CN212543303U - Main structure embedded pipeline regulator - Google Patents

Main structure embedded pipeline regulator Download PDF

Info

Publication number
CN212543303U
CN212543303U CN202021309627.2U CN202021309627U CN212543303U CN 212543303 U CN212543303 U CN 212543303U CN 202021309627 U CN202021309627 U CN 202021309627U CN 212543303 U CN212543303 U CN 212543303U
Authority
CN
China
Prior art keywords
angle steel
angle
short pipe
edge
main structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021309627.2U
Other languages
Chinese (zh)
Inventor
张艳平
刘川正
王涛
刘培栓
齐文英
闫文强
夏春刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Fifth Construction Group Co Ltd
Original Assignee
Shanxi Fifth Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Fifth Construction Group Co Ltd filed Critical Shanxi Fifth Construction Group Co Ltd
Priority to CN202021309627.2U priority Critical patent/CN212543303U/en
Application granted granted Critical
Publication of CN212543303U publication Critical patent/CN212543303U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pipeline Systems (AREA)

Abstract

The utility model relates to a main structure pre-buried pipeline adjuster, which comprises an angle steel, wherein a plurality of short pipe joints are arranged at intervals on one side right-angle edge of the angle steel, and the axes of the short pipe joints and the right-angle edge of the angle steel are arranged vertically; the other side right angle edge of angle steel releasable connection has U type card. The utility model discloses the adjuster can adjust the hidden piping such as electric line pipe, water supply branch pipe, heating branch pipe at the major structure construction, adjusts control to the interval and the straightness that hangs down of pre-buried pipeline through the intensity of steel promptly. The regulator can be repeatedly used in a standard structural layer, the waste of the one-time use of the conventional PVC line pipe is reduced, and the construction cost is reduced. After the main body concrete pouring or the masonry is built by laying bricks or stones and is accomplished, the displacement can not take place for the pre-buried pipeline mounting position, has still improved the whole impression quality of main body engineering simultaneously, has reduced the unnecessary cost for the engineering construction in later stage and has taken place.

