CN110206064A - A kind of piping lane bracket and system - Google Patents

A kind of piping lane bracket and system Download PDF

Info

Publication number
CN110206064A
CN110206064A CN201910541794.5A CN201910541794A CN110206064A CN 110206064 A CN110206064 A CN 110206064A CN 201910541794 A CN201910541794 A CN 201910541794A CN 110206064 A CN110206064 A CN 110206064A
Authority
CN
China
Prior art keywords
piping lane
built
groove
connector
trailing arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910541794.5A
Other languages
Chinese (zh)
Inventor
李蕾
尹瑞
崔海龙
姜素云
齐临冬
庄璐
季明明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Capital Engineering and Research Incorporation Ltd
Zhongye Jingcheng Engineering Technology Co Ltd
Original Assignee
Zhongye Jingcheng Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongye Jingcheng Engineering Technology Co Ltd filed Critical Zhongye Jingcheng Engineering Technology Co Ltd
Priority to CN201910541794.5A priority Critical patent/CN110206064A/en
Publication of CN110206064A publication Critical patent/CN110206064A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Supports For Pipes And Cables (AREA)

Abstract

The present invention proposes a kind of piping lane bracket and system, it is related to underground pipe gallery field, the piping lane bracket includes trailing arm and at least one horizontal bracing, one end of trailing arm is the installation end for connecting with built-in groove, the other end of trailing arm is connecting pin, one end of horizontal bracing is provided with the first connection component, and horizontal bracing is mounted on connecting pin by the first connection component, and the other end of horizontal bracing is provided with the second connection component for connecting with another built-in groove.Piping lane bracket proposed by the present invention and system can increase the ability that its trailing arm of piping lane bracket bears horizontal loading.

