CN104032969A - Precise positioning and process regulation and control device for vibration isolation support embedded plate - Google Patents

Precise positioning and process regulation and control device for vibration isolation support embedded plate Download PDF

Info

Publication number
CN104032969A
CN104032969A CN201410298921.0A CN201410298921A CN104032969A CN 104032969 A CN104032969 A CN 104032969A CN 201410298921 A CN201410298921 A CN 201410298921A CN 104032969 A CN104032969 A CN 104032969A
Authority
CN
China
Prior art keywords
positioning
embedded plate
seismic isolation
isolation support
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410298921.0A
Other languages
Chinese (zh)
Inventor
赵云鹏
汪再红
向小青
朱彤
杨桃
陈敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201410298921.0A priority Critical patent/CN104032969A/en
Publication of CN104032969A publication Critical patent/CN104032969A/en
Pending legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

本发明公开了一种隔震支座预埋板精确定位及过程调控装置,包括隔震支座预埋板(1),其特征是:还包括竖向标高调节器、水平定位调节器;所述竖向标高调节器包括定位钢筋(4)、丝扣(5)、螺帽(6)、套管(7)、角钢(8);所述定位钢筋(4)顶部车丝为丝扣(5);所述螺帽(6)套于所述丝扣(5)上;所述套管(7)套于所述螺帽(6)上,并与所述角钢(8)固定连接(焊接);所述水平定位调节器包括短钢筋(9)、套筒(10),所述套筒(10)设于所述短钢筋(9)端部车丝段。本发明装置操作简单,投入少,能避免因预埋件体量大造成的操作困难,能有效保证预埋板安装及浇筑过程中的精确定位和标高控制,确保隔震支座预埋板的施工质量。

The invention discloses a precise positioning and process control device for a pre-embedded plate of a shock-isolation support, which comprises a pre-embedded plate (1) of a shock-isolation support, and is characterized in that it also includes a vertical elevation adjuster and a horizontal positioning adjuster; Described vertical elevation adjuster comprises positioning reinforcing bar (4), threaded button (5), nut (6), sleeve pipe (7), angle steel (8); Described positioning reinforcing bar (4) top car wire is threaded button ( 5); the nut (6) is placed on the threaded button (5); the sleeve (7) is placed on the nut (6), and fixedly connected with the angle steel (8) ( Welding); the horizontal positioning regulator includes a short steel bar (9), a sleeve (10), and the sleeve (10) is located at the end of the short steel bar (9) in the wire section. The device of the present invention is easy to operate, requires less investment, can avoid operational difficulties caused by the large volume of embedded parts, can effectively ensure the precise positioning and elevation control of the embedded slab installation and pouring process, and ensure the stability of the embedded slab of the seismic isolation support. Construction Quality.

Description

一种隔震支座预埋板精确定位及过程调控装置Precise positioning and process control device for pre-buried plate of seismic isolation support

技术领域technical field

本发明涉及一种抗震建筑施工用的定位及调控装置,尤其涉及一种隔震支座预埋板精确定位及过程调控装置,特别涉及一种橡胶隔震支座预埋板精确定位及过程调控装置。The invention relates to a positioning and control device for earthquake-resistant building construction, in particular to a precise positioning and process control device for a pre-buried plate of a shock-isolation bearing, in particular to a precise positioning and process control of a pre-buried plate of a rubber shock-isolation support device.

背景技术Background technique

在抗震要求高的地区和有特殊功能的结构中,通过在建筑物底部和基础之间设置结构隔震层及隔震支座,改变结构的动力特性和动力作用,减轻结构物的地震反应,来提高建筑物防震、抗震等级,确保结构在罕遇地震下的结构安全。通过工程实例分析,发明人发现隔震支座下预埋钢板的预埋过程中存在以下问题:隔震支座安装精度要求高,水平定位及标高控制难度大;隔震支座预埋板体量大,普通设备无法满足吊装定位精度要求,独立柱基的立筋与钢筋较密,人工操作极为不便;下部钢筋笼的加固、混凝土振捣易造成预埋板的偏位;因此,做好预埋板安装及浇筑过程中的水平定位及标高控制将直接影响隔震层的隔震效果乃至整体结构的安全稳定。In areas with high seismic requirements and structures with special functions, by setting a structural isolation layer and isolation support between the bottom of the building and the foundation, the dynamic characteristics and dynamic effects of the structure can be changed, and the seismic response of the structure can be reduced. To improve the earthquake resistance and earthquake resistance level of buildings, and ensure the structural safety of structures under rare earthquakes. Through the analysis of engineering examples, the inventor found that the following problems existed in the pre-embedding process of the pre-embedded steel plate under the seismic isolation support: the installation accuracy of the seismic isolation support is high, and the horizontal positioning and elevation control are difficult; the pre-embedded plate of the seismic isolation support The amount is large, and ordinary equipment cannot meet the hoisting and positioning accuracy requirements. The vertical bars and steel bars of the independent column base are relatively dense, and manual operation is extremely inconvenient; the reinforcement of the lower steel cage and the vibration of the concrete may easily cause the deviation of the embedded slab; therefore, do a good job The horizontal positioning and elevation control during the installation and pouring of the embedded slab will directly affect the isolation effect of the isolation layer and even the safety and stability of the overall structure.