Description

Main structure embedded pipeline regulator
Technical Field
The utility model relates to a construction technical field specifically is a pre-buried pipeline adjuster of major structure.
Background
The existing main body structure is provided with pre-buried electric pipelines, pre-buried water supply pipelines, pre-buried heating pipelines and other pre-buried pipelines at the joint of the construction of a hidden pipe and an exposed pipe, and PVC transverse pipelines are adopted for simple fixation at the exposed pipe, wherein the spacing and the verticality of the pre-buried pipelines are difficult to fix accurately; meanwhile, when the embedded pipeline is prolonged in the later period, the position adjustment construction difficulty of the embedded line pipe is high, and unnecessary cost can be caused sometimes.
Disclosure of Invention
The utility model aims at solving the problems existing in the prior art, and providing a pre-buried pipeline adjuster of main structure. The regulator can be widely used for adjusting the concrete pouring process and the pipeline in the brick laying process of pre-buried electric pipelines, pre-buried water supply pipelines, pre-buried heating branch pipes and the like in structural types such as frame structures, frame-shear wall structures, brick-concrete structures and the like.
The utility model discloses a realize through following technical scheme:
a main structure embedded pipeline adjuster comprises angle steel, wherein a plurality of short pipe joints are arranged on the right-angle edge of one side of the angle steel at intervals, and the axes of the short pipe joints and the right-angle edge of the angle steel are arranged in a vertical manner; the other side right angle edge of angle steel releasable connection has U type card.
In the construction process of the main structure, before concrete pouring or masonry, the regulator of the utility model fixes the concealed pipes such as the electric line pipe, the water supply branch pipe and the heating branch pipe, namely, the concealed pipes are orderly inserted into the short pipe joints of the device; after the main body concrete is poured or the masonry is built, the regulator is dismantled, and the next pipeline installation and use are carried out. Therefore, the installation position of the pre-buried pipeline can not be displaced, the overall impression quality of the main engineering is improved, and unnecessary cost is reduced for later engineering construction.
As a preferred technical scheme, the connection mode between the U-shaped card and the angle steel is specifically as follows: connecting threads are arranged at the end parts of the two ends of the U-shaped clamp, a through hole is formed in the right-angle edge of the angle steel, and the end parts of the two ends of the U-shaped clamp are respectively connected with first fastening nuts in a threaded mode after penetrating through the corresponding through holes.
As a preferred technical scheme, the connection mode between the short pipe joint and the angle steel is as follows: two upper and lower slides have been seted up along its length direction to the right angle edge of angle steel, are fixed with two upper and lower screw rods on the pipe wall of short tube coupling, and two upper and lower screw rods pass two upper and lower slides of correspondence respectively and have the second fastening nut in threaded connection. Therefore, the short pipe joint can move relative to the angle steel, so that the positioning of pre-buried pipelines with different intervals is met, and the application range and the practicability of the adjuster are further improved.
As a preferred technical scheme, the specification of the angle steel is 50 x 5mm, and the length of the angle steel is 500 mm; the length of the short pipe joint is 100 mm; the specification of the U-shaped card is DN100 mm.
This pre-buried pipeline regulator reuse reduces the waste of PVC spool, reduces construction cost, provides convenience for the installation of later stage spool simultaneously.
The utility model discloses a problem to the fixed mode existence of traditional buried pipeline, and the fixed new instrument of a buried pipeline who obtains after improving of a proposed, this instrument is the buried pipeline adjuster who adopts angle steel, stub pipe festival, U type card to make promptly, and this adjuster can adjust the hidden tube such as electric line pipe, water supply branch pipe, heating branch pipe at the major structure construction, adjusts control through the intensity of steel to the interval and the straightness that hangs down of buried pipeline promptly. The regulator can be repeatedly used in a standard structural layer, the waste of the one-time use of the conventional PVC line pipe is reduced, and the construction cost is reduced. After the main body concrete pouring or the masonry is built by laying bricks or stones and is accomplished, the displacement can not take place for the pre-buried pipeline mounting position, has still improved the whole impression quality of main body engineering simultaneously, has reduced the unnecessary cost for the engineering construction in later stage and has taken place.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, illustrate exemplary embodiments of the invention and, together with the description, serve to explain the invention and not to limit the invention in any way.
Fig. 1 is a front view of the structure of the present invention.
Fig. 2 is a rear view of the structure of the present invention.
Fig. 3 is a top view of the present invention.
Fig. 4 is a right side view of the structure of the present invention.
In the figure: the steel pipe comprises 1-angle steel, 2-short pipe joints, 3-U-shaped clamps, 4-first fastening nuts, 5-slideways, 6-screws and 7-second fastening nuts.
Detailed Description
In order to make the present invention better understood by those skilled in the art, the present invention will be further clearly and completely described below with reference to the accompanying drawings and embodiments. It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict.
As shown in fig. 1 to 4, the adjuster for the pre-buried pipeline of the main structure comprises an angle steel 1, wherein a plurality of short pipe joints 2 are arranged at intervals on a right-angle edge on one side of the angle steel 1, and the axes of the short pipe joints 2 are perpendicular to the right-angle edge of the angle steel 1; but the detachable connection has U type card 3 on the opposite side right angle edge of angle steel 1, and specific connected mode is: the both ends tip of U type card 3 is provided with connecting thread, and the through hole has been seted up on the right angle edge of angle steel 1, and threaded connection has first fastening nut 4 behind the corresponding through hole is passed respectively to the both ends tip of U type card 3.
Further, in order to optimize the utility model discloses the structure of adjuster to widen its application scope, the connected mode between its upper short tube coupling 2 and the angle steel 1 can be designed as following form: two upper and lower slides 5 have been seted up along its length direction on the right angle edge of angle steel 1, are fixed with two upper and lower screw rods 6 on the pipe wall of short tube coupling 2, and threaded connection has second fastening nut 7 after two upper and lower screw rods 6 passed two upper and lower slides 5 that correspond respectively. Therefore, the position of the short pipe joint 2 on the angle steel 1 can be adjusted according to actual needs to meet the fixed positioning of the embedded pipelines at various intervals.
Further, the specification of the angle steel 1 is 50 x 5mm, and the length of the angle steel 1 is 500 mm; the length of the short pipe joint 2 is 100mm, the diameter of the short pipe joint 2 is selected according to the diameter of the embedded pipeline, and the diameter of the short pipe joint 2 is required to be slightly larger than the diameter of the embedded pipeline; the specification of the U-card 3 is DN100 mm.
Wherein, short tube coupling 2 is removable part, at this in-process of actual construction, can match with pre-buried pipeline according to the short tube coupling 2 and the pre-buried pipeline of the actual demand on scene equipped with different pipe diameters, for example: when three DN32 pipes, two DN25 pipes and two DN20 pipes are arranged in the pipeline discharging the concrete ground, seven short pipe joints 2 with the pipe diameters matched with the pipe diameters can be designed according to the seven pipeline for field installation and use.
The utility model discloses the adjuster installation, demolish the convenience, can have enough to meet the need the use many times, and the cost is lower, appraises the excellent very big help to promoting pre-buried pipeline impression quality and later stage completion quality.
The technical solutions in the embodiments of the present invention have been clearly and completely described above, and the described embodiments are only a part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.