Description

A kind of piping lane bracket and system
Technical field
The present invention relates to underground pipe gallery field, in particular to a kind of piping lane bracket and system.
Background technique
Pipe gallery, which refers to, is built in Urban Underground for accommodating the structures of two classes and the above municipal engineering pipeline and attached setting It applies, mainly includes main line pipe gallery, branch line pipe gallery and cable piping lane etc..Pipe gallery accommodate pipeline include water supply, Recycled water, heating power, combustion gas, electric power and telecommunication etc..
Piping lane support system refers mainly to the bracket of several support tube lines spaced along its length in pipe gallery Mechanism, including slot type embedded part and finished product bracket, finished product bracket have the trailing arm for installing pipeline, and the civil construction stage will be pre- It buries slot to bury, is easily installed and adjusts trailing arm spacing.
Existing piping lane support system mainly considers the effect of pipeline vertical load, only leads between trailing arm and pre-buried channel flow Two are bolted above and below crossing, and the ability that such connection type bears horizontal loading is not good enough.But effect of all kinds of pipelines to bracket There is also the horizontal loading at horizontal loading, especially pipeline hold-down support is larger in addition to vertical load, existing piping lane bracket The unbearable biggish horizontal loading of system.Although can greatly increase trailing arm by the way that horizontal bracing is arranged at trailing arm and bear water The ability of flat load.But there is also many defects for the existing technical solution that horizontal bracing is arranged at trailing arm.
Firstly, the mode embedded part position of traditional embedded iron slugging diagonal brace is fixed, the later period can not adjust pipeline height With the position of hold-down support, trailing arm can not be replaced, flexibility is lower.
Secondly as piping lane environment is moister, get rusty easily corrosion at embedded iron and solder joint, increases maintenance cost.
Again, welding sequence is complicated, long construction period, and cost of labor is higher.
In view of this, the present inventor is according to the production design experience for being engaged in this field and related fields for many years, by repeatedly Experimental design goes out a kind of piping lane bracket and system, of the existing technology to solve the problems, such as.
Summary of the invention
The purpose of the present invention is to provide a kind of piping lane bracket and systems, can increase its trailing arm receiving level of piping lane bracket The ability of load.
In order to achieve the above objectives, the present invention proposes a kind of piping lane bracket, wherein the piping lane bracket includes trailing arm and at least One horizontal bracing, one end of the trailing arm are the installation end for connecting with built-in groove, and the other end of the trailing arm is connection End, one end of the horizontal bracing are provided with the first connection component, and the horizontal bracing is installed by first connection component On the connecting pin, the other end of the horizontal bracing is provided with the second connection component for connecting with another built-in groove.
Piping lane bracket as described above, wherein the piping lane bracket includes two horizontal bracings, two levels Diagonal brace is symmetrically disposed in the left and right sides of the trailing arm, and the trailing arm and the horizontal bracing are in the shape of a rod.
Piping lane bracket as described above, wherein first connection component includes the first fixing seat and the first connector, institute The first fixing seat is stated to be removedly connected with the connecting pin, one end of first connector with can adjusting angle with it is described First fixing seat is connected, and the other end and the horizontal bracing of first connector are removedly connected.
Piping lane bracket as described above, wherein first fixing seat includes L-type plate and two otic placodes, the L-type plate tool There are horizontal part and vertical portion, the horizontal part is removedly mounted on the top surface or bottom surface of the connecting pin, the vertical portion Side wall along the connecting pin is arranged, and two otic placodes are fixed on the outer wall of the vertical portion, above and below two otic placodes It is arranged and has preset interval, the end of first connector is protruded between two otic placodes, is equipped on the otic placode The anchor bolt being vertically arranged, the otic placode are removedly connected by the anchor bolt and first connector.
Piping lane bracket as described above, wherein first fixing seat includes L-type plate and two otic placodes, the L-type plate tool There are horizontal part and vertical portion, the horizontal part is removedly mounted on the top surface or bottom surface of the connecting pin, the vertical portion Side wall along the connecting pin is arranged, and two otic placodes are fixed on the outer wall of the vertical portion, above and below two otic placodes It is arranged and has preset interval, the end of first connector is protruded between two otic placodes, is equipped on the otic placode The pin shaft being vertically arranged, the otic placode are hinged by pin shaft and first connector.
