CN209604683U - Multi-pipeline fixes bracket - Google Patents

Multi-pipeline fixes bracket Download PDF

Info

Publication number
CN209604683U
CN209604683U CN201920341889.8U CN201920341889U CN209604683U CN 209604683 U CN209604683 U CN 209604683U CN 201920341889 U CN201920341889 U CN 201920341889U CN 209604683 U CN209604683 U CN 209604683U
Authority
CN
China
Prior art keywords
pipeline
fixed
horizontal beam
bracket
cross
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920341889.8U
Other languages
Chinese (zh)
Inventor
田春城
吴学年
顾振凯
刘立伟
张静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Uni-Construction 3rd Development And Construction Co Ltd
Original Assignee
Beijing Uni-Construction 3rd Development And Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Uni-Construction 3rd Development And Construction Co Ltd filed Critical Beijing Uni-Construction 3rd Development And Construction Co Ltd
Priority to CN201920341889.8U priority Critical patent/CN209604683U/en
Application granted granted Critical
Publication of CN209604683U publication Critical patent/CN209604683U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model relates to building pipe technique for fixing fields, disclose the fixed bracket of multi-pipeline.The fixed bracket is cuboid framework structure, it is enclosed by the rectangular reinforcing frame of four horizontal beams arranged in parallel and horizontal beam both ends, the two root posts top of the rectangular reinforcing frame extends to form the interconnecting piece being connected with the post-install in top layer foundation structure straight up, cross-arm is provided between neighbouring horizontal beam, cross-arm is parallel to each other with horizontal beam, pipeline is perpendicular to horizontal beam, horizontal through fixed bracket, support bracket fastened two side elevations that pipeline passes through are followed successively by stationary plane and guide surface, pipeline by pipeline fixation kit on stationary plane horizontal beam or cross-arm fix.The utility model solves the problems such as pipeline concentration, caliber are big, and load disperses at the biggish space of mounting height and conduit running stress, fully meets design requirement.