发明内容Contents of the invention

本发明所要解决的技术问题提供一种抗震建筑施工用的定位及调控装置,尤其提供一种隔震支座预埋板精确定位及过程调控装置,特别提供一种橡胶隔震支座预埋板精确定位及过程调控装置,克服了现有技术中水平定位及标高控制存在的问题,提高了建筑结构隔震层的隔震效果,使整体结构安全稳定。The technical problem to be solved by the present invention is to provide a positioning and control device for earthquake-resistant building construction, especially to provide a precise positioning and process control device for the embedded plate of seismic isolation bearing, especially to provide an embedded plate for rubber seismic isolation bearing The precise positioning and process control device overcomes the problems of horizontal positioning and elevation control in the prior art, improves the seismic isolation effect of the seismic isolation layer of the building structure, and makes the overall structure safe and stable.

本发明所要解决的技术问题是通过以下技术方案来实现的:The technical problem to be solved by the present invention is achieved through the following technical solutions:

一种隔震支座预埋板精确定位及过程调控装置,包括隔震支座预埋板,其特征是:还包括竖向标高调节器、与所述竖向标高调节器配合使用的水平定位调节器;所述竖向标高调节器包括定位钢筋、丝扣、螺帽、套管、角钢;所述定位钢筋顶部车丝为丝扣;所述螺帽套于所述丝扣上;所述套管套于所述螺帽上,并与所述角钢固定连接,如,焊接等,所述螺帽用于调节所述套管高度,以实现调节所述预埋板标高;A device for precise positioning and process control of a pre-embedded plate for a seismic isolation support, including a pre-embedded plate for a seismic isolation support, characterized in that it also includes a vertical height adjuster, and a horizontal positioning device used in conjunction with the vertical height adjuster Regulator; the vertical level regulator includes positioning steel bars, threaded buckles, nuts, casings, and angle steel; the top of the positioning steel bar is threaded to be threaded; the nut is placed on the threaded buckles; The casing is put on the nut and fixedly connected with the angle steel, such as welding, etc., and the nut is used to adjust the height of the casing, so as to adjust the elevation of the embedded plate;

所述水平定位调节器包括短钢筋、套筒,所述套筒设于所述短钢筋端部车丝段。The horizontal positioning adjuster includes a short steel bar and a sleeve, and the sleeve is arranged on the end of the short steel bar to be threaded.

所述预埋板设有螺栓孔,用于安装所述隔震支座,底面设有锚筋(2),以确保预埋板与独立基础形成有效锚固。The pre-embedded plate is provided with bolt holes for installing the seismic isolation support, and the bottom surface is provided with anchor bars (2) to ensure effective anchorage between the pre-embedded plate and the independent foundation.

所述定位钢筋为L形,使所述装置稳固。The positioning steel bars are L-shaped to make the device stable.

所述定位钢筋下设有支撑加固钢筋,用于增强定位钢筋的竖向稳定性。A supporting reinforcing bar is provided under the positioning reinforcing bar to enhance the vertical stability of the positioning reinforcing bar.

所述预埋板埋入待浇筑的独立柱基中。The embedded slab is embedded in the independent column base to be poured.

所述定位钢筋与独立柱基的面筋和底筋点焊牢固。The positioning reinforcement is firmly spot-welded with the gluten and bottom reinforcement of the independent column base.