Piping lane bracket as described above, wherein second connection component includes the second connector and can be mounted on pre- The second fixing seat on slot is buried, one end and the horizontal bracing of second connector are removedly connected, and described second connects The other end of fitting is connected in second fixing seat in which can adjust angle.
Piping lane bracket as described above, wherein second fixing seat includes the second mounting plate and two otic placodes, and described the Two mounting plates are vertically arranged and are removedly connected with the built-in groove, and two otic placodes are fixed in second mounting plate On, two otic placodes it is setting up and down and have preset interval, the end of second connector protrude into two otic placodes it Between, the anchor bolt being vertically arranged is installed, the otic placode can be dismantled by the anchor bolt and second connector on the otic placode Ground connection.
Piping lane bracket as described above, wherein second fixing seat includes the second mounting plate and two otic placodes, and described the Two mounting plates are vertically arranged and are removedly connected with the built-in groove, and two otic placodes are fixed in second mounting plate On, two otic placodes it is setting up and down and have preset interval, the end of second connector protrude into two otic placodes it Between, the pin shaft being vertically arranged is installed, the otic placode is hinged by the pin shaft and second connector on the otic placode.
The present invention also proposes a kind of piping lane support system, wherein the piping lane support system include multiple built-in groove groups and Multiple piping lane brackets as described above, multiple built-in groove groups are installed on the inner sidewall of piping lane and horizontally spaced row Column, each built-in groove group include an installation built-in groove and at least one auxiliary built-in groove, the installation built-in groove with The auxiliary built-in groove is vertically arranged and has preset interval, and each built-in groove group correspondence is equipped at least one institute Piping lane bracket is stated, the installation end of the trailing arm of the piping lane bracket is fixedly connected on the installation built-in groove, the level One end of diagonal brace is connected on the auxiliary built-in groove by second connector, and the other end of the horizontal bracing passes through institute State the connecting pin that the first connector is connected to the trailing arm.
A kind of piping lane support system as described above, wherein the built-in groove group correspondence is equipped with multiple piping lane branch Frame, multiple piping lane brackets are alternatively arranged along the vertical direction.
Compared with prior art, the invention has the characteristics that and advantage:
Piping lane bracket proposed by the present invention and piping lane support system, increase horizontal bracing, significantly on the basis of trailing arm The bearing capacity of trailing arm is increased, the ability that trailing arm bears horizontal loading is especially increased, meets level when pipeline installation Load requirement.
Piping lane bracket proposed by the present invention and piping lane support system, trailing arm, horizontal bracing, the first connection in piping lane bracket Standardized production may be implemented in component and the second connection component, and unified preservative treatment on the one hand can be carried out in factory, is ensured Construction quality.
Piping lane bracket proposed by the present invention and piping lane support system, improve the Its ultimate bearing capacity of support system, for 110kV power cable, water supply, the biggish pipeline of the horizontal loadings such as combustion gas use, and have unified the support system of pipe gallery pipeline, Greatly facilitate the design, construction and operation of pipe gallery.
Detailed description of the invention
Attached drawing described here is only used for task of explanation, and is not intended to limit model disclosed by the invention in any way It encloses.In addition, shape and proportional sizes of each component in figure etc. are only schematical, it is used to help the understanding of the present invention, and It is not the specific shape and proportional sizes for limiting each component of the present invention.Those skilled in the art under the teachings of the present invention, can Implement the present invention to select various possible shapes and proportional sizes as the case may be.
Fig. 1 is the structural schematic diagram of piping lane bracket proposed by the present invention;
Fig. 2 is the front view of piping lane bracket proposed by the present invention;
Fig. 3 is the top view of piping lane bracket proposed by the present invention;