Description

Multi-pipeline fixes bracket
Technical field
The utility model relates to building pipe technique for fixing fields, more particularly to a kind of fixed bracket of multi-pipeline.
Background technique
Pipe-hanger support using very extensive, can all be used in the project for much having pipeline laying, it is ground restocking A kind of structural member of empty roughing-in support.It is required according to the behavior in service of pipeline and arrangement, pipe support is divided into fixed and movable two Kind, the fixed bracket that is known as of fixed point, and a kind of relatively common construction technology, this pipe support and support of pipelines are set Relative displacement cannot occur, and require pipe support that there is enough rigidity.At home, by Jie of pipe-line system and pipeline transportation It is the most universal that rack construction is fixed in matter.
But this traditional construction technology, every pack support supporting pipeline quantity is few when installation, if every group of pipeline is all made of Conventional stent construction will occupy a large amount of space, increase fixed suspension and support and make workload, also result in unnecessary waste, The suspension and support of redundancy occupies space, drastically influences pipeline space arrangement and integral layout, not only considerably increases construction and set Difficulty is counted, and fixed bracket installation also will affect furred ceiling absolute altitude, directly affect the impression quality of integrated piping installation, and arrange Structure is complicated, is not easy to maintenance in the future.
Traditional high-altitude support of pipelines is typically all that individual fixed frame is arranged in independent root canal road, is not only taken up space big, It cannot achieve the rice collection arrangement of pipeline, and require that additional skewed horizontal load is arranged to disperse the load that bracket receives, still Frame bottom to top floor height generally in 1m or so, cannot achieve biggish height, so support of pipelines cannot achieve The arrangement up and down of pipe group.
Traditional pipeline fixing bracket requires to be separately provided within the scope of adjacent 1-2m leading of avoiding pipeline extension from deviating To bracket, it is ensured that pipeline is straight, but guiding trestle does not carry load, all pipelines and support bracket fastened load, all acts on On fixed bracket.
Utility model content
The utility model provides a kind of simple installation, and rigidity is strong, occupies little space, the intensive reasonable multi-pipeline of pipeline arrangement Fixed bracket.
The technical issues of solution, is: the case where will appear laid out in parallel in more root canal trace gathers in electromechanical installation, existing Pipeline fixing bracket it is complicated for operation, take up space big, also will affect furred ceiling absolute altitude, influence integrated piping installation impression quality and It is not easy to repair from now on.
In order to solve the above technical problems, the utility model adopts the following technical solution:
The utility model multi-pipeline fixes bracket, and the fixed bracket is cuboid framework structure, and You Sigen is parallel to each other The horizontal beam of setting and the rectangular reinforcing frame at horizontal beam both ends enclose, and the two root posts top of the rectangular reinforcing frame is vertical The interconnecting piece to be formed and be connected with the post-install in top layer foundation structure is upwardly extended, is arranged between neighbouring horizontal beam Have cross-arm, cross-arm is parallel to each other with horizontal beam, pipeline perpendicular to horizontal beam, horizontal through fixed bracket, the fixation that pipeline passes through Two side elevations of bracket are followed successively by stationary plane and guide surface, pipeline by horizontal beam on pipeline fixation kit and stationary plane or Cross-arm is fixed.
Further, at least one baffle frame is additionally provided in the fixed bracket, the baffle frame adds with rectangular Gu frame is arranged in parallel.
Further, two of the rectangular reinforcing frame it is diagonal on be each provided with a raker beam, two raker beams It is arranged in X-shaped.Further, the pipeline fixation kit is weldingly fixed on the opposite sides facade of horizontal beam or cross-arm, edge The pipeline fixation kit of the arrangement of horizontal beam length direction spacing parallel arranging, horizontal beam or cross-arm two sides is arranged in a one-to-one correspondence.
Further, the pipeline fixation kit includes coating steel pipe fixing clamp, and the coating steel pipe fixing clamp includes two The clamping plate that block is oppositely arranged, the centre of the clamping plate are provided with semicircular groove, and two groove obvolvents are formed for holding Receive the accommodating chamber of pipeline, the both ends of the clamping plate are bolted.
Further, the pipeline fixation kit further includes freezing pipe fixing bracket, and freezing pipeline fixed mount setting is solid On the stationary plane of fixed rack, including the limit floor being fixed below freezing pipeline and it is fixed on the bracket freezed on the outside of pipeline, It limits floor in pairs, is symmetricly set on horizontal beam or cross-arm two sides, upper edge is welded and fixed with freezing pipeline lateral wall, side Along fixing on the side elevation of horizontal beam or cross-arm, bracket is fixed on horizontal beam or cross-arm stile, spacing parallel arranging arrangement.
Further, it is also provided with thermal insulation board between limit floor and horizontal beam or the side elevation of cross-arm, every Hot plate is the polyfluortetraethylene plate that thickness is not less than 3mm.
