CN209702159U - A kind of tower crane foundation levelness regulating device - Google Patents

A kind of tower crane foundation levelness regulating device Download PDF

Info

Publication number
CN209702159U
CN209702159U CN201920470549.5U CN201920470549U CN209702159U CN 209702159 U CN209702159 U CN 209702159U CN 201920470549 U CN201920470549 U CN 201920470549U CN 209702159 U CN209702159 U CN 209702159U
Authority
CN
China
Prior art keywords
anchor slab
gusset
screw rod
regulating device
square sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920470549.5U
Other languages
Chinese (zh)
Inventor
姚萃
惠鹏
雷晶涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAANXI CONSTRUCTION MACHINERY CO Ltd
Original Assignee
SHAANXI CONSTRUCTION MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAANXI CONSTRUCTION MACHINERY CO Ltd filed Critical SHAANXI CONSTRUCTION MACHINERY CO Ltd
Priority to CN201920470549.5U priority Critical patent/CN209702159U/en
Application granted granted Critical
Publication of CN209702159U publication Critical patent/CN209702159U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a kind of tower crane foundation levelness regulating devices, the levelness regulating device includes the upper anchor slab that upper and lower horizontal distribution has and lower anchor slab, right-angled intersection gusset is provided between upper anchor slab and lower anchor slab, right-angled intersection gusset is located between the gusset of two sides, the centre bit of upper anchor slab is provided with a square sleeve, the lower end of square sleeve is weldingly fixed on anchor slab surface, the center of square sleeve offers internal thread hole, the lower section of adjusting screw rod is screw rod section, the screw rod section screws in downwards in above-mentioned internal thread hole, the upper end of adjusting screw rod forms an expanded letter portion;Compared to the prior art, it originally has the following technical effect that (A) is adjusted by high-strength bolt, ensure that the precision of base water Pingdu;(B) steel construction load-bearing is relied on, and larger with bed course base surface, guarantees not generating sedimentation under fixed supporting leg Gravitative Loads;(C) this regulating device makes in warehouse in advance, and construction site can be used directly, and work efficiency significantly improves.