Fig. 4 is the structural schematic diagram of the second connection component proposed by the present invention;
Fig. 5 is the structural schematic diagram of the first connection component proposed by the present invention.
Description of symbols:
10, piping lane bracket;11, trailing arm;
12, horizontal bracing;13, the first connection component;
131, the first fixing seat;132, the first connector;
133, anchor bolt;134, otic placode;
135, mounting hole;136, bolt;
137, bolt;14, the second connection component;
141, the second fixing seat;142, the second connector;
143, anchor bolt;144, otic placode;
145, mounting hole;146, bolt;
147, bolt;15, pedestal;
21, built-in groove is installed;22, built-in groove is assisted.
Specific embodiment
With reference to the drawings and the description of the specific embodiments of the present invention, details of the invention can clearly be understood.But It is the specific embodiment of invention described herein, purpose for explaining only the invention, and cannot understand in any way At being limitation of the present invention.Under the teachings of the present invention, technical staff is contemplated that based on any possible change of the invention Shape, these are regarded as belonging to the scope of the present invention.
As shown in Figures 1 to 5, the present invention proposes a kind of piping lane bracket 10, and the piping lane bracket 10 is including trailing arm 11 and at least One horizontal bracing 12, one end of trailing arm 11 are the installation end for connecting with built-in groove, and the other end of trailing arm 11 is connecting pin, The both ends of horizontal bracing 12 are respectively arranged with the first connection component 13 and the second connection component 14, and horizontal bracing 12 connects by first Connected components 13 are mounted on connecting pin, and the other end of horizontal bracing 12 is mounted on another built-in groove by the second connection component 14 On.
The present invention also proposes a kind of piping lane support system, which includes multiple built-in groove groups and multiple piping lanes Bracket 10, multiple built-in groove groups are installed on the inner sidewall of piping lane and horizontally spaced arrangement, and each built-in groove group is wrapped An installation built-in groove 21 and at least one auxiliary built-in groove 22 are included, installation built-in groove 21 and auxiliary built-in groove 22 are vertically arranged And there is preset interval, each built-in groove group correspondence is equipped at least one piping lane bracket 10, the trailing arm 11 of piping lane bracket 10 Installation end be fixedly connected with installation built-in groove 21, one end of horizontal bracing 12 is pre-buried by the second connection component 14 and auxiliary Slot 22 is hinged, and the other end of horizontal bracing 12 is hinged by the connecting pin of the first connection component 13 and trailing arm 11.
Piping lane bracket 10 proposed by the present invention and piping lane support system increase horizontal bracing on the basis of trailing arm 11 12, the bearing capacity of trailing arm 11 is considerably increased, the ability that trailing arm 11 bears horizontal loading is especially increased, meets pipeline peace Horizontal loading requirement when dress.
Piping lane bracket 10 proposed by the present invention and piping lane support system, trailing arm 11, horizontal bracing 12 in piping lane bracket 10, Standardized production may be implemented in first connection component 13 and the second connection component 14, and unified anti-corrosion on the one hand can be carried out in factory Processing, has ensured construction quality.
Piping lane bracket 10 proposed by the present invention and piping lane support system, improve the Its ultimate bearing capacity of support system, can For 110kV power cable, water supply, the biggish pipeline of the horizontal loadings such as combustion gas is used, and has unified the carriage support of pipe gallery pipeline System, greatly facilitates the design, construction and operation of pipe gallery.
Piping lane bracket 10 proposed by the present invention and piping lane support system, can be in the premise for not destroying piping lane main structure Under, it is easy for installation, it is easy to adjust the vertical spacing of trailing arm 11, and be easy to later period replacement trailing arm 11.
In an optional example of the invention, each built-in groove group correspondence is equipped with multiple piping lane brackets 10, Duo Geguan Corridor bracket 10 is alternatively arranged along the vertical direction.
In an optional example of the invention, piping lane bracket 10 includes two horizontal bracings 12, two horizontal bracings 12 It is symmetrically disposed in the left and right sides of trailing arm 11, trailing arm 11 and horizontal bracing 12 are in the shape of a rod.
Further, built-in groove group includes there are two auxiliary built-in groove 22, and two auxiliary built-in grooves 22 are separately positioned on peace The two sides of built-in groove 21 are filled, two horizontal bracings 12 are connected by the second connection component 14 with corresponding auxiliary built-in groove 22 respectively It connects.