Further, the bracket include fasten the heat-insulated wooden block being disposed around on the outside of freezing pipeline and connect heat-insulated wooden block and Support bracket fastened curved plate, curved plate are disposed around outside heat-insulated wooden block, and end horizontal outward bending forms engaging lug, engaging lug It is fixed by bolt and horizontal beam or cross-arm.
Further, the pipeline is additionally provided with U-tube support, U-shaped on guide surface directly through support bracket fastened guide surface Conduit saddle is erected at below pipeline, and the cross-arm or horizontal beam of bottom and guide surface are fixed.
The fixed bracket of the utility model multi-pipeline compared with prior art, has the following beneficial effects:
The utility model solves multi-pipeline peace using the large-scale fixed bracket of the production such as I-steel, channel steel, steel plate and auxiliary material Support bracket fastened manufacture craft problem when dress, by design accounting, solve pipeline concentrate, caliber it is big, it is larger in mounting height Space and the problems such as load disperses when conduit running stress, fully meet design requirement.The utility model fixes bracket specification Larger, after bracket installation itself, height of the cradle bottom surface apart from top level structure floor can achieve 4-5m, may be implemented not of the same race The concentration up and down of class pipeline is arranged, and has been arranged space, has been substantially reduced the space that pipeline occupies;It can be adapted for different types of It is designed while pipe group, such as electrical, water route, air hose;Meet the fixed requirement of pipeline, strictly avoid that pipeline is subjected to displacement can It can property;The settable height of the arrangement of pipe group suitable for large space, pipeline is high, greatly reduces the difficulty of spatial design, Increase the feasibility type of indoor design.
The fixed bracket of the utility model is rectangular parallelepiped structure, and pipe level passes through support bracket fastened two opposite side elevations, The stationary plane for being fixed as pipeline of side, opposite side are the guide surface of pipeline, are equivalent to setting beside the fixed bracket of tradition Guiding trestle no longer needs to that support bracket fastened guiding trestle is additionally arranged, and simplifies working procedure, and pipeline extension device can directly be set It sets between stationary plane and guide surface;This support bracket fastened fixed point and guiding point are the structures of an entirety, and guide surface can be held The stress of the former stationary plane in load part, disperses load, so as to reduce rolled steel dosage, subtract on the basis of same load requirement It is small it is support bracket fastened self weight and take up space.Frame structure is forced through frame dispersion, does not need additional oblique outside frame Support, reduction take up space, and greatly reduce the design difficulty of pipeline arrangement.
The cross-operation that the utility model avoids conventional stent excessive improves construction efficiency, is effectively reduced steel use Amount, is conducive to cost control, meets the reasonable arrangement of pipeline, controls furred ceiling absolute altitude, the effective utilization rate for increasing space.This reality With it is novel have practicability, economy, create an aesthetic feeling, can be engineering construction bring value-added service.
Freezing pipeline fixed mount setting on the utility model stationary plane is one group two rows of, and pipeline sequentially passes through two rows of fixed groups Part can undertake the bidirectional propulsion of pipeline, improve pipeline fixed fastness and stability, improve the fixed safety of pipeline, Realize double-layer safety.Coating steel pipe cannot weld, and not have to welding using hood type fixation kit, avoid being welded and fixed construction to plating The destruction of zinc layers;And the setting of double fixation kit, the bidirectional propulsion of coating steel pipe can be effectively undertaken, coating steel pipe is enhanced Fixed fastness and stability.
In the present invention, hood type fixation kit not only acts as the effect of fixed coating steel pipe, and coating steel pipe During actual use, with the difference of use environment, such as temperature change, radial thrust can be generated, in radial thrust It is secured to that frictional force can be generated between component under effect, frictional force passes through fixed bracket conduction and is dispersed to top floor, will be by Power uninstalls.
The fixed bracket of the multi-pipeline of the utility model is described further with reference to the accompanying drawing.
Detailed description of the invention
Fig. 1 is the support bracket fastened structural schematic diagram one of the utility model multi-pipeline;
Fig. 2 is the support bracket fastened structural schematic diagram two of the utility model multi-pipeline;
Fig. 3 is the support bracket fastened structural schematic diagram three of the utility model multi-pipeline;
Fig. 4 is the support bracket fastened bottom view of the utility model multi-pipeline;
Fig. 5 is the mounting structure schematic diagram of horizontal beam and rectangular reinforcing frame;
Fig. 6 is the structural schematic diagram of the support bracket fastened coating steel pipe fixing clamp of the utility model multi-pipeline;
Fig. 7 is the mounting structure schematic diagram of the utility model multi-pipeline support bracket fastened heat-insulated wooden block and curved plate;
Wherein, the rectangular reinforcing frame of 1- horizontal beam, 2-, 3- raker beam, 4- interconnecting piece, 5- cross-arm, 6- coating steel pipe fixing clamp, 61- clamping plate, 62- accommodating chamber, the heat-insulated wooden block of 7-, 8- curved plate, the first securing plate of 9-, the second securing plate of 10-, 11- third add Solid plate, 12- baffle frame, 13- limit floor;14-U shape conduit saddle.
