CN206233264U - For the rear-mounted adjustable support of piping lane - Google Patents

For the rear-mounted adjustable support of piping lane Download PDF

Info

Publication number
CN206233264U
CN206233264U CN201621167220.4U CN201621167220U CN206233264U CN 206233264 U CN206233264 U CN 206233264U CN 201621167220 U CN201621167220 U CN 201621167220U CN 206233264 U CN206233264 U CN 206233264U
Authority
CN
China
Prior art keywords
piping lane
column
support
mounted adjustable
adjustable support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621167220.4U
Other languages
Chinese (zh)
Inventor
周克宇
何震华
戈祥林
曾宏强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201621167220.4U priority Critical patent/CN206233264U/en
Application granted granted Critical
Publication of CN206233264U publication Critical patent/CN206233264U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of rear-mounted adjustable support for piping lane, including:Along the spaced support body of piping lane, support body includes:The column of piping lane wall is fixedly arranged on by the first connector, column is interval with adjustment hole;And multiple horizontal supports, the end of horizontal support is installed with shackle member, and shackle member is fastened in column, and shackle member wears corresponding adjustment hole and is fixedly connected with column by the second connector.The height and levelness of the relatively simple horizontal support of adjustment of the adjustment hole on column can be utilized so as to the utility model is used for the rear-mounted adjustable support of piping lane, the problems such as positioning when solving the pre-buried use unwrapping wire of general tradition built-in type support with this is inaccurate, concreting produces displacement, while being adjusted to the height of horizontal support and the error of levelness in greatly facilitating installation process.