In the present invention, for existing piping lane and built-in groove, a kind of mode is can artificially to draw existing built-in groove It is divided into multiple built-in groove groups, specifically, making adjacent three built-in grooves, one built-in groove group, makes to be located in the middle built-in groove Built-in groove 21 is installed, the built-in groove on both sides is auxiliary built-in groove 22, carries out the installation of piping lane bracket 10 later, in this way can be In the case where not destroying the built-in groove that existing piping lane has been set, the installation of piping lane bracket 10 is rapidly realized.For existing Piping lane and built-in groove, another way are to set existing built-in groove in construction to increase to install built-in groove 21, and in its two sides Frame assists built-in groove 22, and then forms built-in groove group, then piping lane bracket 10 is installed in built-in groove group, wherein installation is pre-buried The distance d of slot 21 and auxiliary built-in groove 22 can be according to actual engineering design.
In an optional example of the invention, the first connection component 13 includes the first fixing seat 131 and the first connector 132, the first fixing seat 131 is removedly connected in connecting pin, and one end of the first connector 132 is with can adjusting angle with first Fixing seat 131 connects, and the other end of the first connector 132 and the end of horizontal bracing 12 are removedly connected.
In an optional example of the invention, the second connection component 14 includes the second connector 142 and can be mounted on The second fixing seat 141 on built-in groove 22 is assisted, one end of the second connector 142 removedly connects with the end of horizontal bracing 12 It connects, the other end of the second connector 142 is connect in which can adjust angle with the second fixing seat 141.
In the present invention, one end of horizontal bracing 12 is connect by the first connection component 13 with trailing arm 11, makes level The other end of the angle adjustable of angle between diagonal brace 12 and trailing arm 11, horizontal bracing 12 passes through the second connection component 14 and auxiliary Built-in groove 22 connects, so that the angle of angle is also adjustable between horizontal bracing 12 and auxiliary built-in groove 22, even if installation Spacing between built-in groove 21 and auxiliary built-in groove 22 is different, and horizontal bracing 12 also can be carried out installation, so as to not destroy now In the case where the built-in groove for thering is piping lane to be set, the installation of piping lane bracket 10 is rapidly carried out.
Optional at one, the first fixing seat 131 includes L-type plate and two otic placodes 134, and L-type plate has horizontal part and erects Straight portion, horizontal part are removedly mounted on the top surface or bottom surface of connecting pin, and side wall of the vertical portion along connecting pin is arranged, two otic placodes 134 are fixed on the outer wall of vertical portion, and two otic placodes 134 are setting up and down and have preset interval, the end of the first connector 132 Portion protrudes between two otic placodes 134, and pin shaft is provided on otic placode 134, and otic placode 134 is hinged by pin shaft and the first connector 132. In this way, the first fixing seat 131 of the first connection component 13 and the first connector 132 can be any in the range of 0 degree~180 degree Angular adjustment.It is also provided with locating part between first connector 132 and the first fixing seat 131, when 132 He of the first connector It adjusts between first fixing seat 131 to suitable angle, fixes the angle using locating part.
In another optional example of the invention, the first fixing seat 131 includes L-type plate and two otic placodes 134, L-type plate With horizontal part and vertical portion, horizontal part is removedly mounted on the top surface or bottom surface of connecting pin, side of the vertical portion along connecting pin Wall setting, two otic placodes 134 are fixed on the outer wall of vertical portion, and two otic placodes 134 are setting up and down and have preset interval, the The end of a connection piece 132 is protruded between two otic placodes 134, and anchor bolt 133 is provided on otic placode 134, and otic placode 134 passes through anchor bolt 133 are removedly connected with the first connector 132, and when installation, when anchor bolt 133 is not tightened, the first of the first connection component 13 is solid Reservation 131 and the first connector 132 any angle can be adjusted in the range of 0 degree~180 degree, tighten anchor after angle is suitable 133 fixed angle of bolt.
In an optional example, the horizontal part of L-type plate is connect by bolt 137 with connecting pin, specifically, horizontal part On offer threaded hole at two, it is corresponding on connecting pin to open up there are two mounting hole, be provided with a bolt in each threaded hole 137, L-type plate and connecting pin are fixed together by bolt 137 through threaded hole and mounting hole, and mounting hole can be circular hole, It is also possible to strip hole.Equally, the first connector 132 is also to be connect by bolt 136 with horizontal bracing 12, the first connector Mounting hole 135 at two are offered on 132, are also corresponded to and are opened up there are two mounting hole in horizontal bracing 12, mounting hole 135 can be circle Hole is also possible to strip hole.When installation, first the first fixing seat 131 of the first connection component 13 and the first connector 132 can be adjusted It is whole then to tighten bolt to after suitable angle and position, it realizes and fixes.