Description

A kind of tower crane foundation levelness regulating device
Technical field
The utility model relates to the technical field of derrick crane, especially a kind of tower crane foundation levelness is adjusted Device, in particular to its mechanical connecting structure.
Background technique
The levelness of tower crane foundation be its installation, jacking and attachment most basic guarantee, and required precision Within 1/1000 (permissible value about 0-2mm), if it does not meet the requirements, will lead to equipment can not install base water Pingdu, and basis needs Remake or increase conversion equipment.
The defect and deficiency of the prior art:
1. site operation mostly uses steel reinforcing, degree of regulation is inadequate, is easy to exceed base water Pingdu allowed band;
2. the reinforcing bar of sole plate lower part may be made to deform due to the influence of basis self weight, sedimentation is generated;
3. work efficiency is lower due to needing in-site measurement size and positioning using steel reinforcing.
Utility model content
The purpose of this utility model is to provide a kind of tower crane foundation levelness regulating devices, to solve tower crane base Levelness problem in plinth manufacturing process.Overcome defect and deficiency existing in the prior art.
To achieve the goals above, a kind of the technical solution of the utility model are as follows: tower crane foundation levelness adjusting Device, the levelness regulating device includes the upper anchor slab that upper and lower horizontal distribution has and lower anchor slab, between upper anchor slab and lower anchor slab The vertical gusset being parallel to each other equipped with two panels, the upper limb of gusset and upper anchor slab are fixedly welded and are distributed perpendicular to upper anchor slab, gusset Lower edge and lower anchor slab be fixedly welded and perpendicular to lower anchor slab be distributed, be provided with right-angled intersection muscle between upper anchor slab and lower anchor slab Plate, right-angled intersection gusset are located between the gusset of two sides, and the centre bit of upper anchor slab is provided with a square sleeve, square sleeve Lower end is weldingly fixed on anchor slab surface, and the center of square sleeve offers internal thread hole, and the lower section of adjusting screw rod is screw rod section, The screw rod section screws in downwards in above-mentioned internal thread hole, and the upper end of adjusting screw rod forms an expanded letter portion.
The utility model discloses a kind of tower crane foundation levelness regulating devices, compared to the prior art, this tool There is following technical effect:
(A) it is adjusted by high-strength bolt, ensure that the precision of base water Pingdu;
(B) steel construction load-bearing is relied on, and larger with bed course base surface, it is heavy to guarantee not generating under fixed supporting leg Gravitative Loads Drop;
(C) this regulating device makes in warehouse in advance, and construction site can be used directly, and work efficiency significantly improves;
(D) derrick crane to same model is, it can be achieved that batch production.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model.
Fig. 2 is the utility model top view.
Fig. 3 is the utility model usage state diagram.
Specific embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described Embodiment is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, originally Field those of ordinary skill every other embodiment obtained without making creative work belongs to practical Novel protected range.
The utility model discloses a kind of tower crane foundation levelness regulating devices to be different from as shown in fig. 1 The prior art is: the levelness regulating device includes the upper anchor slab 1 that upper and lower horizontal distribution has and lower anchor slab 2, upper 1 He of anchor slab The gusset 3 that two panels is parallel to each other vertically is equipped between lower anchor slab 2, the upper limb of gusset 3 is fixedly welded and with upper anchor slab 1 perpendicular to upper Anchor slab 1 is distributed, and the lower edge of gusset 3 and lower anchor slab 2 are fixedly welded and are distributed perpendicular to lower anchor slab 2, upper anchor slab 1 and lower anchor slab 2 it Between be provided with right-angled intersection gusset 4, right-angled intersection gusset 4 is located between the gusset 3 of two sides, and the centre bit of upper anchor slab 1 is provided with One square sleeve 8, the lower end of square sleeve 8 are weldingly fixed on 1 surface of anchor slab, and the center of square sleeve 8 offers interior spiral shell The lower section of pit 5, adjusting screw rod 6 is screw rod section, which screws in downwards in above-mentioned internal thread hole 5, the upper end of adjusting screw rod 6 Form an expanded letter portion 7.
In the specific implementation, a hole for injecting glue is offered on the side wall of square sleeve 8, after adjusting screw rod 6 is adjusted in place External injecting glue can be carried out, adjusting screw rod 6 and square sleeve 8 are fixed to each other, prevents adjusting screw rod 6 from welding with fixed supporting leg 9 It is displaced in the process
The present apparatus carries out levelness adjusting using high-strength bolt, and can ensure that the levelness of four fixed supporting legs is no more than allows Value.
The present apparatus is welded into half box-structure using steel plate, can be within 1.0 tons of load-bearing, and the substance of fixed supporting leg is no more than 0.5 ton.
For the present apparatus according to the height and basic drawing of tower crane supporting leg in back court batch machining, the adjustable extent of screw rod is 0- Error within 50mm, live 50mm is adjustable, eliminates the time of in-site measurement and blanking, improves work efficiency.
In use process the following steps are included:
(1) first according to the foundation location of derrick crane, four levelness is successively adjusted into auxiliary device and are placed on basis Immediately below fixed supporting leg;
(2) successively four fixed supporting legs of tower crane and the integral hoisting of foundation location frame are placed in the present apparatus;
(3) levelness for measuring four fixed supporting legs respectively with level meter adjusts the screw rod of the present apparatus according to measurement result, The levelness of four fixed supporting legs 9 is set to reach allowed band.
The positioning and reinforcing of fixed supporting leg:
A. the levelness for measuring four fixed supporting leg base surfaces will fix if levelness meets 1/1000 regulation The upper end of supporting leg and the adjusting screw rod of the present apparatus 6 forms 7 reinforcement of weld of an expanded letter portion;
B. if levelness is unsatisfactory for 1/1000, according to measured value, with one relatively highest in four fixed supporting legs On the basis of point, with spanner slightly rotate adjust screw rod, other three fixed supporting legs are successively turned up to same datum level, measure again The levelness of four fixed supporting legs, if meeting can reinforce according to A method;
C. it if do not met still, is readjusted according to the step of B, until the levelness of four fixed supporting legs meets 1/1000 After it is required that, just it can be reinforced.
It, cannot the above content is specific preferred embodiment further detailed description of the utility model is combined Assert that the utility model specific implementation is confined to these above-mentioned explanations.For the common skill of the utility model technical field For art personnel, without departing from the concept of the premise utility, a number of simple deductions or replacements can also be made, all should It is considered as belonging to the protection scope of the utility model.