所述水平定位调节器位于所述独立柱基边缘的面筋与模板之间;所述短钢筋未车丝段与所述独立柱基的面筋焊接;所述套筒端抵紧所述独立柱基(12)的模板。The horizontal positioning regulator is located between the gluten on the edge of the independent column base and the template; the unthreaded section of the short steel bar is welded to the gluten of the independent column base; the sleeve end is pressed against the independent column base (12) template.

所述定位钢筋与独立基础的面筋和底筋点焊牢固。The positioning reinforcement is firmly spot-welded with the gluten and bottom reinforcement of the independent foundation.

所述定位钢筋优选为直径18mm的钢筋等优级产品,顶部车丝20cm形成丝扣。The positioning steel bars are preferably high-grade products such as steel bars with a diameter of 18 mm, and the top is threaded at 20 cm to form a threaded buckle.

所述预埋板可选为20mm厚的镀锌圆钢板等优级产品;所述角钢为30mm*30mm*3mm等边角钢,用于支撑隔震支座预埋板。The pre-embedded board can be selected as high-quality products such as 20mm thick galvanized round steel plate; the angle steel is 30mm*30mm*3mm equilateral angle steel, which is used to support the pre-embedded board of the seismic isolation support.

本发明隔震支座预埋板精确定位及过程调控装置采用上述技术方案,与现有技术相比具有以下有益效果:The precise positioning and process control device of the pre-embedded plate of the seismic isolation support of the present invention adopts the above-mentioned technical scheme, and has the following beneficial effects compared with the prior art:

1.本发明装置的竖向标高调节器可通过螺帽对预埋板标高进行动态调节,水平定位调节器可随时对预埋板水平定位进行复核修正,以保证所述预埋板的板面标高和水平定位符合设计及规范要求。1. The vertical elevation adjuster of the device of the present invention can dynamically adjust the elevation of the embedded slab through the nut, and the horizontal positioning adjuster can check and correct the horizontal positioning of the embedded slab at any time to ensure the surface of the embedded slab Elevation and horizontal positioning meet design and specification requirements.

2.本发明装置操作简单,投入少,能避免因预埋件体量大造成的操作困难,能有效保证预埋板安装及浇筑过程中的精确定位和标高控制,确保隔震支座预埋板的施工质量。2. The device of the present invention is easy to operate, requires less investment, can avoid operational difficulties caused by the large volume of embedded parts, can effectively ensure the precise positioning and elevation control of the embedded slab installation and pouring process, and ensure that the seismic isolation support is embedded Board construction quality.

3.本发明装置特别适用于精度要求高、过程控制难的重型、大型预埋件安装定位及调控,也适用于普通预埋件安装定位及调控。3. The device of the present invention is especially suitable for the installation, positioning and regulation of heavy and large embedded parts with high precision requirements and difficult process control, and is also suitable for the installation, positioning and regulation of ordinary embedded parts.

附图说明Description of drawings

图1为本发明安装定位结构示意图Fig. 1 is a schematic diagram of the installation and positioning structure of the present invention

图2-1为本发明预埋板结构示意图Figure 2-1 is a schematic diagram of the structure of the embedded board of the present invention

图2-2为图1的A-A视图Figure 2-2 is the A-A view of Figure 1

图3为本发明竖向标高调节器结构示意图Fig. 3 is a structural schematic diagram of the vertical level adjuster of the present invention

图4为本发明水平定位调节器结构示意图Fig. 4 is a structural schematic diagram of the horizontal positioning regulator of the present invention

图5-1为本发明在独立柱基加固平面结构示意图Figure 5-1 is a schematic diagram of the plane structure reinforced by the independent column base of the present invention

图5-2为本发明在独立柱基加固立面结构示意图Fig. 5-2 is the schematic diagram of the facade structure reinforced by the independent column foundation of the present invention

图中所示,1-预埋板,2-锚筋,3-螺栓孔,4-定位钢筋,5-丝扣,6-螺帽,7-套管,8-角钢,9-短钢筋,10-套筒,11-支撑加固钢筋,12-待浇筑独立柱基,13-模板,14-面筋,15-底筋。As shown in the figure, 1-embedded plate, 2-anchor bar, 3-bolt hole, 4-positioning steel bar, 5-screw, 6-nut, 7-sleeve, 8-angle steel, 9-short steel bar, 10-sleeve, 11-support reinforcement, 12-independent column foundation to be poured, 13-formwork, 14-gluten bar, 15-bottom bar.