Certainly, it can also be adopted between the horizontal part and connecting pin of L-type plate, between the first connector 132 and horizontal bracing 12 Connection, such as anchor bolts are realized with other structures familiar to those skilled in the art, herein without repeating.
In an optional example of the invention, the second fixing seat 141 includes the second mounting plate and two otic placodes 144, the Two mounting plates are vertically arranged and are removedly connected with auxiliary built-in groove 22, and two otic placodes 144 are fixedly connected in the second installation On plate, two otic placodes 144 it is setting up and down and have preset interval, the end of the second connector 142 protrude into two otic placodes 144 it Between, pin shaft is provided on otic placode 144, otic placode 144 is hinged by pin shaft and the second connector 142.In this way, the second connection component 14 The second fixing seat 141 and the second connector 142 can in the range of 0 degree~180 degree any angle adjust.
In another optional example of the invention, the second fixing seat 141 includes the second mounting plate and two otic placodes 144, Second mounting plate is vertically arranged and is removedly connected with auxiliary built-in groove 22, and two otic placodes 144 are fixedly connected in the second peace In loading board, two otic placodes 144 it is setting up and down and have preset interval, the end of the second connector 142 protrude into two otic placodes 144 it Between, anchor bolt 143 is provided on otic placode 144, anchor bolt 143 runs through the second connector 142 and otic placode 144, and such otic placode 144 will pass through Anchor bolt 143 is removedly connected with the second connector 142, when installation, anchor bolt 143 is made to be in the state that do not tighten, second is fixed Seat 141 and the second connector 142 any angle can be adjusted in the range of 0 degree~180 degree, tighten anchor bolt after angle is suitable Fixed angle.
In an optional example, the second mounting plate is connect by bolt 147 with auxiliary built-in groove 22, the second mounting plate On offer for bolt installation mounting hole;Equally, the second connector 142 is also to be connected by bolt 146 and horizontal bracing 12 It connects, the mounting hole for bolt installation is offered on the second connector 142 and horizontal bracing 12 respectively, on the second connector 142 Mounting hole 145 can be circular hole, be also possible to strip hole.The installation of second connection component 14 and fixation procedure and the first connection Component 13 is similar, herein without repeating.
It certainly, can also be between the second mounting plate and auxiliary built-in groove 22, between the second connector 142 and horizontal bracing 12 Connection, such as anchor bolts are realized using other structures familiar to those skilled in the art, herein without repeating.
In an optional example of the invention, trailing arm 11 and horizontal bracing 12 are C-shaped channel steel (single side channel steel).
In an optional example of the invention, the installation end of trailing arm 11 is provided with the pedestal 15 that can be connect with built-in groove, The connecting pin of trailing arm 11 is removedly connected by bolt with the first connection component 13.
In an optional example, pedestal 15 is the installation end of rectangular base and welded connecting in trailing arm 11, pedestal 15 On equally offer mounting hole, these mounting holes are convenient to be bolted with built-in groove.Certainly, the structure of pedestal 15 and its with Trailing arm 11, built-in groove connection type can also use other prior arts well known to those skilled in the art, herein without It repeats.
In the present invention, cold-rolled forming section can also be used in trailing arm 11 and horizontal bracing 12, and hot-rolled steel section etc. is made, can be according to reality Border condition selects different patterns.
In an optional example of the invention, the first connection component 13 and the second connection component 14 are by lvanized cold rolled strip Processing.
For explaining in detail for the respective embodiments described above, purpose, which is only that, explains the present invention, in order to be able to More fully understand the present invention, still, these descriptions cannot with any explanation at being limitation of the present invention, in particular, Each feature described in different embodiments can also mutual any combination, so that other embodiments are formed, in addition to having Opposite description is specified, these features should be understood to can be applied in any one embodiment, and be not limited merely to Described embodiment.