Claims (1)

1. a kind of tower crane foundation levelness regulating device, it is characterised in that: the levelness regulating device includes up and down The upper anchor slab (1) and lower anchor slab (2) that horizontal distribution has, are vertically parallel to each other equipped with two panels between upper anchor slab (1) and lower anchor slab (2) Gusset (3), the upper limb of gusset (3) and upper anchor slab (1) are fixedly welded and are distributed perpendicular to upper anchor slab (1), the lower edge of gusset (3) It is fixedly welded with lower anchor slab (2) and is distributed perpendicular to lower anchor slab (2), cross friendship is provided between upper anchor slab (1) and lower anchor slab (2) It pitches gusset (4), right-angled intersection gusset (4) is located between the gusset (3) of two sides, and the centre bit of upper anchor slab (1) is provided with a side Shape sleeve (8), the lower end of square sleeve (8) are weldingly fixed on anchor slab (1) surface, and the center of square sleeve (8) offers interior Threaded hole (5), the lower section of adjusting screw rod (6) are screw rod section, which screws in downwards in above-mentioned internal thread hole (5), adjust spiral shell The upper end of bar (6) forms an expanded letter portion (7).
CN201920470549.5U 2019-04-09 2019-04-09 A kind of tower crane foundation levelness regulating device Expired - Fee Related CN209702159U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920470549.5U CN209702159U (en) 2019-04-09 2019-04-09 A kind of tower crane foundation levelness regulating device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920470549.5U CN209702159U (en) 2019-04-09 2019-04-09 A kind of tower crane foundation levelness regulating device

Publications (1)

Publication Number Publication Date
CN209702159U true CN209702159U (en) 2019-11-29

Family

ID=68649103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920470549.5U Expired - Fee Related CN209702159U (en) 2019-04-09 2019-04-09 A kind of tower crane foundation levelness regulating device

Country Status (1)

Country Link
CN (1) CN209702159U (en)

Similar Documents

Publication Publication Date Title
CN106006404A (en) Super-high-rise external movable arm tower crane climbing supporting device
CN108343163A (en) Steel column butt joint adjusts fixing device and method
CN202073323U (en) Supporting frame for regulating installing horizontality of embedded part
CN104032969A (en) Precise positioning and process regulation and control device for vibration isolation support embedded plate
CN111424674A (en) Foundation pit reverse construction method steel pipe structure column butt joint platform and butt joint method
CN211113707U (en) Embedded positioning device for foundation bolt
CN209702159U (en) A kind of tower crane foundation levelness regulating device
CN202181511U (en) Device for adjusting and dismantling pier coping beam template
CN203238967U (en) Large steel structure frame whole lifting device
CN206707266U (en) Plastic formwork early removing system
CN205933000U (en) External swing arm tower crane in superelevation layer strutting arrangement that climbs
CN105480842B (en) Equipment support beam and its construction method are poured after one kind
CN211080288U (en) Adjusting device for mounting anchor bolt cage of wind driven generator
CN111636696A (en) Accurate adjustment support of concrete built-in fitting
CN211948530U (en) Positioning device for embedding foundation bolt
CN210395423U (en) Tower machine basis installation positioner
CN208361753U (en) A kind of tower crane supporting leg anchoring pre-buried structure and tower crane
CN210268621U (en) Adjustable anti-loss foundation anchor rod
CN212984674U (en) Accurate adjustment support of concrete built-in fitting
CN206828925U (en) A kind of adjustable road construction side shaper
CN219158410U (en) Unloading plate bottom die supporting device
CN212641466U (en) Foundation ditch reverse construction method steel tubular construction post butt joint platform
CN210828396U (en) Supporting system for installing prefabricated wallboard
CN219161316U (en) Multifunctional detection equipment for house building construction
CN220767724U (en) Cable-stayed bridge steel anchor box base positioning device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191129

CF01 Termination of patent right due to non-payment of annual fee