具体实施方式Detailed ways

参见图1、图2-1、图2-2、图3、图4所示的一种隔震支座预埋板精确定位及过程调控装置,包括加工成型的预埋板1、竖向标高调节器、水平定位调节器;所述预埋板为镀锌圆钢板,预埋板1底面设有带弯钩的锚筋2,锚入独立柱基内;所述的竖向标高调节器安装在定位钢筋4车丝段,由螺帽6、套管7及角钢8组成;所述的水平定位调节器由短钢筋9和套筒10组成,短钢筋9的车丝段用于安装套筒10,未车丝段与独立柱基面筋焊接牢固;所述定位钢筋4为L形钢筋,顶端20cm车丝,点焊在独立柱基面筋和底筋上,下设支撑加固钢筋11用于加固定位钢筋4;所述螺帽6安装在丝扣5上,所述套管7套于螺帽6之上,所述角钢8与套管7焊接牢固。Refer to Fig. 1, Fig. 2-1, Fig. 2-2, Fig. 3 and Fig. 4 for a precise positioning and process control device for the pre-embedded plate of the seismic isolation bearing, including the pre-embedded plate processed and formed 1, the vertical elevation regulator, horizontal positioning regulator; the embedded plate is a galvanized round steel plate, and the bottom surface of the embedded plate 1 is provided with an anchor bar 2 with a hook, which is anchored into an independent column base; the vertical elevation adjuster is installed In the wire section of positioning steel bar 4, it is made up of nut 6, sleeve pipe 7 and angle steel 8; described horizontal positioning regulator is made up of short steel bar 9 and sleeve 10, and the wire section of short steel bar 9 is used for installing sleeve 10. The unthreaded section is firmly welded to the independent column base gluten; the positioning steel bar 4 is an L-shaped steel bar, the top 20 cm of wire is spot-welded on the independent column base gluten and the bottom bar, and the supporting reinforcement bar 11 is set up for reinforcement Locating the reinforcing bar 4; the nut 6 is installed on the threaded buckle 5, the sleeve 7 is set on the nut 6, and the angle steel 8 and the sleeve 7 are welded firmly.

具体实施工程如下:The specific implementation project is as follows:

通过测量定位,在预埋板1安装位置点焊4根定位钢筋4,并在定位钢筋4的丝扣5上安装螺帽6和套管7,安装套管7前预先将角钢8焊接在套管7上。Through measurement and positioning, spot weld four positioning steel bars 4 at the installation position of the embedded plate 1, and install nuts 6 and sleeves 7 on the threaded buckles 5 of the positioning steel bars 4, and weld the angle steel 8 on the sleeves before installing the sleeves 7. on tube 7.

然后将预埋钢板1置于角钢8上,通过微调螺帽6精确调整预埋板1竖向标高;利用水平尺复核预埋板1的平整度,利用水准仪复核预埋板1的标高,根据复核结果调整后再次复核,直到预埋板1平整度和标高满足要求。Then place the embedded steel plate 1 on the angle steel 8, and adjust the vertical elevation of the embedded plate 1 accurately through the fine-tuning nut 6; check the flatness of the embedded plate 1 with a level ruler, and check the elevation of the embedded plate 1 with a level gauge, according to After the review results are adjusted, review again until the flatness and elevation of the embedded slab 1 meet the requirements.

预埋板1安装到位后,在定位钢筋4上分别点焊支撑加固钢筋11。After the pre-embedded plate 1 is installed in place, spot-weld the supporting reinforcing bars 11 on the positioning reinforcing bars 4 respectively.

模板封闭前,将短钢筋9焊接到独立柱基边缘的面筋上,焊接前预先将套筒10安装到短钢筋9上,独立柱基的模板封闭后,在全站仪的实时监控下,通过微调套筒10带动独立柱基钢筋笼微移,使预埋板1的水平定位满足要求。Before the template is closed, the short steel bar 9 is welded to the gluten on the edge of the independent column base, and the sleeve 10 is pre-installed on the short steel bar 9 before welding. The fine-tuning sleeve 10 drives the independent column base reinforcement cage to move slightly, so that the horizontal positioning of the embedded plate 1 meets the requirements.