Description

For the rear-mounted adjustable support of piping lane
Technical field
The utility model is related to the realm of building construction, espespecially a kind of rear-mounted adjustable support for piping lane.
Background technology
In the realm of building construction, the line holder quantity of city integrated underground pipe gallery is more, and absolute altitude changes greatly.Pipe in piping lane Line is including power pipeline, communication line, feedwater piping, intermediate water pipeline and cold and heat supply pipeline etc..It is special that piping lane gut line is related to Industry system is more, quantities big, it is intensive to arrange, and spaces compact, arrangement are intensive in piping lane.
It is many using pre-buried method is carried out before concreting in conventional art, however, it was found that there is pre-buried enormous amount It is unfavorable to the duration, the problems such as position is inaccurate, formwork erection is difficult, and positioning workload is big, and concreting is easily produced Displacement, support installation process can also produce error, pre-buried to involve great expense.
Traditional built-in type support built-in fitting is fixed in joist, and joist colligation positioning inherently has error in construction, causes The error for being allowed to after-poppet built-in fitting positioning further expands.Simultaneously in concreting process, fall along with concrete And flowing, loosely generation loosens, shifts for built-in fitting fixation.
Utility model content
The purpose of this utility model is the defect for overcoming prior art, there is provided a kind of for the rear-mounted adjustable of piping lane Support, the positioning workload for solving built-in type support of the prior art is big, and concreting easily produces displacement, very flexible Problem.
Realizing the technical scheme of above-mentioned purpose is:
The utility model provides a kind of rear-mounted adjustable support for piping lane, including:
Along the spaced support body of piping lane, the support body includes:
The column of piping lane wall is fixedly arranged on by the first connector, the column is interval with adjustment hole;And
Multiple horizontal supports, the end of the horizontal support is installed with shackle member, and the shackle member is fastened in the column, the clamping Part wears corresponding adjustment hole and is fixedly connected with the column by the second connector.
The utility model is used for the beneficial effect of the rear-mounted adjustable support of piping lane:
The utility model be used for piping lane rear-mounted adjustable support by support body along piping lane interval setting, wherein support body bag Column and multiple horizontal supports are included, column is fixed on the piping lane wall for having poured completion, and adjustment hole is provided with column, horizontal support End is installed with shackle member, shackle member is fastened in into column, and wears corresponding adjustment hole by the second connector and consolidated with column Fixed connection, can utilize the adjustment hole on column relatively simple so that the utility model is used for the rear-mounted adjustable support of piping lane The horizontal support of adjustment height and levelness, positioning when solving the pre-buried use unwrapping wire of general tradition built-in type support with this is not The problems such as accurate, concreting produces displacement, while to the height and the mistake of levelness of horizontal support in greatly facilitating installation process Difference is adjusted.
The utility model be used for piping lane rear-mounted adjustable support further improvement is that, the column is the first groove Steel, first channel-section steel includes a pair of flange plates and is connected to the connecting plate of the pair of flange plate, first connector It is expansion bolt, the connecting plate is attached at the piping lane wall and fixed with the piping lane wall by the expansion bolt Connection.
The utility model be used for piping lane rear-mounted adjustable support further improvement is that, on the pair of flange plate The adjustment hole is provided with along short transverse.
The utility model be used for piping lane rear-mounted adjustable support further improvement is that, the adjustment hole is elongated Hole.
The utility model be used for piping lane rear-mounted adjustable support further improvement is that, the horizontal support is the second groove Steel, the shackle member is the 3rd channel-section steel, and second connector is fastening bolt, and the connecting plate of the 3rd channel-section steel is welded in institute The end of the second channel-section steel is stated, the 3rd channel-section steel is fastened in first channel-section steel and is worn by the fastening bolt corresponding The adjustment hole is fixedly connected.
The utility model be used for piping lane rear-mounted adjustable support further improvement is that, the horizontal support and described vertical It is oblique between post to have installed hound.
Brief description of the drawings
Fig. 1 is that the utility model is used for constructing structure signal of the rear-mounted adjustable support of piping lane in underground pipe gallery Figure.
Fig. 2 is the front view of the rear-mounted adjustable support that the utility model is used for piping lane.
Fig. 3 is the side view of the rear-mounted adjustable support that the utility model is used for piping lane.
Fig. 4 is the front view of the horizontal support of the rear-mounted adjustable support that the utility model is used for piping lane.
Fig. 5 is the side view of the horizontal support of the rear-mounted adjustable support that the utility model is used for piping lane.
Specific embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1, it is shown that the utility model is used for construction of the rear-mounted adjustable support of piping lane in underground pipe gallery Structural representation.As shown in figure 1, the both sides of underground pipe gallery are the concrete structure piping lane wall for having poured completion, in piping lane The utility model is installed on wall 1 is used for the rear-mounted adjustable support of piping lane.The utility model can for the rear-mounted of piping lane Adjusting bracket includes that, along the spaced support body of piping lane, support body includes column 2 and multiple horizontal supports 3, and its central post 2 passes through first Connector is fixedly arranged on piping lane wall 1, and adjustment hole 20 is interval with column 2, and the end of horizontal support 3 is installed with shackle member 5, shackle member 5 are fastened in column 2, and shackle member 5 wears corresponding adjustment hole 20 and is fixedly connected with column 2 by the second connector 6.Such that it is able to The adjustment hole 20 on column 2 at corresponding height is selected to fix horizontal support 3 as needed, can be with the relatively simple horizontal support 3 of adjustment Height and levelness, positioning when solving the pre-buried use unwrapping wire of general tradition built-in type support with this is inaccurate, concreting The problems such as producing displacement, while being adjusted to the height of horizontal support 3 and the error of levelness in greatly facilitating installation process, enters And the pipeline in piping lane is placed come support using the horizontal support 3 at sustained height.
Refering to Fig. 2, it is shown that the utility model is used for the front view of the rear-mounted adjustable support of piping lane.Refering to Fig. 3, show Show the utility model for the side view of the rear-mounted adjustable support of piping lane.With reference to shown in Fig. 2 and Fig. 3, in the present embodiment In, column 2 is the first channel-section steel, and the first channel-section steel includes a pair of flange plates and is connected to a pair of connecting plates of flange plate, accordingly, First connector 4 is expansion bolt.When column 2 is installed, the connecting plate of column 2 is vertically attached at piping lane wall 1, in connection Plate opens up through hole, and connecting plate is fixedly connected with piping lane wall 1 by expansion bolt.Specifically, the number of expansion bolt and Depending on situation when spacing is according to practice of construction such as the height of connecting plate.
Multiple adjustment holes 20 are provided with along short transverse on a pair of flange plates, in the present embodiment, adjustment hole 20 is elongated Hole.The number and size of elongated hole are decided according to the actual requirements.Because adjustment hole 20 is elongated hole, so with certain regulation Space, so that fastening bolt 51 can be moved up and down in adjustment hole 20, can be by the horizontal fine setting held in the palm and carry out vertical direction.
Refering to Fig. 4, it is shown that the utility model is used for the front view of the horizontal support of the rear-mounted adjustable support of piping lane.Refer to Fig. 5, it is shown that the utility model is used for the side view of the horizontal support of the rear-mounted adjustable support of piping lane.With reference to Fig. 4 and Fig. 5 institutes Show, horizontal support 3 is the second channel-section steel, shackle member 5 is the 3rd channel-section steel, and the second connector 6 is fastening bolt, and the connecting plate of the 3rd channel-section steel is welded The end of the second channel-section steel is connected to, so as to shackle member 5 to be fixed on the end of horizontal support 3.3rd channel-section steel is fastened in the first channel-section steel, specifically Ground, by the connection corresponding with a pair of flange plates of the first channel-section steel of a pair of flange plates of the 3rd channel-section steel, so as to shackle member 5 is fastened in vertical On post 2, and it is fixedly connected using the adjustment hole that fastening bolt wears corresponding position.
Install the utility model for piping lane rear-mounted adjustable support when, fastening bolt 51 can be in adjustment hole Move up and down in 20, during such that it is able to elder generation according to practice of construction to the height of support the need for and select the regulation of appropriate position Hole 20, then appropriate adjustment is done to the position of fastening bolt 51, to carry out the fine setting in horizontally and vertically direction.By said structure Multiple support bodys are installed one by one along piping lane interval, form the overall rear-mounted adjustable support for piping lane.
In order to strengthen the utility model for the globality and steadiness of the rear-mounted adjustable support of piping lane, in horizontal support 3 The oblique hound that installed is reinforced and column 2 between.
Specifically, channel-section steel is processed in zinc-plated post-passivation, to improve anti-corrosion life.The axially arranged ribbed stiffener of horizontal support 3 is special Groove, strengthen section rigidity, increase bending resistance.Auxiliary spacing is carved with the surface of column 2 and horizontal support 3, easy for installation flexible.
The construction method for being used for the rear-mounted adjustable support of piping lane to the utility model below is illustrated:
Unwrapping wire positioning, column is sticked on piping lane wall at the construction field (site), with expansion bolt by column and piping lane wall It is fixed.
After after column installation, the connecting plate of the 3rd channel-section steel is welded in the end of the second channel-section steel, by the 3rd channel-section steel A pair of flange plates connection corresponding with a pair of flange plates of the first channel-section steel so that the 3rd channel-section steel and the mutual cutting ferrule of the first channel-section steel, with tight Fixing bolt wears the adjustment hole of appropriate position on the first channel-section steel, and fastening bolt is tightened, and moment of torsion is 40Nm, and the 3rd channel-section steel is consolidated It is scheduled on the first channel-section steel.
Check the height and levelness of horizontal support.After after the installation of horizontal support, height and levelness to horizontal support are detected, Horizontal support to being unsatisfactory for requiring can unclamp fastening bolt, tighten fastening bolt after realigning again.
The utility model is used for having the beneficial effect that for the rear-mounted adjustable support of piping lane:
The utility model be used for piping lane rear-mounted adjustable support by support body along piping lane interval setting, wherein support body bag Column and multiple horizontal supports are included, column is fixed on the piping lane wall for having poured completion, and adjustment hole is provided with column, horizontal support End is installed with shackle member, shackle member is fastened in into column, and wears corresponding adjustment hole by the second connector and consolidated with column Fixed connection, can utilize the adjustment hole on column relatively simple so that the utility model is used for the rear-mounted adjustable support of piping lane The horizontal support of adjustment height and levelness, positioning when solving the pre-buried use unwrapping wire of general tradition built-in type support with this is not The problems such as accurate, concreting produces displacement, while to the height and the mistake of levelness of horizontal support in greatly facilitating installation process Difference is adjusted.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to described above.Thus, some of embodiment details should not be constituted to this practicality New restriction, the scope that the utility model will be defined using appended claims is used as protection domain of the present utility model.