Specific embodiment
As shown in Fig. 1-Fig. 7, the fixed bracket of the utility model multi-pipeline, fixed bracket is cuboid framework structure, by four Root horizontal beam 1 arranged in parallel and the rectangular reinforcing frame 2 at 1 both ends of horizontal beam enclose, and the height of rectangular reinforcing frame 2 is not Greater than 5m, two of rectangular reinforcing frame 2 it is diagonal on be respectively welded with a raker beam 3, two raker beams 3 are arranged in X-shaped, rectangular to add Gu the two root posts top of frame 2 extends to form the interconnecting piece 4 being connected with the post-install in top layer foundation structure straight up, Cross-arm 5 is provided between neighbouring horizontal beam 1, cross-arm 5 is parallel to each other with horizontal beam 1, and pipeline is perpendicular to horizontal beam 1, water It puts down across fixed bracket, support bracket fastened two side elevations that pipeline passes through are followed successively by stationary plane and guide surface, and pipeline simultaneously passes through Horizontal beam 1 or cross-arm 5 on pipeline fixation kit and stationary plane is fixed;Pipeline is fixed directly through support bracket fastened guide surface Expansion bend is provided on pipeline between face and guide surface.
It is also provided with U-tube support 14 on guide surface, U-tube support 14 is erected at below pipeline, bottom and guide surface Cross-arm 5 or horizontal beam 1 are fixed, play the role of traditional direction bracket, and U-tube support 14 and top set up and can also set between pipeline It is equipped with thermal insulation layer.
I-steel can be used in horizontal beam 1, rectangular reinforcing frame 2 and cross-arm 5 or channel steel cutting is welded, will when installation Interconnecting piece 4 is welded on post-install, and pipe level is mounted on fixed internal stent and fixes.
The quantity of cross-arm 5 and its with the distance between horizontal beam 1 or adjacent cross-arm 5, can according to pipeline arrange situation, into Row flexibly adjustment, fixing bracket, classifying rationally is multiple regions for all having pipeline fixation kit in the vertical direction, It can be effective by different Pipe installings on different cross-arms 5 or horizontal beam 1 to wear fixed different types of pipeline Realize the reasonable neat arrangement of the densely covered pipeline of multiple types.
Pipeline arrangement principle is the top that air hose is arranged in fixed bracket, and aqueduct is in lowest level, bottom pipeline row Cloth is close, and farther out, transport pipeline is being full of distance of the least favorable point of bottom pipeline apart from top plate fixed point when making spatial arrangement When medium is run, the expansive force of pipeline itself will lead to the transversely and horizontally thrust on fixed bracket and greatly increase, bottom pipeline Least favorable point bears biggish load in a short time, while dispersion is reached entire fixed branch by load suffered by least favorable point In the various components such as the cross-arm 5 of frame, raker beam 3, column, load is uniformly shared, prevents the postposition in column with top plate from burying Part stress is excessive, and fracture occurs and causes serious consequence.
It is additionally provided at least one baffle frame 12 in fixed bracket, baffle frame 12 is arranged in parallel with rectangular reinforcing frame 2. The setting of baffle frame 12, can arrange situation according to pipeline, and the factors such as type, distributing order according to pipeline determine baffle The setting quantity of frame 12 and setting position, will fix bracket and be divided into multiple regions in the horizontal direction, for different pipes Road is passed through and is fixed, meanwhile, the setting of baffle frame 12 can also reinforce support bracket fastened structural strength.
Pipeline fixation kit is arranged on support bracket fastened stationary plane, including coating steel pipe fixing clamp 6, and coating steel pipe is fixed Folder 6 is weldingly fixed on the opposite sides facade of horizontal beam 1 or cross-arm 5, spacing parallel arranging arrangement, 5 two sides of horizontal beam 1 or cross-arm Coating steel pipe fixing clamp 6 is arranged in a one-to-one correspondence.Coating steel pipe fixing clamp 6 includes two pieces of opposite clamping plates 61 for fastening setting, clamping plate 61 centre is provided with semicircular groove, and two groove obvolvents form the accommodating chamber 62 for accommodating pipeline, and the two of clamping plate 61 End is bolted.When fixed -piping, after pipeline is threaded through in the accommodating chamber 62 of 61 obvolvent of two clamping plates formation, it will press from both sides The bolt at 61 both ends of plate tightens fixation, can be fixed on pipeline on fixed bracket, and efficiently solving coating steel pipe cannot weld The problem that connects and can not be welded and fixed with fixed bracket, suitable for the pipeline that cannot be directly welded and fixed with fixed bracket, other The pipeline that can be welded can be directly welded on horizontal beam 1 or cross-arm 5.Coating steel pipe sequentially passes through the galvanized steel being oppositely arranged Pipe clip 6 can effectively undertake the bidirectional propulsion that coating steel pipe is generated by environmental change, improve the fixed jail of coating steel pipe Solidity and stability improve the fixed safety of pipeline, realize double-layer safety.