Claims (10)

1.一种隔震支座预埋板精确定位及过程调控装置,包括隔震支座预埋板(1),其特征是:还包括竖向标高调节器、与所述竖向标高调节器配合使用的水平定位调节器;所述竖向标高调节器包括定位钢筋(4)、丝扣(5)、螺帽(6)、套管(7)、角钢(8);所述定位钢筋(4)顶部车丝为丝扣(5);所述螺帽(6)套于所述丝扣(5)上;所述套管(7)套于所述螺帽(6)上,并与所述角钢(8)固定连接;1. A device for precise positioning and process control of a pre-embedded plate of a seismic isolation support, comprising a pre-embedded plate of a seismic isolation support (1), characterized in that: it also includes a vertical elevation regulator, and the vertical elevation regulator The horizontal positioning adjuster used in conjunction with it; the vertical elevation adjuster includes a positioning reinforcement (4), a threaded button (5), a nut (6), a casing (7), and an angle steel (8); the positioning reinforcement ( 4) The top thread is a threaded button (5); the nut (6) is placed on the threaded button (5); the sleeve (7) is placed on the nut (6), and The angle steel (8) is fixedly connected; 所述水平定位调节器包括短钢筋(9)、套筒(10),所述套筒(10)设于所述短钢筋(9)端部车丝段。The horizontal positioning adjuster includes a short steel bar (9) and a sleeve (10), and the sleeve (10) is arranged on the threaded section at the end of the short steel bar (9). 2.根据权利要求1所述的隔震支座预埋板精确定位及过程调控装置,其特征是:所述预埋板(1)上设有螺栓孔(3),底面设有锚筋(2)。2. The precise positioning and process control device for the pre-embedded plate of the seismic isolation support according to claim 1, characterized in that: the pre-embedded plate (1) is provided with bolt holes (3), and the bottom surface is provided with anchor bars ( 2). 3.根据权利要求1或2所述的隔震支座预埋板精确定位及过程调控装置,其特征是:所述定位钢筋(4)为L形(使所述装置更加稳固)。3. The device for precise positioning and process control of the pre-embedded plate of the seismic isolation support according to claim 1 or 2, characterized in that: the positioning reinforcement (4) is L-shaped (making the device more stable). 4.根据权利要求1所述的隔震支座预埋板精确定位及过程调控装置,其特征是:所述定位钢筋(4)下设有支撑加固钢筋(11)。4. The precise positioning and process control device for the pre-embedded plate of the seismic isolation support according to claim 1, characterized in that: the positioning reinforcement (4) is provided with a supporting reinforcement reinforcement (11). 5.根据权利要求1的隔震支座预埋板精确定位及过程调控装置,其特征是:所述预埋板(1)埋入待浇筑砼的独立柱基(12)中。5. The device for precise positioning and process control of the pre-embedded plate of the seismic isolation support according to claim 1, characterized in that: the pre-embedded plate (1) is embedded in the independent column base (12) to be poured. 6.根据权利要求1的隔震支座预埋板精确定位及过程调控装置,其特征是:所述定位钢筋(4)与独立柱基的面筋(14)和底筋(15)点焊牢固。6. The precise positioning and process control device for the pre-embedded plate of the seismic isolation bearing according to claim 1, characterized in that: the positioning reinforcement (4) is firmly spot-welded with the gluten (14) and bottom reinforcement (15) of the independent column base . 7.根据权利要求1的隔震支座预埋板精确定位及过程调控装置,其特征是:所述水平定位调节器位于所述独立柱基(12)与模板(13)之间;所述短钢筋(9)未车丝段与所述独立柱基(12)的面筋(14)焊接;所述套筒(10)端抵紧所述独立柱基(12)的模板(13)。7. The precise positioning and process control device for the embedded plate of the seismic isolation support according to claim 1, characterized in that: the horizontal positioning regulator is located between the independent column base (12) and the formwork (13); The unwired section of the short steel bar (9) is welded to the gluten (14) of the independent column base (12); the end of the sleeve (10) presses against the formwork (13) of the independent column base (12). 8.根据权利要求1的隔震支座预埋板精确定位及过程调控装置,其特征是:所述定位钢筋(4)与独立基础(12)的面筋(14)和底筋(15)点焊牢固。8. The precise positioning and process control device for the pre-embedded plate of the seismic isolation bearing according to claim 1, characterized in that: the positioning reinforcement (4) and the gluten (14) and bottom reinforcement (15) points of the independent foundation (12) Weld firmly. 9.根据权利要求1所述的隔震支座预埋板精确定位及过程调控装置,其特征是:所述定位钢筋(4)直径为18mm的钢筋,顶部车丝20cm形成丝扣(5)。9. The precise positioning and process control device for the pre-embedded plate of the seismic isolation support according to claim 1, characterized in that: the positioning steel bar (4) is a steel bar with a diameter of 18 mm, and the top is threaded at 20 cm to form a threaded buckle (5) . 10.根据权利要求1所述的隔震支座预埋板精确定位及过程调控装置,其特征是:所述预埋板(1)为20mm厚的镀锌圆钢板;所述角钢(8)为30mm*30mm*3mm等边角钢,用于支撑隔震支座预埋板(1)。10. The precise positioning and process control device for the embedded plate of the seismic isolation support according to claim 1, characterized in that: the embedded plate (1) is a galvanized round steel plate with a thickness of 20mm; the angle steel (8) It is 30mm*30mm*3mm equilateral angle steel, which is used to support the pre-embedded plate (1) of the seismic isolation bearing.
CN201410298921.0A 2014-06-27 2014-06-27 Precise positioning and process regulation and control device for vibration isolation support embedded plate Pending CN104032969A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410298921.0A CN104032969A (en) 2014-06-27 2014-06-27 Precise positioning and process regulation and control device for vibration isolation support embedded plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410298921.0A CN104032969A (en) 2014-06-27 2014-06-27 Precise positioning and process regulation and control device for vibration isolation support embedded plate

