest structures are the same as the air inlet device 5, the wind direction rudder and the bell mouth in the air outlet device are positioned on the same side of the rotating shaft, and thus the wind direction rudder and the bell mouth on the air outlet device 6 are both positioned in the downwind direction, namely the bell mouth on the air outlet device faces away from the incoming wind direction, so that the air in the board room 1 is extracted through the air outlet pipeline 4.

Claims (5)

1. A sound-insulation and ventilation construction site project management board house is characterized in that a board house (1) is built on a foundation (2), and an air inlet pipeline (3) and an air outlet pipeline (4) are arranged on the board house; the method is characterized in that: the air outlet of the air inlet pipeline is arranged at the upper part of the board room, the air inlet of the air outlet pipeline is positioned at the lower part of the board room, the air inlet of the air inlet pipeline is provided with an air inlet device (5), the air outlet of the air outlet pipeline is provided with an air outlet device (6), the air inlet of the air inlet device always faces the incoming air direction, and the air outlet of the air outlet device always faces away from the incoming air direction;
the air inlet device (5) consists of a rotating shaft (14), a vertical cylinder (8), a horizontal cylinder (9) and an air rudder (16), the vertical cylinder is communicated with the horizontal cylinder, an upper end opening of the air inlet pipeline (3) faces, the vertical cylinder is inserted into the upper end opening of the air inlet pipeline, a lower bearing (11) and an upper bearing (12) are arranged in an inner cavity of the upper part of the vertical cylinder, the rotating shaft is rotatably arranged on the lower bearing and the upper bearing in the vertical direction, and the inner wall of the vertical cylinder is fixed on the rotating shaft (14) through a plurality of second connecting rods (15); the wind rudder is fixed on the vertical cylinder (8) or the horizontal cylinder (9) through a third connecting rod (17), and the outer port of the horizontal cylinder and the wind rudder are respectively positioned at two sides of the rotating shaft (14).
2. The sound insulating, ventilated building site project management board room of claim 1, wherein: the air outlet device (6) has the same structure as the air inlet device (5) except the arrangement position of the wind direction rudder (16), and the wind direction rudder on the air outlet device and the outer port of the horizontal cylinder are positioned on the same side of the rotating shaft (14).
3. A sound-proofing ventilated building site project management board room of claim 1 or 2, wherein: the outer port of the horizontal cylinder (9) is connected with an outward-expanding bell mouth (10).
4. A sound-proofing ventilated building site project management board room of claim 1 or 2, wherein: and the air outlet of the air inlet pipeline (3) is provided with replaceable filter cotton (7).
5. A sound-proofing ventilated building site project management board room of claim 1 or 2, wherein: and the air outlet of the air inlet pipeline (3) and the air inlet of the air outlet pipeline (4) are both provided with manual switch valves.
CN201921275096.7U 2019-08-08 2019-08-08 Building site project management board house that gives sound insulation and ventilates Expired - Fee Related CN210373951U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921275096.7U CN210373951U (en) 2019-08-08 2019-08-08 Building site project management board house that gives sound insulation and ventilates

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921275096.7U CN210373951U (en) 2019-08-08 2019-08-08 Building site project management board house that gives sound insulation and ventilates

Publications (1)

Publication Number Publication Date
CN210373951U true CN210373951U (en) 2020-04-21

Family

ID=70249618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921275096.7U Expired - Fee Related CN210373951U (en) 2019-08-08 2019-08-08 Building site project management board house that gives sound insulation and ventilates

Country Status (1)

Country Link
CN (1) CN210373951U (en)

Similar Documents

Publication Publication Date Title
Khan et al. A review on wind driven ventilation techniques
CN101187488A (en) Double layer glass curtain aeration technology and method and structure
CN208998272U (en) A kind of ventilation systems in underground car parks system
CN205909449U (en) From conditioning air curtain system
CN201340049Y (en) Natural wind power ventilating device
Wang et al. A novel turbine ventilator with a damper regulator to adjust exhausted air for energy-saving in buildings
CN207881073U (en) A kind of space heating ventilating system
CN210373951U (en) Building site project management board house that gives sound insulation and ventilates
CN206308763U (en) A kind of public lavatory post unpowered exhaust system of formula
CN101187489A (en) Indoor aeration and cleaning equipment using natural wind power
CN205717713U (en) A kind of energy-saving ventilator for building
CN208011960U (en) A kind of ventilating system for wind and rain playground building
CN111878990A (en) Intelligent rainproof shutter system and method
CN107120774A (en) A kind of air inlet system and its installation method for residential housing
CN103363613A (en) Air feeding and exhausting device of fresh air unit for super high-rise building
CN202299064U (en) A natural ventilation building
CN201050856Y (en) Ventilation means for indoor and outdoor
CN205606822U (en) Underground garage mechanical ventilation system based on solar energy
CN211739403U (en) Building ventilation duct based on venturi effect
CN204753916U (en) Energy -conserving curtain of double -deck type of respiration of inner loop
CN101672506B (en) Novel air vent structure for crude cave house and construction process thereof
CN209588322U (en) The vertical air duct connecting structure of assembled
CN208059203U (en) A kind of intelligent fresh air system
CN101169274A (en) Modified double layer glass curtain aeration technology and method and structure
CN206859766U (en) Self ventilated type low-rise building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200421

Termination date: 20210808

CF01 Termination of patent right due to non-payment of annual fee