Claims (10)

1. a kind of piping lane bracket, which is characterized in that the piping lane bracket includes trailing arm and at least one horizontal bracing, the trailing arm One end be installation end for being connect with built-in groove, the other end of the trailing arm is connecting pin, one end of the horizontal bracing It is provided with the first connection component, the horizontal bracing is mounted on the connecting pin by first connection component, the water The other end of flat diagonal brace is provided with the second connection component for connecting with another built-in groove.
2. piping lane bracket as described in claim 1, which is characterized in that the piping lane bracket includes two horizontal bracings, Two horizontal bracings are symmetrically disposed in the left and right sides of the trailing arm, and the trailing arm and the horizontal bracing are in bar Shape.
3. piping lane bracket as described in claim 1, which is characterized in that first connection component includes the first fixing seat and the A connection piece, first fixing seat are removedly connected with the connecting pin, and one end of first connector can be adjusted It is connected with first fixing seat to angle, the other end and the horizontal bracing of first connector removedly connect It connects.
4. piping lane bracket as claimed in claim 3, which is characterized in that first fixing seat includes L-type plate and two otic placodes, The L-type plate has horizontal part and vertical portion, and the horizontal part is removedly mounted on the top surface or bottom surface of the connecting pin, Side wall of the vertical portion along the connecting pin is arranged, and two otic placodes are fixed on the outer wall of the vertical portion, two institutes It is setting up and down and there is preset interval to state otic placode, the end of first connector protrudes between two otic placodes, the ear The anchor bolt being vertically arranged is installed, the otic placode is removedly connected by the anchor bolt and first connector on plate.
5. piping lane bracket as claimed in claim 3, which is characterized in that first fixing seat includes L-type plate and two otic placodes, The L-type plate has horizontal part and vertical portion, and the horizontal part is removedly mounted on the top surface or bottom surface of the connecting pin, Side wall of the vertical portion along the connecting pin is arranged, and two otic placodes are fixed on the outer wall of the vertical portion, two institutes It is setting up and down and there is preset interval to state otic placode, the end of first connector protrudes between two otic placodes, the ear The pin shaft being vertically arranged is installed, the otic placode is hinged by pin shaft and first connector on plate.
6. piping lane bracket as described in claim 1, which is characterized in that second connection component includes the second connector and energy The second fixing seat being enough mounted on built-in groove, one end and the horizontal bracing of second connector are removedly connected, The other end of second connector is connected in second fixing seat in which can adjust angle.
7. piping lane bracket as claimed in claim 6, which is characterized in that second fixing seat includes the second mounting plate and two Otic placode, second mounting plate are vertically arranged and are removedly connected with the built-in groove, and two otic placodes are fixed in described On second mounting plate, two otic placodes are setting up and down and have preset interval, and the end of second connector protrudes into two Between the otic placode, the anchor bolt being vertically arranged is installed on the otic placode, the otic placode is connected by the anchor bolt and described second Fitting is removedly connected.
8. piping lane bracket as claimed in claim 6, which is characterized in that second fixing seat includes the second mounting plate and two Otic placode, second mounting plate are vertically arranged and are removedly connected with the built-in groove, and two otic placodes are fixed in described On second mounting plate, two otic placodes are setting up and down and have interval, and the end of second connector is protruded into described in two Between otic placode, the pin shaft being vertically arranged is installed on the otic placode, the otic placode passes through the pin shaft and second connector Hingedly.
9. a kind of piping lane support system, which is characterized in that the piping lane support system includes multiple built-in groove groups and multiple such as power Benefit require any one of 1 to 8 described in piping lane bracket, multiple built-in groove groups are installed on the inner sidewall of piping lane and along level Direction is alternatively arranged, and each built-in groove group includes an installation built-in groove and at least one auxiliary built-in groove, the peace Dress built-in groove and the auxiliary built-in groove are vertically arranged and have preset interval, and each built-in groove group correspondence is equipped with At least one described piping lane bracket, the installation end of the trailing arm of the piping lane bracket are fixedly connected on the installation built-in groove On, one end of the horizontal bracing is connected on the auxiliary built-in groove by second connector, the horizontal bracing The other end is connected to the connecting pin of the trailing arm by first connector.
10. a kind of piping lane support system as claimed in claim 9, which is characterized in that the built-in groove group correspondence is equipped with more A piping lane bracket, multiple piping lane brackets are alternatively arranged along the vertical direction.
CN201910541794.5A 2019-06-21 2019-06-21 A kind of piping lane bracket and system Pending CN110206064A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910541794.5A CN110206064A (en) 2019-06-21 2019-06-21 A kind of piping lane bracket and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910541794.5A CN110206064A (en) 2019-06-21 2019-06-21 A kind of piping lane bracket and system