Pipeline fixation kit further includes freezing pipe fixing bracket, and freezing pipe fixing bracket is similarly disposed at support bracket fastened solid Determine on face, including the limit floor 13 being fixed below freezing pipeline and the bracket being fixed on the outside of freezing pipeline, limits floor 13 in pairs, is symmetricly set on 5 two sides of horizontal beam 1 or cross-arm, and upper edge is welded and fixed with pipeline lateral wall, edge-on edge card Gu on the side elevation of horizontal beam 1 or cross-arm 5, to prevent pipeline from moving displacement occurs along caliber direction;Limit floor 13 and water Thermal insulation board is also provided between the side elevation of flat-topped ridge 1 or cross-arm 5, thermal insulation board is the polytetrafluoroethylene (PTFE) that thickness is not less than 3mm Plate avoids that heat exchange occurs between freezing pipeline and fixed bracket;Bracket includes being fixed on horizontal beam 1 or cross-arm 5, and interval is simultaneously Column arrangement, bracket include fastening the heat-insulated wooden block 7 being disposed around on the outside of freezing pipeline and the heat-insulated wooden block 7 of connection and support bracket fastened arc Shape steel plate 8, curved plate 8 are disposed around outside heat-insulated wooden block 7, and end horizontal outward bending forms engaging lug, and engaging lug passes through bolt Fixed with horizontal beam 1 or cross-arm 5, heat-insulated wooden block 7 is about two pieces fastening settings, mainly prevents cold bridge effect, avoids generating cold Condensate.The freezing pipe fixing bracket is suitable for extra heavy pipe diameter pipeline or heating power, freezing pipeline, by heating power, freezing pipeline be mounted on every On hot wooden block 7, since heat-insulated wooden block 7 is made of timber, so the pyroconductivity of heat-insulated wooden block 7 is extremely low, efficiently solve The problem of the anti-condensation of heat distribution pipeline and fixed bracket connecting node, extends support bracket fastened service life.
Pipeline fixation kit may also include the pipeline fixer of other structures form.
It is welded with the first securing plate 9 being square inside and outside the junction of horizontal beam 1 and rectangular reinforcing frame 2, two The second securing plate 10 in regular hexagon, the company of raker beam and rectangular reinforcing frame are welded with inside and outside the point of intersection of raker beam Third securing plate 11 triangular in shape is welded with inside and outside the place of connecing.First securing plate 9, the second securing plate 10 and third are reinforced Plate 11 is used to reinforce the intensity of weld, enhances support bracket fastened structural strength.
The support bracket fastened construction method of the utility model multi-pipeline, comprising the following steps:
Step 1: calculating support bracket fastened stress condition according to pipeline arrangement design requirement;
Specifically includes the following steps:
(1.1), the section face for the column being fixedly connected in rectangular reinforcing frame 2 with top layer foundation structure is determined by calculation Product;
(1.2), adjacent support bracket fastened arrangement spacing is determined;
(1.3), it determines the practical stroke of pipeline, and determines the horizontal thrust that fixed bracket is subject to according to this.
Step 2: selecting profile according to support bracket fastened force analysis situation, the design of fixed bracket specific structure is determined Scheme;
Step 3: be prefabricated in the factory fixed bracket according to design scheme;
Step 4: fixed bracket is transported to construction site, and do preparation of construction;
When fixed bracket is temporarily stored at the construction field (site), cushion block or backing plate is arranged in bottom, and protection is arranged outside fixed bracket Set, it is ensured that support bracket fastened component, part are indeformable, do not scatter and disappear, and do not obscure, and take under the beam bottom or board bottom of position to be onstructed If foot hand;
Step 5: determining support bracket fastened installation site, and in top layer foundation structure by accurate measurement and unwrapping wire Post-install is arranged in corresponding position;
Post-install is anchor slab and rear base expanding and base expanding expansion bolt, and impact drill on concrete structure when drilling, depth as required Degree drilling, it is ensured that the length of embedment of rear base expanding and base expanding expansion bolt, to M12x160 bolt, buried depth is not less than 90mm;It is right M16x190 bolt, buried depth are not less than 120mm;In boring procedure, when encountering reinforcing bar, should be staggered reinforcement location, separately select Kong Dian;
Built-in fitting can also be set in floor in advance during concrete floor slab placement according to condition of construction, to it is solid The interconnecting piece of fixed rack connects;
Step 6: bracket lifting is fixed after post-install quality inspection is qualified;
Fixed bracket is steadily lifted by crane using lifting equipment, column point is welded on post-install behind adjustment position and is faced When fix, then correct fixed bracket, by the control of its perpendicularity deviation within 20mm, then using column bolt by column with Post-install is fixedly connected;
Step 7: laying demand according to pipeline, pipe level is passed through into fixed bracket, and will manage using pipeline fixation kit Road is fixed with fixed bracket;
Step 8: carrying out anti-corrosion cleaning and derusting to fixed rack surface, and antirust paint is coated, completes construction.
Above embodiment is only that preferred embodiments of the present invention are described, not to the utility model Range be defined, under the premise of not departing from the spirit of the design of the utility model, those of ordinary skill in the art are to this is practical The various changes and improvements that novel technical solution is made should all fall into the protection scope that the utility model claims book determines It is interior.