Claims (6)

1. a kind of rear-mounted adjustable support for piping lane, it is characterised in that including:Along the spaced support body of piping lane, The support body includes:
The column of piping lane wall is fixedly arranged on by the first connector, the column is interval with adjustment hole;And
Multiple horizontal supports, the end of the horizontal support is installed with shackle member, and the shackle member is fastened in the column, the shackle member and The column wears corresponding adjustment hole and is fixedly connected by the second connector.
2. the rear-mounted adjustable support of piping lane is used for as claimed in claim 1, it is characterised in that the column is the first groove Steel, first channel-section steel includes a pair of flange plates and is connected to the connecting plate of the pair of flange plate, first connector It is expansion bolt, the connecting plate is attached at the piping lane wall and fixed with the piping lane wall by the expansion bolt Connection.
3. the rear-mounted adjustable support of piping lane is used for as claimed in claim 2, it is characterised in that on the pair of flange plate The adjustment hole is provided with along short transverse.
4. the rear-mounted adjustable support of piping lane is used for as claimed in claim 3, it is characterised in that the adjustment hole is elongated Hole.
5. the rear-mounted adjustable support of piping lane is used for as claimed in claim 2, it is characterised in that the horizontal support is the second groove Steel, the shackle member is the 3rd channel-section steel, and second connector is fastening bolt, and the connecting plate of the 3rd channel-section steel is welded in institute The end of the second channel-section steel is stated, the 3rd channel-section steel is fastened in first channel-section steel and is worn by the fastening bolt corresponding The adjustment hole is fixedly connected.
6. the rear-mounted adjustable support of piping lane is used for as claimed in claim 1, it is characterised in that the horizontal support is vertical with described It is oblique between post to have installed hound.
CN201621167220.4U 2016-10-26 2016-10-26 For the rear-mounted adjustable support of piping lane Expired - Fee Related CN206233264U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621167220.4U CN206233264U (en) 2016-10-26 2016-10-26 For the rear-mounted adjustable support of piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621167220.4U CN206233264U (en) 2016-10-26 2016-10-26 For the rear-mounted adjustable support of piping lane

Publications (1)

Publication Number Publication Date
CN206233264U true CN206233264U (en) 2017-06-09

Family

ID=58983052

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621167220.4U Expired - Fee Related CN206233264U (en) 2016-10-26 2016-10-26 For the rear-mounted adjustable support of piping lane

Country Status (1)

Country Link
CN (1) CN206233264U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107153243A (en) * 2017-07-12 2017-09-12 悉地(苏州)勘察设计顾问有限公司 The installation supporting structure of optical cable in piping lane
CN108512184A (en) * 2017-07-14 2018-09-07 安徽华电工程咨询设计有限公司 It is a kind of can bidirectional modulation assembled cable bearer
CN114790691A (en) * 2022-04-14 2022-07-26 通号建设集团有限公司 Construction method for steel structure pipe gallery channel under bridge

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107153243A (en) * 2017-07-12 2017-09-12 悉地(苏州)勘察设计顾问有限公司 The installation supporting structure of optical cable in piping lane
CN108512184A (en) * 2017-07-14 2018-09-07 安徽华电工程咨询设计有限公司 It is a kind of can bidirectional modulation assembled cable bearer
CN114790691A (en) * 2022-04-14 2022-07-26 通号建设集团有限公司 Construction method for steel structure pipe gallery channel under bridge
CN114790691B (en) * 2022-04-14 2023-10-20 通号建设集团有限公司 Construction method for under-bridge steel structure pipe gallery channel

Similar Documents

Publication Publication Date Title
CN206233264U (en) For the rear-mounted adjustable support of piping lane
CN205978823U (en) Pump line fixing device
CN209891084U (en) Bridge support cushion stone anchor bolt hole positioning fixture
CN202578718U (en) Locating system for embedded part at construction joint between tunnel invert and secondary lining
CN107965065A (en) Buckling support Combined type pre-embedded member construction method
CN209604683U (en) Multi-pipeline fixes bracket
CN205875206U (en) Utility tunnel lateral wall built -in fitting fixing device
CN212249293U (en) Electric spool fixing device based on manger plate platform
CN204455823U (en) A kind of suspension bridge push-and-pull rod anchor system
CN105178986B (en) Variable curve mold for lining positioning of earth-sheltered dwelling and construction technology of variable-curve mold
CN106758663A (en) Buried rubber fastening band installs positioning construction method in one kind
CN206503071U (en) A kind of anticollision barrier pre-embedded steel slab fast-positioning device
CN207211784U (en) A kind of positioner of prefabricated components installation reinforcing bar
CN203559505U (en) Cast-in-place light steel bar truss wall
CN212336092U (en) Underground pipe gallery
CN206815542U (en) A kind of portable bracket pre-embedded bolt fixed structure
CN204782001U (en) Regulation formula post rebar positioning appearance
CN105781056B (en) Special-shaped metope moulding can adjust gusseted point hang device
CN210976098U (en) Underground pipe gallery pre-buried support
CN212543303U (en) Main structure embedded pipeline regulator
CN210397943U (en) Through floor pipe sleeve positioning device
CN211925015U (en) Settlement-preventing construction device for underground pipeline of building
CN211621021U (en) Inclined shaft assembled support high track
CN112483730A (en) No pre-buried, no crab-bolt arc pipe gallery multi-angle adjustable support
CN214119192U (en) Hafen groove is with novel adjustable support of taking stand

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170609