Publications (1)

Publication Number Publication Date
CN104032969A true CN104032969A (en) 2014-09-10

Family

ID=51463941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410298921.0A Pending CN104032969A (en) 2014-06-27 2014-06-27 Precise positioning and process regulation and control device for vibration isolation support embedded plate

Country Status (1)

Country Link
CN (1) CN104032969A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895319A (en) * 2015-05-11 2015-09-09 中国十七冶集团有限公司 Cast-in-place concrete shear wall and frame column template installation elevation positioning device
CN105256894A (en) * 2015-10-23 2016-01-20 中国十七冶集团有限公司 Construction method for precisely mounting embedded bolt sleeves of seismic isolation and reduction support
CN105350654A (en) * 2015-11-13 2016-02-24 中国水利水电第十四工程局有限公司 Construction method for adjusting steel plate embedded parts to reach design and construction accuracy
CN105386531A (en) * 2015-12-01 2016-03-09 中国建筑第八工程局有限公司 Locating device used between buttress and vibration insulation support and construction method thereof
CN108487650A (en) * 2018-03-28 2018-09-04 中国建筑第八工程局有限公司 The installation method of pre-buried board mounting structure and lower embedded board under shock isolating pedestal
CN112030771A (en) * 2020-09-10 2020-12-04 中建三局集团有限公司 A device for installing embedded parts of seismic isolation bearings and construction method thereof
CN113832842A (en) * 2021-10-18 2021-12-24 中电建十一局工程有限公司 A ball bearing leveling device and a bearing installation and leveling method
CN114150859A (en) * 2021-09-26 2022-03-08 中建三局集团有限公司 A kind of cantilever frame I-beam precise positioning, anchoring and laying construction method
CN116717092A (en) * 2023-06-07 2023-09-08 中建-大成建筑有限责任公司 A flatness and position adjustment device and method for installing isolation bearings
CN120738956A (en) * 2025-09-01 2025-10-03 烟建集团有限公司 High-precision installation construction device for super-long traveling crane track embedded plate

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0518119A (en) * 1991-07-17 1993-01-26 Kajima Corp Stigma level adjusting device and adjusting method in steel structure
CN201605822U (en) * 2010-03-18 2010-10-13 中冶实久建设有限公司 Structure for installing pre-cast iron parts
CN202073323U (en) * 2011-05-25 2011-12-14 中冶建工集团有限公司 Supporting frame for regulating installing horizontality of embedded part
CN102561712A (en) * 2012-01-11 2012-07-11 中国建筑第二工程局有限公司 Accurate positioning frame for large steel column and equipment foundation fixing bolt and construction method thereof
CN203223002U (en) * 2013-04-28 2013-10-02 中建七局建筑装饰工程有限公司 Large pre-burying board installing and leveling device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0518119A (en) * 1991-07-17 1993-01-26 Kajima Corp Stigma level adjusting device and adjusting method in steel structure
CN201605822U (en) * 2010-03-18 2010-10-13 中冶实久建设有限公司 Structure for installing pre-cast iron parts
CN202073323U (en) * 2011-05-25 2011-12-14 中冶建工集团有限公司 Supporting frame for regulating installing horizontality of embedded part
CN102561712A (en) * 2012-01-11 2012-07-11 中国建筑第二工程局有限公司 Accurate positioning frame for large steel column and equipment foundation fixing bolt and construction method thereof
CN203223002U (en) * 2013-04-28 2013-10-02 中建七局建筑装饰工程有限公司 Large pre-burying board installing and leveling device