Publications (1)

Publication Number Publication Date
CN110206064A true CN110206064A (en) 2019-09-06

Family

ID=67793865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910541794.5A Pending CN110206064A (en) 2019-06-21 2019-06-21 A kind of piping lane bracket and system

Country Status (1)

Country Link
CN (1) CN110206064A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112033813A (en) * 2020-08-17 2020-12-04 中铁二十二局集团第三工程有限公司 Comprehensive pipe gallery cable support bearing capacity test method
CN112411765A (en) * 2020-11-10 2021-02-26 新疆维泰开发建设(集团)股份有限公司 Anti-displacement construction method for pre-buried groove of finished support

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207921486U (en) * 2018-03-14 2018-09-28 山东天元建设机械有限公司 A kind of city integrated piping lane heating power heavy type holder
CN108758083A (en) * 2018-06-08 2018-11-06 中铁十七局集团电气化工程有限公司 A kind of construction method of the comprehensive suspension and support anti-seismic performance of enhancing
CN208618447U (en) * 2018-06-19 2019-03-19 郭东良 A kind of pipe gallery
CN208703284U (en) * 2018-08-09 2019-04-05 北京雅仕格机电科技有限公司 A kind of pipe gallery para-seismic support
CN210737596U (en) * 2019-06-21 2020-06-12 中冶京诚工程技术有限公司 Piping lane support and system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207921486U (en) * 2018-03-14 2018-09-28 山东天元建设机械有限公司 A kind of city integrated piping lane heating power heavy type holder
CN108758083A (en) * 2018-06-08 2018-11-06 中铁十七局集团电气化工程有限公司 A kind of construction method of the comprehensive suspension and support anti-seismic performance of enhancing
CN208618447U (en) * 2018-06-19 2019-03-19 郭东良 A kind of pipe gallery
CN208703284U (en) * 2018-08-09 2019-04-05 北京雅仕格机电科技有限公司 A kind of pipe gallery para-seismic support
CN210737596U (en) * 2019-06-21 2020-06-12 中冶京诚工程技术有限公司 Piping lane support and system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112033813A (en) * 2020-08-17 2020-12-04 中铁二十二局集团第三工程有限公司 Comprehensive pipe gallery cable support bearing capacity test method
CN112411765A (en) * 2020-11-10 2021-02-26 新疆维泰开发建设(集团)股份有限公司 Anti-displacement construction method for pre-buried groove of finished support
CN112411765B (en) * 2020-11-10 2021-06-25 新疆维泰开发建设(集团)股份有限公司 Anti-displacement construction method for pre-buried groove of finished support

Similar Documents

Publication Publication Date Title
CA2759673C (en) Structural duct bearing system
US9422734B1 (en) System and method for straightening and/or supporting a wall
CN110206064A (en) A kind of piping lane bracket and system
US6782668B2 (en) Roof-screen system
CN109780330A (en) The fixed bracket of multi-pipeline and its construction method
CN207621488U (en) Adjustable limited support auxiliary device
CN209604683U (en) Multi-pipeline fixes bracket
CN210286436U (en) Rain sewage pipe hoist and mount system that slides
CN210127662U (en) Support combination
CN210737596U (en) Piping lane support and system
CN211772964U (en) Bridging suspension beam for box culvert first-aid repair
CN205314319U (en) Metal curtain wall articulates subassembly
CN207368589U (en) A kind of cable installs multilayer adjustable support
EP0253150A2 (en) Wall of pre-cast panels, particulary for earth-retaining and for building liquid-holding tanks
CN2533360Y (en) Grate type electric cable bridge support
CN210567041U (en) Vibration-damping and anti-seismic support hanger
CN203383457U (en) Board mounting system
CN111877390A (en) Large-scale tower crane basis fixing device
CN112982934A (en) But angle of adjustment's basket of flowers I-shaped steel roof beam construction equipment that encorbelments
CN219708900U (en) Arc water supply pipe manufacturing device
CN216566611U (en) Positioning adjustment device for corrugated steel plate connecting angle steel
CN110130391A (en) Isolated footing pre-embedded bolt mounting structure and method
CN211455922U (en) Adjustable short pole holding support for floor antenna
CN217711705U (en) Terrace construction joint side form erects structure
CN219930825U (en) Quick-mounting device for jet flow functional module of gas turbine

Legal Events