Claims (9)

1. multi-pipeline fixes bracket, it is characterised in that: the fixed bracket is cuboid framework structure, and You Sigen, which is parallel to each other, to be set The rectangular reinforcing frame (2) of the horizontal beam (1) and horizontal beam (1) both ends set encloses, and two of the rectangular reinforcing frame (2) are vertical Top end extends to form the interconnecting piece (4) being connected with the post-install in top layer foundation structure straight up, neighbouring It is provided between horizontal beam (1) cross-arm (5), cross-arm (5) is parallel to each other with horizontal beam (1), and pipeline is perpendicular to horizontal beam (1), water It puts down across fixed bracket, support bracket fastened two side elevations that pipeline passes through are followed successively by stationary plane and guide surface, and pipeline passes through pipe Horizontal beam (1) or cross-arm (5) on road fixation kit and stationary plane is fixed.
2. the fixed bracket of multi-pipeline according to claim 1, it is characterised in that: be additionally provided at least in the fixed bracket One baffle frame (12), the baffle frame (12) are arranged in parallel with rectangular reinforcing frame (2).
3. the fixed bracket of multi-pipeline according to claim 1, it is characterised in that: two of the rectangular reinforcing frame (2) are right A raker beam (3) is each provided on angle, two raker beams (3) are arranged in X-shaped.
4. the fixed bracket of multi-pipeline according to claim 1, it is characterised in that: the pipeline fixation kit includes galvanized steel Pipe clip (6), coating steel pipe fixing clamp (6) are weldingly fixed on the opposite sides facade of horizontal beam (1) or cross-arm (5), edge The coating steel pipe fixing clamp (6) one of the arrangement of horizontal beam (1) length direction spacing parallel arranging, horizontal beam (1) or cross-arm (5) two sides is a pair of It should be arranged.
5. the fixed bracket of multi-pipeline according to claim 4, it is characterised in that: the coating steel pipe fixing clamp (6) includes Two pieces of clamping plates (61) being oppositely arranged, the centre of the clamping plate (61) are provided with semicircular groove, two groove obvolvents The accommodating chamber (62) for accommodating pipeline is formed, the both ends of the clamping plate (61) are bolted.
6. the fixed bracket of multi-pipeline according to claim 1, it is characterised in that: the pipeline fixation kit further includes freezing Pipe fixing bracket freezes pipeline fixed mount setting on support bracket fastened stationary plane, including the limit being fixed below freezing pipeline Position floor (13) and the bracket being fixed on the outside of freezing pipeline, limit floor (13) in pairs, are symmetricly set on horizontal beam (1) Or cross-arm (5) two sides, upper edge are welded and fixed with freezing pipeline lateral wall, edge-on edge is fixed in horizontal beam (1) or cross-arm (5) Side elevation on, bracket is fixed on horizontal beam (1) or cross-arm (5), spacing parallel arranging arrangement.
7. the fixed bracket of multi-pipeline according to claim 6, it is characterised in that: the limit floor (13) and horizontal beam (1) or between the side elevation of cross-arm (5) it is also provided with thermal insulation board, thermal insulation board is the polytetrafluoroethylene (PTFE) that thickness is not less than 3mm Plate.
8. the fixed bracket of multi-pipeline according to claim 6, it is characterised in that: the bracket includes fastening to be disposed around freezing Heat-insulated wooden block (7) and the heat-insulated wooden block (7) of connection and support bracket fastened curved plate (8) on the outside of pipeline, curved plate (8), which encloses, to be set Heat-insulated wooden block (7) outside, end horizontal outward bending forms engaging lug, and engaging lug passes through bolt and horizontal beam (1) or cross-arm (5) It is fixed.
9. the fixed bracket of multi-pipeline according to claim 1, it is characterised in that: the pipeline is directly through support bracket fastened Guide surface is additionally provided with U-tube support (14) on guide surface, and U-tube support (14) is erected at below pipeline, the cross of bottom and guide surface It carries on a shoulder pole (5) or horizontal beam (1) is fixed.
CN201920341889.8U 2019-03-18 2019-03-18 Multi-pipeline fixes bracket Expired - Fee Related CN209604683U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920341889.8U CN209604683U (en) 2019-03-18 2019-03-18 Multi-pipeline fixes bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920341889.8U CN209604683U (en) 2019-03-18 2019-03-18 Multi-pipeline fixes bracket

Publications (1)

Publication Number Publication Date
CN209604683U true CN209604683U (en) 2019-11-08

Family

ID=68404904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920341889.8U Expired - Fee Related CN209604683U (en) 2019-03-18 2019-03-18 Multi-pipeline fixes bracket

Country Status (1)

Country Link
CN (1) CN209604683U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109780330A (en) * 2019-03-18 2019-05-21 北京住总第三开发建设有限公司 The fixed bracket of multi-pipeline and its construction method
CN114250982A (en) * 2022-02-21 2022-03-29 北京建工集团有限责任公司 Synchronous lifting and mounting method for equipment pipeline and large-span roof steel structure
CN114857690A (en) * 2022-05-09 2022-08-05 中建八局第三建设有限公司 Four-pipe system purification air conditioner roof pipeline support and pipeline distribution system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109780330A (en) * 2019-03-18 2019-05-21 北京住总第三开发建设有限公司 The fixed bracket of multi-pipeline and its construction method
CN114250982A (en) * 2022-02-21 2022-03-29 北京建工集团有限责任公司 Synchronous lifting and mounting method for equipment pipeline and large-span roof steel structure
CN114250982B (en) * 2022-02-21 2022-05-24 北京建工集团有限责任公司 Synchronous lifting and mounting method for equipment pipeline and large-span roof steel structure
CN114857690A (en) * 2022-05-09 2022-08-05 中建八局第三建设有限公司 Four-pipe system purification air conditioner roof pipeline support and pipeline distribution system

Similar Documents

Publication Publication Date Title
CN109780330A (en) The fixed bracket of multi-pipeline and its construction method
CN209604683U (en) Multi-pipeline fixes bracket
CN106989211B (en) Assembled architecture pipeline hanger system installation method based on BIM
CN103924802B (en) A kind of large-scale straight tube cone segment type steel structure cooling tower
CN201723853U (en) Integrated supporting and hanging frame with comprehensive pipeline arrangement technology for large public building installation project
CN106592775A (en) High-precision embedded part reinforcing and mounting device and method and purpose
CN102444270B (en) Sleeve joint oblique key type support bracket
CN207211784U (en) A kind of positioner of prefabricated components installation reinforcing bar
CN206233264U (en) For the rear-mounted adjustable support of piping lane
CN104696658B (en) Unstressed piping lane system
CN106958689B (en) Hot water pipeline piping lane is uncompensated laying method
CN205956559U (en) Pipeline gallows
CN107687541A (en) A kind of pipeline provided with people's row access path shares suspension bracket
CN209164763U (en) Heat supply pipeline support
CN206445449U (en) A kind of prefabricated platform assembled for pipe-line system batch production
CN110030005A (en) The light-duty guarantor's circle support system of shield tunnel and its construction method
CN110206064A (en) Piping lane support and system
CN207017300U (en) A kind of corrugated steel retaining wall
CN204828929U (en) Vertical hot and cold water pipeline supporting assembly of high -rise building
CN109469338A (en) A kind of tall and big workshop self-control grid platform and its construction method as electromechanical pipeline
CN109058584A (en) Heat supply pipeline barrier detour method and heat preservation pipe prefabricated detour device
CN203703477U (en) Exhaust duct with double-compensation function
CN206608617U (en) The heat-insulated fixed support of heat-net-pipeline
CN111895184A (en) Comprehensive pipeline supporting and hanging frame in limited space
CN205857459U (en) Light gauge steel inner partition wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191108