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895319A (en) * 2015-05-11 2015-09-09 中国十七冶集团有限公司 Cast-in-place concrete shear wall and frame column template installation elevation positioning device
CN105256894A (en) * 2015-10-23 2016-01-20 中国十七冶集团有限公司 Construction method for precisely mounting embedded bolt sleeves of seismic isolation and reduction support
CN105350654A (en) * 2015-11-13 2016-02-24 中国水利水电第十四工程局有限公司 Construction method for adjusting steel plate embedded parts to reach design and construction accuracy
CN105386531A (en) * 2015-12-01 2016-03-09 中国建筑第八工程局有限公司 Locating device used between buttress and vibration insulation support and construction method thereof
CN108487650A (en) * 2018-03-28 2018-09-04 中国建筑第八工程局有限公司 The installation method of pre-buried board mounting structure and lower embedded board under shock isolating pedestal
CN112030771A (en) * 2020-09-10 2020-12-04 中建三局集团有限公司 A device for installing embedded parts of seismic isolation bearings and construction method thereof
CN112030771B (en) * 2020-09-10 2022-03-15 中建三局集团有限公司 Construction method of device for installing embedded part of seismic isolation support
CN114150859A (en) * 2021-09-26 2022-03-08 中建三局集团有限公司 A kind of cantilever frame I-beam precise positioning, anchoring and laying construction method
CN113832842A (en) * 2021-10-18 2021-12-24 中电建十一局工程有限公司 A ball bearing leveling device and a bearing installation and leveling method
CN116717092A (en) * 2023-06-07 2023-09-08 中建-大成建筑有限责任公司 A flatness and position adjustment device and method for installing isolation bearings
CN120738956A (en) * 2025-09-01 2025-10-03 烟建集团有限公司 High-precision installation construction device for super-long traveling crane track embedded plate
CN120738956B (en) * 2025-09-01 2025-11-18 烟建集团有限公司 High-precision installation construction device for super-long traveling crane track embedded plate

Similar Documents

Publication Publication Date Title
CN201943191U (en) Novel cold-bent rectangular steel pipe column assembled pedestal
CN204530742U (en) A kind of adjustable suspension column
CN105350654B (en) A kind of construction method for adjusting pre-embedded steel slab and reaching design and construction precision
CN203891484U (en) Rapid mounting and positioning device for precast-concrete vertical components
CN212375900U (en) A large-scale equipment installation base positioning steel plate support structure
CN203654313U (en) Embedded anchor bolt positioning mold
CN201896365U (en) Installing and fixing device for flat plate pre-embedded piece on surface of concrete
CN203891058U (en) Built-in foundation bolt positioning tool for fixed type tower crane foundation
CN205530322U (en) A construction device for pre-embedded screw at the foot of a fixed steel column
CN204492134U (en) Be convenient to the height scaffolding installed
CN103061249A (en) Quick positioning construction device and construction method for steel-pipe column of bridge
CN206971769U (en) A kind of rubber support installation positioning special purpose device
CN203175052U (en) Leveler for building floor beam slab construction
CN107386316A (en) One-time grouting fixture for anchor bolts and construction method thereof
CN115262998A (en) Construction process for vertically placing and aligning reserved steel bars of assembled shear wall
CN207363272U (en) Cast-in-place concrete floor thickness control instrument
CN106567538A (en) Positioning mold for bathroom concrete flanges
CN205116231U (en) Independent strutting arrangement in basement post -cast strip
CN209457405U (en) Floor concrete leveling device
CN205935706U (en) A elevation controlling means for terrace construction
CN206722225U (en) A kind of accurate spacing and strip thickness control device of concreting floor bar skeleton
CN205369630U (en) Prefabricated formula reinforced concrete superimposed sheet
CN209244243U (en) A kind of fixed device of fashioned iron sizing tripod for builder's jack
CN105643791B (en) Precast wall body grout sleeve strip solid matter exposed steel bar accurate positioning die
CN210013489U (en) A three-in-one plate thickness controller

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140910