Claims (4)

1. The utility model provides a pre-buried pipeline adjuster of major structure which characterized in that: the pipe joint comprises angle steel, wherein a plurality of short pipe joints are arranged on the right-angle edge of one side of the angle steel at intervals, and the axes of the short pipe joints are perpendicular to the right-angle edge of the angle steel; the other side right angle edge of angle steel releasable connection has U type card.
2. The main structure embedded pipeline adjuster according to claim 1, wherein: the connection mode between U type card and the angle steel specifically is: connecting threads are arranged at the end parts of the two ends of the U-shaped clamp, a through hole is formed in the right-angle edge of the angle steel, and the end parts of the two ends of the U-shaped clamp are respectively connected with first fastening nuts in a threaded mode after penetrating through the corresponding through holes.
3. The main structure embedded pipeline adjuster according to claim 1 or 2, wherein: the connection mode between the short pipe joint and the angle steel is as follows: two upper and lower slides have been seted up along its length direction to the right angle edge of angle steel, are fixed with two upper and lower screw rods on the pipe wall of short tube coupling, and two upper and lower screw rods pass two upper and lower slides of correspondence respectively and have the second fastening nut in threaded connection.
4. The main structure embedded pipeline adjuster according to claim 3, wherein: the specification of the angle steel is ^ 50 x 5mm, and the length of the angle steel is 500 mm; the length of the short pipe joint is 100 mm; the specification of the U-shaped card is DN100 mm.
CN202021309627.2U 2020-07-07 2020-07-07 Main structure embedded pipeline regulator Active CN212543303U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021309627.2U CN212543303U (en) 2020-07-07 2020-07-07 Main structure embedded pipeline regulator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021309627.2U CN212543303U (en) 2020-07-07 2020-07-07 Main structure embedded pipeline regulator

Publications (1)

Publication Number Publication Date
CN212543303U true CN212543303U (en) 2021-02-12

Family

ID=74522354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021309627.2U Active CN212543303U (en) 2020-07-07 2020-07-07 Main structure embedded pipeline regulator

Country Status (1)

Country Link
CN (1) CN212543303U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116576304A (en) * 2023-07-05 2023-08-11 山西五建集团有限公司 Multifunctional combined support system for bedding

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116576304A (en) * 2023-07-05 2023-08-11 山西五建集团有限公司 Multifunctional combined support system for bedding
CN116576304B (en) * 2023-07-05 2023-09-05 山西五建集团有限公司 Multifunctional combined support system for bedding

Similar Documents

Publication Publication Date Title
CN212543303U (en) Main structure embedded pipeline regulator
CN202578718U (en) Locating system for embedded part at construction joint between tunnel invert and secondary lining
CN207229922U (en) Adjustable upper and lower conduit channel fixing device
CN207177917U (en) A kind of duct pieces of shield tunnel provided with plug-in conduit
CN212249293U (en) Electric spool fixing device based on manger plate platform
CN211775899U (en) Support system for one-time embedded box in masonry
CN210976098U (en) Underground pipe gallery pre-buried support
CN211774410U (en) Inspection shaft chute typical forms
CN207229119U (en) A kind of template and tunnel segment structure for being used to manufacture duct pieces of shield tunnel
CN210397943U (en) Through floor pipe sleeve positioning device
CN212718427U (en) Line pipe connection fixer
CN210262677U (en) Embedded part for laying cable bridge
CN207776302U (en) A kind of pitched roof bar planting welding levelling constructing device of zinc-plated square tube
CN205713104U (en) Civil engineering basic mode side head part
CN206971809U (en) A kind of civil engineering support
CN208934708U (en) Slip casting pipe joint arrangement
CN202298771U (en) Construction installing and controlling device for dual channel water outlets
CN213204313U (en) Mixed tap internal thread elbow installation levelling device
CN110685435A (en) Waterproof structure for screw hole of shear wall of outer vertical surface
CN207421539U (en) A kind of wall bushing with pipeline alignment positioning device
CN217441766U (en) Adjustable pipe well ground heating coil fixing device
CN220058848U (en) Integrated device for positioning and anti-collision of embedded wire pipe
CN111765299A (en) Combined pre-buried sleeve
CN216380265U (en) Building supporting beam and supporting column connecting structure
CN105863264B (en) A kind of civil engineering basic mode side head part

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant